CN208294041U - One kind being used for side slope construction Integral foldable scaffold - Google Patents

One kind being used for side slope construction Integral foldable scaffold Download PDF

Info

Publication number
CN208294041U
CN208294041U CN201820387427.5U CN201820387427U CN208294041U CN 208294041 U CN208294041 U CN 208294041U CN 201820387427 U CN201820387427 U CN 201820387427U CN 208294041 U CN208294041 U CN 208294041U
Authority
CN
China
Prior art keywords
upright bar
cross bar
bar
slideway
door type
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820387427.5U
Other languages
Chinese (zh)
Inventor
熊耀
汤雷
刘晓程
徐雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN201820387427.5U priority Critical patent/CN208294041U/en
Application granted granted Critical
Publication of CN208294041U publication Critical patent/CN208294041U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model discloses one kind to be used for side slope construction Integral foldable scaffold, including fixed transverse rod, upright bar, removable cross bar, oblique pull bracket, job platform and concrete embedded component;Wherein: door type structure is formed between upright bar and fixed transverse rod;The scaffold includes multiple door type structures;Upright bar is internally provided with slideway, and removable cross bar both ends are connected with the upper end of the slideway of two adjacent door type structures respectively, and removable cross bar both ends can be slided up and down along upright bar and locking;Oblique pull bracket both ends are connected with the lower end of the slideway of two adjacent door type structures respectively, and the both ends of oblique pull bracket can be slided up and down along upright bar and locking;Concrete embedded component is arranged on the different height position of high slope, and upright bar is fixed on the different height position of high slope by concrete embedded component respectively;After door type structure is fixed, job platform is fixedly mounted on removable cross bar.The utility model overall performance is good, and stability is strong, durable using reliable.

Description

One kind being used for side slope construction Integral foldable scaffold
Technical field
The utility model relates to side slope construction scaffolding work field, more particularly to one kind are whole for side slope construction Folding scaffold.
Background technique
Existing side slope construction is staggeredly set up using design of coupler scaffold according to cross bar and upright bar, fastener connection, by Grade of side slope influences, and complicated for operation, fastener is easily lost, and sets up that difficulty is big, and at high cost, danger coefficient is larger, causes to construction Certain difficulty.
Utility model content
It is a kind of for high slope the technical problem to be solved by the present invention is to for the defects in the prior art, provide Construction Integral foldable scaffold.
The technical scheme adopted by the utility model to solve the technical problem is as follows:
The utility model provide it is a kind of for side slope construction Integral foldable scaffold, including fixed transverse rod, upright bar, Removable cross bar, oblique pull bracket, job platform and concrete embedded component;Wherein:
Two upright bars are arranged in parallel, and are fixedly connected by multiple fixed transverse rods being arranged in parallel between upright bar, Door type structure is formed between upright bar and fixed transverse rod;The scaffold includes multiple door type structures, is separately positioned on high slope not With height;Upright bar is internally provided with slideway, moves the cross bar both ends upper end with the slideway of two adjacent door type structures respectively It is connected, removable cross bar both ends can be slided up and down along upright bar and locking;Oblique pull bracket both ends respectively with two adjacent gate-types The lower end of the slideway of structure is connected, and the both ends of oblique pull bracket can be slided up and down along upright bar and locking;Concrete embedded component is set It sets on the different height position of high slope, upright bar is fixed on the different height position of high slope by concrete embedded component respectively It sets;After door type structure is fixed, job platform is fixedly mounted on removable cross bar.
Further, the removable cross bar both ends of the utility model are provided with slide bolt, and slide bolt is matched with slideway Connection is closed, cross bar is moved and realizes sliding and locking in upright bar by slide bolt.
Further, the oblique pull bracket both ends of the utility model are provided with slide bolt, and slide bolt and slideway cooperate Connection, oblique pull bracket realize sliding and locking in upright bar by slide bolt.
Further, bottom slide track is provided on the concrete embedded part of the utility model.
Further, the bottom of upright rod of the utility model is provided with bottom fixing bolt, and bottom fixing bolt and bottom are sliding Road is cooperatively connected, and sliding and locking on concrete embedded part are realized in upright bar by bottom fixing bolt.
Further, no less than 3 fixations are provided between two upright bars in each door type structure of the utility model Cross bar.
The beneficial effect that the utility model generates is: the utility model is used for side slope construction Integral foldable foot hand Frame, is used for high slope rockmass scaffolding work, and Integral foldable scaffold has the characteristics that installing and dismounting is efficient and convenient;Oblique pull Bracket and the adjustable height of packaged type cross bar and angle, adapt to the construction environment of high slope rockmass engineering complexity, meet construction Every demand, strong applicability;The utility model overall performance is good, and stability is strong, durable using reliable.
Detailed description of the invention
Below in conjunction with accompanying drawings and embodiments, the utility model is described in further detail, in attached drawing:
Fig. 1 is the structural schematic diagram of the utility model embodiment;
Fig. 2 is the side structure schematic view of the utility model embodiment;
Fig. 3 is the upright bar structural schematic diagram of the utility model embodiment;
Fig. 4 is the concrete embedded part structural schematic diagram of the utility model embodiment;
In figure: 1- fixed transverse rod, 2- upright bar, 3- move cross bar, 4- oblique pull bracket, 5- job platform, and 6- concrete is pre- Embedded part, 7- slideway, 8- slide bolt, 9- bottom slide track, the unrivalled fixing bolt of 10-.
Specific embodiment
In order to make the purpose of the utility model, technical solutions and advantages more clearly understood, below in conjunction with attached drawing and implementation Example, the present invention will be further described in detail.It should be appreciated that specific embodiment described herein is only to explain this Utility model is not used to limit the utility model.
As shown in Figure 1, the utility model embodiment is used for side slope construction Integral foldable scaffold, including fixation Cross bar 1, upright bar 2, removable cross bar 3, oblique pull bracket 4, job platform 5 and concrete embedded component 6;Wherein:
Two upright bars 2 are arranged in parallel, and pass through multiple 1 companies of being fixed of fixed transverse rod being arranged in parallel between upright bar 2 It connects, forms door type structure between upright bar 2 and fixed transverse rod 1;The scaffold includes multiple door type structures, is separately positioned on high slope Different height;Upright bar 2 is internally provided with slideway 7, moves 3 both ends of the cross bar slideway with two adjacent door type structures respectively 7 upper end is connected, and removable 3 both ends of cross bar can be slided up and down along upright bar 2 and locking;4 both ends of oblique pull bracket respectively with it is adjacent The lower ends of slideway 7 of two door type structures be connected, the both ends of oblique pull bracket 4 can slide up and down and locking along upright bar 2;Coagulation Native preburied component 6 is arranged on the different height position of high slope, and upright bar 2 is fixed on height by concrete embedded component 6 respectively The different height position of side slope;After door type structure is fixed, job platform 5 is fixedly mounted on removable cross bar 3.
As shown in Fig. 2, removable 3 both ends of cross bar are provided with slide bolt 8, slide bolt 8 and slideway 7 are cooperatively connected, Removable cross bar 3 realizes sliding and locking in upright bar 2 by slide bolt 8.
As shown in figure 3,4 both ends of oblique pull bracket are provided with slide bolt 8, slide bolt 8 and slideway 7 are cooperatively connected, tiltedly Bracket 4 is drawn to realize sliding and locking in upright bar 2 by slide bolt 8.
As shown in figure 4, being provided with bottom slide track 9 on concrete embedded part 6.2 bottom of upright bar is provided with bottom fixing bolt 10, bottom fixing bolt 10 and bottom slide track 9 are cooperatively connected, and upright bar 2 is realized by bottom fixing bolt 10 concrete embedded Sliding and locking on part 6.No less than 3 fixed transverse rods 1 are provided between two upright bars 2 in each door type structure.
In another specific embodiment of the utility model: using a kind of foldable integral type scaffold, pass through oblique pull Bracket and packaged type cross bar adjust the spacing between upright bar so that job platform can up and down adjustment, then fixing bolt, shape At firm job platform, convenient disassembly is set up, meets the needs of complicated construction environment.
A kind of primary structure for side slope construction Integral foldable scaffold is upright bar, mobile horizontal cross bar, Fixed transverse rod, oblique pull bracket, concrete embedded component composition.
Solve the above problems used scheme are as follows: is connected between upright bar and upright bar using fixed transverse rod, forms gate-type knot Structure, top uses packaged type cross bar between door type structure and door type structure, and mobile cross bar is fixed by bolts with upright bar, Cross bar top can shelve job platform, and job platform can adjust height, middle part by packaged type cross bar according to geographical environment It is connected using oblique pull bracket, oblique pull bracket one end is articulated with upright bar, and one end slidably, adapts to the geographical conditions of side slope complexity, whole Body is height-adjustable, and lower part is connected using built-in connection, forms stable side slope scaffolding structure.
Workflow:
Door type structure, top between door type structure and door type structure are formed by three fixed transverse rods between upright bar and upright bar It is connected using mobile cross bar, both ends are connect by slide bolt with upright bar, and middle part is connected using oblique pull bracket, oblique pull bracket one End is hingedly fixed with upright bar, the other end by using slide bolt, and when reaching certain slope, upright bar is vertical, fixed sliding spiral shell Platform is shelved on bolt, mobile cross bar top, so that it may form a firm platform structure.
Bottom of upright rod is connected using concrete embedded component, and slideway is arranged in preburied component top, and the setting of upright bar lower part is fixed Bolt, in use, upright bar can be slided up and down according to geographical environment by preburied component slideway, and adjustment height works as upright bar Vertically, fixing bolt can make it stable when reaching slope requirement.
Oblique pull bracket slide bolt need to be only loosened when disassembly, remove top packaged type cross bar, so that it may folding door type structure, Then fixed bottom when next time uses just can be used according to the fixed packaged type cross bar of construction requirement and oblique pull bracket.
The utility model has the beneficial effects that
1, the present invention is used for high slope rockmass scaffolding work, and Integral foldable scaffold has installing and dismounting fast side Just the characteristics of.
2, oblique pull bracket and the adjustable height of packaged type cross bar and angle, adapt to the construction of high slope rockmass engineering complexity Environment meets every demand of construction, strong applicability.
3, the utility model overall performance is good, and stability is strong, durable using reliable.
It should be understood that for those of ordinary skills, it can be modified or changed according to the above description, And all these modifications and variations all should belong to the protection scope of the appended claims for the utility model.

Claims (6)

1. one kind is used for side slope construction Integral foldable scaffold, which is characterized in that including fixed transverse rod (1), upright bar (2), cross bar (3), oblique pull bracket (4), job platform (5) and concrete embedded part (6) are moved;Wherein:
Two upright bars (2) are arranged in parallel, and are fixed by multiple fixed transverse rods (1) being arranged in parallel between upright bar (2) Connection, forms door type structure between upright bar (2) and fixed transverse rod (1);The scaffold includes multiple door type structures, is separately positioned on The different height of high slope;Upright bar (2) is internally provided with slideway (7), move cross bar (3) both ends respectively with two adjacent doors The upper end of the slideway (7) of formula structure is connected, and removable cross bar (3) both ends can be slided up and down along upright bar (2) and locking;Oblique pull branch Frame (4) both ends are connected with the lower end of the slideway (7) of two adjacent door type structures respectively, and the both ends of oblique pull bracket (4) can edge Upright bar (2) slides up and down and locking;Concrete embedded part (6) is arranged on the different height position of high slope, and upright bar (2) is respectively The different height position of high slope is fixed on by concrete embedded part (6);After door type structure is fixed, job platform (5) is fixed It is mounted on removable cross bar (3).
2. according to claim 1 be used for side slope construction Integral foldable scaffold, which is characterized in that removable cross Bar (3) both ends are provided with slide bolt (8), and slide bolt (8) and slideway (7) are cooperatively connected, and removable cross bar (3) pass through cunning Dynamic bolt (8) realize sliding and locking on upright bar (2).
3. according to claim 1 be used for side slope construction Integral foldable scaffold, which is characterized in that oblique pull bracket (4) both ends are provided with slide bolt (8), and slide bolt (8) and slideway (7) are cooperatively connected, and oblique pull bracket (4) passes through sliding spiral shell Bolt (8) realizes sliding and locking on upright bar (2).
4. according to claim 1 be used for side slope construction Integral foldable scaffold, which is characterized in that concrete is pre- Bottom slide track (9) are provided on embedded part (6).
5. according to claim 4 be used for side slope construction Integral foldable scaffold, which is characterized in that upright bar (2) Bottom is provided with bottom fixing bolt (10), and bottom fixing bolt (10) and bottom slide track (9) are cooperatively connected, and upright bar (2) passes through Bottom fixing bolt (10) realizes sliding and locking on concrete embedded part (6).
6. according to claim 1 be used for side slope construction Integral foldable scaffold, which is characterized in that each gate-type No less than 3 fixed transverse rods (1) are provided between two upright bars (2) in structure.
CN201820387427.5U 2018-03-21 2018-03-21 One kind being used for side slope construction Integral foldable scaffold Expired - Fee Related CN208294041U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820387427.5U CN208294041U (en) 2018-03-21 2018-03-21 One kind being used for side slope construction Integral foldable scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820387427.5U CN208294041U (en) 2018-03-21 2018-03-21 One kind being used for side slope construction Integral foldable scaffold

Publications (1)

Publication Number Publication Date
CN208294041U true CN208294041U (en) 2018-12-28

Family

ID=64694578

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820387427.5U Expired - Fee Related CN208294041U (en) 2018-03-21 2018-03-21 One kind being used for side slope construction Integral foldable scaffold

Country Status (1)

Country Link
CN (1) CN208294041U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109653479A (en) * 2019-01-09 2019-04-19 中国冶集团有限公司 The whole adjustable scaffold of side slope construction
CN111005543A (en) * 2019-11-21 2020-04-14 中欧国际建工集团有限公司 Adjustable door type formwork system and construction method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109653479A (en) * 2019-01-09 2019-04-19 中国冶集团有限公司 The whole adjustable scaffold of side slope construction
CN111005543A (en) * 2019-11-21 2020-04-14 中欧国际建工集团有限公司 Adjustable door type formwork system and construction method thereof
CN111005543B (en) * 2019-11-21 2021-08-06 中欧国际建工集团有限公司 Construction method of adjustable door type formwork system

Similar Documents

Publication Publication Date Title
CN208294041U (en) One kind being used for side slope construction Integral foldable scaffold
CN209011579U (en) A kind of adjustable vertical pump line support frame
CN205590174U (en) Handling support frame for building
CN201129027Y (en) Two-hinge-turning-plate guard rail for widening scaffold
CN103104186B (en) Outdoor operation ladder
CN105479412B (en) A kind of rudder blade mounting tool
CN201671315U (en) Adjustable scaffold
CN203640127U (en) Sunshade for operation platform
CN210918316U (en) Elevator shaft opening safety protection device
CN208310154U (en) A kind of construction scaffold
CN110104205A (en) A kind of aviation working stand
CN203890758U (en) Floor type folding clothes hanger
CN205822584U (en) Adjustable high strength I-beam structure
CN201649607U (en) Overhung-type outer wall scaffold
CN209024965U (en) A kind of adjustable anticollision wall form
CN205135390U (en) Fitment is with ladder
CN209428070U (en) A kind of overhead job platform of bridge construction
CN209277575U (en) A kind of protection canopy with buffer unit
CN207144430U (en) A kind of scalable operating platform
CN208571420U (en) Cable channel cover plate lifts lift tool
CN207110415U (en) A kind of building construction scaffold being easily installed
CN205562179U (en) Convenient to carry's test stand
CN204357085U (en) Pin-connected panel operating platform
CN205422745U (en) Tunnel lining trolley
CN213061709U (en) Hanging basket for road and bridge construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181228

CF01 Termination of patent right due to non-payment of annual fee