CN208184195U - A kind of architectural engineering scaffold - Google Patents
A kind of architectural engineering scaffold Download PDFInfo
- Publication number
- CN208184195U CN208184195U CN201820369525.6U CN201820369525U CN208184195U CN 208184195 U CN208184195 U CN 208184195U CN 201820369525 U CN201820369525 U CN 201820369525U CN 208184195 U CN208184195 U CN 208184195U
- Authority
- CN
- China
- Prior art keywords
- threaded rod
- pedestal
- mounting blocks
- rod
- architectural engineering
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Movable Scaffolding (AREA)
Abstract
The utility model discloses a kind of architectural engineering scaffolds, including multiple pedestals, first threaded rod there are two being threadedly coupled on the pedestal, first threaded rod runs through pedestal, the lower end of two first threaded rods is rotatably connected to steadying plate, telescopic rod is connected between two steadying plates, the pedestal lower end is equipped with groove, the side wall of the steadying plate is rotatably connected to the first mounting blocks, nut is fixedly connected on first mounting blocks, the nut inner thread is connected with third threaded rod, there are two support rods for rotation connection on the side wall of the nut, the lower end of the third threaded rod is rotatably connected to the second mounting blocks, there are two connecting rods for rotation connection on second mounting blocks.The utility model can directly be built on the ground of out-of-flatness, and temporarily the pedestal of scaffold can be adjusted, and cope with different ground environments, and widely applicable, stabilized structure is highly-safe.
Description
Technical field
The utility model relates to Construction Formwork & Scaffold Technology field more particularly to a kind of architectural engineering scaffolds.
Background technique
Scaffold is to be worker operation and high-rise working at the construction field (site) and the various brackets set up, and is the logical of building field
With term, it is mainly used in exterior wall, interior decoration or the higher place that can not directly construct of layer height, scaffold system on building sites
Making material usually has bamboo and wood, steel pipe or synthetic material etc., at present also uses scaffold as template in the engineering of part, this
Outer its is also widely used in the fields such as advertising, municipal administration, traffic road bridge, mine, at present foot hand used in building trade
Frame, typically no pedestal is directly built on the ground, however is built on the ground of out-of-flatness, the bottom of scaffold because it is unstable very
It is easy to happen safety accident, common soil ground is easy to cause to sink because of the factors such as rainy, causes scaffold contact not
It to ground, is easy to happen and collapses, traditional scaffold cannot temporarily be adjusted scaffold pedestal, it is difficult to adapt to different ground
Environment.
Utility model content
Purpose of the utility model is to solve disadvantages existing in the prior art, and a kind of architectural engineering proposed is used
Scaffold.
To achieve the goals above, the utility model adopts the technical scheme that
A kind of architectural engineering scaffold, including multiple pedestals are threadedly coupled on the pedestal there are two the first threaded rod,
First threaded rod runs through pedestal, and the lower end of two first threaded rods is rotatably connected to steadying plate, and two described steady
Telescopic rod is connected between fixed board, the pedestal lower end is equipped with groove, and the side wall of the steadying plate is rotatably connected to the first installation
Block is fixedly connected with nut on first mounting blocks, and the nut inner thread is connected with third threaded rod, the side of the nut
There are two support rod, the lower end of the third threaded rod is rotatably connected to the second mounting blocks, second peace for rotation connection on wall
Filling rotation connection on block, there are two connecting rods, and the connecting rod is rotatably connected on support rod far from one end of the second mounting blocks, described
The upper end of pedestal is equipped with the second threaded rod, is socketed with steel pipe on second threaded rod, the lower end of the steel pipe is rotatably connected to
Rotating block, the rotating block are threadedly coupled with the second threaded rod, and the steel pipe is equipped with locking device, are socketed on the steel pipe
Connecting shaft is equipped with connection frame between two adjacent connecting shafts.
Preferably, the end of the support rod is pointed.
Preferably, the locking device is clamping screw.
Preferably, the telescopic rod includes the first hollow stem and the second hollow stem, and first hollow stem is socketed in second
In hollow stem.
Preferably, the upper end of the third threaded rod is equipped with integrally formed handle.
Preferably, the inner wall of the connecting shaft is equipped with anti-skid chequer.
In the utility model, structure is reliable, and rotation rotating block cooperates the second threaded rod when use, adjusts steel pipe and rises, makes
Base contacts ground rotates the first threaded rod, changes the angle of steadying plate and pedestal, so that steadying plate is close to landing ground, will support
Bar is inserted into ground, rotates third threaded rod, opens support rod in subsurface, pedestal is tightly secured on ground.This is practical
It is novel directly to be built on the ground of out-of-flatness, and temporarily scaffold pedestal can be adjusted, cope with different ground
Face ring border, widely applicable, stabilized structure are highly-safe.
Detailed description of the invention
Fig. 1 be the utility model proposes a kind of architectural engineering scaffold structural schematic diagram;
Fig. 2 is enlarged drawing at A in Fig. 1;
Fig. 3 is enlarged drawing at B in Fig. 1.
In figure: 1 steadying plate, 2 pedestals, 3 first threaded rods, 4 rotating blocks, 5 locking devices, 6 connecting shafts, 7 steel pipes, 8 second
Threaded rod, 9 grooves, 10 third threaded rods, 11 first mounting blocks, 12 nuts, 13 support rods, 14 second mounting blocks, 15 connecting rods, 16
Telescopic rod.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.
Referring to Fig.1-3, a kind of architectural engineering scaffold, including multiple pedestals 2, are threadedly coupled that there are two the on pedestal 2
One threaded rod 3, the first threaded rod 3 run through pedestal 2, and the lower end of two the first threaded rods 3 is rotatably connected to steadying plate 1, and two
It is connected with telescopic rod 16 between steadying plate 1, keeps the distance between two steadying plates 1 adjustable, 2 lower end of pedestal is equipped with groove 9,
The side wall of steadying plate 1 is rotatably connected to the first mounting blocks 11, and nut 12, spiral shell in nut 12 are fixedly connected on the first mounting blocks 11
Line is connected with third threaded rod 10, and there are two support rod 13, the lower ends of third threaded rod 10 for rotation connection on the side wall of nut 12
The second mounting blocks 14 are rotatably connected to, there are two connecting rods 15 for rotation connection on the second mounting blocks 14, and connecting rod 15 is far from the second installation
One end of block 14 is rotatably connected on support rod 13, and the upper end of pedestal 2 is equipped with the second threaded rod 8, is socketed on the second threaded rod 8
Steel pipe 7, the lower end of steel pipe 7 are rotatably connected to rotating block 4, and rotating block 4 is threadedly coupled with the second threaded rod 8, and rotation rotating block 4 is matched
The second threaded rod 8 is closed, steel pipe 7 is adjusted and rises, pedestal 2 is made to contact ground, steel pipe 7 is equipped with locking device 5, fixes steel pipe 7,
It is socketed with connecting shaft 6 on steel pipe 7, is equipped with connection frame between two adjacent connecting shafts 6, multiple scaffolds is connected.
In the utility model, the end of support rod 13 is pointed, it is easier to be inserted into ground.Locking device 5 is clamping screw,
Facilitate adjusting.Telescopic rod 16 includes the first hollow stem and the second hollow stem, and the first hollow stem is socketed in the second hollow stem, can be certainly
By stretching.The upper end of third threaded rod 10 is equipped with integrally formed handle, facilitates rotation.The inner wall of connecting shaft 6 is equipped with anti-skid chequer,
It effectively prevent sliding.
In the utility model, structure is reliable, and rotation rotating block 4 cooperates the second threaded rod 8 when use, adjusts steel pipe 7 and rises,
So that pedestal 2 is contacted ground, rotate the first threaded rod 3, change the angle of steadying plate 1 and pedestal 2, steadying plate 1 is made to be close to landing ground,
Support rod 13 is inserted into ground, rotates third threaded rod 10, support rod 13 is opened in subsurface, pedestal 2 is tightly secured in
On ground.
The preferable specific embodiment of the above, only the utility model, but the protection scope of the utility model is not
It is confined to this, anyone skilled in the art is within the technical scope disclosed by the utility model, practical according to this
Novel technical solution and its utility model design are subject to equivalent substitution or change, should all cover the protection model in the utility model
Within enclosing.
Claims (6)
1. a kind of architectural engineering scaffold, including multiple pedestals (2), which is characterized in that be threaded on the pedestal (2)
Two the first threaded rods (3), first threaded rod (3) run through pedestal (2), and the lower end of two first threaded rods (3) is equal
It is rotatably connected to steadying plate (1), is connected with telescopic rod (16) between two steadying plates (1), pedestal (2) lower end is equipped with
The side wall of groove (9), the steadying plate (1) is rotatably connected to the first mounting blocks (11), fixed on first mounting blocks (11)
It is connected with nut (12), nut (12) internal screw thread is connected with third threaded rod (10), is turned on the side wall of the nut (12)
There are two support rod (13) for dynamic connection, and the lower end of the third threaded rod (10) is rotatably connected to the second mounting blocks (14), described
There are two connecting rod (15), the connecting rod (15) to turn far from the one end of the second mounting blocks (14) for rotation connection on second mounting blocks (14)
Dynamic to be connected on support rod (13), the upper end of the pedestal (2) is equipped with the second threaded rod (8), covers on second threaded rod (8)
It is connected to steel pipe (7), the lower end of the steel pipe (7) is rotatably connected to rotating block (4), the rotating block (4) and the second threaded rod (8)
It is threadedly coupled, the steel pipe (7) is equipped with locking device (5), is socketed with connecting shaft (6) on the steel pipe (7), adjacent two
Connection frame is equipped between connecting shaft (6).
2. a kind of architectural engineering scaffold according to claim 1, which is characterized in that the end of the support rod (13)
It is pointed.
3. a kind of architectural engineering scaffold according to claim 1, which is characterized in that the locking device (5) is lock
Tight bolt.
4. a kind of architectural engineering scaffold according to claim 1, which is characterized in that the telescopic rod (16) includes the
One hollow stem and the second hollow stem, first hollow stem are socketed in the second hollow stem.
5. a kind of architectural engineering scaffold according to claim 1, which is characterized in that the third threaded rod (10)
Upper end is equipped with integrally formed handle.
6. a kind of architectural engineering scaffold according to claim 1, which is characterized in that the inner wall of the connecting shaft (6)
Equipped with anti-skid chequer.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820369525.6U CN208184195U (en) | 2018-03-19 | 2018-03-19 | A kind of architectural engineering scaffold |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820369525.6U CN208184195U (en) | 2018-03-19 | 2018-03-19 | A kind of architectural engineering scaffold |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208184195U true CN208184195U (en) | 2018-12-04 |
Family
ID=64438007
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820369525.6U Expired - Fee Related CN208184195U (en) | 2018-03-19 | 2018-03-19 | A kind of architectural engineering scaffold |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208184195U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110642196A (en) * | 2019-09-19 | 2020-01-03 | 嘉兴勤慎智能技术有限公司 | Industrial robot fast overhaul maintains device |
-
2018
- 2018-03-19 CN CN201820369525.6U patent/CN208184195U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110642196A (en) * | 2019-09-19 | 2020-01-03 | 嘉兴勤慎智能技术有限公司 | Industrial robot fast overhaul maintains device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204876508U (en) | Portable height -adjustable scaffold | |
CN208184195U (en) | A kind of architectural engineering scaffold | |
CN107288329B (en) | Scaffold frame that can level | |
CN212054092U (en) | Fender is enclosed with monitoring formula to building engineering construction | |
CN210263929U (en) | A preformed hole template for building civil engineering | |
CN210827512U (en) | Slope protection protector for civil engineering | |
CN205935638U (en) | Integrative house preparation mould of energy -concerving and environment -protective reinforced concrete | |
CN208072912U (en) | A kind of Easy opened scaffold that construction site auxiliary is built | |
CN209339555U (en) | A kind of construction scaffold | |
CN208235833U (en) | A kind of municipal administration skyscraper protective fence | |
CN210741897U (en) | Sampling device convenient for adjusting length dimension for soil detection | |
CN211691478U (en) | Building templates link for civil engineering | |
CN210713932U (en) | Strutting arrangement for ancient building protection | |
CN207862779U (en) | One road and bridge protective device | |
AU2016100599A4 (en) | A new multi-functional lockset | |
CN207405997U (en) | A kind of building, which pours, encloses column sizing articles for use | |
CN207079510U (en) | A kind of electronic police intelligence bar | |
CN210988593U (en) | Rain-proof device for building construction | |
CN216766696U (en) | But height-adjusting's load-bearing scaffolding for construction | |
CN220013698U (en) | Foundation pit supporting device with adjustable | |
CN205976451U (en) | Scaffold connecting device for building engineering | |
AU2016100601A4 (en) | A new U-shaped lockset | |
AU2016100598A4 (en) | A multi-functional lockset | |
CN211974481U (en) | People living container capable of adapting to different terrains | |
CN213869263U (en) | Civil engineering encloses fender device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20190917 Address after: 510000 Room 1108, 1138 Zhongshan Avenue West, Tianhe District, Guangzhou City, Guangdong Province (office only) Patentee after: Guangdong Zhongsong Construction Engineering Co.,Ltd. Address before: 312500 Dongchen 111, Dongchen Village, Dongcheng Town, Chengtan Town, Xinchang County, Shaoxing City, Zhejiang Province Patentee before: ZHEJIANG JIAYUDA MACHINERY Co.,Ltd. |
|
TR01 | Transfer of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20181204 |
|
CF01 | Termination of patent right due to non-payment of annual fee |