CN208251606U - Scaffold and electricity tower fixed fastener in overhead operation - Google Patents

Scaffold and electricity tower fixed fastener in overhead operation Download PDF

Info

Publication number
CN208251606U
CN208251606U CN201820747210.0U CN201820747210U CN208251606U CN 208251606 U CN208251606 U CN 208251606U CN 201820747210 U CN201820747210 U CN 201820747210U CN 208251606 U CN208251606 U CN 208251606U
Authority
CN
China
Prior art keywords
fastener
scaffold
steel
bolt
steel plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820747210.0U
Other languages
Chinese (zh)
Inventor
吴伟明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dongguan Changying Power Engineering Co ltd
Guangdong Power Grid Co Ltd
Dongguan Power Supply Bureau of Guangdong Power Grid Co Ltd
Original Assignee
Dongguan Changying Power Engineering Co ltd
Guangdong Power Grid Co Ltd
Dongguan Power Supply Bureau of Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dongguan Changying Power Engineering Co ltd, Guangdong Power Grid Co Ltd, Dongguan Power Supply Bureau of Guangdong Power Grid Co Ltd filed Critical Dongguan Changying Power Engineering Co ltd
Priority to CN201820747210.0U priority Critical patent/CN208251606U/en
Application granted granted Critical
Publication of CN208251606U publication Critical patent/CN208251606U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Clamps And Clips (AREA)

Abstract

The embodiment of the utility model discloses scaffold and electricity tower fixed fastener in overhead work, including first steel sheet, first bolt, mounting, second bolt, first fastener, third bolt, second steel sheet, fastener, fourth bolt, second fastener, sheetmetal, opening, electricity tower angle steel, scaffold frame and metal hemisphere. The right-angle structure formed by the two first steel plates of the utility model is matched with the fastener, so that the electric tower angle steel can be occluded, the connection between the fastener and the electric tower angle steel is more compact, and the problem of unstable connection caused by connecting the scaffold and the electric tower angle steel by using the traditional fastener is also avoided; the device is provided with first fastener, second fastener and third fastener, and its direction of first fastener and second fastener all can rotate, and the third fastener direction is fixed to satisfy the different operation requirement of user, the device simple structure, convenient to use is fit for using widely.

Description

Scaffold and pylon attachment fastener in a kind of aerial operation
Technical field
The utility model relates to scaffold and pylons in Architectural Equipment applied technical field more particularly to a kind of aerial operation Attachment fastener.
Background technique
Pylon, the tower-like building such as trapezoidal or triangle, height are usually 25-40 meters, are steel frame construction, and pylon is built more It is located at the power plant in field, near power distribution station, it is the critical facility of power department, trolley wire and can play protection and support Effect.Design, manufacture, installation, maintenance and the quality testing of electric power tower are the important guarantors of modern power systems operation and development Barrier.
When building installation pylon, often to use scaffold and carry out aerial operation, in aerial operation, scaffold Fixation, often use support rod, but in soil, using the poor effect of support rod, scaffold cannot be stablized, it is traditional Scaffold clasp, since its oral area is circle, and pylon is made of angle steel, so traditional scaffold clasp can not be in pylon Upper fixed scaffold;And traditional scaffold only one attachment fastener, it tends not to meet using a variety of demands only.Cause This, provides scaffold and pylon fixed card buckle in a kind of aerial operation regarding to the issue above.
Utility model content
The utility model embodiment provides scaffold and pylon attachment fastener in a kind of aerial operation, including two First steel plate, affixed by the first bolt between one end of two first steel plates, the side of two first steel plates is logical It crosses fixing piece and is rotatablely connected the first fastener, the one end of two first steel plates away from each other passes through third bolt installation second Steel plate;
Second steel plate is close to the affixed fastener in the side of the first steel plate;Two close to the first steel plate of the fastener Side is respectively provided with sheet metal;Side of second steel plate far from fastener the second fastener is installed by the 4th bolt.
Preferably, right angle configuration between two first steel plates.
Preferably, the second bolt is set on first fastener.
Preferably, right angle configuration between two sheet metals, and the angular bisector between described two sheet metals with Angular bisector between two first steel plates is located along the same line.
Preferably, the third bolt-through is opened in the opening on first steel plate.
Preferably, the surface of the sheet metal is uniformly arranged several metal hemisphere.
Preferably, pylon angle steel has been gripped between the fastener and two first steel plates;Two described Affixed scaffold among one fastener and second fastener.
Preferably, the fixing piece is " I-shaped " structure.
The beneficial effects of the utility model are:
1. the right-angle structure matching fastener that two first steel plates of the utility model are formed, can be engaged pylon angle steel, Keep the connection between the fastener and pylon angle steel even closer, also avoids connecting scaffold and pylon angle steel using traditional fastener Instability problem is connected caused by connecing;
2. the device is provided with the first fastener, the second fastener and third fastener, the first fastener and its direction of the second fastener are equal It can rotate, third fastener direction is fixed, and to meet the different requirement of user, the apparatus structure is simple, and it is easy to use, It is suitble to promote the use of.
Detailed description of the invention
In order to illustrate the embodiment of the utility model or the technical proposal in the existing technology more clearly, below will be to embodiment Or attached drawing needed to be used in the description of the prior art is briefly described, it should be apparent that, the accompanying drawings in the following description is only It is some embodiments of the utility model, for those of ordinary skill in the art, before not making the creative labor property It puts, can also be obtained according to these attached drawings other attached drawings.
Fig. 1 is the utility model overlooking structure diagram;
Fig. 2 is the utility model overall structure diagram;
Fig. 3 is the utility model sheet metal structure schematic diagram.
In figure: 1, first steel plate, the 2, first bolt, 3, fixing piece, the 4, second bolt, the 5, first fastener, 6, third bolt, 7, the second steel plate, 8, fastener, the 9, the 4th bolt, the 10, second fastener, 11, sheet metal, 12, opening, 13, pylon angle steel, 14, Scaffold, 15, metal hemisphere.
Specific embodiment
In order to make those skilled in the art better understand the scheme of the utility model, with reference to the accompanying drawing and specific implementation The utility model is described in further detail for mode.Obviously, described embodiment is only the utility model a part Embodiment, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art are not doing Every other embodiment obtained under the premise of creative work out, fall within the protection scope of the utility model.
It please refers to shown in Fig. 1-3, scaffold and pylon attachment fastener in a kind of aerial operation, including two the first steel plates 1, It is affixed by the first bolt 2 between one end of two first steel plates 1, convenient for allowing between two the first steel plates 1 into right angle knot The side of structure, two first steel plates 1 is rotatablely connected the first fastener 5 by fixing piece 3, convenient for fixed scaffold, two institutes It states the one end of the first steel plate 1 away from each other and passes through the second steel plate 7 of installation of third bolt 6, be easily installed fastener 8;
Second steel plate 7 is solid convenient for fastener 8 and the first steel plate 1 close to the affixed fastener 8 in the side of the first steel plate 1 It is scheduled on pylon angle steel 13;The fastener 8 is respectively provided with sheet metal 11 close to two sides of the first steel plate 1, convenient for setting gold Belong to cricket 15;The second fastener 10 is installed by the 4th bolt 9 in side of second steel plate 7 far from fastener 8, is convenient for fixed feet Hand cradle 14.
As a kind of technical optimization scheme of the utility model, right angle configuration between two first steel plates 1 makes this Fastener is more bonded pylon angle steel 13.
As a kind of technical optimization scheme of the utility model, second bolt 4 is set on first fastener 5, convenient for solid Determine scaffold 14.
As a kind of technical optimization scheme of the utility model, right angle configuration between two sheet metals 11, and institute The angular bisector stated between the angular bisector between two sheet metals 11 and two first steel plates 1 is located along the same line, Pylon angle steel 13 is pressed together on two the first steel plates 1 convenient for fastener 8.
As a kind of technical optimization scheme of the utility model, the third bolt 6, which runs through, to be opened on first steel plate 1 Opening 12, be conveniently adjusted the position of third bolt 6.
As a kind of technical optimization scheme of the utility model, the surface of the sheet metal 11 is uniformly arranged several metals half Ball 15, convenient for providing frictional force to fix pylon angle steel 13.
As a kind of technical optimization scheme of the utility model, pressed from both sides between the fastener 8 and two first steel plates 1 It holds and is fixed with pylon angle steel 13;Two first fasteners 5 and affixed scaffold 14 among second fastener 10, convenient for making Scaffold 14 and pylon angle steel 13 are fixed.
As a kind of technical optimization scheme of the utility model, the fixing piece 3 is " I-shaped " structure, convenient for making first Fastener 5 is rotated relative to the first steel plate 1./
When the utility model is used, third bolt 6 is dismantled, the second steel plate 7 is removed, two the first steel plates 1 are bonded After on pylon angle steel 13, the second steel plate 7 is installed by third bolt 6 to two the first steel plates 1, third bolt is adjusted Behind 6 position, third bolt 6 is tightened, keyed bolt 6 is constantly tightened, and the second steel plate 7 is constantly to the direction position of pylon angle steel 13 It moves, the second steel plate 7 drives fastener 8 to be displaced to 13 direction of pylon angle steel, the work of fastener 8 and two the first steel plates 1 in pressure It is fixed under on pylon angle steel 13;Wherein, metal hemisphere 15 plays the role of increasing frictional force, and opening 12 plays adjustment and limits The effect of 6 position of third bolt processed;
Scaffold is fixed in the first fastener 5 and the second fastener 10, and is consolidated by the second bolt 4 with the 4th bolt 9 Determine scaffold.
Scaffold in a kind of aerial operation provided by the utility model and pylon attachment fastener have been carried out in detail above It introduces, for those of ordinary skill in the art, based on the idea of the embodiment of the present invention, in specific embodiment and application There will be changes in range, in conclusion the content of the present specification should not be construed as a limitation of the present invention.

Claims (8)

1. scaffold and pylon attachment fastener in a kind of aerial operation, including two the first steel plates (1), it is characterised in that: two Affixed by the first bolt (2) between one end of first steel plate (1), the side of two first steel plates (1) passes through solid Determine part (3) rotation connection the first fastener (5), the one end of two first steel plates (1) away from each other passes through third bolt (6) The both ends of second steel plate (7) are installed;
Side affixed fastener (8) of second steel plate (7) close to the first steel plate (1);The fastener (8) is close to the first steel Two sides of plate (1) are respectively provided with sheet metal (11);Second steel plate (7) passes through the 4th spiral shell far from the side of fastener (8) Bolt (9) installs the second fastener (10).
2. scaffold and pylon attachment fastener in a kind of aerial operation according to claim 1, it is characterised in that: two institutes State right angle configuration between the first steel plate (1).
3. scaffold and pylon attachment fastener in a kind of aerial operation according to claim 1, it is characterised in that: described the Second bolt (4) are set on one fastener (5).
4. scaffold and pylon attachment fastener in a kind of aerial operation according to claim 1, it is characterised in that: two institutes Right angle configuration between sheet metal (11) is stated, and angular bisector and two first steel between described two sheet metals (11) Angular bisector between plate (1) is located along the same line.
5. scaffold and pylon attachment fastener in a kind of aerial operation according to claim 1, it is characterised in that: described the Three bolts (6), which run through, to be opened in the opening (12) on first steel plate (1).
6. scaffold and pylon attachment fastener in a kind of aerial operation according to claim 1, it is characterised in that: the gold The surface for belonging to piece (11) is uniformly arranged several metal hemisphere (15).
7. scaffold and pylon attachment fastener in a kind of aerial operation according to claim 1, it is characterised in that: described tight Pylon angle steel (13) have been gripped between firmware (8) and two first steel plates (1);Two first fasteners (5) with The intermediate affixed scaffold (14) of second fastener (10).
8. scaffold and pylon attachment fastener in a kind of aerial operation according to claim 1, it is characterised in that: described solid Determining part (3) is " I-shaped " structure.
CN201820747210.0U 2018-05-18 2018-05-18 Scaffold and electricity tower fixed fastener in overhead operation Active CN208251606U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820747210.0U CN208251606U (en) 2018-05-18 2018-05-18 Scaffold and electricity tower fixed fastener in overhead operation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820747210.0U CN208251606U (en) 2018-05-18 2018-05-18 Scaffold and electricity tower fixed fastener in overhead operation

Publications (1)

Publication Number Publication Date
CN208251606U true CN208251606U (en) 2018-12-18

Family

ID=66480804

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820747210.0U Active CN208251606U (en) 2018-05-18 2018-05-18 Scaffold and electricity tower fixed fastener in overhead operation

Country Status (1)

Country Link
CN (1) CN208251606U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112177420A (en) * 2020-09-24 2021-01-05 广东电网有限责任公司东莞供电局 Anti-drop fastener for electric power iron tower

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112177420A (en) * 2020-09-24 2021-01-05 广东电网有限责任公司东莞供电局 Anti-drop fastener for electric power iron tower
CN112177420B (en) * 2020-09-24 2021-09-17 广东电网有限责任公司东莞供电局 Anti-drop fastener for electric power iron tower

Similar Documents

Publication Publication Date Title
CN202646935U (en) Universal rotating cable support
CN208251606U (en) Scaffold and electricity tower fixed fastener in overhead operation
CN208904578U (en) A kind of buckle-type slot type straight-through cable gantry
CN208521742U (en) A kind of device for fixing transformer
CN209329176U (en) A kind of power distribution cabinet copper bar quick lap joint device
CN205592493U (en) An assembled gallows
CN209443893U (en) A kind of building construction protective fence
CN208830712U (en) A kind of cantilever form
CN204012417U (en) One is applicable to two circuit intelligent power distribution equipment arrangement
CN106329394A (en) Line-tightening apparatus used in electric power installation
CN206259498U (en) A kind of electrical tilt antenna structure of integrated built-in RCU
CN209562057U (en) A kind of reinforced cable bridge
CN104165973A (en) Online detection device for sulfur hexafluoride gas of high-altitude circuit breaker and detection method
CN208939533U (en) A kind of outdoor abrupt slope conduit line segmented combination plate
CN208874645U (en) A kind of monitoring camera of rail mounted
CN209163581U (en) Connection structure of the computer room on communication iron tower
CN209027430U (en) Ovality detection device
CN211040397U (en) Intelligent visual detection structure support convenient to adjust
CN207624892U (en) A kind of GPS antenna mounting structure for outdoor cabinet
CN214404952U (en) Anti-seismic support and hanger with adjusting structure and convenient to splice
CN206906428U (en) Sensor stand and installation tool
CN205242721U (en) Wallboard bracket with adjustable
CN205037908U (en) Ultrasonic sensor installation device
CN205242724U (en) Shower room pull rod with angle modulation function
CN214033189U (en) Rail connecting buckle for rail transit

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant