CN208169707U - Flexible blockage device - Google Patents

Flexible blockage device Download PDF

Info

Publication number
CN208169707U
CN208169707U CN201820381685.2U CN201820381685U CN208169707U CN 208169707 U CN208169707 U CN 208169707U CN 201820381685 U CN201820381685 U CN 201820381685U CN 208169707 U CN208169707 U CN 208169707U
Authority
CN
China
Prior art keywords
plate
flexible blockage
pipeline
equipment
flexible
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820381685.2U
Other languages
Chinese (zh)
Inventor
张春艳
熊国栋
张持
石亮
刘广
邵小
黄亮
王超
于江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China General Nuclear Power Corp
China Nuclear Power Technology Research Institute Co Ltd
CGN Power Co Ltd
China Nuclear Power Institute Co Ltd
Original Assignee
China General Nuclear Power Corp
China Nuclear Power Technology Research Institute Co Ltd
CGN Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China General Nuclear Power Corp, China Nuclear Power Technology Research Institute Co Ltd, CGN Power Co Ltd filed Critical China General Nuclear Power Corp
Priority to CN201820381685.2U priority Critical patent/CN208169707U/en
Application granted granted Critical
Publication of CN208169707U publication Critical patent/CN208169707U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The utility model discloses a kind of flexible blockage device, for blocking between equipment and pipeline, in interface on conduit insertion device, including flexible blockage plate and pipe clamp, flexible blockage plate is posted by equipment in a ring and around interface, flexible blockage plate is equipped with multiple gaps for extending to edge, and pipe clamp is arranged and is positioned on pipeline with to equipment bias flexible blockage plate.The interface of equipment is posted by due to flexible blockage plate and equipment is biased towards by pipe clamp, is able to maintain in work progress to the closure between equipment interface and pipeline, foreign matter is effectively prevent to enter in equipment or pipeline by interface.Pipe clamp is to be placed on pipeline and any position on pipeline can be set, and the flexibility, adaptability when site layout project are higher.Therefore flexible blockage plate is equipped with gap has certain flexibility in structure, and it is not fixed with pipeline, therefore the oscillating load on pipeline can be isolated without being transmitted in equipment.

Description

Flexible blockage device
Technical field
The utility model relates to a kind of duct closing type devices, more particularly to a kind of flexible blockage that oscillating load can be isolated Device.
Background technique
It is very high to cleannes requirement during PIPING OF MAIN LOOPS IN NUCLEAR POWER STATION Pipe installing and operation, it, will be right if entering foreign matter accidentally The normal operation of reactor causes a hidden trouble.During nuclear power station construction and in-service pipeline replacement, there are retaining wall on slope, weld grinding Etc. the more process for being easily accessible foreign matter, if blocked not in time to the interface on pipeline and equipment, the foreign matters such as iron filings Reactor core will be entered by pipeline, equipment interface, bring very big difficulty to cleaning task afterwards.If cleaning is not thorough, foreign matter It can be flowed with primary Ioops coolant, be easy to cause the equipment damages such as in-pile component, heat exchange pipe of evaporator, main pump, influence nuclear power station Safe operation.
Currently, in the construction process, usually round plank is put into pipeline, by stainless steel adhesive tape by plank and pipeline It is bonded together, prevents the foreign matters such as iron filings from entering.Above-mentioned closure mode is although relatively simple, but there is following defects:Plank is only It is to be blocked to pipeline without plugging device interface, foreign matter may still enter from equipment interface;Due to need to will be wooden Plate is put into inside pipeline, therefore is only capable of being arranged in pipe end neighbouring position, and flexibility is poor.
Therefore, it can be plugged at equipment interface it is necessory to provide one kind, and the unrestricted plugging device in position is set.
Utility model content
The purpose of this utility model is to provide one kind to be plugged at equipment interface, and the unrestricted closure in position is arranged Device.
To achieve the goals above, the utility model provides a kind of flexible blockage device, for blocking in equipment and pipe Between road, the pipeline is inserted into the interface in the equipment, including flexible blockage plate and pipe clamp, and the flexible blockage plate is in ring Shape is simultaneously posted by the equipment around the interface, and the flexible blockage plate is equipped with multiple gaps for extending to edge, institute Pipe clamp is stated to be arranged and be positioned on the pipeline with to flexible blockage plate described in the equipment bias.
Compared with prior art, since the flexible blockage plate in the utility model flexible blockage device is posted by connecing for equipment It is biased towards equipment at mouthful and by pipe clamp, therefore can keep having the closure between equipment interface and pipeline in the construction process Effect prevents foreign matter from entering in equipment or pipeline by interface.Again since pipe clamp is placed on pipeline without being put into pipeline Inside, therefore nearby any position on pipeline can be set in the end that can't be limited in pipeline, when site layout project Flexibility, adaptability it is higher.In addition, therefore flexible blockage plate is equipped with gap has certain flexibility in structure, and soft Property plugging plate not fixed with pipeline, therefore the oscillating load on pipeline can be isolated without transmitting in the construction process Onto equipment, be conducive to keep pipeline and the structural integrity of equipment in the construction process.Finally, the structure of the present apparatus is simple, tear open Dress is convenient, convenient for safeguarding and replacement.
Preferably, the flexible blockage plate includes the first plugging plate and the second plugging plate of arc, first plugging plate Both ends separably docked with the both ends of second plugging plate respectively.
Specifically, an end of first plugging plate is equipped with groove, and an end of second plugging plate is equipped with engaging Portion, first plugging plate are caught in the groove by the holding section with the second plugging plate and are docked.
Preferably, the gap radially extending along the flexible blockage plate.
Preferably, including several first gaps and several second gaps in multiple gaps, first gap extends To the inward flange of the flexible blockage plate, second gap extends to the outer edge of the flexible blockage plate.
Specifically, several first gaps are arranged alternately on the flexible blockage plate with several second gaps Setting.
Preferably, the pipe clamp includes the clamping piece of two arcs, the end of two clamping pieces is separably docked solid Determine and is positioned on the pipeline.
It specifically, further include the bolts and nuts for being set to the two clamping piece ends, the end of two clamping pieces passes through The threaded connection of the bolts and nuts and dock fixation.
It specifically, further include two ring flat-plates, two clamping pieces pass through flexible blockage plate described in the two ring flat-plate biass respectively.
Preferably, further including a pipe sleeve being placed on the pipeline, the pipe clamp and the flexible blockage plate are placed on institute It states on pipe sleeve.
Detailed description of the invention
Fig. 1 is cross-sectional view when this flexible blockage device is set between equipment and pipeline.
Fig. 2 is the perspective view of this device for flexible encapsulation.
Fig. 3 is the structural schematic diagram of flexible blockage plate in this flexible blockage device.
Specific embodiment
Description is made to the preferred embodiment of the utility model below with reference to the Figure of description provided.
In conjunction with shown in Fig. 1 to Fig. 3, the utility model provides a kind of flexible blockage device, for blocking in equipment 2 and pipeline Between 3, to prevent foreign matter from entering pipeline 3, equipment 2 in the construction process.In the interface 21 that pipeline 3 is inserted into equipment 2 and manage Road 3 and equipment 2 are clearance fit, have gap between the inner wall of interface 21 and the outer peripheral surface of pipeline 3.
Flexible blockage device includes pipe sleeve 11, pipe clamp, ring flat-plate 13 and flexible blockage plate 14, and wherein the length of pipe sleeve 11 is big In the length of pipe clamp, ring flat-plate 13 and flexible blockage plate 14.11 sets of the pipe sleeve positions being located at interface 21 on pipeline 3, and have portion It point extend into interface 21, the pipe sleeve 11 in the present embodiment is the big arc close to full circle, thinner thickness, therefore has certain become Shape ability, is suitable for 3 size of pipeline, and pipe sleeve 11 is also possible to complete circle.Flexible blockage plate 14 in a ring and is covered in pipe sleeve On 11, and flexible blockage plate 14 is posted by equipment 2 around 21 ground of interface, and the specific structure of flexible blockage plate 14 will be in following theory It is bright.
Pipe clamp includes the clamping piece 121 of two arcs, and two 121 sets of clamping pieces are on pipe sleeve 11 and the end of two clamping pieces 121 Fixation is separably docked in portion, so that two clamping pieces 121 can be positioned with respect to pipe sleeve 11, pipeline 3.Specifically, clamping piece 121 End is threadedly coupled after there is the docking section 122 being parallel to each other, a bolt 124 to pass through two docking sections 122 with a nut 125.When Nut 125 can be realized the docking of two clamping pieces 121 and fix when tightening.
Ring flat-plate 13 is also there are two arc and quantity, not have ring flat-plate 13 corresponding with two clamping pieces 121 respectively.Ring flat-plate 13 is located at folder Between gripping member 121 and flexible blockage plate 14.Clamping piece 121 applies flexible blockage plate 14 by ring flat-plate 13 after positioning on pipe sleeve 11 Pressure, is biased towards equipment 2 for flexible blockage plate 14 and is adjacent to equipment 2.Adjustable angle between clamping piece 121 and ring flat-plate 13 leads to It crosses and the front and rear sides face of clamping piece 121 is made into not parallel and is realized with certain inclination angle, then ring flat-plate 13 can be biased flexibility Plugging plate 14 adapts to 2 metope of equipment with inclination angle.Each ring flat-plate 13 can also be first fixed with corresponding clamping piece 121.
When installation, flexible blockage plate 14 is first placed on pipeline 3 to and is adjacent to 21 position of interface, is then inserted in ring flat-plate 13 and pipe Pipe sleeve 11, is finally inserted in, with 124 nut of bolt, 125 Duct fixing clamp by folder.The flexible blockage apparatus structure of this structure is simple, It is convenient for disassembly and assembly, it is conveniently replaceable and safeguards.
Since pipe sleeve 11 and the contact area of pipeline 3 are larger, can be avoided when clamping piece 121 directly clamps pipeline 3 to pipe Road 3 causes to damage, if but do not consider this factor, pipe clamp can also be clamped directly on pipeline 3.Due to clamping piece 121 Rear end area is smaller, therefore works as clamping piece by the bigger ring flat-plate 13 of contact area come 14 better effect of bias flexible blockage plate 121 are then not provided with ring flat-plate 13 when sufficiently thick can also be with.
The specific structure is shown in FIG. 3 for flexible blockage plate 14 comprising the first plugging plate 141 of arc and the second plugging plate 142, the both ends of the first plugging plate 141 are separably docked with the both ends of the second plugging plate 142 respectively.Specifically, first blocks Two ends of plate 141 are respectively equipped with groove 146 and holding section 147, and two ends of the second plugging plate 142 are also respectively equipped with holding section 147 with groove 146, the first plugging plate 141 and the second plugging plate 142 can be achieved by the way that holding section 147 to be caught in groove 146 Docking.First plugging plate 141 is equipped with multiple gaps, these gaps radially extend and include extending to the first plugging plate First gap 143 of 141 inward flanges and outer peripheral second gap 144 for extending to flexible blockage plate 14, the first gap 143 It is arranged alternately on the first plugging plate 141 setting with the second gap 144.Likewise, also being provided with first on the second plugging plate 142 Gap 143 and the second gap 144.By the way that the first gap 143, the second gap 144 are arranged on flexible blockage plate 14, can make soft Property plugging plate 14 shows deformable flexible in structure.
The quantity of flexible blockage plate 14 can be for one or multiple in flexible blockage device, in the present embodiment diagram Specially three.
Compared with prior art, since the flexible blockage plate 14 in the utility model flexible blockage device is posted by equipment 2 Interface 21 at and equipment 2 is biased towards by pipe clamp, therefore can keep in the construction process to equipment 2 interface 21 and pipeline 3 it Between closure, effectively prevent foreign matter by being entered in equipment 2 or pipeline 3 at interface 21.Again due to pipe clamp be placed on pipeline 3 it On without being put into inside pipeline 3, therefore can't be limited in pipeline 3 end nearby and can be set on pipeline 3 Any position, the flexibility, adaptability when site layout project are higher.In addition, flexible blockage plate 14 is equipped with gap therefore in structure It is upper that there is certain flexibility, and flexible blockage plate 14 is not fixed with pipeline 3, therefore the vibration on pipeline 3 in the construction process Dynamic loading, which can be isolated, to be conducive to keep pipeline 3 and the structure of equipment 2 in the construction process without being transmitted in equipment 2 Completely.Finally, the present apparatus is simple in construction, easy to disassemble and assemble, convenient for safeguarding and replacement.
Above disclosed is only the preferred embodiments of the utility model, and effect is to facilitate those skilled in the art Understand and implement accordingly, the interest field of the utility model cannot be limited with this certainly, therefore special according to the present utility model application Equivalent variations made by sharp range still falls within the range that the utility model is covered.

Claims (10)

1. a kind of flexible blockage device, for blocking between equipment and pipeline, the pipeline is inserted into the interface in the equipment In, it is characterised in that:Including flexible blockage plate and pipe clamp, the flexible blockage plate is posted by a ring and around the interface The equipment, the flexible blockage plate are equipped with multiple gaps for extending to edge, and the pipe clamp is arranged and is positioned at the pipe With to flexible blockage plate described in the equipment bias on road.
2. flexible blockage device as described in claim 1, it is characterised in that:The flexible blockage plate includes the first envelope of arc Closure plate and the second plugging plate, the both ends of first plugging plate are separably docked with the both ends of second plugging plate respectively.
3. flexible blockage device as claimed in claim 2, it is characterised in that:One end of first plugging plate is equipped with recessed One end of slot, second plugging plate is equipped with holding section, and first plugging plate and the second plugging plate are by the holding section It is caught in the groove and docks.
4. flexible blockage device as described in claim 1, it is characterised in that:Radial direction of the gap along the flexible blockage plate Extend.
5. flexible blockage device as described in claim 1, it is characterised in that:It include several first gaps in multiple gaps With several second gaps, first gap extends to the inward flange of the flexible blockage plate, and second gap extends to institute State the outer edge of flexible blockage plate.
6. flexible blockage device as claimed in claim 5, it is characterised in that:Several first gaps and several described second Gap is arranged alternately setting on the flexible blockage plate.
7. flexible blockage device as described in claim 1, it is characterised in that:The pipe clamp includes the clamping piece of two arcs, It separably docks fixed and is positioned on the pipeline in the end of two clamping pieces.
8. flexible blockage device as claimed in claim 7, it is characterised in that:It further include the spiral shell set on the two clamping piece ends The end of bolt and nut, two clamping pieces fixation is docked by the threaded connection of the bolts and nuts.
9. flexible blockage device as claimed in claim 7, it is characterised in that:It further include two ring flat-plates, the two clamping piece difference Pass through flexible blockage plate described in the two ring flat-plate biass.
10. flexible blockage device as described in claim 1, it is characterised in that:It further include a pipe sleeve being placed on the pipeline, The pipe clamp and the flexible blockage plate are placed on the pipe sleeve.
CN201820381685.2U 2018-03-19 2018-03-19 Flexible blockage device Active CN208169707U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820381685.2U CN208169707U (en) 2018-03-19 2018-03-19 Flexible blockage device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820381685.2U CN208169707U (en) 2018-03-19 2018-03-19 Flexible blockage device

Publications (1)

Publication Number Publication Date
CN208169707U true CN208169707U (en) 2018-11-30

Family

ID=64373560

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820381685.2U Active CN208169707U (en) 2018-03-19 2018-03-19 Flexible blockage device

Country Status (1)

Country Link
CN (1) CN208169707U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111550611A (en) * 2020-05-09 2020-08-18 中铁八局集团建筑工程有限公司 Flexible unloading device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111550611A (en) * 2020-05-09 2020-08-18 中铁八局集团建筑工程有限公司 Flexible unloading device
CN111550611B (en) * 2020-05-09 2021-08-24 中铁八局集团建筑工程有限公司 Flexible unloading device

Similar Documents

Publication Publication Date Title
CN101706231B (en) Jet nozzle, nozzle for cleaning heat exchanger and cleaning method
CN109780350B (en) Liquid leakage-proof pipeline flange
CN208169707U (en) Flexible blockage device
JP6751796B1 (en) Steel pipe alignment jig
CN106704763B (en) Lined pipeline patching device
CN106322008A (en) Pipe fitting
US8176929B1 (en) Line-stopping sheath spigot assemblies and line-stopping sheath assemblies using the same
CN111076004B (en) Fire fighting pipeline installation structure and installation method thereof
CN203853736U (en) Positioning device for installing and butting pipelines
AU2016247565B2 (en) Pipe flange
CN211501977U (en) Aluminum alloy rail expansion piece
CN103939688B (en) A kind of aqueduct changed with fastener for connection for underground RPM
CN205479751U (en) A pipe strap for heat exchanger tube bundles is last
CN216843482U (en) High-sealing wear-resistant explosion-proof pipeline
KR101442690B1 (en) One-touch combined with a structure Collector Solar Collectors
CN208173249U (en) Connect plugging device
CN108662328A (en) A kind of drinking water pipeline no-dig technique liner reparation connector
CN208579053U (en) A kind of conveying material ceramic wear-resisting plumbing installation
CN204487442U (en) The auxiliary spanner that a kind of flanged dish Large Diameter Pipeline iron pipe is installed
CN208595307U (en) The support device of channel bend
CN210716474U (en) Flexible tee joint for pipeline
CN211449968U (en) Hydraulic engineering is with pipeline structure of convenient high-speed joint
CN105570544A (en) One-side hinged winding pipe hoop
CN114085944B (en) Combined jig frame for flue system and assembling method for flue system
CN210424160U (en) Natural gas line plugging device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant