CN208309776U - A kind of prefabricated Boosting pumping station - Google Patents
A kind of prefabricated Boosting pumping station Download PDFInfo
- Publication number
- CN208309776U CN208309776U CN201820596279.8U CN201820596279U CN208309776U CN 208309776 U CN208309776 U CN 208309776U CN 201820596279 U CN201820596279 U CN 201820596279U CN 208309776 U CN208309776 U CN 208309776U
- Authority
- CN
- China
- Prior art keywords
- cylinder
- pumping station
- liquid level
- prefabricated
- dredge pump
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Structures Of Non-Positive Displacement Pumps (AREA)
Abstract
The utility model relates to a kind of prefabricated Boosting pumping stations, it includes at least one cylinder and the intelligence communication control cabinet that is set to above the cylinder, the inner barrel is at least provided with dredge pump, water pump inspection control module is provided in the intelligence communication control cabinet, and the water pump inspection control module is electrically connected with the dredge pump.The prefabricated Boosting pumping station of the utility model in intelligence communication control cabinet by adding water pump inspection control module, when water pump is not run for a long time, it can control dredge pump short-time running by the module, guarantee that dredge pump operates normally, simultaneously, the module can make dredge pump around master control system, directly runs and the intracorporal liquid level of cylinder is prevented to be decreased until dredge pump from until sucking sewage, the controlled turbulence generated by water pump in suction pump and can also be excluded the particle of dredge pump bottom is deposited in together with dross, so that the prefabricated Boosting pumping station of the utility model has self-cleaning function.
Description
Technical field
The utility model relates to sewage disposal system technical field more particularly to a kind of prefabricated Boosting pumping stations.
Background technique
In the undesirable environment of sewage or rainwater conditions of discharge, as sewage pipe is lower than municipal administration supervisor's net or is separate
The place of municipal administration supervisor's net, the discharge of sewage or rainwater are extremely difficult.These sewage or rainwater prolonged stay are for integral loop
Border can generate large effect, in order to collect and be passed to specific sewage, rainwater treatment factory or defined place, sewage
Pumping plant comes into being, and it is using more and more extensive.
During urban development, the type and function of pumping plant are had changed a lot, and earliest sewage pumping station is
Concrete pumping plant.Concrete pumping plant there are installation procedures it is complicated, maintenance is inconvenient the defects of, and will also result in use
The waste of very big man power and material.Importantly, the failure blocked often occurs in concrete pumping plant, deal with quite
Trouble.
On the other hand, the depth of pumping plant is up to ten meters or more, and so air does not circulate in deep pumping plant, in addition being sewage
Boosting pumping station, stand in there is sewage to flow through for a long time so that a large amount of poisonous fume of the accumulation in pumping plant, and pumping plant mouth is closed for a long time,
Lead in pumping plant not only atmosphere draught-free, it is also possible to it is toxic, when under staff needs to when being safeguarded to pumping plant in pumping plant,
There are some potential safety problemss.
Therefore, existing prefabricated Boosting pumping station is improved, is provided a kind of with without the prefabricated of blocking self-cleaning function
Boosting pumping station becomes those skilled in the art's technical problem urgently to be solved.
Utility model content
The technical issues of for plugging fault is easy to appear existing for prior art concrete pumping plant, the utility model provide
A kind of prefabricated Boosting pumping station, the prefabricated Boosting pumping station of the utility model is in intelligence communication control cabinet by adding water pump inspection
Control module can control dredge pump short-time running by the module, guarantee dredge pump when water pump is not run for a long time
It operates normally, meanwhile, which can make dredge pump around master control system, directly run and be decreased until the intracorporal liquid level of cylinder
Until dredge pump cannot suck sewage, the controlled turbulence that is generated by water pump can also be deposited in the particle of dredge pump bottom with
Suction pump is interior together and excludes for dross, so that the prefabricated Boosting pumping station of the utility model has self-cleaning function.
To achieve the above object, the utility model provides following technical scheme:
The prefabricated Boosting pumping station of the utility model is logical including at least one cylinder and the intelligence being set to above the cylinder
Believe control cabinet, the inner barrel is at least provided with dredge pump, which is characterized in that is provided with water in the intelligence communication control cabinet
Inspection control module is pumped, and the water pump inspection control module is electrically connected with the dredge pump, not transport in the dredge pump
When row, the operating of the dredge pump is controlled by the water pump inspection control module, and drop to the intracorporal liquid level of the cylinder
Until the dredge pump cannot suck sewage.
Further, the bottom of the cylinder is equipped with bottom plate, and the bottom plate includes Outer Bottom Plating, inner bottom plating and flat underside,
Wherein, the periphery of the flat underside is connected by the Outer Bottom Plating and the inner bottom plating with the side wall of the cylinder, and described
Inner bottom plating is the structure of reduced diameter from the top down, to increase the whirlpool that the dredge pump pumping procedure generates.
Further, the cylinder is equipped with water inlet and water outlet, and the inner barrel is additionally provided with grid device institute
Stating grid device is basket grid and/or crushed rack bar screen, and the grid device is disposed in proximity to the water inlet side,
So that the grid device intercepts the sewage entered by the water inlet.
Further, it is provided with check-valves on the pressure pipeline system between the water outlet and the dredge pump, and
The non-return valve surface is coated with epoxy coating.
Further, the barrel outer surface is coated with anti oxidation layer, and the cylinder inner surface is coated with erosion resistant coating and prevents
Infiltration layer, and the cylinder inner surface is additionally provided with enhancement layer.
It further, further include level monitoring device, the level monitoring device includes at least the first level monitoring device
With the second level monitoring device, and first level monitoring device and second level monitoring device with the intelligence
The electrical connection of communication control cabinet.
Further, first level monitoring device is static pressure difference called putting-into-type liquid level meter, and the static pressure difference is put into
Formula liquidometer is set to the inner sidewall of the cylinder, and second level monitoring device is mechanical Weight type floating ball device, and
The machinery Weight type floating ball device includes high liquid level machinery Weight type floating ball and low liquid level machinery Weight type floating ball, wherein high
Liquid level machinery Weight type floating ball is set in the cylinder at preset highest liquid level, and low liquid level machinery Weight type floating ball is set to
In the cylinder at preset minimum liquid level.
Further, further include gas-detecting device, the gas-detecting device be set to the cylinder inboard wall and with institute
The electrical connection of intelligence communication control cabinet is stated, and the gas-detecting device includes at least concentration of hydrogen sulfide sensor, oxygen concentration
One of sensor, gas concentration lwevel sensor, sensing methane concentration device and ammonia concentration sensor are a variety of.
It further, further include gas discharging apparatus, the gas discharging apparatus includes at least axial flow blower, wherein institute
It states axial flow blower and is installed on the lower section that the well lid of the pumping plant inlet is set, and the axial flow blower enters with the pumping plant
Mouth is detachably connected.
It further, further include deodorization device, the deodorization device is to be installed in the ventilation that the well lid side is arranged in
Activated carbon adsorption device inside pipe, and the ventilation duct is connect with the air outlet of the axial flow blower, so that from the axis
The foul smell of flow fan discharge enters the activated carbon adsorption device and carries out deodorizing process.
Prefabricated Boosting pumping station provided by the utility model at least has following advantageous effects:
The prefabricated Boosting pumping station of the utility model by adding water pump inspection control module in intelligence communication control cabinet,
When water pump is not run for a long time, dredge pump short-time running can control by the module, guarantee that dredge pump operates normally, together
When, which can make dredge pump around master control system, directly run and prevent the intracorporal liquid level of cylinder be decreased until dredge pump from
Until sucking sewage, the particle for being deposited in dredge pump bottom can also be inhaled together with dross by the controlled turbulence that water pump generates
Enter in pump and exclude, so that the prefabricated Boosting pumping station of the utility model has self-cleaning function.
In addition, the utility model optimal technical scheme can also have the following technical effects:
The first level monitoring device and the second liquid is at least arranged in the prefabricated Boosting pumping station of the utility model optimal technical scheme
Position monitoring device, acquires different liquid levels by the first level monitoring device and the second level monitoring device and is opened with controlling water pump
It is dynamic, it can be damaged caused by water pump to avoid in the case where a wherein level monitoring device failure or inaccurate monitoring.
The prefabricated Boosting pumping station of the utility model optimal technical scheme also have gas-detecting device, gas discharging apparatus and
Deodorization device analyzes in intelligence communication control cabinet and starts gas discharge dress when toxic gas content in cylinder is more than preset value
It sets, the intracorporal toxic gas of cylinder is discharged by gas discharging apparatus and is handled through deodorization device, reach deodorization and processing is dangerous
The effect of gas guarantees the intracorporal air quality of cylinder, makes staff that safety accident will not occur when entering work in cylinder.
Detailed description of the invention
In order to illustrate the embodiment of the utility model or the technical proposal in the existing technology more clearly, below will be to embodiment
Or attached drawing needed to be used in the description of the prior art is briefly described, it should be apparent that, the accompanying drawings in the following description is only
It is some embodiments of the utility model, for those of ordinary skill in the art, in the premise not made the creative labor
Under, it is also possible to obtain other drawings based on these drawings.
Fig. 1 is the cross-sectional view of prefabricated one preferred embodiment of Boosting pumping station;
Fig. 2 is the top view of prefabricated one preferred embodiment of Boosting pumping station.
1- cylinder in figure;2- intelligence communication control cabinet;3- dredge pump;4- Outer Bottom Plating;5- inner bottom plating;6- flat underside;7- enters
The mouth of a river;8- water outlet;9- grid device;10- pressure pipeline system;11- check-valves;The first level monitoring device of 12-;13-
Two level monitoring devices;14- well lid;15- ventilation duct.
Specific embodiment
To keep the purpose of this utility model, technical solution and advantage clearer, below by the technology to the utility model
Scheme is described in detail.Obviously, the described embodiments are only a part of the embodiments of the utility model, rather than all
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are not before making creative work
Obtained all other embodiment is put, the range that the utility model is protected is belonged to.
Fig. 1 shows the cross-sectional view of prefabricated one preferred embodiment of Boosting pumping station, and Fig. 2 shows prefabricated Boosting pumping stations one
The top view of a preferred embodiment is specifically described below with reference to prefabricated Boosting pumping station of the Fig. 1 and Fig. 2 to the utility model.
As shown in Figure 1, the prefabricated Boosting pumping station of the utility model includes at least one cylinder 1 and is set to above cylinder 1
Intelligence communication control cabinet 2, at least provided with dredge pump 3 inside cylinder 1.Preferably, water is provided in intelligence communication control cabinet 2
Inspection control module is pumped, and water pump inspection control module is electrically connected with dredge pump 3, to pass through water in 3 not running of dredge pump
The operating of inspection control module control of sewage disposal pump 3 is pumped, and so that the liquid level in cylinder 1 is dropped to dredge pump 3 from sucking sewage and is
Only.
According to a preferred embodiment, the intelligence communication control cabinet 2 of the utility model is 304 stainless steel outdoor types, is prevented
Rain is antitheft, carries PLC device, and biswitch can be operated by human-computer interaction interface.It is logical that its electrical source of power introduces intelligence nearby
Believe control cabinet 2, the remote controlled equipment start-stop of intelligence communication control cabinet 2.
The prefabricated Boosting pumping station of the utility model by adding water pump inspection control module in intelligence communication control cabinet 2,
When water pump is not run for a long time, 3 short-time running of dredge pump can control by the module, guarantee that dredge pump 3 is normally transported
Row, meanwhile, which can make dredge pump 3 around master control system, directly run and the liquid level in cylinder 1 is made to be decreased until blowdown
Until pump 3 cannot suck sewage, the controlled turbulence that generates by water pump can also be the particle that is deposited in 3 bottom of dredge pump and floating
Suction pump is interior together and excludes for slag, so that the prefabricated Boosting pumping station of the utility model has self-cleaning function.
Referring again to Fig. 1, the bottom of cylinder 1 is equipped with bottom plate, and bottom plate includes Outer Bottom Plating 4, inner bottom plating 5 and flat underside 6.It is preferred that
, the periphery of flat underside 6 is connected by Outer Bottom Plating 4 and inner bottom plating 5 with the side wall of cylinder 1, and inner bottom plating 5 is straight from the top down
The diminishing structure of diameter, to increase the whirlpool of 3 pumping procedure of dredge pump generation.
The prefabricated Boosting pumping station of the utility model optimal technical scheme sets inner bottom plating 5 to the knot of reduced diameter
Structure is rolled the mud of 1 bottom of cylinder to arrange by the whirlpool of generation with increasing the whirlpool of 3 pumping procedure of dredge pump generation
Out, the self-cleaning function of prefabricated Boosting pumping station is further enhanced, and can effectively prevent the mud siltation of 1 bottom of cylinder, is effectively pressed down
It is formed with the generation of poison and foul gas.
With continued reference to Fig. 1 or Fig. 2, cylinder 1 is equipped with water inlet 7 and water outlet 8, and grid dress is additionally provided with inside cylinder 1
Set 9.Preferably, grid device 9 is basket grid and/or crushed rack bar screen.It is furthermore preferred that grid device 9 be disposed in proximity into
7 side of the mouth of a river, so that grid device 9 intercepts the sewage entered by water inlet 7.
The prefabricated Boosting pumping station of the utility model optimal technical scheme is arranged in 1 inside of cylinder and close to 7 side of water inlet
Grid device 9 is intercepted by 9 pairs of sewage entered through water inlet 7 of grid device, so can not only reduce dredge pump 3
The dirt of sucking, prolongs its service life, moreover it is possible to which the dirt to deposit in cylinder 1 extends the cleaning to cylinder 1 and time between overhauls(TBO).
On the other hand, the grid device 9 of the prefabricated elevator pump of the utility model optimal technical scheme is basket grid and/or powder
Fragility grid.Preferably, the basket grid of the prefabricated elevator pump of the utility model optimal technical scheme is opened the door using side and is designed, convenient
The cleaning of dirt.The material that the basket grid of the prefabricated elevator pump of the utility model optimal technical scheme uses is all steel material
Matter has corrosion-resistant, long-lived advantage.It is also set on the basket grid of the prefabricated elevator pump of the utility model optimal technical scheme
It is equipped with guiding rail, to facilitate the lifting of basket grid, is convenient to clean.It is mentioned in addition, the utility model optimal technical scheme is prefabricated
Rise pump basket grid also have it is at low cost, easy to use, can according to flow optimization design, reduce manual cleaning frequency it is excellent
Gesture.
Preferably, the blade of the crushed rack bar screen of the prefabricated elevator pump of the utility model optimal technical scheme is closed using heat treatment
Uniform cure process is passed through on Jin Gang, surface, and hardness is not less than 45~50HRC, and monolithic case uses spheroidal graphite cast-iron or stainless steel,
So that crushed rack bar screen can be adapted for different dirt, durable.The prefabricated elevator pump of the utility model optimal technical scheme
Crushed rack bar screen motor be special motor, waterborne can continuously run 24 hours under water, multiple power is optional.The utility model
The crushed rack bar screen of the prefabricated elevator pump of optimal technical scheme uses planetary reducer, and anti-load impact ability is strong.This is practical
The motor of the crushed rack bar screen of the novel prefabricated elevator pump of optimal technical scheme can with positive and negative rotation so that crushed rack bar screen have it is miscellaneous
Object can be debugged automatically when blocking by alternately positive and negative rotation.
With continued reference to Fig. 1, check-valves 11 is provided on the pressure pipeline system 10 between water outlet 8 and dredge pump 3.It is preferred that
, pressure pipeline system 10 is arranged in close to one end of water outlet 8 in check-valves 11.The utility model optimal technical scheme it is prefabricated
Elevator pump stands by setting check-valves 11 at water outlet 8, and promotion can be effectively prevented to pressure pipeline system 10 and water outlet 8
The sewage at place again returns in cylinder, influences the drainage efficiency of prefabricated Boosting pumping station.Preferably, 11 surface of check-valves is coated with
Epoxy coating.The prefabricated Boosting pumping station of the utility model optimal technical scheme is applied in 11 surface of check-valves coating epoxy resin
Layer makes check-valves 11 have good corrosion resistance, enhances its service life.
According to a preferred embodiment, 1 outer surface of cylinder is coated with anti oxidation layer, and 1 inner surface of cylinder is coated with anti-corrosion
Layer and impervious barrier, and 1 inner surface of cylinder is additionally provided with enhancement layer.Preferably, cylinder 1 uses strengthened glass steel body material.This
1 outer surface of cylinder of the prefabricated Boosting pumping station of utility model optimal technical scheme is coated with anti oxidation layer, and inner surface is coated with anti-
Rotten layer and impervious barrier make it have extremely strong anti-corrosion, impermeable and anti-aging performance, can satisfy the various extreme works of user
Condition, service life are up to 50 years or more.
The prefabricated Boosting pumping station of the utility model optimal technical scheme further includes level monitoring device, and level monitoring device is extremely
It less include the first level monitoring device 12 and the second level monitoring device 13, and the first level monitoring device 12 and the second liquid level
Monitoring device 13 is electrically connected with intelligence communication control cabinet 2.
Prefabricated sewage lifting pump station in the prior art is generally provided only with a set of level monitoring device, and trade effluent, rain
Often there is destructive substance containing corrosive substance or to level monitoring device in water etc., in addition level monitoring device pair
It is had differences in precision and adaptability in different media, therefore the pumping plant for being only equipped with a set of level monitoring device is using
Level monitoring failure is often had in the process or inaccurate situation occurs, and will result in empty pumping at this time or water level is full
Water pump does not start to work really, and water pump is made to be easy to be damaged.The prefabricated Boosting pumping station of the utility model optimal technical scheme is at least
First level monitoring device 12 and the second level monitoring device 13 are set, supervised by the first level monitoring device 12 and the second liquid level
Survey device 13 acquire different liquid levels with control water pump starting, can be to avoid a level monitoring device failure or prison wherein
It is damaged caused by water pump in indeterminable situation.
According to a preferred embodiment, the first level monitoring device 12 is static pressure difference called putting-into-type liquid level meter, and static pressure
Poor called putting-into-type liquid level meter is set to the inner sidewall of cylinder 1.Second level monitoring device 13 is mechanical Weight type floating ball device, and
Mechanical Weight type floating ball device includes high liquid level machinery Weight type floating ball and low liquid level machinery Weight type floating ball, wherein high liquid level
Mechanical Weight type floating ball is set in cylinder 1 at preset highest liquid level, and low liquid level machinery Weight type floating ball is set in cylinder 1
At preset minimum liquid level.
First level monitoring device 12 of the utility model optimal technical scheme is static pressure difference called putting-into-type liquid level meter, is had
Stability is good, advantage with high accuracy.Static pressure difference called putting-into-type liquid level meter is directly thrown into measured medium, is installed and used very square
Just, and static pressure difference called putting-into-type liquid level meter is solid-state structure, no movable member, reliability with higher, long service life.It is quiet
Pressure difference called putting-into-type liquid level meter can carry out high-acruracy survey to water, oil and the bigger paste of viscosity, not by tested Jie
Matter bubble, deposition, electrical characteristic influence.
The utility model optimal technical scheme is mechanical Weight type floating ball device, uses engineering plastics shell, machinery
Intensity height, good airproof performance.The cable of mechanical Weight type floating ball device is made of special material, has oil resistant, acid, alkali, anti-corruption
The excellent performance of erosion.Mechanical Weight type floating ball device also has the characteristics that installation and debugging are convenient.
The prefabricated Boosting pumping station of the utility model optimal technical scheme further includes gas-detecting device, and gas-detecting device is set
It is placed in 1 inner wall of cylinder and is electrically connected with intelligence communication control cabinet 2.Preferably, the gas inspection of the utility model optimal technical scheme
It surveys device and includes at least concentration of hydrogen sulfide sensor, oxygen concentration sensor, gas concentration lwevel sensor, sensing methane concentration
One of device and ammonia concentration sensor are a variety of.
The data that the gas-detecting device of the utility model optimal technical scheme will test are sent to intelligence communication control
Cabinet 2, intelligence communication control cabinet 2 analyze the toxic gas content in cylinder 1 according to the data received, and toxic in cylinder 1
Gas content starts gas discharging apparatus when being more than preset value.
The prefabricated Boosting pumping station of the utility model optimal technical scheme further includes gas discharging apparatus.Preferably, gas is arranged
Device is put including at least axial flow blower, wherein axial flow blower is installed on the lower section that the well lid 14 of pumping plant inlet is arranged in, and
Axial flow blower is detachably connected with pumping plant entrance.
The prefabricated Boosting pumping station of the utility model optimal technical scheme analyzes in cylinder 1 in intelligence communication control cabinet 2 to be had
Poisonous gas content starts axial flow blower when being more than preset value, by axial flow blower by the toxic gas discharge in cylinder 1 and through removing
Smelly device processing, has the function that deodorization and processing hazardous gas, guarantees the air quality in cylinder 1, enter staff
Safety accident will not occur when work in cylinder 1.
The prefabricated Boosting pumping station of the utility model optimal technical scheme further includes deodorization device.Preferably, deodorization device is
It is installed in the activated carbon adsorption device being arranged in inside the ventilation duct 15 of 14 side of well lid.It is furthermore preferred that ventilation duct 15 and axis stream
The air outlet of blower connects, so that entering activated carbon adsorption device from the foul smell that axial flow blower is discharged carries out deodorizing process.
The prefabricated Boosting pumping station of the utility model optimal technical scheme installs activated carbon adsorption device additional inside ventilation duct 15,
The foul smell generated when pumping plant ventilation can be effectively removed by activated carbon adsorption device.In addition, deodorization device is preferably that active carbon is inhaled
Adsorption device also has and replaces convenient advantage.
According to a preferred embodiment, the prefabricated Boosting pumping station of the utility model optimal technical scheme is pre-installed inside factory
It completes, only needs to lift at user scene, shorten construction period.Preferably, the prefabricated of the utility model optimal technical scheme mentions
Rising pumping plant may customize multiple cylinders 1, and multiple cylinders 1 are connected and/or parallel connection, then be equipped with garbage grille, gate etc., make the functions of pumping stations
It is more perfect.The prefabricated Boosting pumping station of the utility model optimal technical scheme passes through static pressure difference called putting-into-type liquid level meter and mechanical weight
Formula floating ball device monitors flow, and daily small flow starts 1 dredge pump, and big flow can start 2 even more dredge pumps,
Meet sewage, rainwater emission request.
The prefabricated Boosting pumping station of the utility model optimal technical scheme have small in size, land occupation less, integrated level is high, installation letter
Just, short construction period, resistance to corrosion are strong, long service life, safety and stability, low noise, odorless, are easy to ambient enviroment association
It adjusts, realize the features such as unattended, maintenance management is convenient.
Above description is only a specific implementation of the present invention, but the protection scope of the utility model is not limited to
In this, anyone skilled in the art within the technical scope disclosed by the utility model, can readily occur in variation
Or replacement, it should be covered within the scope of the utility model.Therefore, the protection scope of the utility model should be with the power
Subject to the protection scope that benefit requires.
Claims (10)
1. a kind of prefabricated Boosting pumping station, including at least one cylinder (1) and the intelligence communication control being set to above the cylinder (1)
Cabinet (2) processed, the cylinder (1) are internal at least provided with dredge pump (3), which is characterized in that in the intelligence communication control cabinet (2)
It is provided with water pump inspection control module, and the water pump inspection control module is electrically connected with the dredge pump (3), described
When dredge pump (3) not running, the operating of the dredge pump (3) is controlled by the water pump inspection control module, and makes the cylinder
Liquid level in body (1) drops to until the dredge pump (3) cannot suck sewage.
2. prefabricated Boosting pumping station according to claim 1, which is characterized in that the bottom of the cylinder (1) is equipped with bottom plate, institute
Stating bottom plate includes Outer Bottom Plating (4), inner bottom plating (5) and flat underside (6), wherein
The side wall phase that the periphery of the flat underside (6) passes through the Outer Bottom Plating (4) and the inner bottom plating (5) and the cylinder (1)
Connect, and the inner bottom plating (5) is the structure of reduced diameter from the top down, to increase the dredge pump (3) pumping procedure
The whirlpool of generation.
3. prefabricated Boosting pumping station according to claim 2, which is characterized in that the cylinder (1) be equipped with water inlet (7) and
Water outlet (8), the cylinder (1) is internal to be additionally provided with grid device (9), and the grid device (9) is basket grid and/or powder
Fragility grid, and the grid device (9) is disposed in proximity to the water inlet (7) side, so that the grid device (9) is right
It is intercepted by the sewage that the water inlet (7) enter.
4. prefabricated Boosting pumping station according to claim 3, which is characterized in that the water outlet (8) and the dredge pump (3)
Between pressure pipeline system (10) on be provided with check-valves (11), and the check-valves (11) surface be coated with epoxy resin
Coating.
5. prefabricated Boosting pumping station according to claim 4, which is characterized in that cylinder (1) outer surface is coated with antioxygen
Change layer, cylinder (1) inner surface is coated with erosion resistant coating and impervious barrier, and the cylinder (1) inner surface is additionally provided with reinforcement
Layer.
6. prefabricated Boosting pumping station according to claim 5, which is characterized in that it further include level monitoring device, the liquid level
Monitoring device includes at least the first level monitoring device (12) and the second level monitoring device (13), and first liquid level is supervised
It surveys device (12) and second level monitoring device (13) is electrically connected with the intelligence communication control cabinet (2).
7. prefabricated Boosting pumping station according to claim 6, which is characterized in that first level monitoring device (12) is quiet
Pressure difference called putting-into-type liquid level meter, and the static pressure difference called putting-into-type liquid level meter is set to the inner sidewall of the cylinder (1),
Second level monitoring device (13) is mechanical Weight type floating ball device, and the mechanical Weight type floating ball device packet
Include high liquid level machinery Weight type floating ball and low liquid level machinery Weight type floating ball, wherein the high liquid level machinery Weight type floating ball is set
It is placed in the cylinder (1) at preset highest liquid level, the low liquid level machinery Weight type floating ball is set in the cylinder (1)
At preset minimum liquid level.
8. according to claim 1 to prefabricated Boosting pumping station described in one of 7, which is characterized in that it further include gas-detecting device, institute
Gas-detecting device is stated to be set to the cylinder (1) inner wall and be electrically connected with the intelligence communication control cabinet (2), and
The gas-detecting device includes at least concentration of hydrogen sulfide sensor, oxygen concentration sensor, gas concentration lwevel sensing
One of device, sensing methane concentration device and ammonia concentration sensor are a variety of.
9. prefabricated Boosting pumping station according to claim 8, which is characterized in that it further include gas discharging apparatus, the gas
Tapping equipment includes at least axial flow blower, wherein
The axial flow blower is installed on the lower section that the well lid (14) of the pumping plant inlet is arranged in, and the axial flow blower with
The pumping plant entrance is detachably connected.
10. prefabricated Boosting pumping station according to claim 9, which is characterized in that it further include deodorization device, the deodorization device
To be installed in the setting activated carbon adsorption device internal in the ventilation duct (15) of the well lid (14) side, and the ventilation duct
(15) it is connect with the air outlet of the axial flow blower, so that the foul smell being discharged from the axial flow blower enters the activated carbon adsorption
Device carries out deodorizing process.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820596279.8U CN208309776U (en) | 2018-04-24 | 2018-04-24 | A kind of prefabricated Boosting pumping station |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820596279.8U CN208309776U (en) | 2018-04-24 | 2018-04-24 | A kind of prefabricated Boosting pumping station |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208309776U true CN208309776U (en) | 2019-01-01 |
Family
ID=64714409
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820596279.8U Active CN208309776U (en) | 2018-04-24 | 2018-04-24 | A kind of prefabricated Boosting pumping station |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208309776U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110607837A (en) * | 2019-09-20 | 2019-12-24 | 华南泵业(赣州)有限公司 | Sewage intercepting well and application |
-
2018
- 2018-04-24 CN CN201820596279.8U patent/CN208309776U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110607837A (en) * | 2019-09-20 | 2019-12-24 | 华南泵业(赣州)有限公司 | Sewage intercepting well and application |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN210507755U (en) | Prefabricated pump station of sewage promotion | |
CN114167017B (en) | Municipal administration sewage control early warning control system | |
CN208309776U (en) | A kind of prefabricated Boosting pumping station | |
KR102131426B1 (en) | The subsurface water tube well of easiable washing inside | |
CN110314925A (en) | A kind of refuse landfill original position aerobic stabilization processing unit and processing method | |
CN1660699A (en) | Sewage disposal process system possessing effect of preliminary filtration and dedicated equipment | |
CN205348378U (en) | Prefabricated pump station bottom pull rod goes up and down from cleaning device | |
CN107514054A (en) | The prevention waterlogging prefabricated pumping plant of integrated sewage water | |
CN105804160A (en) | Intelligent integrated pump station | |
CN205242607U (en) | Prefabricated pump station of integral type intelligence | |
CN207812635U (en) | A kind of anti-smell-back device based on life special sewage disposal | |
CN206769015U (en) | It is a kind of can deodorization prefabricated sewage lifting pump station | |
CN213174126U (en) | Prefabricated pump station of integration that contains automatic ventilation function | |
KR20150089131A (en) | A Sludge discharge apparatus of rotary type for a settling basin | |
KR100518684B1 (en) | Atomatic Sewage Sampling System in Manhole | |
CN210214846U (en) | Effluent water sump sealing system | |
CN208518060U (en) | Convenient for cleaning the integrated pump station of bottom | |
CN107653973B (en) | Device for storing garbage leachate | |
JP5769612B2 (en) | Outlet water monitor | |
CN207295964U (en) | A kind of horizontal prefabricated pumping plant of integration | |
CN218501639U (en) | Prevent leaking effectual spray column | |
CN112302148A (en) | Intelligent sewage lifting pump station system | |
CN204850033U (en) | Take deodorizing device's sewage pumping station | |
CN205444429U (en) | Single pump sewage promotes pump station | |
CN207211349U (en) | integrated pump station |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |