CN208112223U - Power of alterating and direct current multi-function test stand distribution system - Google Patents

Power of alterating and direct current multi-function test stand distribution system Download PDF

Info

Publication number
CN208112223U
CN208112223U CN201721628608.4U CN201721628608U CN208112223U CN 208112223 U CN208112223 U CN 208112223U CN 201721628608 U CN201721628608 U CN 201721628608U CN 208112223 U CN208112223 U CN 208112223U
Authority
CN
China
Prior art keywords
power
alternating current
phase
distribution
controller
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721628608.4U
Other languages
Chinese (zh)
Inventor
刘克林
林亮
董华林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHENGDU FEIYA AIRBORNE EQUIPMENT APPLICATION RESEARCH Co Ltd
Original Assignee
CHENGDU FEIYA AIRBORNE EQUIPMENT APPLICATION RESEARCH Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHENGDU FEIYA AIRBORNE EQUIPMENT APPLICATION RESEARCH Co Ltd filed Critical CHENGDU FEIYA AIRBORNE EQUIPMENT APPLICATION RESEARCH Co Ltd
Priority to CN201721628608.4U priority Critical patent/CN208112223U/en
Application granted granted Critical
Publication of CN208112223U publication Critical patent/CN208112223U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Emergency Protection Circuit Devices (AREA)

Abstract

The utility model discloses a kind of power of alterating and direct current multi-function test stand distribution systems, including power distribution cabinet and distribution box, general supply controller is equipped in the power distribution cabinet, for the distribution box output three-phase alternating current to general supply controller, alternating current is distributed to corresponding electrical equipment by general supply controller.The utility model introduces the overcurrent relay of three 0~9.99A in the three-phase alternating current of power supply, by matching 50 outside:1 D.C mutual-inductor come realize when any one phase current in system line be more than setting electric current when, just disconnect system input power protection circuit function.After 380V power supply introducing system, power supply a part of general supply controller supplies frequency conversion tank three-phase 380V alternating current by voltage output controller, another part then with frequency conversion tank isolated from power, station, programmable power supply and the single-phase 220V alternating current of load box, the electric energy for completing distribution system is supplied by one-way safety isolating transformer and voltage output controller to share out the work.

Description

Power of alterating and direct current multi-function test stand distribution system
Technical field
The utility model relates to a kind of power of alterating and direct current multi-function test stand distribution systems.
Background technique
Power distribution cabinet sub-power power distribution cabinet, light distribution cabinet and metering cabinet are the final stage devices of distribution system.Power distribution cabinet is electricity The general designation of motivation control centre is often used in the occasion that load is more dispersed, circuit is less, and effect is upper level controller switching equipment The electric energy of a certain circuit distributes to nearest load, is protected, monitored and is controlled to load.Power distribution cabinet application non-combustible materials Production, each electrical component, instrument, switch and route are answered marshalling, are firmly installed, easy to operate.There must not be bare tape other than cabinet The electric external electrical component that reveals and must be installed on cabinet outer surface or power distribution cabinet, it is necessary to have reliable screen shield.Its product is adopted Of large-screen lc touch screen, the power qualities such as voltage, electric current, frequency, available power, useless power, electric energy, harmonic wave are made entirely The monitoring in orientation keeps user very clear to distribution system operation conditions, in order to find security risk early, evades wind early Danger.
Utility model content
The purpose of the utility model is to overcome the deficiencies in the prior art, a kind of power of alterating and direct current multi-function test stand is provided and is matched Electric system.
The purpose of this utility model is achieved through the following technical solutions:Power of alterating and direct current multi-function test stand power distribution system System, including power distribution cabinet and distribution box, the power distribution cabinet is interior to be equipped with general supply controller, and the distribution box output three-phase alternating current is extremely Alternating current is distributed to corresponding electrical equipment by general supply controller, general supply controller.
Several voltage output controllers are additionally provided in the power distribution cabinet, the alternating current of general supply controller distribution is through voltage O controller is input to corresponding electrical equipment.
The electrical equipment includes frequency conversion tank, station, programmable power supply and load box.
Three-phase alternating current is distributed to frequency conversion tank, general supply control through voltage output controller by the general supply controller Single-phase electricity is distributed to station, programmable power supply and load box through voltage output controller respectively by device.
Further include several one-way safety isolating transformers, the single-phase electricity of general supply controller distribution respectively through one-way safety every Station, programmable power supply and load box are distributed to from transformer, voltage output controller.
The friendship that connection is matched there are three overcurrent relay and respectively with three overcurrent relays is set in the distribution box Current transformer, each phase of three-phase alternating current concatenates an overcurrent relay respectively, by the three-phase alternating current of overcurrent relay It is input in power distribution cabinet.
Air switch is additionally provided in the distribution box, external three-phase alternating current is through in air switch input distribution box.
Phase sequence relay is additionally provided in the power distribution cabinet, the three-phase alternating current that distribution box is input to power distribution cabinet is first input into Phase sequence relay, then general supply controller is input to by phase sequence relay.
The power supply of entire testing stand is 380V/50Hz three-phase four-wire system, and external power supply separates frequency conversion after entering power distribution cabinet Cabinet, station, programmable power supply, load box and dragging platform.
Monitoring and power distribution unit of the power distribution cabinet as input power, by 380V input display, sequence examing and instruction, Inverter supply instruction, air blower power supply instruction, load box case cooling fan power supply instruction, dragging platform cooling fan power supply refer to Show, programmable power supply cabinet power supply instruction, operate the compositions such as control cabinet power supply instruction.
The utility model has the beneficial effects that:
1)Phase sequence relay is installed inside power distribution cabinet, is used as sequence examing, is only just connect when input power phase sequence is correct Logical main contactor, avoiding some special electromechanical equipments because of reversing after power phase is reversed leads to accident or equipment damage.
2)Three overcurrent relays are introduced in the three-phase alternating current of power supply, and system is worked as to realize by D.C mutual-inductor When any one phase current in route is more than setting electric current, function that just disconnection system input power is protected.
3)System increases air switch, as long as electric current is more than that rated current will disconnect progress overcurrent guarantor automatically in circuit Shield, in addition to it can complete contact and disjunction circuit, moreover it is possible to short circuit, heavy overload and the under-voltage etc. that circuit or electrical equipment are occurred It is protected.
Detailed description of the invention
Fig. 1 is the utility model principle block diagram.
Specific embodiment
Below in conjunction with embodiment, the technical solution of the utility model is clearly and completely described, it is clear that retouched The embodiment stated is only the utility model a part of the embodiment, instead of all the embodiments.Based in the utility model Embodiment, those skilled in the art's every other embodiment obtained under the premise of not making the creative labor, all belongs to In the range of the utility model protection.
Refering to fig. 1, the utility model provides a kind of technical solution:Power of alterating and direct current multi-function test stand distribution system, including Power distribution cabinet and distribution box, the power distribution cabinet is interior to be equipped with general supply controller, and the distribution box exports three-phase alternating current to general supply Alternating current is distributed to corresponding electrical equipment by controller, general supply controller.Computer and central controller in general supply controller Power supply requirement property according to electrical equipment carries out reasonability control to power supply.
Several voltage output controllers are additionally provided in the power distribution cabinet, the alternating current of general supply controller distribution is through voltage O controller is input to corresponding electrical equipment, and the electrical equipment includes frequency conversion tank, station, programmable power supply and load Case.
The frequency conversion tank realizes the control action for dragging platform on aircraft at a high speed using internal frequency converter, realizes high speed variable-frequency electric The speed regulating control of machine.
The station is the core component of whole system, is responsible for the integrated management of all test resources, and station uses The design of PXI bussing technique works come the function of completing whole system and performance test.
The programmable power supply be divided into program-control DC power with exchange programmable power supply two parts, it acts as carry out power supply system When system performance test, electric current is exported to meet the different power supply requirement of tested department enclosure.
The load box is mainly made of AC load case and DC load case, for simulating aircraft electrical equipment, will be flown The utilization of power load box that machine generator issues is consumed, to verify the working characteristics of generator.According to testing requirement, load Case interior design has resistance/capacitance/inductive load case, cooling fan, temperature detection and protection circuit, load box output control electricity Road, Switching Power Supply etc..
Three-phase alternating current is distributed to frequency conversion tank, general supply control through voltage output controller by the general supply controller Single-phase electricity is distributed to station, programmable power supply and load box through voltage output controller respectively by device.
The power of alterating and direct current multi-function test stand distribution system further includes several one-way safety isolating transformers, general supply The single-phase electricity of controller distribution distributes to station, program-controlled electric through one-way safety isolating transformer, voltage output controller respectively Source and load box.The one-way safety isolating transformer is made defeated by the insulation at least corresponding to double insulation or reinforcing insulating Enter winding electrically separating with output winding, single-phase electricity is transported to by voltage output controller, voltage output with extra low voltage Voltage is then delivered to station, programmable power supply and load box according to the nominal parameter of electrical equipment by controller.
The friendship that connection is matched there are three overcurrent relay and respectively with three overcurrent relays is set in the distribution box Current transformer, each phase of three-phase alternating current concatenates an overcurrent relay respectively, by the three-phase alternating current of overcurrent relay It is input in power distribution cabinet.
After external three-phase 380V/50Hz power input, overcurrent protective device is designed in inlet wire distribution box, i.e., in power supply The overcurrent relay that three 0~9.99A are introduced in three-phase alternating current, by matching 50 outside:1 D.C mutual-inductor is realized when being When any one phase current in route of uniting is more than setting electric current, the just function protected of disconnection system input power.
Air switch is additionally provided in the distribution box, external three-phase alternating current inputs in distribution box through air switch, described Air switch in be equipped with leakage protection circuit and carry out current foldback circuit, leakage protection circuit controlled by zero curve through general supply Device is connected with voltage output controller.
Phase sequence relay is additionally provided in the power distribution cabinet, the three-phase alternating current that distribution box is input to power distribution cabinet is first input into Phase sequence relay, then general supply controller is input to by phase sequence relay.The phase sequence relay be used as sequence examing, only when Main contactor, and the protective relay of the automatic phase sequence cognition of energy are just connected when input power phase sequence is correct, avoid some special machines Electric equipment leads to accident or equipment damage because of reversing after power phase is reversed.The control signal output of general supply controller Also realize that signal is connect with system controller, display unit and protection circuit, system controller, display unit and protection circuit are General supply controller provides the logistics support guarantee on basis, plays the role of management, display and protection, protects general supply controller Hold normal operating conditions.
The above is only the preferred embodiment of the utility model, it should be understood that the utility model is not limited to herein Disclosed form, should not be regarded as an exclusion of other examples, and can be used for other combinations, modifications, and environments, and Can be in contemplated scope described herein, modifications can be made through the above teachings or related fields of technology or knowledge.And this field The modifications and changes that personnel are carried out do not depart from the spirit and scope of the utility model, then all should be in right appended by the utility model It is required that protection scope in.

Claims (2)

1. power of alterating and direct current multi-function test stand distribution system, it is characterised in that:Including power distribution cabinet and distribution box, in the power distribution cabinet Equipped with general supply controller, the distribution box exports three-phase alternating current to general supply controller, and general supply controller is by alternating current Corresponding electrical equipment is distributed to, the electrical equipment includes frequency conversion tank, station, programmable power supply and load box;
It is set in the distribution box there are three overcurrent relay and mutual with exchanging for three overcurrent relays matching connection respectively Sensor, each phase of three-phase alternating current concatenate an overcurrent relay respectively, input by the three-phase alternating current of overcurrent relay Into power distribution cabinet;
Air switch is additionally provided in the distribution box, external three-phase alternating current is through in air switch input distribution box;
Phase sequence relay is additionally provided in the power distribution cabinet, the three-phase alternating current that distribution box is input to power distribution cabinet is first input into phase sequence Protector, then general supply controller is input to by phase sequence relay;
Several voltage output controllers are additionally provided in the power distribution cabinet, the alternating current of general supply controller distribution is through voltage output Controller is input to corresponding electrical equipment;
Three-phase alternating current is distributed to frequency conversion tank through voltage output controller by the general supply controller, and general supply controller will Single-phase electricity distributes to station, programmable power supply and load box through voltage output controller respectively.
2. power of alterating and direct current multi-function test stand distribution system according to claim 1, it is characterised in that:It further include several lists To safety isolating transformer, the single-phase electricity of general supply controller distribution is respectively through one-way safety isolating transformer, voltage output control Device processed distributes to station, programmable power supply and load box.
CN201721628608.4U 2017-11-29 2017-11-29 Power of alterating and direct current multi-function test stand distribution system Active CN208112223U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721628608.4U CN208112223U (en) 2017-11-29 2017-11-29 Power of alterating and direct current multi-function test stand distribution system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721628608.4U CN208112223U (en) 2017-11-29 2017-11-29 Power of alterating and direct current multi-function test stand distribution system

Publications (1)

Publication Number Publication Date
CN208112223U true CN208112223U (en) 2018-11-16

Family

ID=64130574

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721628608.4U Active CN208112223U (en) 2017-11-29 2017-11-29 Power of alterating and direct current multi-function test stand distribution system

Country Status (1)

Country Link
CN (1) CN208112223U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110018342A (en) * 2019-05-17 2019-07-16 南方电网科学研究院有限责任公司 A kind of program-controlled power signal test device based on transformer

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110018342A (en) * 2019-05-17 2019-07-16 南方电网科学研究院有限责任公司 A kind of program-controlled power signal test device based on transformer

Similar Documents

Publication Publication Date Title
CN102435899B (en) Locomotive traction converter test apparatus and method thereof
Keller et al. Understanding fault characteristics of inverter-based distributed energy resources
CN103399184B (en) Conveniently can adjust the combined connection box of phase sequence
CN103760441B (en) A kind of Multifunctional adjustment table of distribution box
CN103595037B (en) Three-phase alternating current phase sequence error correction device
CN109347134B (en) Bipolar flexible direct-current power grid polar line electric main wiring system and online maintenance method
CN208571394U (en) A kind of photovoltaic power generation box-type substation based on intelligent controller
CN106356905A (en) Alternating-current and direct-current double-bus controllable power transmission system
KR20130044247A (en) Recovery device and method of recovery for open-phase in the power system line
CN201256360Y (en) Intelligent multifunctional low voltage frequency changing power device
CN104090191A (en) Loading testing device and method used for frequency converter
CN208112223U (en) Power of alterating and direct current multi-function test stand distribution system
CN202949138U (en) Low-voltage cable branch box
CN204696702U (en) Grid-connected distribution box
CN106451500A (en) Inter-phase load transfer terminal device based on transient waveform fitting
KR20210051862A (en) Reactive Power Compensation type Ground Transformer
CN206712478U (en) A kind of distributed photovoltaic power generation grid-connected system
Smith Performing detailed power system studies for designing and analyzing electrical distribution systems-Power system studies for cement plants
CN201576011U (en) Alternating current-direct current comprehensive load box
CN208461317U (en) All insulation type voltage transformer GIS cabinet
CN106208080A (en) A kind of low-voltage circuit active power regulator control system
CN207368541U (en) Distribution frock
CN207053400U (en) Switch power supply equipment and system
CN105158618A (en) Multifunctional test platform
CN204967265U (en) Electric system of transformer substation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant