CN208184759U CN201820670575.8U CN201820670575U CN208184759U CN 208184759 U CN208184759 U CN 208184759U CN 201820670575 U CN201820670575 U CN 201820670575U CN 208184759 U CN208184759 U CN 208184759U
Authority
CN
China
Prior art keywords
top beam
needling
pair
beam body
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820670575.8U
Other languages
Chinese (zh)
Inventor
倪和平
樊军
付照明
杨宏峰
孙建和
赵琪
刘军锋
杨德利
刘阳
唐飞
唐一飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou Coal Mining Machinery Group Co Ltd
Original Assignee
Zhengzhou Coal Mining Machinery Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou Coal Mining Machinery Group Co Ltd filed Critical Zhengzhou Coal Mining Machinery Group Co Ltd
Priority to CN201820670575.8U priority Critical patent/CN208184759U/en
Application granted granted Critical
Publication of CN208184759U publication Critical patent/CN208184759U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of seperated advance timbering top beams, two top beam bodies including seperated arrangement side by side, two top girder constructions are identical, and each top beam body includes: two pairs of needlings that top beam body front and rear portions are arranged in, and each pair of needling is horizontally arranged at interval along top beam body;Main reinforcement two sides are respectively welded stiffening plate in top beam between each pair of needling;Auxiliary support plate is respectively welded between each pair of needling and top beam top plate, each pair of needling is mutually welded with the auxiliary support plate respectively, constitutes box-structure between auxiliary support plate and the top beam top plate.The utility model advantage is that each top beam body is welded there are four needling, compared with conventional solution, can connect column quantity and promote one times, bracket support intensity is significantly promoted;Laterally above while there are two root posts to be supported in each top beam body simultaneously, support stability is higher.

Description

Seperated advance timbering top beam
Technical field
The utility model relates to mine hydraulic brackets, more particularly, to seperated advance timbering top beam.
Background technique
Downhole crossheading tunnel is to modernize fully-mechanized mining working important material transportation and underground ventilating channel.Due to underground Complex geologic conditions, terrane stress distribution are difficult to accurately calculate, and back is caused to deform, and roadway's sides inwardly squeeze contraction, Personnel and equipment safety are directly affected, therefore the supporting of crossheading haulage drift is highly important.It is asked to solve above-mentioned roadway support Topic mostly uses advanced hydraulic support to carry out mechanization supporting at present.
With the development of fully mechanized mining technology, mining depth is continuously increased, and coal mining transporting equipment develops to enlargement, underground coal mine The height and width of gate road, which are also all complied with, increase, is broadening, and Underground pressure shows more acutely, especially in work of mining At front 20-30 meters of industry working face, tunnel can largely be deformed, and advanced pressure is especially big, this just needs advanced hydraulic support to have There are higher supporting intensity and stability.Direct contact component of the top beam as hydraulic support and top plate, structural strength and shape Formula directly affects advanced hydraulic support to the supporting effect and service efficiency of back.Patent publication No. CN101191419, Advance timbering top beam disclosed in CN101634230 uses split left and right formula, wherein being distributed two columns before and after each independent top beam Nest is connected with column, this kind of structure type support stability is poor, and toppling property is strong;Surpass in patent CN201137500, CN2828315 Fore-stock top beam uses integral form, and top beam is divided into four needlings of cloth in vertical and horizontal respectively and connect with column, this kind of structure Though ensure that the overall stability of bracket, bracket need to integrally move frame when mobile, and operating flexibility is poor.
Summary of the invention
The utility model aim is to provide a kind of seperated advance timbering top beam.
To achieve the above object, the utility model takes following technical proposals:
Fission advance timbering top beam described in the utility model, two top beam bodies including seperated arrangement side by side, two institutes State that top girder construction is identical, and each top beam body includes: two pairs of needlings that top beam body front and rear portions are arranged in, each pair of column Nest is horizontally arranged at interval along top beam body;Main reinforcement two sides are respectively welded stiffening plate in top beam between each pair of needling;It is each pair of Auxiliary support plate is respectively welded between needling and top beam top plate, each pair of needling is mutually welded with the auxiliary support plate respectively, auxiliary It helps between support plate and the top beam top plate and constitutes box-structure.
The utility model advantage major embodiment is in the following areas:
1, each top beam body is welded there are four needling, compared with conventional solution, can be connected column quantity and be promoted one Times, bracket support intensity is significantly promoted;Laterally above while there are two root posts to be supported in each top beam body simultaneously, props up Frame stability is higher.
2, stiffening plate is respectively welded in main reinforcement two sides in top beam, improves the cross-section surface intensity of main reinforcement in top beam, while meeting Top beam overall width can be compressed under the premise of design requirement as far as possible, is not take up the other equipment arrangement spaces in tunnel.
3, each pair of needling is respectively welded on auxiliary support plate, and box knot is constituted between auxiliary support plate and top beam top plate Structure, effectively increases the rigidity of structure of top beam body, and shock resistance is stronger.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model.
Fig. 2 is the structural schematic diagram of two top beam bodies of arrangement seperated side by side described in the utility model.
Specific embodiment
It elaborates with reference to the accompanying drawing to the embodiment of the present invention, the present embodiment before being with technical solution of the present invention It puts and is implemented, the detailed implementation method and specific operation process are given, but protection scope of the present invention is not limited to down State embodiment.
As shown in Figure 1, 2, seperated advance timbering top beam described in the utility model, two tops including seperated arrangement side by side Beam body 1.1,1.2, two top beam bodies 1.1,1.2 structures are identical, are now illustrated by taking top beam body 1.1 as an example: before top beam body 1.1, Rear portion is respectively arranged with two pairs of needlings 2,3, and each pair of needling 2,3 is horizontally arranged at interval along top beam body 1.1;Positioned at each pair of needling 2,3 Between top beam in 4 two sides of main reinforcement be respectively welded stiffening plate 5;It is respectively welded between each pair of needling 2,3 and top beam top plate 6 auxiliary Support plate 7 is helped, each pair of needling 2,3 is welded with 7 phase of auxiliary support plate respectively, constitutes case between auxiliary support plate 7 and top beam top plate 6 Type structure.

Claims (1)

1. a kind of fission advance timbering top beam, two top beam bodies including seperated arrangement side by side, it is characterised in that: two tops Girder construction is identical, and each top beam body includes: two pairs of needlings that top beam body front and rear portions are arranged in, each pair of needling edge Top beam body is horizontally arranged at interval;Main reinforcement two sides are respectively welded stiffening plate in top beam between each pair of needling;Each pair of needling Auxiliary support plate is respectively welded between top beam top plate, each pair of needling is mutually welded with the auxiliary support plate respectively, auxiliary branch Box-structure is constituted between fagging and the top beam top plate.
CN201820670575.8U 2018-05-07 2018-05-07 Seperated advance timbering top beam Active CN208184759U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820670575.8U CN208184759U (en) 2018-05-07 2018-05-07 Seperated advance timbering top beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820670575.8U CN208184759U (en) 2018-05-07 2018-05-07 Seperated advance timbering top beam

Publications (1)

Publication Number Publication Date
CN208184759U true CN208184759U (en) 2018-12-04

Family

ID=64433210

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820670575.8U Active CN208184759U (en) 2018-05-07 2018-05-07 Seperated advance timbering top beam

Country Status (1)

Country Link
CN (1) CN208184759U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109926800A (en) * 2019-04-08 2019-06-25 安徽省矿业机电装备有限责任公司 A kind of process of box-structure batch rivet welding

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109926800A (en) * 2019-04-08 2019-06-25 安徽省矿业机电装备有限责任公司 A kind of process of box-structure batch rivet welding
CN109926800B (en) * 2019-04-08 2021-02-12 安徽省矿业机电装备有限责任公司 Process method for batch rivet welding of box-type structures

Similar Documents

Publication Publication Date Title
CN101761338A (en) Gob-side entry retaining method of a solid filling coal mining half-section one-leg shed
CN103643979B (en) Hydraulic support used for roadway temporary support and erecting and use method of hydraulic support
CN105003288B (en) A kind of method and support system of medium-thickness seam gob side entry retaining
CN103061771A (en) Remining mine fully-mechanized coal mining face open-off cut tunneling process and supporting method
CN103775117A (en) Waste-rock-blocking top-cutting mold-hanging gob-side entry retaining hydraulic bracket for mining working face
CN103758529A (en) Coal mine gob-side entry retaining side supporting method
CN103775095A (en) Ridge soft-foundation tunnel advance double guide tunnel and construction method thereof
CN203362198U (en) Track walking type immediate support device of fully-mechanized drivage roadway
CN208184759U (en) Seperated advance timbering top beam
CN104405392A (en) Three-soft thick coal seam roadway top-support bottom-retaining anchor-net cable active supporting fully-mechanized caving mining method
CN203717008U (en) Gangue blocking top cutting deviation correcting self moving gob-side entry retaining hydraulic support frame
CN208184762U (en) Seperated advance timbering pedestal
CN211666747U (en) Coal mine underground crossheading roadway tunneling composite supporting device
CN203145980U (en) Mining shed lifting support
CN110159327B (en) Continuous tunneling temporary support device and method for tunnel with separated tunneling and anchoring
CN203716985U (en) Advanced dual guide hole of mountain ridge soft foundation tunnel
CN202659267U (en) Integral graded spanning-type walking bracket
CN104863599B (en) Fully-mechanized mining working synchronously expands side installation method and support system
CN203130131U (en) Suspension hydraulic support for underground coal mine large channel end
CN203717006U (en) Rock-blocking, top-cutting and mold-hanging gob-side entryretaining hydraulic support for mining working face
CN102444413A (en) Hydraulic support and top beam thereof
CN203716976U (en) Track panel frame for backup of tunnel boring machine and transportation in tunnel
CN103195458A (en) Underground coal mine large channel end socket suspension hydraulic support
CN202431286U (en) Hydraulic bracket and top beam thereof
CN206554965U (en) Fully-mechanized mining working automatic moving type lifts canopy

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant