CN208272572U - A kind of temporary cable stringer - Google Patents
A kind of temporary cable stringer Download PDFInfo
- Publication number
- CN208272572U CN208272572U CN201820516335.2U CN201820516335U CN208272572U CN 208272572 U CN208272572 U CN 208272572U CN 201820516335 U CN201820516335 U CN 201820516335U CN 208272572 U CN208272572 U CN 208272572U
- Authority
- CN
- China
- Prior art keywords
- upright bar
- lower upright
- temporary cable
- chock
- temporary
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000009434 installation Methods 0.000 claims abstract description 24
- 238000005520 cutting process Methods 0.000 claims abstract description 13
- 229910000831 Steel Inorganic materials 0.000 claims description 32
- 239000010959 steel Substances 0.000 claims description 32
- 238000010276 construction Methods 0.000 abstract description 6
- 238000000034 method Methods 0.000 abstract description 4
- 230000005484 gravity Effects 0.000 description 5
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 2
- 230000004888 barrier function Effects 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000005611 electricity Effects 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 238000003466 welding Methods 0.000 description 2
- 239000002023 wood Substances 0.000 description 2
- 229910001018 Cast iron Inorganic materials 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 229910052742 iron Inorganic materials 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 239000004033 plastic Substances 0.000 description 1
- 229920003023 plastic Polymers 0.000 description 1
- 230000001737 promoting effect Effects 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
The utility model discloses a kind of temporary cable stringers, and the Screw Pile including screwing in installation ground, bottom is socketed in the lower upright bar at the top of the Screw Pile, the upper pright stanchion being co-axially inserted from the lower upright bar upper end;The temporary cable stringer further include the chock for being bolted in the Screw Pile, the cutting for extending transversely through the Screw Pile and the lower upright bar connecting portion, be connected on the upper pright stanchion for connecting the cable installation rack of temporary cable, the connection structure for limiting the upper pright stanchion and being fixed in the lower upright bar.The utility model is designed reasonably, structure is simple, stablizes, and is easily assembled to, conveniently moving, with tearing open with frame, is suitable for a variety of temporary cables and sets up environment, carries out effective protection to temporary cable used in power supply for construction process.
Description
Technical field
The utility model relates to engineering construction field, in particular to a kind of temporary cable stringer.
Background technique
Facing between construction site temporary electricity second level case and three-level case, between three-level case and construction equipment in engineering construction
When cable often along temporary facilities such as building, structures, scaffolds using the aerial laying of hook, or directly it is exposed on the ground.
The aerial laying of hook is limited by ambient enviroment, needs works as support;Directly it is exposed ground because long-time pull or
Personnel, equipment, which roll, can damage cable, and Electrical Safety does not ensure.Especially cable will pass through the barrier such as road, ditch, catch pit
When hindering object, it is desirable to which temporary cable is maked somebody a mere figurehead laying by suitable stringer.
Utility model content
The purpose of the utility model is to provide a kind of temporary cable stringer, rationally, structure is simple, stablizes, easily for design
In assembling, conveniently moving is adaptable with tearing open with frame, carries out effective protection to temporary cable used in power supply for construction process.
The above-mentioned technical purpose of the utility model has the technical scheme that
A kind of temporary cable stringer, the Screw Pile including screwing in installation ground, bottom is socketed in the screw thread stake top
The lower upright bar in portion, the upper pright stanchion being co-axially inserted from the lower upright bar upper end;The temporary cable stringer further includes being bolted in
The chock of the Screw Pile, the cutting for extending transversely through the Screw Pile and the lower upright bar connecting portion, be connected to it is described vertical
It is used to connect the cable installation rack of temporary cable, the connection for limiting the upper pright stanchion and being fixed in the lower upright bar on bar
Structure.
Screw Pile can be the screw thread member of cast iron quality, have sharp head, easily screw in installation ground, be device
Securely support is provided.Chock is used to increase the weight of device, reduces device center of gravity, improves mounting stability.Cutting material is iron
Matter can open the transversal openings being adapted with cutting at the top of Screw Pile and the bottom of lower upright bar, be connected in lower vertical rod sleeve
Screw Pile, and after the alignment of two through holes, cutting is laterally inserted into two through holes, completes the connection of lower upright bar and Screw Pile.It inserts
Both ends grow lower upright bar both ends, and cutting is pressed in Screw Pile by lower upright bar and the self weight for the part being connected thereto, connection
Stablize;On the other hand, cutting can be used as force application rod, and adjusting Screw Pile is facilitated to install ground with whole device in chock
Interior screw-in depth guarantees the connective stability of device to adapt to the ground of different hardness.
Preferably, the connection structure is included out in the axial link slot in the lower upright bar, along the lower upright bar axis
The multiple limiting slots communicated with the axial link slot opened up to interval are being convexly equipped in the upper pright stanchion surface with the axial direction
The gag lever post that link slot and the limiting slot are adapted.
Locating part can be a pin, be also possible to the columns nose bar such as bolt, upper pright stanchion is by the locating part in axial direction
The height of mobile adjusting upper pillar stand and the cable installation rack on upper pillar stand in link slot, so that the erection for adjusting temporary cable is high
Degree;After reaching the antenna height needed, gag lever post is caught in into limiting slot, to maintain the antenna height.
Preferably, the cable installation rack offers mounting groove, the cable installation rack for connecting temporary cable
It is equipped between the upper pright stanchion and is fastenedly connected circle.
Being fastenedly connected circle can be elastic rubber ring, and tensioner makes cable installation rack between cable installation rack and upper pillar stand
Stable connection, at the same make cable installation rack can sliding axially along upper pillar stand, be conveniently adjusted temporary cable antenna height.Electricity
The pattern of the mounting bar including multiple radial extensions can be set into cable mounting rack, and material can be rigid plastics, each to install
The mounting groove is set on item, is installed to adapt to multi-quantity while multidirectional temporary cable.
Preferably, the temporary cable stringer includes the encapsulating steel plate being coated on outside the chock, it is set to described
Encapsulate the pull ring of steel plate top surface and the lower upright bar surface.
Encapsulating steel plate by welding is coated on chock appearance, guarantee the durable of the structure of chock, prevent chock corrode or by
It destroys, and clump weight can be increased on encapsulating steel plate, to increase the weight of chock, make the center of gravity of device during installation more
Surely.Pull ring can be attached by welding, and the pull ring encapsulated on steel plate is connected with the pull ring in lower upright bar by rope, be improved
The mounting stability of device prevents the threaded connection of chock and screwed plug from failing.Pull ring may be configured as it is multiple, it is each to encapsulate on steel plate
Pull ring arrange that the pull ring in each lower upright bar is arranged along lower upright bar axially spaced-apart by benchmark axis uniform intervals of chock center, and
It is uniformly arranged under identical height multiple, chock and the rope of lower upright bar is made to connect stress more evenly, connected more stable.
Preferably, the temporary cable stringer further includes chock splicing block, the spelling of the chock splicing block is coated
Connect block encapsulating steel plate;The side and the encapsulating steel plate side are equipped with the connection grab of interworking.
Connection grab is respectively provided at the side of encapsulating steel plate and splicing block encapsulating steel plate, and chock splice plate is connected to pad
Wood, and can also continue to connect other chock splice plates by connecting grab except the chock splice plate being mounted on chock,
So as to any area for increasing chock as needed, increases the quantity and size that can prevent the pouring weight on chock, make to fill
The weight set is bigger, and center of gravity is more steady, and the erection of temporary cable is more stable.
Preferably, the splicing block encapsulating steel plate is equipped with the pull ring.
Pull ring can be set to chock splicing block center, it is connect with the pull ring in lower upright bar by rope, guarantee that chock is spelled
The position for connecing block is stablized, and prevents the connection of chock splicing block and chock from loosening.
Preferably, the lower upright bar, the upper pright stanchion is thin-wall steel tube, the inner hole aperture of the lower upright bar and it is described on
The outer diameter of upright bar is adapted.
In conclusion the utility model has the following beneficial effects:
1, be threaded connection or plug connection between each structure of the utility model, dismount conveniently moving, can with tear open with
Frame, it is adaptable.
2, the utility model is slided in the axial link slot of lower upright bar by upper pright stanchion and cable installation rack is upper vertical
The adjustable temporary cable antenna height of sliding in bar meets the erection requirement to temporary cable different height.
3, the utility model is adapted to difference by adjustable screw-in depth of the Screw Pile in chock of rotation of cutting
The ground of hardness, so that it is guaranteed that the stability of device.Such as it is deep for the ground screw-in depth such as soil property, rubble, for cement,
The ground such as concrete, rock, screw.
4, the utility model increases chock area, places counterweight on chock by splicing chock splicing block in chock side
Block is connected with rope between chock and chock splicing block and the pull ring of lower upright bar to increase weight, lower the center of gravity, device can be improved
Stability, for ground out-of-flatness, Screw Pile can not anchor on the ground, wind-force is larger etc., and situations are adaptable.
5, the utility model, which can set up cable and efficiently solve temporary cable, does not have works support, and cable will pass through
The problem of barriers such as road, ditch, catch pit.
6, the low manufacture cost of the utility model, using effect is good, convenient for promoting the use of.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is the cross-sectional view of the utility model;
Fig. 3 is structural schematic diagram when the utility model is connected with chock splicing block.
In figure:
1- encapsulates steel plate;2- chock;3- Screw Pile;Upright bar under 4-;41- axial direction link slot;42- limiting slot;5- upper pright stanchion;
6- cutting;7- is fastenedly connected circle;8- cable installation rack;81- mounting groove;9- gag lever post;10- connection grab;11- pull ring;12- is spelled
Connect block encapsulating steel plate;13- chock splicing block.
Specific embodiment
The utility model is described in more detail for scheme with reference to the accompanying drawing and preferably.
This specific embodiment is only the explanation to the utility model, is not limitations of the present invention, ability
Field technique personnel can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but
As long as all by the protection of Patent Law in the scope of the claims of the utility model.
Embodiment: a kind of temporary cable stringer as shown in Figs. 1-2, the Screw Pile 3 including screwing in installation ground, bottom
Portion is socketed in the lower upright bar 4 at the top of Screw Pile, the upper pright stanchion 5 being co-axially inserted from lower upright bar upper end;Temporary cable stringer is also
Including being bolted in the chock 2 of Screw Pile, the cutting 6 for extending transversely through Screw Pile and lower upright bar connecting portion, being connected on upper pright stanchion
For connecting the cable installation rack 8 of temporary cable, the connection structure for limiting upper pright stanchion and being fixed in lower upright bar.
Connection structure includes out the multiple and axis in the axial link slot 41 in lower upright bar, opened up along lower upright bar axially spaced-apart
The limiting slot 42 communicated to link slot is convexly equipped in the gag lever post 9 adaptable with axial link slot and limiting slot on upper pright stanchion surface;
Cable installation rack is offered to be equipped between mounting groove 81, cable installation rack and upper pright stanchion for connecting temporary cable and is fastenedly connected
Circle 7;Temporary cable stringer includes the encapsulating steel plate 1 being coated on outside chock, is set to encapsulating steel plate top surface and lower upright bar surface
Pull ring 11.
Lower upright bar 4, upper pright stanchion 5 are thin-wall steel tube, and the inner hole aperture of lower upright bar and the outer diameter of upper pright stanchion are adapted.
As shown in figure 3, temporary cable stringer further includes chock splicing block 13, the splicing block packet of chock splicing block is coated
Seal steel plate 12;Side and encapsulating steel plate side are equipped with the connection grab 10 of interworking;Splicing block encapsulates steel plate and is equipped with pull ring 11.
The temporary cable stringer is mainly used for temporary cable erection, in use, be first installed device assembly, then
Temporary cable is placed in the mounting groove of cable installation rack, height of the 7 adjustable temporary cables of circle on upper pright stanchion is fastenedly connected
Gag lever post 9 after height is adjusted in upright bar 4 under then sliding by connection structure, is placed in limiting slot 42 fixed, most back spin by degree
Turn cutting 6, adjusts screw-in depth of the Screw Pile 3 in chock 1 and installation ground, it is ensured that device is stablized.
In the present embodiment, the chock splicing block 13 encapsulated with splicing block encapsulating steel plate 12 and the pad encapsulated with encapsulating steel plate 2
Wood 1 is connected by connection grab 10, to increase chock area;It is described to be placed on splicing block encapsulating steel plate 12 and encapsulating steel plate 2
Clump weight is to increase weight, lower the center of gravity;Pull ring between the splicing block encapsulating steel plate 12 and encapsulating steel plate 2 and lower upright bar 4
Between 11 with rope connection, device stability can be improved, for ground out-of-flatness, Screw Pile can not anchor on the ground, wind-force compared with
The situations such as big are adaptable.
In the present embodiment, the chock 2 and Screw Pile 3, Screw Pile 3 and lower upright bar 4, lower upright bar 4 and upper pright stanchion 5, cutting 6
With lower upright bar 4, Screw Pile 3, gag lever post 9 and upper pright stanchion 5, are fastenedly connected circle 7 and upper pright stanchion 5 is that threaded connection or grafting connect
It connects, dismounts conveniently moving, it can be adaptable with tearing open with frame.
Claims (7)
1. a kind of temporary cable stringer, it is characterised in that: the Screw Pile (3) including screwing in installation ground, bottom is socketed in
Lower upright bar (4) at the top of the Screw Pile, the upper pright stanchion (5) being co-axially inserted from the lower upright bar upper end;The temporary cable frame
If device further includes the chock (2) for being bolted in the Screw Pile, extends transversely through the Screw Pile and the lower upright bar connecting portion
Cutting (6), be connected on the upper pright stanchion the cable installation rack (8) for connecting temporary cable, the upper pright stanchion limited
Position and the connection structure being fixed in the lower upright bar.
2. a kind of temporary cable stringer according to claim 1, it is characterised in that: the connection structure include open in
Axial link slot (41) in the lower upright bar, the multiple and axial link slot phase opened up along the lower upright bar axially spaced-apart
Logical limiting slot (42) is convexly equipped in the limit adaptable with the axial link slot and the limiting slot on the upper pright stanchion surface
Bar (9).
3. a kind of temporary cable stringer according to claim 1, it is characterised in that: the cable installation rack offers
It is equipped between mounting groove (81), the cable installation rack and the upper pright stanchion for connecting temporary cable and is fastenedly connected circle (7).
4. a kind of temporary cable stringer according to claim 1, it is characterised in that: the temporary cable stringer
Pull ring including the encapsulating steel plate (1) being coated on outside the chock, set on encapsulating the steel plate top surface and the lower upright bar surface
(11).
5. a kind of temporary cable stringer according to claim 4, it is characterised in that: the temporary cable stringer
Further include chock splicing block (13), coats splicing block encapsulating steel plate (12) of the chock splicing block;The side and the packet
Seal the connection grab (10) that steel plate side is equipped with interworking.
6. a kind of temporary cable stringer according to claim 5, it is characterised in that: on the splicing block encapsulating steel plate
Equipped with the pull ring (11).
7. a kind of temporary cable stringer according to claim 1, it is characterised in that: the lower upright bar (4), it is described on
Upright bar (5) is thin-wall steel tube, and the inner hole aperture of the lower upright bar and the outer diameter of the upper pright stanchion are adapted.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820516335.2U CN208272572U (en) | 2018-04-12 | 2018-04-12 | A kind of temporary cable stringer |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820516335.2U CN208272572U (en) | 2018-04-12 | 2018-04-12 | A kind of temporary cable stringer |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208272572U true CN208272572U (en) | 2018-12-21 |
Family
ID=64677837
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820516335.2U Expired - Fee Related CN208272572U (en) | 2018-04-12 | 2018-04-12 | A kind of temporary cable stringer |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208272572U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109830917A (en) * | 2019-03-15 | 2019-05-31 | 中国三冶集团有限公司 | A kind of device and method setting up temporary cable |
CN112234511A (en) * | 2020-09-30 | 2021-01-15 | 国网河南省电力公司南召县供电公司 | Temporary cable erecting device |
-
2018
- 2018-04-12 CN CN201820516335.2U patent/CN208272572U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109830917A (en) * | 2019-03-15 | 2019-05-31 | 中国三冶集团有限公司 | A kind of device and method setting up temporary cable |
CN112234511A (en) * | 2020-09-30 | 2021-01-15 | 国网河南省电力公司南召县供电公司 | Temporary cable erecting device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8505265B2 (en) | Power line tower alignment method | |
US8407967B2 (en) | Apparatus and method for an adjustable column | |
CN208272572U (en) | A kind of temporary cable stringer | |
US20080230108A1 (en) | Solar panel apparatus and method utilizing pounded vertical supports | |
JP2014517170A (en) | Frame support | |
CN211257011U (en) | Triaxial stirring stake stagnant water curtain structure | |
DE102005003972A1 (en) | Offshore-wind turbine foundation, has tower stabilized in its position by cable wirings and joint provided as connection between tower pedestal/tower lower side and bearing pole and allowing slight tilting movements of foundation supports | |
CN110894759A (en) | Power transmission line erected electric power telegraph pole | |
US5081804A (en) | Power line pylon and lamp post | |
CN207632371U (en) | A kind of soft soil foundation Super High tower crane firm banking | |
KR101353488B1 (en) | Multiple supporting file foundation | |
CN204385762U (en) | A kind of Rock Bolt Foundation structure | |
CN110158498B (en) | Construction method of elastic passive protective net upright post structure | |
CN210946537U (en) | Elastic passive protective net upright post structure | |
CN106495026A (en) | Attachment built temporarily by construction tower crane | |
CN104532873A (en) | Rock anchor rod foundation structure | |
FI86755B (en) | STOLPE. | |
US8490287B2 (en) | Fence end spacer apparatus and method for use | |
US20090064633A1 (en) | Telescopic Post and Bracing System for Bedrock Locations | |
CN206143797U (en) | Overhead transmission line foundation | |
CN206328867U (en) | A kind of post bottom steel structure member | |
RU153340U1 (en) | THE BASE OF REUSABLE USE UNDER THE COMPOSITE SUPPORT OF THE ELECTRIC TRANSMISSION LINE | |
CN219219360U (en) | Steel construction assembled building for building engineering | |
CN215888009U (en) | Town road crossing is with limit for height device | |
CN214033674U (en) | Steel structure supporting column with good stability |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder |
Address after: 313000 4th Floor, 666 Huanzhu Road, Wuxing District, Huzhou City, Zhejiang Province Patentee after: NUCLEAR INDUSTRY WELL AND ROADWAY CONSTRUCTION GROUP Co.,Ltd. Address before: 313000 4th Floor, 666 Huanzhu Road, Wuxing District, Huzhou City, Zhejiang Province Patentee before: NUCLEAR SHAFT AND ROADWAY ENGINEERING Group Corp. |
|
CP01 | Change in the name or title of a patent holder | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20181221 |
|
CF01 | Termination of patent right due to non-payment of annual fee |