CN208104289U - Refuse gasification boiler high temperature batcher - Google Patents
Refuse gasification boiler high temperature batcher Download PDFInfo
- Publication number
- CN208104289U CN208104289U CN201820606922.0U CN201820606922U CN208104289U CN 208104289 U CN208104289 U CN 208104289U CN 201820606922 U CN201820606922 U CN 201820606922U CN 208104289 U CN208104289 U CN 208104289U
- Authority
- CN
- China
- Prior art keywords
- circular arc
- high temperature
- semicanal
- boiler high
- refuse gasification
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Processing Of Solid Wastes (AREA)
Abstract
This application discloses refuse gasification boiler high temperature batchers, including rack, transmission pipeline in the rack is set, spiral material conveying member in the transmission pipeline is set, and driving mechanism, the driving mechanism includes decelerating motor, the transmission shaft being connected by water-cooling bearing block with the decelerating motor, and make airtight and watertight padding seal box between the transmission shaft and the transmission pipeline, the transmission pipeline includes upper circular arc semicanal and lower circular arc semicanal, the upper circular arc semicanal and the lower circular arc semicanal are extended with mounting ear on the whole length direction of two arc end part, the upper circular arc semicanal and the lower circular arc semicanal are spirally connected installation by the mounting ear, and gasket seal is provided between both described mounting ear.Have the characteristics that reduce gasification process energy consumption.
Description
Technical field
This application involves garbage transfer equipment technical fields, and in particular to a kind of level-one gasification for refuse gasification processing
Furnace is to the high temperature batcher between second level gasification furnace.
Background technique
Refuse pyrolysis gasification is in confined chamber to be heated at high temperature the synthesis gas converted garbage into as carbon monoxide and hydrogen.
Then pass through and remove toxic granular and gas after filtering and chemical cleaning, and burned for energy or be converted into methane, ethyl alcohol or
The fuel such as combined diesel oil.Refuse gasification processing quickly can convert energy for household refuse, and rubbish can become providing from debt
It produces, the clean energy resource source that can be used on the spot is provided.
Currently, two-stage refuse gasification processing mode is, the rubbish to be processed in feed bin initially enters level-one gasification furnace, complete
After level-one gasification process, second level gasification furnace is conveyed by screw(-type) feeder, since rubbish material is in screw(-type) feeder medium temperature
Degree can be greatly reduced, thus rubbish material needs the gasification that heats up again in second level gasification furnace.Thus, in level-one gasification process and
Between second level gasification process, rubbish is warmed, and-cooling-heats up again, thus there are energy loss, increase equipment energy consumption and
The working efficiency of refuse gasification processing.
Summary of the invention
The goal of the invention of the utility model is to overcome above-mentioned technical problem, thus provide a kind of refuse gasification boiler high temperature to
Material machine still keeps close after entering second level gasification furnace in the rubbish material in level-one gasification furnace with preferable airtightness
Temperature when level-one gasification furnace is left, only less thermal losses, rubbish material is still in the condition of high temperature, without two
Grade gasification furnace is heated again, and directly can be carried out gasification process in second level gasification furnace with the condition of high temperature, saved second level gasification
The energy consumption of processing.
One embodiment of the utility model discloses refuse gasification boiler high temperature batcher, including rack, setting described
Transmission pipeline in rack, the spiral material conveying member being arranged in the transmission pipeline and driving mechanism, the driving mechanism
Including decelerating motor, the transmission shaft being connected by water-cooling bearing block with the decelerating motor and make the transmission shaft and the biography
Airtight and watertight padding seal box between defeated pipeline, the transmission pipeline include upper circular arc semicanal and lower circular arc semicanal, the upper circular arc
Semicanal and the lower circular arc semicanal are extended with mounting ear, the upper circular arc on the whole length direction of two arc end part
Semicanal and the lower circular arc semicanal are spirally connected installation by the mounting ear, and are provided between both described mounting ear close
Gasket.
By above structure, by the setting of filling sealing tank and gasket seal, the air-tightness in transmission pipeline is improved,
The reduction of the rubbish material temperature in transmission pipeline is avoided, rubbish material is not necessarily to heat up again after entering second level gasification furnace, from
And reduce the energy consumption of gasification process.On the other hand, by the setting of water-cooling bearing block, high temperature rubbish material is avoided by passing
To the influence of drive mechanism when defeated pipeline, guarantee that equipment works normally in a high temperauture environment.
Further, silicon carbide liner plate is covered on the inner wall of the transmission pipeline.
In the technical scheme, carbofrax material has heat-resisting quantity, to avoid high temperature rubbish material to conveyance conduit
The damage of inner wall.
Further, the silicon carbide liner plate is to pour silicon carbide plate.
Further, the silicon carbide liner plate is covered on the inner wall of the lower circular arc semicanal.
In the technical scheme, rubbish material under the effect of gravity, is more deposited on lower circular arc semicanal, as a result, by
The conveying space medium temperature built up more heats in the conveying space that lower circular arc semicanal surrounds, and circular arc semicanal is descended to surround relatively
Degree is more preferable, thus silicon carbide liner plate is arranged on the inner wall of lower circular arc semicanal to the protection that can not only realize to conveyance conduit, also
Material utilization amount, save the cost can be reduced.In addition, having accumulated more rubbish objects in the conveying space that lower circular arc semicanal surrounds
Material, and during transportation, machine drawing material mainly causes friction damage to the inner wall of lower circular arc semicanal, and carbofrax material has
Better wear-resisting property, thus further protect conveyance conduit.
Further, the water-cooling bearing block is connected to by rotary joint with water source.
Further, the spiral material conveying member is shaftless screw conveying blade.
Further, circle is enclosed with heat preservation rock on the outer wall of the conveyance conduit.
Further, the gasket seal is soft graphite metal wound gasket.
To sum up, the refuse gasification high temperature batcher of the application at least has the advantages that energy saving, in level-one gasification furnace
Rubbish material be directly entered in second level gasification furnace by the high temperature batcher of technical scheme, only less heat damage
Consumption, rubbish material can be directly with the condition of high temperature two without being heated again in second level gasification furnace still in the condition of high temperature
Gasification process is carried out in grade gasification furnace, has saved the energy consumption of second level gasification process.
The above description is merely an outline of the technical solution of the present invention, in order to better understand the skill of the utility model
Art means, and can be implemented in accordance with the contents of the specification, with the preferred embodiment of the utility model, detailed description is as follows below.
Detailed description of the invention
Fig. 1 is a kind of schematic diagram of the refuse gasification boiler high temperature batcher of the utility model embodiment;
Fig. 2 is sectional view along A-A;
Fig. 3 is a kind of schematic diagram of the gasket seal of the utility model embodiment;
In attached drawing:
1, rack, 2, transmission pipeline, 3, spiral material conveying member, 4, water-cooling bearing block, 5, transmission shaft, 6, packing seal
Case, 7, silicon carbide liner plate, 8, rotary joint, 21, upper circular arc semicanal, 22, lower circular arc semicanal, 23, mounting ear, 24, gasket seal,
241, shim body, 242, channel, 243, partition.
Specific embodiment
Below with reference to embodiment, specific embodiment of the present utility model is described in further detail.Following embodiment
For illustrating the utility model, but it is not intended to limit the scope of the present invention.
Embodiment:Refuse gasification boiler high temperature batcher as illustrated in fig. 1 and 2, for will be handled in level-one refuse gasification boiler
The rubbish material of completion is delivered to second level gasification furnace, is transmitting including rack 1, the transmission pipeline being arranged in rack 12, setting
Spiral material conveying member 3 and driving mechanism in pipeline 2.In the present embodiment, spiral material conveying member 3 is that shaftless screw is defeated
Blade is sent, and is cast by stainless steel 310S.
Driving mechanism includes decelerating motor, the transmission shaft being connected by water-cooling bearing block 4 with decelerating motor 5 and makes to be driven
Airtight and watertight padding seal box 6 between axis 5 and transmission pipeline 2, water-cooling bearing block 4 are connected to by rotary joint 8 with water source.
Transmission pipeline 2 includes upper circular arc semicanal 21 and lower circular arc semicanal 22, and upper circular arc semicanal 21 and lower circular arc semicanal 22 are equal
Mounting ear 23 is extended on the whole length direction of two arc end part, upper circular arc semicanal 21 and lower circular arc semicanal 22 pass through
Mounting ear 23 is spirally connected installation, and gasket seal 24 is provided between the mounting ear 23 of the two.Offered on upper circular arc semicanal 21 with
The feed inlet of the discharge port docking of level-one gasification furnace is offered on lower circular arc semicanal 22 and is docked with the feeding inlet of second level gasification furnace
Discharge port, the end 500mm of the central axis Distance Transmission pipeline 2 of feed inlet, discharge port are located at the end of transmission pipeline 2.Rack
1, upper circular arc semicanal 21 and lower circular arc semicanal 22 are cast by stainless steel 310S.Gasket seal 24 is entire along mounting ear 23
Length direction arrangement is soft graphite metal wound gasket.
Turn to see Fig. 2, silicon carbide liner plate 7 is covered on the inner wall of transmission pipeline 2.Preferably, silicon carbide liner plate 7 is to pour carbon
SiClx plate, and silicon carbide liner plate 7 is covered on the inner wall of lower circular arc semicanal 22.
In other implementations, circle is enclosed with heat preservation rock on the outer wall of conveyance conduit 2.
In other implementations, as shown in figure 3, gasket seal 24 includes shim body 241, along the length of ontology 241
Direction is spent through the plurality of passages 242 of setting, and 242 inner-use clapboard 243 of channel forms multiple compartments, swollen filled with heat in compartment
Swollen particle.In the present embodiment, the cross section in channel 242 is triangular in shape.
The above is only the preferred embodiment of the utility model, is not intended to limit the utility model, it is noted that
For those skilled in the art, without deviating from the technical principle of the utility model, it can also do
Several improvements and modifications out, these improvements and modifications also should be regarded as the protection scope of the utility model.
Claims (8)
1. refuse gasification boiler high temperature batcher, it is characterised in that:Including rack(1), be arranged in the rack(1)On transfer tube
Road(2), be arranged in the transmission pipeline(2)Interior spiral material conveying member(3)And driving mechanism, the driving mechanism include
Decelerating motor passes through water-cooling bearing block(4)The transmission shaft being connected with the decelerating motor(5)And make the transmission shaft(5)With institute
State transmission pipeline(2)Between airtight and watertight padding seal box(6), the transmission pipeline(2)Including upper circular arc semicanal(21)With lower circle
Arc semicanal(22), the upper circular arc semicanal(21)With the lower circular arc semicanal(22)In the whole length of two arc end part
Mounting ear is extended on direction(23), the upper circular arc semicanal(21)With the lower circular arc semicanal(22)Pass through the mounting ear
(23)Be spirally connected installation, and both described mounting ear(23)Between be provided with gasket seal(24).
2. refuse gasification boiler high temperature batcher according to claim 1, it is characterised in that:The transmission pipeline(2)It is interior
Silicon carbide liner plate is covered on wall(7).
3. refuse gasification boiler high temperature batcher according to claim 2, it is characterised in that:The silicon carbide liner plate(7)For
Pour silicon carbide plate.
4. refuse gasification boiler high temperature batcher according to claim 2, it is characterised in that:The silicon carbide liner plate(7)It covers
It covers in the lower circular arc semicanal(22)Inner wall on.
5. refuse gasification boiler high temperature batcher according to claim 1, it is characterised in that:The water-cooling bearing block(4)It is logical
Cross rotary joint(8)It is connected to water source.
6. refuse gasification boiler high temperature batcher according to claim 1, it is characterised in that:The spiral material conveying member
(3)For shaftless screw conveying blade.
7. refuse gasification boiler high temperature batcher according to claim 1, it is characterised in that:The conveyance conduit(2)It is outer
Circle is enclosed with heat preservation rock on wall.
8. refuse gasification boiler high temperature batcher according to claim 1, it is characterised in that:The gasket seal(24)It is soft
Property graphite metal wound gasket.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820606922.0U CN208104289U (en) | 2018-04-26 | 2018-04-26 | Refuse gasification boiler high temperature batcher |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820606922.0U CN208104289U (en) | 2018-04-26 | 2018-04-26 | Refuse gasification boiler high temperature batcher |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208104289U true CN208104289U (en) | 2018-11-16 |
Family
ID=64117084
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820606922.0U Active CN208104289U (en) | 2018-04-26 | 2018-04-26 | Refuse gasification boiler high temperature batcher |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208104289U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111974480A (en) * | 2020-09-02 | 2020-11-24 | 杭州潘达科技有限公司 | Stabilize effectual constant temperature water bath with many interlayers |
-
2018
- 2018-04-26 CN CN201820606922.0U patent/CN208104289U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111974480A (en) * | 2020-09-02 | 2020-11-24 | 杭州潘达科技有限公司 | Stabilize effectual constant temperature water bath with many interlayers |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US5709779A (en) | Device for conveying waste in a pyrolysis reactor | |
CN208104289U (en) | Refuse gasification boiler high temperature batcher | |
CN101598334A (en) | Bottom slag cooling method of circulating fluidized bed | |
CN101269744B (en) | High-temperature water-cooling screw conveyor | |
CN202321536U (en) | Self-sealing shaft-free spiral conveyor | |
CN209512032U (en) | Spirally water cooling self-adapting seal discharging device | |
CN218520423U (en) | Spiral conveying internal cooling device | |
CN114032110B (en) | Pyrolysis material discharging device and discharging system of pyrolysis furnace | |
CN211060684U (en) | Waste heat recovery device for cement rotary kiln | |
CN211261722U (en) | Deoiling rotary kiln device | |
CN209783267U (en) | Chemical converter | |
CN104851469B (en) | Spirally whole bucket feeds processing system to one kind | |
CN103387842B (en) | A kind of oil refining cracker with heat pipe | |
CN111960633A (en) | Roller pyrolysis machine and pyrolysis method | |
CN217322511U (en) | Novel pyrolysis oven feeding device | |
CN102012170B (en) | High-temperature heat energy recycling converter | |
CN206709081U (en) | Solid waste pyrolysis treatment systems | |
CN201819541U (en) | Rotary cooling furnace used in coal-based activated carbon production process | |
CN218435589U (en) | Waste rubber-plastic thermal cracking treatment equipment | |
CN109762605A (en) | Circulating Fluidized Bed Gasifier For Biomass material returning device carbonizing device | |
CN207196509U (en) | A kind of house refuse microwave cracking stove anoxybiotic discharge system | |
CN212320269U (en) | Biomass fuel drying machine | |
CN201209061Y (en) | High-temperature water-cooling screw conveyor | |
CN109761197A (en) | Reacting furnace furnace tail gypsum slag-draining device and reacting furnace for Acid of Hydrofluoric Acid Production technique | |
CN214528856U (en) | Continuous tube type pyrolysis furnace for finally disposing waste plastics |