CN208152040U - Device is fixed with stake in a kind of construction site - Google Patents
Device is fixed with stake in a kind of construction site Download PDFInfo
- Publication number
- CN208152040U CN208152040U CN201820712802.9U CN201820712802U CN208152040U CN 208152040 U CN208152040 U CN 208152040U CN 201820712802 U CN201820712802 U CN 201820712802U CN 208152040 U CN208152040 U CN 208152040U
- Authority
- CN
- China
- Prior art keywords
- fixed
- fixedly connected
- stake
- wall
- mounting blocks
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model discloses a kind of construction sites to fix device with stake, including mounting blocks, multiple support devices are symmetrically fixedly connected on the side wall of the mounting blocks, run through at the center of the mounting blocks and is communicated with fixing pipe, clamping device is symmetrically fixedly connected on the fixed inside pipe wall, a plurality of cavities are symmetrically arranged in the mounting blocks, the inner wall of each cavity on slidably connect sealing-plug, brill the thin end of the scroll is fixedly connected on the downside of each sealing-plug, the other end for boring the thin end of the scroll offsets through the inner wall of cavity with ground, the side wall of each cavity is equipped with multiple circular channels, the cavity is connected by circular channel with fixing pipe.Device is fixed in spud pile with stake in this kind of novel building building site of the utility model, increase the contact area of fixed device and the earth, allow fixed device well with greatly contact, so as to be brought conveniently to construction in later period on the ground by stake being fixed on steadily is big, promote the progress of construction.
Description
Technical field
The utility model relates to technical field of buildings more particularly to a kind of construction site to fix device with stake.
Background technique
Device with stake is fixed in present construction site, and there are many kinds of classes, have different use under different conditions, with work
The continuous development of journey technology, novel construction site stake purposes in engineering construction is more and more extensive, and different pile-type is special
Point is also different;Modern major part construction site stake is not enough, so as to cause solid in spud pile due to contacting with the earth
Fixed stake very steady can not fix on the ground, and larger problem is brought to construction in later period, affects the progress of construction.
Utility model content
Purpose of the utility model is to solve problems of the prior art, such as:Modern major part construction site
With stake in spud pile, due to contacting and be not enough with the earth, so as to cause fixed stake can not be very steady be fixed on ground
On, larger problem is brought to construction in later period, affects the progress of construction, and dress is fixed with stake in a kind of construction site proposed
It sets.
To achieve the goals above, the utility model uses following technical solution:
Device is fixed with stake in a kind of construction site, including device, including mounting blocks are fixed with stake in a kind of construction site, described
It is symmetrically fixedly connected with multiple support devices on the side wall of mounting blocks, runs through at the center of the mounting blocks and is communicated with fixing pipe,
It is symmetrically fixedly connected with clamping device on the fixed inside pipe wall, is symmetrically arranged with a plurality of cavities in the mounting blocks, it is each described
The inner wall of cavity on slidably connect sealing-plug, brill the thin end of the scroll, the brill are fixedly connected on the downside of each sealing-plug
The other end of the thin end of the scroll offsets through the inner wall of cavity with ground, and the side wall of each cavity is equipped with multiple circular channels, institute
It states cavity and is connected by circular channel with fixing pipe, telescopic rod is slidably connected on the circular channel inner wall, it is described flexible
One end of bar is fixedly connected with fixed plug.
Preferably, the clamping device includes follow block, and the side of the follow block slidably connects spud pile, the follow block
The other side is fixedly connected with the first spring, and the other end of first spring is fixedly connected on the inner wall of fixing pipe, described to stretch
One end away from fixed plug of contracting bar is fixed on follow block.
Preferably, the support device includes fixed block, and limited block, the fixed block are fixedly connected on the fixed block
On be rotatably connected to shaft, rotating bar is fixedly connected in the shaft, the side of the rotating bar is fixedly connected with the second bullet
Spring, the second spring other end are fixedly connected on mounting blocks, and the other end of the rotating bar is fixedly connected with support plate.
Preferably, be symmetrically fixedly connected with multiple foam-rubber cushions on the inner wall of the fixing pipe, each foam-rubber cushion with support
Plate offsets.
Preferably, the mounting blocks are cylinder.
In the utility model, device is fixed in spud pile with stake in this kind of novel building building site, increase fixed device with
The contact area of the earth, allow fixed device well with greatly contact, so as to by stake steadily be fixed on big ground
It is brought conveniently to construction in later period, promotes the progress of construction.
Detailed description of the invention
Fig. 1 be the utility model proposes a kind of construction site fix with stake the structural schematic diagram of device;
Fig. 2 be the utility model proposes a kind of construction site fix with stake the overlooking structure diagram of device.
In figure:1 mounting blocks, 2 foam-rubber cushions, 3 spud piles, 4 follow blocks, 5 first springs, 6 fixed plugs, 7 cavitys, 8 telescopic rods, 9
The thin end of the scroll, 16 fixing pipes, 17 limits are bored in fixed block, 10 shafts, 11 rotating bars, 12 support plates, 13 second springs, 14 sealing-plugs, 15
Block.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.
In the description of the present invention, it should be understood that term " on ", "lower", "front", "rear", "left", "right",
The orientation or positional relationship of the instructions such as "top", "bottom", "inner", "outside" is to be based on the orientation or positional relationship shown in the drawings, and is only
For ease of description the utility model and simplify description, rather than the device or element of indication or suggestion meaning must have it is specific
Orientation, be constructed and operated in a specific orientation, therefore should not be understood as limiting the present invention.
Referring to Fig.1-2, device, including mounting blocks 1 are fixed with stake in a kind of construction site, and mounting blocks 1 are cylinder, convenient solid
Determine the insertion and fixation of stake 3, multiple support devices are symmetrically fixedly connected on the side wall of mounting blocks 1, support device includes fixing
Block 9 is fixedly connected with limited block 17 on fixed block 9, shaft 10 is rotatably connected on fixed block 9, is fixedly connected in shaft 10
Rotating bar 11,11 side of rotating bar are fixedly connected with second spring 13, and 13 other end of second spring is fixedly connected on mounting blocks 1
On, the other end of rotating bar 11 is fixedly connected with support plate 12, fixed block 9 since mounting blocks 1 are to sinking can also move downward, Gu
The shaft 10 determined on block 9 can rotate, and drive rotating bar 11 to both sides bifurcated, and rotating bar 11 will drive the contact the earth of support plate 12,
And slided to both sides, the contact area of fixed device and the earth is increased, runs through at the center of mounting blocks 1 and is communicated with fixing pipe
16, multiple foam-rubber cushions 2 are symmetrically fixedly connected on the inner wall of fixing pipe 16, and each foam-rubber cushion 2 offsets with follow block 4, and foam-rubber cushion 2 is right
Follow block 4 has support buffer function, is symmetrically fixedly connected with clamping device on 16 inner wall of fixing pipe, and clamping device includes follow block 4,
The side of follow block 4 slidably connects spud pile 3, and the other side of follow block 4 is fixedly connected with the first spring 5, the first spring 5 it is another
End is fixedly connected on the inner wall of fixing pipe 16, and one end away from fixed plug 6 of telescopic rod 8 is fixed on follow block 4, by spud pile
3 one end is placed on the entrance of fixing pipe 16 slowly, and at this moment staff vertically beats the other end of spud pile 3 with hammer,
Spud pile 3 will slowly drop in fixing pipe 16 at this time, until the insertion the earth of spud pile 3, in this process, spud pile 3
Side wall can squeeze the follow block 4 of surrounding, and follow block 4 can squeeze foam-rubber cushion 2 respectively and the first spring 5, foam-rubber cushion 2 and the first spring 5 exist
In the case where compression can reaction give follow block 4 one elastic force, make being against on spud pile 3 tightly of follow block 4, tightly by spud pile 3
Be fixed in fixing pipe 16, be symmetrically arranged with a plurality of cavities 7 in mounting blocks 1, the inner wall of each cavity 7 on slidably connect it is close
Blocking 14, the downside of each sealing-plug 14, which is fixedly connected to, bores the thin end of the scroll 15, and the other end for boring the thin end of the scroll 15 runs through the inner wall of cavity 7
It offsets with ground, the side wall of each cavity 7 is equipped with multiple circular channels, and cavity 7 is connected by circular channel with fixing pipe 16
It is logical, telescopic rod 8 is slidably connected on circular channel inner wall, one end of telescopic rod 8 is fixedly connected with fixed plug 6.
In the utility model, when fixing device with stake using the construction site, firstly, cylindrical mounting blocks 1 are put
Then one end of spud pile 3 is placed on to the entrance of fixing pipe 16 slowly on the ground big, at this moment staff's hammer vertical hammer
The other end of spud pile 3 is beaten, spud pile 3 will slowly drop in fixing pipe 16 at this time, until the insertion the earth of spud pile 3, at this
During a, the side wall of spud pile 3 can squeeze the follow block 4 of surrounding, and follow block 4 can squeeze foam-rubber cushion 2 and the first spring 5, sea respectively
Continuous pad 2 and the first spring 5 in the case where compression can reaction give follow block 4 one elastic force, make follow block 4 tightly be against spud pile
On 3, spud pile 3 is firmly secured in fixing pipe 16, while follow block 4 can squeeze telescopic rod 8, telescopic rod 8 will push fixation
Air in 6 compressing cavity 7 of plug, since multiple telescopic rods 8 and fixed plug 6 are deep into cavity 7, the air pressure in cavity 7 can become
Greatly, the air pressure at this moment in cavity 7 will push sealing-plug 14 along the inner wall slide downward of cavity 7, while sealing-plug 14 will push
Bore the thin end of the scroll 15 move downward, until bore the thin end of the scroll 15 the other end be inserted into the earth, secondly, fixed block 9 due to mounting blocks 1 to sink
It can move downward, the shaft 10 on fixed block 9 can rotate, and drive rotating bar 11 to both sides bifurcated, rotating bar 11 will drive support
The contact the earth of plate 12, and slided to both sides, the contact area of fixed device and the earth is increased, after use, will be fixed
Stake 3 is extracted from fixed device, and the rotating bar 11 on fixation device side face restores original-pack under the effect of 13 elastic force of second spring, together
When, follow block 4 can also restore to the original state under foam-rubber cushion 2 and the effect of 5 elastic force of the first spring, and at this moment the air pressure in cavity 7 becomes smaller, and outer
Boundary forms negative pressure, and at this moment sealing-plug 14 will drive under the action of pressure difference bores in the retraction cavity 7 of the thin end of the scroll 15.
The preferable specific embodiment of the above, only the utility model, but the protection scope of the utility model is not
It is confined to this, anyone skilled in the art is within the technical scope disclosed by the utility model, practical according to this
Novel technical solution and its utility model design are subject to equivalent substitution or change, should all cover the protection model in the utility model
Within enclosing.
Claims (5)
1. device, including mounting blocks are fixed with stake in a kind of construction site(1), which is characterized in that the mounting blocks(1)Side wall on
Symmetrically it is fixedly connected with multiple support devices, the mounting blocks(1)Center at through being communicated with fixing pipe(16), the fixation
Pipe(16)Clamping device, the mounting blocks are symmetrically fixedly connected on inner wall(1)Inside it is symmetrically arranged with a plurality of cavities(7), Mei Gesuo
State cavity(7)Inner wall on slidably connect sealing-plug(14), each sealing-plug(14)Downside be fixedly connected to
Bore the thin end of the scroll(15), the brill the thin end of the scroll(15)The other end run through cavity(7)Inner wall offset with ground, each cavity(7)
Side wall be equipped with multiple circular channels, the cavity(7)Pass through circular channel and fixing pipe(16)It is connected, it is described round logical
Telescopic rod is slidably connected on road inner wall(8), the telescopic rod(8)One end be fixedly connected with fixed plug(6).
2. device is fixed with stake in a kind of construction site according to claim 1, which is characterized in that the clamping device includes
Follow block(4), the follow block(4)Side slidably connect spud pile(3), the follow block(4)The other side be fixedly connected with
One spring(5), first spring(5)The other end be fixedly connected on fixing pipe(16)Inner wall on, the telescopic rod(8)'s
It is filled in away from fixed(6)One end be fixed on follow block(4)On.
3. device is fixed with stake in a kind of construction site according to claim 1, which is characterized in that the support device includes
Fixed block(9), the fixed block(9)On be fixedly connected with limited block(17), the fixed block(9)On be rotatably connected to shaft
(10), the shaft(10)On be fixedly connected with rotating bar(11), the rotating bar(11)Side is fixedly connected with second spring
(13), the second spring(13)The other end is fixedly connected on mounting blocks(1)On, the rotating bar(11)The other end fixed connect
It is connected to support plate(12).
4. device is fixed with stake in a kind of construction site according to claim 1, which is characterized in that the fixing pipe(16)'s
Multiple foam-rubber cushions are symmetrically fixedly connected on inner wall(2), each foam-rubber cushion(2)With follow block(4)It offsets.
5. device is fixed with stake in a kind of construction site according to claim 1, which is characterized in that the mounting blocks(1)For
It is cylindrical.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820712802.9U CN208152040U (en) | 2018-05-14 | 2018-05-14 | Device is fixed with stake in a kind of construction site |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820712802.9U CN208152040U (en) | 2018-05-14 | 2018-05-14 | Device is fixed with stake in a kind of construction site |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208152040U true CN208152040U (en) | 2018-11-27 |
Family
ID=64390550
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820712802.9U Expired - Fee Related CN208152040U (en) | 2018-05-14 | 2018-05-14 | Device is fixed with stake in a kind of construction site |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208152040U (en) |
-
2018
- 2018-05-14 CN CN201820712802.9U patent/CN208152040U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208057139U (en) | A kind of tension and compression coupling deformation anchor pole | |
CN208152040U (en) | Device is fixed with stake in a kind of construction site | |
CN107829679A (en) | A kind of construction safety-type rig of coagulation rammed earth | |
CN114165943A (en) | Ground source heat pump | |
CN214472996U (en) | Tunnel detection knocker | |
CN214702809U (en) | Hydraulic engineering ground soil sampling device | |
CN110359447A (en) | A kind of tubing string | |
CN214089829U (en) | Building pile for building | |
CN215290301U (en) | Portable foundation ditch monitoring devices for engineering with shock-absorbing function | |
CN213482003U (en) | Rainwater infiltration detection device suitable for sponge city | |
CN213173658U (en) | Dyke foundation reinforcing structure facility | |
CN208174732U (en) | A kind of interchanger for intelligent security guard | |
CN210507439U (en) | Piling steam hammer with telescopic ruler | |
CN208605213U (en) | A kind of concertina type grouted anchor bar | |
CN208586597U (en) | A kind of bridge construction geology sampler | |
CN111595388A (en) | Humiture sensing intelligence stock | |
CN214498555U (en) | Damping device of civil engineering structure | |
CN214033772U (en) | Anti-seismic building foundation | |
CN211816362U (en) | Pile foundation securing device for civil engineering | |
CN207420523U (en) | Rotary digging cylinder bores bottom plate fishing device | |
CN216617436U (en) | Drill bit for petroleum drilling | |
CN208347727U (en) | A kind of hydraulic anchor for field of petroleum exploitation | |
CN210977494U (en) | Balancing device for slurry balance pipe-jacking tunneling machine | |
CN209990620U (en) | Fracturing pump protection device | |
CN214708245U (en) | Building tunnel construction 5G communication equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20181127 Termination date: 20190514 |
|
CF01 | Termination of patent right due to non-payment of annual fee |