CN208237218U - For the interim pipe holder in place of pipeline - Google Patents
For the interim pipe holder in place of pipeline Download PDFInfo
- Publication number
- CN208237218U CN208237218U CN201820519930.1U CN201820519930U CN208237218U CN 208237218 U CN208237218 U CN 208237218U CN 201820519930 U CN201820519930 U CN 201820519930U CN 208237218 U CN208237218 U CN 208237218U
- Authority
- CN
- China
- Prior art keywords
- cross bar
- pipeline
- fixed
- small cross
- sunpender
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
A kind of pipe holder temporarily in place for pipeline, include: the small cross bar of several carryings being horizontally fixed in jacket H profile steel respectively, be fixed on upper and lower two sunpenders carried on small cross bar, wherein, a square framework type structure is formed between the small cross bar of several carryings and the sunpender being fixed on the small cross bar of upper and lower two carryings;The frame of limit cross bar and bottom bar is respectively fixed on sunpender;It is equipped with chock on bottom bar, the target pipeline being supported is installed on chock.The problem of the utility model, as supporting point, simplifies structure by girder steel, consumes a large amount of manpower and material resources when not only solving pipeline installation, improves work efficiency;Moreover, the problem of also solving pollution existing structure and equipment;Different-diameter pipeline is met in different trends and the interim needs in place of absolute altitude.
Description
Technical field
The utility model relates to pipe holder more particularly to a kind of pipe holders temporarily in place for pipeline.Belong to ocean work
Pipeline installing area in journey equipment.
Background technique
Currently, being influenced in marine engineering equipment manufacturing industry by equipment and pipeline arrival, based on the need for shortening construction period
It wants, the needs of part pipeline are temporarily in place, the row installation again after equipment or other pipelines are in place.In addition, the pipeline needs that evening arrives
Interspersed main structure installation, it is narrow that this " trying to make a match " way is often limited to working space, needs to build interim pipeline support.
In general, using L-type H profile steel as temporary support, cut off after pipeline is installed, then by temporary support.But the above method
It has the disadvantage in that
(1), since the pipeline temporarily installed in place is numerous, temporary support is done using H profile steel and needs to consume a large amount of steel construction
And welding material;
(2), since the caliber of pipeline is different, absolute altitude and coordinate are various, many kinds of of interim H profile steel support is caused;
(3), due to needing to carry out polishing derusting before welding temporary support, a large amount of manpower and material resources are not only consumed, moreover, it is polished
Generated clast can also be polluted in modeling block;
(4) after pipeline is installed, it is also necessary to cut off the temporary support of welding, and polish flat again;
(5) polishing position (paint has been destroyed) is also needed to carry out coating again.
Utility model content
The main purpose of the utility model is to overcome disadvantages mentioned above of the existing technology, and provide a kind of for pipeline
Interim pipe holder in place simplifies structure by girder steel as supporting point, and consumption is a large amount of when not only solving pipeline installation
Manpower and material resources the problem of, improve work efficiency;Moreover, the problem of also solving pollution existing structure and equipment;It meets
Different-diameter pipeline is in different trends and the interim needs in place of absolute altitude.
The purpose of this utility model is realized by the following technical solutions:
A kind of pipe holder temporarily in place for pipeline, it is characterised in that: include: to be horizontally fixed on jacket H-type respectively
The small cross bar of several carryings on steel, the sunpenders being fixed on the small cross bar of upper and lower two carryings, wherein the small cross bars of several carryings and
A square framework type structure is formed between the sunpender being fixed on the small cross bar of upper and lower two carryings;Limit is respectively fixed on sunpender
The frame of position cross bar and bottom bar;It is equipped with chock on bottom bar, the target pipeline being supported is installed on chock.
Upper and lower two small cross bars of carrying and sunpender fix by right-angle coupler, and the upper and lower of right-angle coupler divides
It She You not safety fastener.
The utility model has the beneficial effects that the utility model is due to the adoption of the above technical scheme, by girder steel as branch
The problem of support point simplifies structure, consumes a large amount of manpower and material resources when not only solving pipeline installation, improves work efficiency;
Moreover, the problem of also solving pollution existing structure and equipment;Different-diameter pipeline is met to face in different trends and absolute altitude
When needs in place.
Detailed description of the invention
Fig. 1-1 is the fixed small cross bar schematic front view of carrying below the utility model H profile steel.
Fig. 1-2 is the fixed small cross bar schematic side view of carrying below the utility model H profile steel.
Fig. 2-1 is the fixed schematic front view of the utility model sunpender.
Fig. 2-2 is the fixed schematic side view of the utility model sunpender.
Fig. 3-1 is the fixed schematic front view of the utility model bottom bar.
Fig. 3-2 is the fixed schematic side view of the utility model bottom bar.
Fig. 4-1 is that the utility model pipeline arranges schematic front view.
Fig. 4-2 is that the utility model pipeline arranges schematic side view.
Fig. 4-3 is the partial enlargement diagram in Fig. 4-2.
Fig. 5-1 is that the utility model limits the fixed schematic front view of cross bar.
Fig. 5-2 is that the utility model limits the fixed schematic side view of cross bar.
Fig. 6-1 is the fixed small cross bar schematic front view of carrying below the utility model H profile steel.
Fig. 6-2 is the fixed small cross bar schematic side view of carrying below the utility model H profile steel.
Fig. 7-1 is the fixed schematic front view of the utility model sunpender.
Fig. 7-2 is the fixed schematic side view of the utility model sunpender.
Fig. 8-1 is the fixed schematic front view of the utility model bottom bar.
Fig. 8-2 is the fixed schematic side view of the utility model bottom bar.
Fig. 9-1 is that the utility model pipeline arranges schematic front view.
Fig. 9-2 is that the utility model pipeline arranges schematic side view.
Figure 10-1 is that the utility model limits the fixed schematic front view of cross bar.
Figure 10-2 is that the utility model limits the fixed schematic side view of cross bar.
Major Symbol illustrates in figure:
1.H fashioned iron;2. fastener of hanging oneself from a beam;3. carrying small cross bar;4. safety fastener;5. right-angle coupler;6. sunpender;7. limit is horizontal
Bar;8. target pipeline;9. chock;10. bottom bar.
Specific embodiment
As shown in Fig. 1-Figure 10-2, the utility model includes: to be horizontally fixed on jacket H-type respectively using overarm fastener 2
The small cross bar 3 (the present embodiment is upper and lower two) of several carryings on steel 1 is fixed on upper and lower two carryings by right-angle coupler 5
Sunpender 6 on small cross bar 3, wherein be respectively fixed on sunpender 6 by several right-angle couplers 5 (the present embodiment is upper and lower two)
Limit the frame of cross bar 7 and bottom bar 10;It is equipped with chock 9 on bottom bar 10, the target being supported is installed on chock 9
Pipeline 8.
A side is formed between above-mentioned several sunpenders 6 for carrying small cross bar 3 and being fixed on the small cross bar 3 of upper and lower two carryings
Shape tower structure.
The upper and lower of above-mentioned right-angle coupler 5 is respectively equipped with safety fastener 4.
When the utility model is used, using following steps:
It is horizontally fixed on H profile steel beam 1 step 1: small cross bar 3 will be carried;
Step 2: sunpender 6 is fixed on the small cross bar 3 of upper and lower two carryings;
In order to increase the bearing capacity of sunpender 6, a safety fastener 4, safety fastener are added in the top for being close to right-angle coupler 5
4 can replace with dedicated safety fastener or with right-angle coupler;
Step 3: bottom bar 10 is fixed on sunpender 6, bottom bar 10 fixes position according to the position of target pipeline 8
Set determination;
In order to increase the bearing capacity of sunpender 6, a safety fastener 4, safety fastener are added in the lower section for being close to right-angle coupler 5
4 can replace with dedicated safety fastener or with right-angle coupler.
Step 4: chock 9 is placed on bottom bar 10, convenient for the uniform power transmission of target pipeline 8 in bottom bar 10.
Step 5: being fixed on sunpender 6 using two right-angle couplers 5 by cross bar 7 is limited after pre-positioned target pipeline 8.Limit
The fixation position of cross bar 7 is determined according to the position of target pipeline 8.
Above-mentioned H profile steel, overarm fastener, right-angle coupler, safety fastener are the prior art, and the technology of not specified (NS) is existing skill
Art, so it will not be repeated.
The above descriptions are merely preferred embodiments of the present invention, not makees in any form to the utility model
Limitation, it is made by the above technical examples according to the technical essence of the present invention it is any it is simple modification, equivalent variations with
Modification, is still within the scope of the technical solutions of the present invention.
Claims (2)
1. a kind of for the interim pipe holder in place of pipeline, it is characterised in that: include: to be horizontally fixed on jacket H profile steel respectively
On the small cross bar of several carryings, the sunpenders that are fixed on the small cross bar of upper and lower two carryings, wherein small cross bars of several carryings and solid
A square framework type structure is formed between the sunpender being scheduled on the small cross bar of upper and lower two carryings;Limit is respectively fixed on sunpender
The frame of cross bar and bottom bar;It is equipped with chock on bottom bar, the target pipeline being supported is installed on chock.
2. according to claim 1 for the interim pipe holder in place of pipeline, it is characterised in that: described upper and lower two are held
It carries small cross bar and sunpender is fixed by right-angle coupler, the upper and lower of right-angle coupler is respectively equipped with safety fastener.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820519930.1U CN208237218U (en) | 2018-04-13 | 2018-04-13 | For the interim pipe holder in place of pipeline |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820519930.1U CN208237218U (en) | 2018-04-13 | 2018-04-13 | For the interim pipe holder in place of pipeline |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208237218U true CN208237218U (en) | 2018-12-14 |
Family
ID=64583207
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820519930.1U Expired - Fee Related CN208237218U (en) | 2018-04-13 | 2018-04-13 | For the interim pipe holder in place of pipeline |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208237218U (en) |
-
2018
- 2018-04-13 CN CN201820519930.1U patent/CN208237218U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN209066791U (en) | A kind of wall surface dry-hang device | |
CN104060746B (en) | The anti-engineering method that supports of a kind of furred ceiling angle bar frame | |
CN202187457U (en) | Suspension apparatus of lower suspended ceiling of steel grating | |
CN204993169U (en) | Float floated counter weight support of photovoltaic | |
CN208237218U (en) | For the interim pipe holder in place of pipeline | |
CN203868523U (en) | Pipeline fixing structure of support and hanger assembly | |
CN203961091U (en) | The anti-bracing or strutting arrangement of a kind of furred ceiling angle bar frame and ceiling structure thereof | |
CN105587058A (en) | Perforated aluminum plate curtain wall of external wall | |
CN205223390U (en) | Electrophoresis hanger | |
CN203248841U (en) | Supporting device for pipeline surface anticorrosion treatment | |
CN203514799U (en) | Back arris clamp for combined aluminum formwork | |
CN205894577U (en) | Bulky heavy stone material flip -chip structure | |
CN204585528U (en) | A kind of hook connecting production for building aerating sheet material | |
CN203905257U (en) | Detachable hidden installation system of glass fiber ceiling decorative sheet | |
CN203569833U (en) | Novel dry hanging system for building outer decoration and insulation integrated boards | |
CN202159860U (en) | Simple installation type lightning protection belt support and assembly mould thereof | |
CN204692771U (en) | A kind of integrated steel pipe | |
CN210369511U (en) | Aluminum profile mounting structure | |
CN202543294U (en) | Cooling device for hot galvanizing system | |
CN203383459U (en) | Ceramic tile back fastening hanging part | |
CN204898506U (en) | Can make pipeline follow case girder construction that bridge laid | |
CN202868246U (en) | Test-piece fixing frame for absorbent thickness expansion rate detection of floor board and the like | |
CN204326341U (en) | Metal honeycomb plate buckle ceiling structure | |
CN203797288U (en) | Support for suspending guide wheel | |
CN203890856U (en) | Wharf pontoon easy to dismantle |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20181214 |