CN208212795U - A kind of circulation dust-arrest device in construction site - Google Patents

A kind of circulation dust-arrest device in construction site Download PDF

Info

Publication number
CN208212795U
CN208212795U CN201820581106.9U CN201820581106U CN208212795U CN 208212795 U CN208212795 U CN 208212795U CN 201820581106 U CN201820581106 U CN 201820581106U CN 208212795 U CN208212795 U CN 208212795U
Authority
CN
China
Prior art keywords
inner plating
drainage
catch basin
injection spray
construction site
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820581106.9U
Other languages
Chinese (zh)
Inventor
杨六英
黄仕江
黄旭珍
黄越
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yichang Fuhai Construction Engineering Co Ltd
Original Assignee
Yichang Fuhai Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yichang Fuhai Construction Engineering Co Ltd filed Critical Yichang Fuhai Construction Engineering Co Ltd
Priority to CN201820581106.9U priority Critical patent/CN208212795U/en
Application granted granted Critical
Publication of CN208212795U publication Critical patent/CN208212795U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses the circulation dust-arrest device in a kind of construction site, including enclosing, enclosing includes inner plating and lamina rara externa interconnected, multiple row beam tube component is equipped between inner plating and lamina rara externa, each column beam tube component includes multiple beam tube clips;The drainage tube by beam tube clip clamping is equipped on each column beam tube component, the upper end sealing of drainage tube, the lower end of drainage tube is connected to supervisor;Drainage tube is equipped with two injection spray pipes in interval, and injection spray pipe is mounted on inner plating and the atomizing nozzle of injection spray pipe passes through inner plating;The building ground of inner plating side is equipped with catch basin, and water pump is equipped on the building ground of catch basin one side, and the water outlet of water pump is connected to supervisor, and the water inlet of water pump is equipped with the water inlet pipe for protruding into the trench bottom that catchments;Several drainage grooves are additionally provided on building ground, drainage groove is connected to catch basin, is equipped with floor drainage cover plate on catch basin and drainage groove, is effectively increased the effect for recycling efficiency and water mist dust fall of depositing dust water.

Description

A kind of circulation dust-arrest device in construction site
Technical field
The utility model relates to Architectural Engineering Environment protection technique fields, and in particular to the circulation suppression in a kind of construction site Dirt device.
Background technique
As the Large scale construction in city is gradually accelerated, inevitably occur a large amount of construction site in city, Dust is diffused on construction site, although in construction site there is enclosing to carry out certain limitation to waving for dust, due to ash Dirt is lighter, can be directly diffused into air and pollute to the air around construction site, and existing dedusting method is logical It crosses and sprays water above enclosing around sparge pipe, the water mist of generation is wrapped up or inhaled to the dust generated on construction site It receives, dust granule is allowed to decline, but be not recycled to falling to water droplet on ground, cause the ground humidity in building site, The case where influencing worker's normal construction;Exposed sparge pipe is easy to be easy the case where being broken by external interference, influences normal It uses, reduces anti-dust effect.
Utility model content
For the deficiency in the presence of the prior art, the utility model provides the circulation dust suppression dress in a kind of construction site It sets, solves existing dust-arrest device using sparge pipe is circular and carry out the case where water spray be easy to cause sparge pipe to be broken, Er Qiegong The problem of ground moisture effect normal construction on ground.
To achieve the above object, the utility model uses the following technical solution:
A kind of circulation dust-arrest device in construction site, including the enclosing being vertically mounted on building ground, the enclosing It is uniformly distributed along inner plating length direction that multiple row is equipped with including inner plating interconnected and lamina rara externa, between inner plating and lamina rara externa Beam tube component, each column beam tube component include multiple evenly distributed beam tube clips from top to bottom;It is equipped on each column beam tube component By the drainage tube of beam tube clip clamping, the upper end of drainage tube is sealed, and the lower end of drainage tube is connected to supervisor;Drainage tube is equipped with Two injection spray pipes are spaced, injection spray pipe is mounted on inner plating and the atomizing nozzle of injection spray pipe passes through inner plating;The inner plating side Building ground be equipped with catch basin, water pump is installed, the water outlet of water pump and supervisor connect on the building ground of catch basin one side Logical, the water inlet of water pump is equipped with the water inlet pipe for protruding into the trench bottom that catchments;Several drainage grooves, drainage trench are additionally provided on building ground Slot is connected to catch basin, is equipped with floor drainage cover plate on catch basin and drainage groove, is offered reticular structure on floor drainage cover plate Limbers.
The water in catch basin is transported in drainage tube by water pump and is sprayed by injection spray pipe, to the ash in construction site Dirt carries out depositing dust, and water mist merges after contacting with dust granule, and directly falls on the ground, and a large amount of water mists converge on building ground Integrated water flow, the drainage groove on building ground drain into water flow in catch basin, so that water circulation utilizes, reduce to collection The amount that moisturizing is carried out in sink carries out two-stage dedusting by dust of the spaced injection spray pipe to different height, can be effective Dust is avoided to permeate outside enclosing.
Compared with the prior art, the utility model has the following beneficial effects:
1, enclosing is designed to double-layer structure, beam tube component is set between inner plating and lamina rara externa, drainage tube is carried out surely Dingan County's dress effectively avoids drainage tube from causing fracture or outer so that drainage tube is protected between inner plating and lamina rara externa The case where boundary destroys;Two injection spray pipes of interval setting, are capable of forming more sheet of water mist, the fusion to dust on drainage tube Degree and level of coverage all greatly enhance;
2, it offers catch basin on building ground to store water, being additionally provided with several drainage grooves will be on building ground Water flow flow back into catch basin so that water mist merges with dust granule and falls the water circulation that is formed afterwards on the ground and utilize, Setting floor drainage cover plate can carry out primary filtration to the water flow for entering drainage groove or catch basin on catch basin and drainage groove, Biggish sundries is avoided to fall in drainage groove or catch basin.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is partial enlargement structural representation at A in Fig. 1;
In figure, enclosing 1, inner plating 101, lamina rara externa 102, beam tube clip 2, drainage tube 3, supervisor 4, water pump 5, water inlet pipe 6, Shut-off valve 7, straight pipe 801, Taper Pipe section 802, limiting slot 803, spray holes 804, position-limit mechanism 9, limit plate 91, is slided injection spray pipe 8 Slot 911, slide opening 912, positive stop strip 92, connection strap 93, baffle 94, limited post 95, catch basin 10, drainage groove 11, floor drainage cover plate 12, reticulated shell 13, securing plate 14, blower device 15, ventilation case 16 are filtered.
Specific embodiment
The utility model is described further with reference to the accompanying drawing.
As shown in FIG. 1 to FIG. 2, circulation dust-arrest device in a kind of construction site described in the utility model, including it is vertical The enclosing 1 being mounted on building ground, enclosing 1 include inner plating 101 interconnected and lamina rara externa 102, inner plating 101 and outer Laminate 102 is all made of the corrugated plating of aluminum alloy material, and is attached by several connecting rods;Inner plating 101 and lamina rara externa Be equipped with the multiple row beam tube component uniformly distributed along 101 length direction of inner plating between 102, each column beam tube component include it is multiple from top to bottom Evenly distributed beam tube clip 2, beam tube clip 2 be it is adjustable, beam tube clip 2 stretch out inner plating 101 be equipped with adjust spanner, lead to It crosses and pulls the front-rear position for adjusting spanner halved tie pipe clip 2 and be adjusted, so that locking hole changes on beam tube clip 2, thus suitable Answer the installation of the pipe of various calibers.The drainage tube 3 by 2 clamping of beam tube clip, drainage tube 3 are equipped on each column beam tube component Upper end sealing, the lower end of drainage tube 3 is connected to being responsible for 4;Drainage tube 3 is equipped with two injection spray pipes 8 in interval, and injection spray pipe 8 is installed On inner plating 101 and the atomizing nozzle of injection spray pipe 8 passes through inner plating 101;Collection is equipped on the building ground of 101 side of inner plating Sink 10 is equipped with water pump 5 on the building ground of 10 one side of catch basin, and the water outlet of water pump 5 is connected to supervisor 4, water pump 5 into The mouth of a river is equipped with the water inlet pipe 6 for protruding into 10 bottom of catch basin, is drawn into the water in catch basin 10 in drainage tube 3 simultaneously by water pump 5 Water mist is sprayed to construction site by injection spray pipe 8, depositing dust processing is carried out to the dust in construction site;In order to injection spray pipe 8 Spray effect is promoted, and is increased the level of coverage formed by spraying, is optimized to the structure of injection spray pipe 8, and injection spray pipe 8 wraps Straight pipe 801 and Taper Pipe section 802 are included, the limit of ring structure is wherein offered on the position of the stretching of straight pipe 801 inner plating 101 Position slot 803, the spray holes 804 of several throat structures are offered in Taper Pipe section 802, are made by being gradually reduced for 8 internal diameter of injection spray pipe The pressure for obtaining the internal water flow flowed through increases in Taper Pipe section 802, and more careful water mist is generated by spray holes 804, raising The formation efficiency of water mist.
The position-limit mechanism 9 for locking injection spray pipe 8 is additionally provided on inner plating 101, position-limit mechanism 9 includes limit plate 91, The limit hole matched with injection spray pipe 8 is offered in the middle part of limit plate 91, it is right with limiting slot 803 to offer on the inner sidewall of limit hole Neat sliding slot 911 offers the slide opening 912 being connected to sliding slot 911 on limit plate 91, and sliding is equipped with limit in the sliding slot 911 Item 92, positive stop strip 92 are equipped with the connection strap 93 across slide opening 912, are connected with baffle 94 on connection strap 93, baffle 94 is equipped with Multiple telescopic limited posts 95, limit plate 91 is fastened on inner plating 101, and by pulling baffle 94 in sliding slot 911 Positive stop strip 92 slided, on injection spray pipe 8 limiting slot 803 carry out clamping, allow limited post 95 to be directly seated in limit plate On 91, so that entire injection spray pipe 8 be allowed to be limited, stable is mounted on inner plating 101, avoids injection spray pipe 8 caused by pressure difference The case where shake.
In order to expand to the moving range for forming water mist, extend that water mist is aerial waves the time, improves water mist With the contact probability of dust granule, multiple blower devices 15 are installed on inner plating 101, blower device 15 is located at two by spraying Between pipe 8, acclivitous ventilation case 16 is equipped at the air outlet of blower device 15, wherein blower device 15 uses cuboid knot Structure, when blowing water mist upwards under guidance of the wind in blower device 15 in ventilation case 16, so that the track that falls of water mist becomes Parabolic, water mist wave apart from farther.
In order to which the water droplet after falling on building ground can be recycled, several drainages are additionally provided on building ground Groove 11, drainage groove 11 are connected to catch basin 10, are equipped with floor drainage cover plate 12, floor drain on catch basin 10 and drainage groove 11 The water flow formed on building ground is recovered to drainage groove 11 or catchmented by the limbers that reticular structure is offered on cover board 12 In slot 10, it is convenient for subsequent recycling, in order to allow the water flow in drainage trough to flow rapidly into the bottom surface of drainage trough in catch basin 10 For to the inclined inclined-plane in 10 side of catch basin.
Shut-off valve 7 is installed on supervisor 4, it can be by the opening size of shut-off valve 7 come regulating water flow, to change The forming process of water mist is adjusted in different water pressures.
In order to carry out primary filtration to the water in catch basin 10, avoids biggish sundries from entering in water pump 5, protect water pump 5 Normal use, the water inlet of water inlet pipe 6 be equipped with column structure filtering reticulated shell 13, filter reticulated shell 13 on offer it is several Cellular filter hole.
It is additionally provided with the securing plate 14 of several triangular structures uniformly distributed along outer panel length direction on lamina rara externa 102, protects The stability for demonstrate,proving enclosing 1, will not there is a situation where topple over.
Finally, it is stated that above embodiments are merely intended for describing the technical solutions of the present application, but not for limiting the present application, although ginseng The utility model is described in detail according to preferred embodiment, those skilled in the art should understand that, it can be to this The technical solution of utility model is modified or replaced equivalently, without departing from the objective and model of technical solutions of the utility model It encloses, should all cover in the scope of the claims of the utility model.

Claims (7)

1. the circulation dust-arrest device in a kind of construction site, including the enclosing (1) being vertically mounted on building ground, feature exists In: the enclosing (1) include inner plating interconnected (101) and lamina rara externa (102), inner plating (101) and lamina rara externa (102) Between be equipped with the multiple row beam tube component uniformly distributed along inner plating (101) length direction, each column beam tube component include it is multiple from top to bottom Evenly distributed beam tube clip (2);It is equipped with the drainage tube (3) by beam tube clip (2) clamping on each column beam tube component, drains The upper end sealing of (3) is managed, the lower end of drainage tube (3) is connected to supervisor (4);Drainage tube (3) is equipped with two injection spray pipes in interval (8), injection spray pipe (8) is mounted on inner plating (101) and the atomizing nozzle of injection spray pipe (8) passes through inner plating (101);The inner plating (101) building ground of side is equipped with catch basin (10), is equipped with water pump (5) on the building ground of catch basin (10) one side, The water outlet of water pump (5) is connected to supervisor (4), and the water inlet of water pump (5) is equipped with the water inlet pipe for protruding into catch basin (10) bottom (6);
Several drainage grooves (11) are additionally provided on building ground, drainage groove (11) is connected to catch basin (10), catch basin (10) it is equipped with floor drainage cover plate (12) in drainage groove (11), the limbers of reticular structure is offered on floor drainage cover plate (12).
2. the circulation dust-arrest device in a kind of construction site according to claim 1, it is characterised in that: the injection spray pipe (8) include straight pipe (801) and Taper Pipe section (802), wherein opened up on the position of straight pipe (801) stretching inner plating (101) There is the limiting slot (803) of ring structure, the spray holes (804) of several throat structures are offered in Taper Pipe section (802).
3. the circulation dust-arrest device in a kind of construction site according to claim 2, it is characterised in that: the inner plating (101) position-limit mechanism (9) for locking injection spray pipe (8) is additionally provided on, position-limit mechanism (9) includes limit plate (91), limit plate (91) middle part offers the limit hole matched with injection spray pipe (8), and it is right with limiting slot (803) to offer on the inner sidewall of limit hole Neat sliding slot (911), offers the slide opening (912) being connected to sliding slot (911) on limit plate (91), sliding in the sliding slot (911) Dynamic to be equipped with positive stop strip (92), positive stop strip (92) is equipped with the connection strap (93) across slide opening (912), and connection strap is connected on (93) Baffle (94), baffle (94) are equipped with multiple telescopic limited posts (95).
4. the circulation dust-arrest device in a kind of construction site according to claim 1, it is characterised in that: the water inlet pipe (6) water inlet is equipped with the filtering reticulated shell (13) of column structure, offers several cellular filterings in filtering reticulated shell (13) Hole.
5. the circulation dust-arrest device in a kind of construction site according to claim 4, it is characterised in that: the inner plating (101) it is equipped on multiple blower devices (15), blower device (15) is located between two injection spray pipes (8), blower device (15) Air outlet at be equipped with acclivitous ventilation case (16).
6. the circulation dust-arrest device in a kind of construction site according to claim 1, it is characterised in that: the supervisor (4) On shut-off valve (7) are installed.
7. the circulation dust-arrest device in a kind of construction site according to claim 6, it is characterised in that: on the outer panel It is additionally provided with the securing plate (14) of several triangular structures uniformly distributed along outer panel length direction.
CN201820581106.9U 2018-04-23 2018-04-23 A kind of circulation dust-arrest device in construction site Expired - Fee Related CN208212795U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820581106.9U CN208212795U (en) 2018-04-23 2018-04-23 A kind of circulation dust-arrest device in construction site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820581106.9U CN208212795U (en) 2018-04-23 2018-04-23 A kind of circulation dust-arrest device in construction site

Publications (1)

Publication Number Publication Date
CN208212795U true CN208212795U (en) 2018-12-11

Family

ID=64512660

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820581106.9U Expired - Fee Related CN208212795U (en) 2018-04-23 2018-04-23 A kind of circulation dust-arrest device in construction site

Country Status (1)

Country Link
CN (1) CN208212795U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114570146A (en) * 2022-03-25 2022-06-03 江苏电子信息职业学院 Environment-friendly dust removal equipment for construction site

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114570146A (en) * 2022-03-25 2022-06-03 江苏电子信息职业学院 Environment-friendly dust removal equipment for construction site

Similar Documents

Publication Publication Date Title
CN104776540B (en) Atomizing humidifier with new structure
CN208212795U (en) A kind of circulation dust-arrest device in construction site
CN205474992U (en) Municipal guardrail of spraying dust fall
CN207228695U (en) A kind of park lobby
CN206419839U (en) A kind of landscape design multi-functional street lamp
CN204678588U (en) There is the atomizing humidifier of new structure
CN105013281A (en) Water spray dedusting device
CN205491844U (en) Roof greening circulating water system
CN206508778U (en) A kind of current stabilization flue gas desulfurization device of multi-absorption
CN105477969B (en) A kind of device for being used to intercept salt fog and aerosol
CN208210941U (en) A kind of garden plants climbing frame
CN109939513B (en) Environment-friendly water mist dust removal device
CN208145748U (en) Ammonia recycling device
CN102937314A (en) Double face air blowing atomizing cooling device
CN207854705U (en) A kind of water sprayer for pouring ornamental trees and shrubs
CN203052199U (en) Improved automatic filtration and drainage device
CN214132447U (en) Landscape fountain device
CN208612122U (en) A kind of closed water curtain desulphurization system
CN205875809U (en) Pavilion
CN215233101U (en) Fog gun device with raise dust automatic monitoring function
CN207491648U (en) A kind of ornamental plant corridor
CN215165148U (en) Road construction is with watering dust suppression device
CN210207267U (en) Shower nozzle
CN201150740Y (en) Water mist anti-blocking separation sprayer
CN214257755U (en) Gardens are protection against insects device for maintenance with automatically, spout medicine function

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181211

Termination date: 20190423

CF01 Termination of patent right due to non-payment of annual fee