CN208167776U - A kind of Wind turbines finish rolling Bar Anchorage basis break structure - Google Patents

A kind of Wind turbines finish rolling Bar Anchorage basis break structure Download PDF

Info

Publication number
CN208167776U
CN208167776U CN201820500875.1U CN201820500875U CN208167776U CN 208167776 U CN208167776 U CN 208167776U CN 201820500875 U CN201820500875 U CN 201820500875U CN 208167776 U CN208167776 U CN 208167776U
Authority
CN
China
Prior art keywords
finish rolling
anchor bolt
connector sleeve
reinforcing bar
strength anchor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820500875.1U
Other languages
Chinese (zh)
Inventor
李学旺
陈素芳
郭彪
王诚辉
张维庆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MingYang Smart Energy Group Co Ltd
Original Assignee
MingYang Smart Energy Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MingYang Smart Energy Group Co Ltd filed Critical MingYang Smart Energy Group Co Ltd
Priority to CN201820500875.1U priority Critical patent/CN208167776U/en
Application granted granted Critical
Publication of CN208167776U publication Critical patent/CN208167776U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)

Abstract

The utility model discloses a kind of Wind turbines finish rolling Bar Anchorage basis break structures, including high-strength anchor bolt, connector sleeve, stop nut, supporting sleeve, fixture nut;Stop nut, connector sleeve sequentially successively screw in the top of finish rolling reinforcing bar, and after connector sleeve screw-in, need to loosen stop nut counter-tightened to avoid connecting between connector sleeve and finish rolling reinforcing bar;High-strength anchor bolt screw thread is tightened against on connector sleeve, after tightening, supporting sleeve is set on high-strength anchor bolt, and its bottom contacts at tower flange in the bottom, supporting sleeve covers the top of connector sleeve, stop nut and finish rolling reinforcing bar simultaneously, and supporting sleeve is stretched out outside the top of high-strength anchor bolt, and be screwed into fixture nut and carry out stretching preload.The utility model improves the tension performance of integral fastening structure, can lose to avoid tensioning pretightning force, improve basic fatigue capacity by giving one section of high-strength anchor bolt of finish rolling steel bar joining.

Description

A kind of Wind turbines finish rolling Bar Anchorage basis break structure
Technical field
The utility model relates to the technical fields on Wind turbines finish rolling Bar Anchorage basis, refer in particular to a kind of Wind turbines Finish rolling Bar Anchorage basis break structure.
Background technique
Finish rolling reinforcing bar is widely used in building structure earth anchor engineering, and there is connection to anchor, and easy, adhesion strength is strong, tensioning peace Entirely, the advantages that easy for construction.But finish rolling reinforcing bar essence is spiral for building, is not able to satisfy machanical fastener standard to material The requirement of matter, performance etc..With the progress and accumulation of knowledge of industry technology, it has been determined that finish rolling reinforcing bar cannot be used for wind-powered electricity generation row Industry.But since finish rolling reinforcing bar price is far below high-strength anchor bolt, in China, Wind Power Development early stage, finish rolling reinforcing bar are also widely used in wind The anchor bolt basis of motor group.It has now been found that anchor bolt breakage problem occur in multiple wind power plants using finish rolling reinforcing bar basis, gives machine Group operation causes huge security risk.Due to the buried underground of anchor bolt, replacement is difficult with reparation, therefore takes before anchor bolt fracture Precautionary measures are most economical reasonable schemes.
Compared to high-strength anchor bolt, finish rolling reinforcing bar has following features:
1, material hardness is big, and yield strength is high, and elastic property is poor, and brittleness is very big;
It 2, is rolling half-thread, it is small with matching nut contact area, it is easy to be broken in occlusal position;
3, tensioning is difficult, and pretightning force is easy to produce heavy losses;
4, accuracy of thread is low, and nut connection is easy to loosen.
The pretightning force of anchor bolt is most important to fatigue carrying, due to the above characteristic of finish rolling reinforcing bar, damages pretightning force seriously It loses, fatigue capacity weakens rapidly.And finish rolling reinforcing bar anchor bolt major cause of failure, as pretightning force reduce caused fatigue Fracture.
Known in the industry, the use on Wind turbines finish rolling Bar Anchorage basis is the not mature enough table of Wind Power Development earlier technique It is existing, it there is no thorough solution at present.Be broken serious wind field in certain basic finish rolling reinforcing bar anchor bolts, take dig vertical shaft into Enter foundation bottom, the method that finish rolling reinforcing bar is changed to steel strand wires, but program cost is high, and the duration is very long, and simultaneously uncomfortable For all foundation soil types.
Utility model content
The shortcomings that the purpose of the utility model is to overcome the prior arts and deficiency propose a kind of safe and reliable wind-powered electricity generation Unit finish rolling Bar Anchorage basis break structure improves integral fastening structure by giving one section of high-strength anchor bolt of finish rolling steel bar joining Tension performance, can be lost to avoid tensioning pretightning force, improve basic fatigue capacity.
To achieve the above object, technical solution provided by the utility model is:A kind of Wind turbines finish rolling Bar Anchorage Basic break structure includes high-strength anchor bolt, connector sleeve, stop nut, supporting sleeve, fixture nut;The connector sleeve is two End band internal thread high-strength oil casing structure, one end are connect with finish rolling screw thread steel, and the other end and high-strength anchor bolt screw thread connect It connects;The stop nut, connector sleeve sequentially successively screw in finish rolling reinforcing bar top, and after connector sleeve screw-in after, need by Stop nut counter-tightened loosens to avoid connecting between connector sleeve and finish rolling reinforcing bar, wherein the finish rolling reinforcing bar is to wear vertically Cross the tower flange in the bottom of Wind turbines;The high-strength anchor bolt screw thread is tightened against on connector sleeve, after tightening, the supporting sleeve It is set on high-strength anchor bolt, and its bottom contacts at tower flange in the bottom, while the supporting sleeve covers connector sleeve, locking spiral shell Female and finish rolling reinforcing bar top, and supporting sleeve is stretched out outside the top of the high-strength anchor bolt, and be screwed into fixture nut and stretched It pre-tightens.
Clip pad has gasket between the fixture nut and the top of supporting sleeve.
The utility model compared with prior art, has the following advantages that and beneficial effect:
By adding one section of high-strength anchor bolt on finish rolling reinforcing bar top, increasing the elastoplasticity of entire foundation anchor structure and opening Drawing ability is easier to maintain the pretightning force of anchor structure, in this way when basis carrying, becomes by the elasticity of top high-strength anchor bolt Shape is buffered, can be to avoid violent fatigue stress is generated inside finish rolling reinforcing bar, to improve finish rolling Bar Anchorage basis Safety solves the problems, such as that finish rolling reinforcing bar is caused to be broken.It is broken in addition, this programme does not generate original basis structure and tower structure It is bad, unit operation risk can be reduced to greatest extent.
Detailed description of the invention
Fig. 1 is one of the scheme of installation of Wind turbines finish rolling Bar Anchorage basis break structure (cross-sectional view).
Fig. 2 is two (single unilateral side appearances of the scheme of installation of Wind turbines finish rolling Bar Anchorage basis break structure Figure).
Fig. 3 is the connection schematic diagram of finish rolling reinforcing bar and high-strength anchor bolt.
Fig. 4 is the structural schematic diagram of supporting sleeve.
Specific embodiment
The utility model is described in further detail combined with specific embodiments below.
Referring to FIG. 1 to FIG. 4, Wind turbines finish rolling Bar Anchorage basis break structure provided by the present embodiment, packet High-strength anchor bolt 1, connector sleeve 2, stop nut 3, supporting sleeve 4, fixture nut 5, gasket 6 are included;The connector sleeve 2 is both ends band Internal thread high-strength oil casing structure, one end are threadedly coupled with finish rolling reinforcing bar 7, and the other end is threadedly coupled with high-strength anchor bolt 1; The stop nut 3, connector sleeve 2 sequentially successively screw in finish rolling reinforcing bar 1 top, and after connector sleeve 2 screw-in after, need by 3 counter-tightened of stop nut loosens to avoid connecting between connector sleeve 2 and finish rolling reinforcing bar 7, wherein the finish rolling reinforcing bar 7 is perpendicular Direct puncture crosses the tower flange in the bottom 8 of Wind turbines, and has in the inside and outside two sides of tower 9;1 screw thread of high-strength anchor bolt is tightened against On connector sleeve 2, after tightening, the supporting sleeve 4 is set on high-strength anchor bolt 1, and its bottom contacts at tower flange in the bottom 8, while the supporting sleeve 4 covers the top of connector sleeve 2, stop nut 3 and finish rolling reinforcing bar 7, and the high-strength anchor bolt 1 is upper Supporting sleeve 4 is stretched out outside portion, and is screwed into fixture nut 5 and is carried out stretching preload, meanwhile, the fixture nut 5 and supporting sleeve 4 Clip pad has gasket 6 between top.
In conclusion the utility model increases entire basis by adding one section of high-strength anchor bolt on finish rolling reinforcing bar top The elastoplasticity and tensioning ability of anchor structure, are easier to maintain the pretightning force of anchor structure, in this way when basis carrying, rely on The flexible deformation of top high-strength anchor bolt is buffered, and can be solved to avoid violent fatigue stress is generated inside finish rolling reinforcing bar The problem of causing finish rolling reinforcing bar to be broken, so that the safety on finish rolling Bar Anchorage basis is improved, in addition, this programme is not to original basis Structure and tower structure generate destruction, can reduce unit operation risk to greatest extent, have actual promotional value, are worth pushing away Extensively.
Embodiment described above is only the preferred embodiment of the utility model, and the implementation of the utility model is not limited with this Range, therefore all shapes according to the utility model, change made by principle, it should all cover within the protection scope of the present utility model.

Claims (2)

1. a kind of Wind turbines finish rolling Bar Anchorage basis break structure, it is characterised in that:Include high-strength anchor bolt, connector sleeve, Stop nut, supporting sleeve, fixture nut;The connector sleeve be both ends band internal thread high-strength oil casing structure, one end with The connection of finish rolling screw thread steel, the other end are threadedly coupled with high-strength anchor bolt;The stop nut, connector sleeve are sequentially successively The top of finish rolling reinforcing bar is screwed in, and after connector sleeve screw-in, it need to be by stop nut counter-tightened, to avoid connector sleeve and finish rolling steel It connects and loosens between muscle, wherein the finish rolling reinforcing bar is the tower flange in the bottom for passing vertically through Wind turbines;The high-strength anchor bolt Screw thread is tightened against on connector sleeve, and after tightening, the supporting sleeve is set on high-strength anchor bolt, and its bottom contacts at tower bottom Portion's flange, while the supporting sleeve covers the top of connector sleeve, stop nut and finish rolling reinforcing bar, and the high-strength anchor bolt is upper Supporting sleeve is stretched out outside portion, and is screwed into fixture nut and is carried out stretching preload.
2. a kind of Wind turbines finish rolling Bar Anchorage basis break structure according to claim 1, it is characterised in that:It is described Clip pad has gasket between fixture nut and the top of supporting sleeve.
CN201820500875.1U 2018-04-10 2018-04-10 A kind of Wind turbines finish rolling Bar Anchorage basis break structure Active CN208167776U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820500875.1U CN208167776U (en) 2018-04-10 2018-04-10 A kind of Wind turbines finish rolling Bar Anchorage basis break structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820500875.1U CN208167776U (en) 2018-04-10 2018-04-10 A kind of Wind turbines finish rolling Bar Anchorage basis break structure

Publications (1)

Publication Number Publication Date
CN208167776U true CN208167776U (en) 2018-11-30

Family

ID=64374147

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820500875.1U Active CN208167776U (en) 2018-04-10 2018-04-10 A kind of Wind turbines finish rolling Bar Anchorage basis break structure

Country Status (1)

Country Link
CN (1) CN208167776U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110130424A (en) * 2019-05-06 2019-08-16 同济大学 Prestressed bolt blower foundation reinforcement means

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110130424A (en) * 2019-05-06 2019-08-16 同济大学 Prestressed bolt blower foundation reinforcement means
CN110130424B (en) * 2019-05-06 2020-08-14 同济大学 Method for reinforcing prestressed anchor bolt fan foundation

Similar Documents

Publication Publication Date Title
CN203383401U (en) Clamping anchor for carbon-fiber composite material bar
CN208167776U (en) A kind of Wind turbines finish rolling Bar Anchorage basis break structure
CN220928904U (en) Electric power stay wire fitting
CN202349448U (en) Hoop structure for tightly fastening pipes
CN202611109U (en) Steel strand connector
CN203347322U (en) Electric pole stay wire clamping apparatus
CN206674808U (en) A kind of net cage mooring anchor chain for adapting to the higher-order of oscillation and impact load
CN202000653U (en) Steel pipe scaffold lack catch
CN202768603U (en) Locking sheet for tower drum connecting bolt of wind turbine
CN112332350A (en) Closed shell wedge-shaped strain clamp for overhead insulated conductor
CN203175139U (en) Novel U-shaped stay wire hoop
CN204012584U (en) Circuit suspension clamp
CN206829745U (en) For the high-rise prestressed, reinforced concrete filled steel tube support member for freezing storehouse
CN211145074U (en) Roughening device suitable for foundation bolt
CN106340828A (en) Special tool for replacing duplex stay wire and fittings of power transmission line
CN204267473U (en) A kind of cement bolt
CN210025762U (en) Precast concrete tower section of thick bamboo connecting piece
CN203188601U (en) Anti-upwarp clamp for scaffold board
CN207905992U (en) A kind of tower cylinder connecting structure of wind generating set
CN212063297U (en) Cable hoop
CN205001332U (en) Medical bed board coupling mechanism
CN205605984U (en) Handle fastening chain formula pipe strap
CN200978679Y (en) Glass fibre reinforced plastic quick-acting self-locking anchor bolt
CN218117965U (en) Fan tower cylinder flange connection structure
CN218912220U (en) Fastener for fixing wood scaffold board

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant