Technological equipment for magnetic pole protection coating curing molding Download PDF

Info

Publication number
CN208101106U
CN208101106U CN201820174303.9U CN201820174303U CN208101106U CN 208101106 U CN208101106 U CN 208101106U CN 201820174303 U CN201820174303 U CN 201820174303U CN 208101106 U CN208101106 U CN 208101106U
Authority
CN
China
Prior art keywords
rotor
magnetic pole
induction heating
electromagnetic induction
bonding agent
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820174303.9U
Other languages
Chinese (zh)
Inventor
马盛骏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Goldwind Science and Creation Windpower Equipment Co Ltd
Original Assignee
Beijing Goldwind Science and Creation Windpower Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Goldwind Science and Creation Windpower Equipment Co Ltd filed Critical Beijing Goldwind Science and Creation Windpower Equipment Co Ltd
Priority to CN201820174303.9U priority Critical patent/CN208101106U/en
Application granted granted Critical
Publication of CN208101106U publication Critical patent/CN208101106U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Manufacture Of Motors, Generators (AREA)

Abstract

The utility model provides a kind of technological equipment for magnetic pole protection coating curing molding.The technological equipment includes the first energy delivery system, and rotor is axially horizontal positioned, and the first energy delivery system includes:First radial limited support component, and pole piece spacing preset distance, to form first receiving space;First flexible cavity component is located in first receiving space;First fluid medium supply system is used to supply pressurized fluid media or pressurized, heated fluid media (medium) to the first flexible cavity component with the first flexible cavity members.Technical solution according to the present utility model, ensure that bonding agent in protection coating molding space circumferentially, the driving force of axially and radially all directions seepage flow, to be sufficient filling with the gap in protection system, magnetic pole protection Forming Quality temperature rise control unification, Temperature Distribution homogenization are realized simultaneously, guarantee Forming Quality, reduces the removing of protection coating, risk of breakage.

Description

Technological equipment for magnetic pole protection coating curing molding
Technical field
The utility model relates to wind-driven generator technical group fields, more particularly, are related to a kind of for wind-driven generator Rotor magnetic pole protection coating curing molding technological equipment.
Background technique
Large size rotor of direct-drive permanent magnet wind driven generator in the prior art is by being fixed on rotor magnetic for permanent magnet pole block Yoke wall and formed.Fig. 1 is the structural schematic diagram of the outer rotor of magneto in the prior art;Fig. 2 is the outer rotor in Fig. 1 Partial structural diagram;Fig. 3 is another rotor structure schematic diagram in the prior art.Fig. 4 is to be used to form magnetic in the prior art The schematic diagram of the vacuum perfusion process equipment of coating is protected in pole;Fig. 5 is in the prior art for keeping magnetic pole protection coating bonding solid Change the schematic diagram of molding process equipment.
As shown in Figure 1-3, magneto includes the stator core 30 being arranged on stator main shaft, it is arranged in stator core 30 The rotor 40 of periphery.Rotor 40 includes rotor rim 41, press strip 42 and magnetic pole 43.Magnetic yoke 41 is generally cylindrical structure, passes through spiral shell After press strip 42 is installed on the internal perisporium of magnetic yoke 41 by the fasteners such as bolt 44, magnetic pole 43 is pushed between adjacent press strip 42.Pressure The cross section of item 42 is trapezoidal, and so as to push down the side wall of magnetic pole 43 by the inclined-plane of press strip 42, magnetic pole 43 is fixed on phase Between adjacent press strip 42.
In the prior art, the magnetic pole of magneto mostly uses neodymium iron boron (NdFeB) permanent-magnet material to be formed.However, warm Under the conditions of wet environment, iron and neodymium in neodymium iron boron are easier that oxidation and electrochemical corrosion occurs, and cause the variation of magnetic property very To the damage of magnetic pole.Therefore, in the prior art, protection coating 45 usually is formed in magnetic pole surfaces using resin, makes magnetic pole and outer Boundary's isolation is opened, and is protected to magnetic pole 43.
Fig. 4 shows the schematic diagram for forming the vacuum perfusion process equipment of magnetic pole protection coating 45 in the prior art.Such as Fig. 4 Shown, the axial vertical placement of rotor rim 41 lays cloth of reinforcement fibers 51 on the surface of magnetic pole 43, vacuum bag 50 is utilized to lay On the inner wall of magnetic yoke 41, the formation perfusion die cavity between vacuum bag 50 and the inner wall of magnetic yoke 41, i.e. bonding agent and press strip 42, Magnetic pole 43, the inner surface of magnetic yoke 41, the bonding of cloth of reinforcement fibers 51 are solidified into integrated bonding agent blending space.In perfusion die cavity Lower part opens up gum-injecting port and connects suction line 55, opens up bleeding point on perfusion die cavity top and connects and draws pipeline 56.It is taking out Port side is additionally provided with resin system collecting tank 57, for collecting extra resin.It is taken out using 53 pairs of perfusion die cavitys of vacuum pump Vacuum is compacted vacuum bag 50 and cloth of reinforcement fibers 51 on the surface of press strip 42 and magnetic pole 43, (is added with by bonding agent The resin of curing agent) priming by vacuum is into the die cavity.Resin from resin container 54 along 55 self-priming injection cavities lower end of suction line into Enter, dipping fiber reinforcement fiber cloth 51, filling magnetic pole 43 and press strip 42 and magnetic yoke while being flowed along axial direction to the other end Gap between 41 inner wall and the surface for covering magnetic pole 43 Yu press strip 42.To bonding agent full of the gap in entire die cavity Afterwards, empty by being mixed to bonding agent after so that bonding agent is sufficiently infiltrated the glued surface of solids in the bonding agent blending space Between heating to make bonding agent curing molding, to make bonding agent while filling each gap and gap in 43 surface shape of magnetic pole Resinophore groups reinforcing material protects coating 45.
In the prior art, in order to control the molding shape of protection coating 45 and protect the thickness of coating 45, in rotor Magnetic yoke 41 on the inside of also set up adhesive mould 60.Adhesive mould 60 is located at the radially inner side of vacuum bag 50, sets with the holding of magnetic pole 43 Fixed gap, to control the groundwater increment of bonding agent and protect the formation thickness of coating 45.
Although protection coating 45 is to a certain degree playing a very good protection to pole piece, by magnetic pole 43 and outside Moisture isolation is opened.But in the long-term use, the moisture of ambient enviroment can result in the reinforcing fiber in protection coating 45 And chemical change occurs for binder matrix, and the performance of reinforcing fiber and binder matrix is caused to decline, moisture can be with by diffusion Interface between protection coating 45 and press strip 42, magnetic yoke 41, causes the removing of bonding interface, leads to material mechanical performance Decline.Bonding agent understands harmomegathus in the environment of temperature and humidity changes and generates mismatch deformation and mismatch stress, influences protection and covers The deformation of the structure of layer 45 and the damage of material.
In addition, during rotor 40 rotates, in the magnetic pull radially pulsed and magnetic by motor stator armature Under the torque of the inner wall circumferencial direction of yoke 41, magnetic pole 43 is become to alter between adjacent two pieces press strip 42 by simple vibration Dynamic, this has been further exacerbated by the removing of the bonding interface of magnetic pole 43 and bonding agent, the removing of protection coating, fracture.Magnetic pole protection is covered After 45 fracture of layer, breathing phenomenon quickly occurs, and humid air, salt fog cause to corrode to magnetic pole, and the size of magnetic pole 43 changes, magnetic Pole 43 loosens, and can jump out under magnetic pole press strip 42 under the action of radial magnetic pull, between generator amature 40 and stator 30 Gap prevents the relative motion of the stator 30 and rotor 40 of motor, destroys the insulation of magnetic pole and stator, and motor is scrapped, and causes greatly Loss.
Therefore, the performance of coating 45 is protected directly to determine the service life of wind-driven generator, and it is vacuum perfusion process, viscous The temperature for connecing the curing molding process of agent directly affects the performance of protection coating 45 again.The Forming Quality of protection coating is improved, The service life for extending protection coating, is the target that those skilled in the art constantly pursue.
Utility model content
In order to further increase the Forming Quality of protection coating and extend protection coating service life, the utility model is provided It is a kind of for making the technological equipment of permanent magnetic part protection coating bonding curing molding.
The utility model provides a kind of technological equipment for magnetic pole protection coating curing molding, to solve magneto The anti-corrosion of magnetic pole protects the full rate problem of coating molding process gap filling, protects in coating and forms asking for bubble or hole Topic, bonding agent is in the heated unification problem of 360 degree of ranges of circumference, magnetic pole and the heated unification problem of magnetic yoke short transverse.
One side according to the present utility model provides a kind of magnetic pole protection coating curing molding for making rotor Technological equipment, the rotor includes magnetic yoke and magnetic pole, and the magnetic pole is fixedly mounted on the inside table positioned at the magnetic yoke On face, the technological equipment includes the first electromagnetic induction heating unit that the outside of the magnetic yoke is arranged in, first electromagnetism Induction heating unit includes the electromagnetic induction heating coil being wrapped in the magnetic yoke and is arranged in the electromagnetic induction heating Outside heat insulating member on the outside of coil, heat insulating member are spaced a predetermined distance with described second side, surround the magnetic yoke to be formed Annulus.
One side according to the present utility model, the outside heat insulating member further includes electromagnetic shielding component, for electromagnetism Wave is shielded.
One side according to the present utility model, the outside heat insulating member include around the magnetic yoke radially around cylinder And the axial limiting baffle of the end radially around cylinder is set, the electromagnetic shielding component is described exhausted to be attached to Aluminium foil on the inside of thermal part.
One side according to the present utility model, the technological equipment further include:First radial limited support component, faces institute The first surface for stating magnetic yoke, and the pole piece spacing preset distance, in the described first radial limited support component and described the First receiving space is formed between one surface;First flexible cavity component, is flexible encapsulated cavity, and setting is radial described first On limited support component, and it is located in the first receiving space;First fluid medium supply system, with first elastic cavity Body component connection makes institute for supplying pressurized fluid media or pressurized, heated fluid media (medium) to the first flexible cavity component It states the first flexible cavity component and squeezes the bonding agent being perfused in the vacuum bag.
One side according to the present utility model, the technological equipment further includes the second electromagnetic induction heating unit, for setting It sets in the rotor internal cavity of the rotor, electromagnetic induction heating is carried out to the magnetic pole from internal rotor.
One side according to the present utility model, the second electromagnetic induction heating unit include supportive body, supporting cantilever, Electromagnetic induction heating cylinder and induction heating power, one end of the supporting cantilever are fixed on the supportive body, the branch The other end for supportting cantilever supports the electromagnetic induction heating cylinder, by the way that the electromagnetic induction heating cylinder is placed on first diameter Come to carry out electromagnetic induction heating to the magnetic pole to the radially inner side of limited support component.
One side according to the present utility model, the electromagnetic induction heating cylinder be cylindrical shape, including coil rack and uniformly Ground is wrapped in the electromagnetic induction heating coil on the coil rack, and the technological equipment further includes laser centring device, is used for It is directed at the electromagnetic induction heating cylinder with the rotor axial, so that between the electromagnetic induction heating cylinder and the rotor Circumferential gap uniformity.
One side according to the present utility model, the technological equipment further include range sensor, for detecting the electromagnetism Gap between induction heating cylinder and the rotor, the range sensor be at least four, it is evenly distributed in the circumferential direction The radially inner side of described first radial limited support component or the outside for being arranged in the electromagnetic induction heating cylinder.
One side according to the present utility model, the supporting cantilever can be relative to the supportive body horizontal extensions and upper Lower lifting;The laser centring device includes laser emitter and laser pickoff, is separately mounted to the rotor and the electricity On magnetic induction cartridge heater.
One side according to the present utility model, the technological equipment further include end thermal insulation board, the end thermal insulation board tool There are heat-insulated, sound insulation and electro-magnetic screen function, the end of the rotor is arranged in the end bulkheads, seals the rotor of the rotor Inner cavity.
One side according to the present utility model, the technological equipment further include rotary drive unit, and the rotation driving is single It is first to be connect with the rotor, drive the rotor to rotate.
One side according to the present utility model, the controller control the radial direction of the protection coating molding space Two sides are symmetrically heated, and keep the Temperature Distribution in circumferentially and axially direction of the protection coating molding space in the rotor equal One changes.
By the technological equipment of the utility model, flexible extruding is carried out to bonding agent by flexible cavity component, can be promoted Into seepage flow of the bonding agent on glued body surface, infiltration, solve the problems, such as that the driving of bonding agent Radial Flow Through Porous Media is hypodynamic.Pass through Electromagnetic induction heater heats magnetic pole, and magnetic pole is made to take the lead in warming up, and temperature is higher than the fluid temperature of bonding agent, reduces solid Contact angle (infiltration angle) between liquid, realizes the bonding between solid-liquid.
Technical solution according to the present utility model, can be realized the mutual centering of laser, overall perfusion, entire pressurisation dipping, External heat is symmetrically heated in integrally curing, protection coating, to realize that temperature rise control is consistent in magnetic pole protection coating forming process Change, Temperature Distribution uniform this target, so that magnetic pole protective layer self-formed shaping process stress is eliminated, guarantee Forming Quality, drop Removing, the risk being broken caused by low later period use process stress.
Detailed description of the invention
The detailed description that the embodiments of the present invention are carried out by following accompanying drawings, the above and other of the utility model Purpose and feature will become apparent, wherein:
Fig. 1 is the structural schematic diagram of the outer rotor of magneto in the prior art;
Fig. 2 is the partial structural diagram of the outer rotor in Fig. 1;
Fig. 3 is the partial structural diagram of another rotor structure in the prior art;
Fig. 4 is the schematic diagram for being used to form the priming by vacuum system of magnetic pole protection coating in the prior art;
Fig. 5 is to be used to form to protect the bonding agent of coating various in blind when rotor is placed vertically in the prior art Flow trace;
Fig. 6 A and be in the prior art formed protect coating when bonding agent flow fronts trace and envelope;
Fig. 6 B is that bonding agent flow fronts due to outflanking converge the schematic diagram for leading to filling defect in the prior art;
Fig. 7-12 is according to the first exemplary embodiment of the utility model for magnetic pole protection coating bonding curing molding Technological equipment schematic diagram;
Figure 13 is the sensor layout schematic diagram in the flexible cavity component according to the utility model exemplary embodiment;
Figure 14 is according to the second exemplary embodiment of the utility model for magnetic pole protection coating bonding curing molding The schematic diagram of technological equipment;
Figure 15 A and 15B show the sectional view of main view and press strip according to the rotor of the utility model embodiment;
Figure 16 A, 16B, 17A, 17B, 18A and 18B are using the technological equipment according to the utility model embodiment respectively The flow characteristics schematic diagram of bonding agent when progress priming by vacuum at rotor different location;
Figure 19 and 20 shows the external structure diagram according to the technological equipment of the utility model embodiment;
Figure 21 shows priming by vacuum and equips the schematic diagram being placed in rotor internal cavity;
Figure 22 shows the schematic diagram of the second electromagnetic induction heating unit according to the utility model embodiment;
Figure 23 is the external perspective decomposition view for using the technological equipment according to the utility model embodiment.
Label in attached drawing:
2- stator support;4- bonding agent blending space (protection coating molding space);30- stator core;40- rotor; 41- magnetic yoke;42- press strip;43- magnetic pole;44- bolt;45- magnetic pole protects coating;421- vertical passage;422- interconnection;50- Vacuum bag;51- reinforcing material;53- vacuum pump;54- resin container;55- suction line;56- draws pipeline;57- resin trap Tank;60- bonding uses mold;
The radial limited support component of 100- first;110,120,410,420- limit pressing plate;The first flexible cavity of 200- portion Part;210- the first side wall;220- second sidewall;230- dividing strip;240- fluid medium channel;250- the first flexible cavity component Boundary before expansion;300- the second flexible cavity component;The radial limited support component of 400- second;500- controller;510- pressure Force snesor;520- temperature sensor;
600- supplying fluid medium system;610- compressor;620- heater;The first connecting pipe of 630-;640- fluid Transfer pipeline;650- fluid recovery pipeline 650;660- bypass line;The first valve of 641-;The second valve of 651-;652- third Valve;The 4th valve of 631-;The 5th valve of 661-;The 6th valve of 662-;642- first pressure gauge;653- second pressure gauge; 645- shunts main pipe;655- reflux main pipe;7,9,11,13,15,17- shunt pipe valve;6,8,10,12,14,16,18- times Flow branch pipe valve;
700- the second electromagnetic induction heating unit;701- supportive body;702- supporting cantilever;703- electromagnetic induction adds cylinder; 704- induction heating power;7031- coil rack;7032- electromagnetic coil;705- driving part;706- track;
800- the first electromagnetic induction heating unit;801- electromagnetic induction coil;802- induction heating power;803- temperature Sensor;804- heat insulating member;The end 805- thermal insulation board;
900- rotary drive unit;901- servo drive component;902- drive shaft;903- shaft coupling;904- conversion section; 906- servo sensor;907- laser centring device;908- support base.
Specific embodiment
For the not high technical problem of the protection coating Forming Quality of pole piece in the prior art, the application's is practical new Type people has carried out a large amount of experimental study and theory analysis by taking outer rotor as an example, proposes one kind and is able to solve magnetic pole and magnetic yoke wall The filling problem in the gap between gap, magnetic pole and magnetic pole, between magnetic pole and press strip improves magnetic pole and protects coating Forming Quality, Improve the technological equipment of reliability of technology.
The utility model people of the application is found through experiments that, protection coating is formed in the state of placing rotor vertically There are bonding agent Radial Flow Through Porous Media later stage missing in technique, the various problems such as gap filling quality are not can guarantee.
By having carried out a large number of experiments for resin is perfused, it is found by experiment that:It places and grasps in rotor vertical axes When making to carry out vacuum infusion resin on platform, still have " vacuole " apart from lower end one third region, and there is protection Coating in axial direction uneven thickness, the larger phenomenon of lower cladding thickness.In the reinforcing material glass-fiber-fabric different using density As a result it also has any different.
For above-mentioned experimental phenomena, the utility model people of the application has made intensive studies and analyzes.By rotor axial In the state of vertical placement, the lower part of perfusion die cavity is arranged in gum-injecting port, and the top of perfusion die cavity, bonding agent is arranged in bleeding point From lower part toward top seepage flow.Pressure near gum-injecting port is close to environmental pressure, and the pressure near the bleeding point on top is close In the reading of the vacuum meter of vacuum pump.Therefore, the inside and outside differential pressure of vacuum bag lower part is less than the inside and outside differential pressure on vacuum bag top, from And to bonding agent, seepage flow causes certain obstruction from the bottom up.At the same time, due to the axial direction along rotor, to viscous Connect dosage form at radial pressure difference it is serious inconsistent so as to lack seepage flow in radial directions dynamic for the bonding agent of rotor lower area Power, it is difficult into the narrow gap between magnetic pole 43, press strip 42, magnetic yoke 41, especially be difficult to cross magnetic pole 43 and press strip 42 Into in the gap between magnetic pole 43 and magnetic yoke 41.Simultaneously as gravity is further slackened from vertical, gravity drainage effect The effect of bonding agent Radial Flow Through Porous Media, the bonding agent for being less useful for magnetic pole and magnetic yoke wall gap are filled, especially radially the seepage flow later period Pressure missing causes to form starved gap between magnetic pole 43 and magnetic yoke 41, becomes the security risk that magnetic pole falls off.
In addition, previously having carried a large amount of air, vapor in the reinforcing materials such as glass-fiber-fabric.Also, between magnetic pole and magnetic pole Gap, the gap between magnetic pole and press strip, in the gap between magnetic pole and magnetic pole plug also adsorb air, vapor.It is attached Water in reinforcing material will gasify for 43 DEG C under vacuum, therefore, the solid components in priming by vacuum die cavity carries Aqueous vapor, bubble is gasificated as when vacuumizing.In addition, water can be such that the sizing material of isocyanate groups solidifies, and it is accompanied by two The release of carbonoxide, causes foamed polymer to be formed.Therefore, bonding agent cannot well seepage flow to and fill magnetic pole gap, institute Bubble easy to form and hole in the protection coating of formation.
By a large number of experiments, rotor is vertical in the prior art, static placement progress vacuum is auxiliary for the utility model discovery When helping form, flowing trace of the bonding agent in protection system has certain rule.Fig. 5 shows rotor and exists Vertically, in the case where static placement, during forming protection coating using vacuum auxiliary pouring and molding technique, bonding agent is being filled out Fill the schematic diagram of the flow trace during gap.
As seen in Figure 5, bonding agent has following several situations to occur in flow process:
(1) there is circumferential section region and axially flows in circle distribution in the bonding agent of magnetic yoke wall and magnetic pole gap Speed is faster than above magnetic pole radial the speed between reinforcing material and vacuum bag film, and bonding agent is axially flowed along gap, and It takes the lead in overflowing the gap between the top layer of magnetic pole 43 and magnetic yoke 41.That is, bonding agent is flowed along the track A-F-E-B, in space Whether there is bonding agent seepage flow between position E and C, between F and D, pass through magnetic pole gap, is all unable to control.
Bonding agent self gravity direction and bonding agent are perpendicular along rotor magnetic pole radial dipping direction;Radial Flow Through Porous Media Pressure from vacuum bag film 50 to the radial pressure of protection system, when vacuum bag film 50 compresses protection system, pressure is transferred to When 43 surface of magnetic pole, when the volume that protection system occupies no longer reduces, radial pressure is promoted to glue by the radial complete equipilibrium of magnetic pole 43 It connects agent and enters magnetic pole gap, the motive force disappearance into E, F area of space, it is difficult to cross magnetic pole and press strip enters magnetic pole and magnetic yoke Gap between wall.Because taking the lead in having bonding agent filling in E, F area of space, these bonding agents fill E, F spatial joint clearance, lead The pressure for causing the later period of the bonding agent Radial Flow Through Porous Media (by the region C to E, D to F) of protection system to push bonding agent flowing weakens very To disappearance, the gap glued dose of filling completely in protection coating molding space can not be ensured.
(2) there is circumferential section region and axially flows in circle distribution in the bonding agent of magnetic yoke wall and magnetic pole gap Speed is slower than above magnetic pole radial the speed between reinforcing material and vacuum bag film, and bonding agent is along flow-guiding screen along motor pole Surface is axially flowed, and takes the lead in overflowing magnetic pole top layer region.I.e.:It is flowed along the track A, D, C, B;Spatial position A, F, E The gap area in direction is still filled without glued dose, and can bonding agent radially pass through magnetic pole gap and magnetic pole and pressure Gap between item, so that seepage flow is between C and E, between D and F, requiring that bonding agent is waited to pass through along axial seepage flow, dipping Extra bonding agent fills up radial clearance after composite protective coating molding space.Bonding agent self gravity direction and bonding agent edge Rotor magnetic pole radial dipping direction it is perpendicular, can not to bonding agent Radial Flow Through Porous Media provide driving force;The drive of Radial Flow Through Porous Media Power is from vacuum bag film 50 to the radial pressure of protection system.After vacuum bag film 50 compresses protection system gradually, along electricity Arbor to flowing and be introduced into the bonding agent in vacuum bag 50 can it is fewer and fewer until stagnate so that bonding agent quality cannot get Supplement.In the case where vacuum pump continues working, when pressure is transferred to magnetic pole surfaces, the volume that protection system occupies is not reducing When, radial pressure is passed through magnetic pole and magnetic pole gap is promoted bonding agent to enter magnetic pole seam by magnetic pole radial reaction force complete equipilibrium Gap, the motive force disappearance into E, F area of space.Further, since the drainage of flow-guiding screen, bonding agent is along magnetic pole surfaces stream Dynamic, so that the filling of the bonding agent of A, D, C, B area of space takes the lead in completing, this phenomenon causes " to be shorted " bonding agent continuation edge The power that axially flows of inner wall gap of magnetic pole 43 and magnetic yoke 41.Therefore, driving force (pressure difference) source of mass flow disappears It loses, continues to supplement so that being difficult to bonding agent in E, F area of space.Therefore, it is impossible to ensure in vacuum perfusion process later period magnetic Pole and magnetic yoke wall gap can glued dose refill.
Experimental study also found, carrying out the technique of priming by vacuum in the state that rotor axial is placed vertically, there is also partial zones Not the phenomenon that domain does not have bonding agent to flow through and forms hole or bubble.The embodiments of the present invention have carried out into one this phenomenon Step is explored and analysis, please refers to Fig. 6 A and 6B.Fig. 6 A and 6B show forward's trace of two kinds of different moments bonding agents flowing.It is attached Icon remembers that a1, a2, a3, a4 indicate that gum-injecting port, appended drawing reference b1, b2, b3 indicate bleeding point.As shown in Figure 6B, on bonding agent edge Axially upwards flow during, the bonding agent of generally existing regional area axially from lower end flow up speed compared with Slowly, the phenomenon that being outflanked by the bonding agent of adjacent two side areas, the left and right sides flowing forward outflank converge after formed one do not have The region that bonding agent flows through.Obviously, such region exists, to bonding agent along Radial Flow, be sufficiently impregnated protection coating, fill out Magnetize clearance between poles, filling magnetic pole and the flowing in magnetic yoke wall gap is worst intrinsic phenomenon.
On the basis of the studies above, the embodiments of the present invention, which propose one kind, can reduce remnants in protection coating Bubble improves the technical solution of protection coating Forming Quality, is described in detail below.Although being with outer rotor in following description Example, but it is clear that the theory of the utility model and equipment can also apply in inner rotor motor and in similar technique.
In the following description, it describes so that the magnetic pole of outer rotor protects coating curing molding as an example according to the utility model The technological equipment for magnetic pole protection coating curing molding of embodiment, and be described in detail on the inside of outer rotor (magnetic pole side) The first energy delivery system of pressurized, heated is carried out to bonding agent blending space (protection coating molding space).With the prior art Technological equipment is compared, and eliminates bonding mold 60 according to the technological equipment of the utility model embodiment, no longer viscous by heating It connects with mold 60 come indirect heating bonding agent blending space, but annular resilient compressible medium capsule components flexibility is used to squeeze Vacuum bag simultaneously directly heats bonding agent blending space with the heated fluid medium circulated.
Fig. 7-12 is that the technological equipment according to the utility model embodiment for magnetic pole protection coating curing molding shows It is intended to.As shown in fig.7-12, rotor is along axial horizontal positioned, and magnetic pole 43 is fixed on the magnetic yoke 41 of rotor by press strip 42 On inner surface.Vacuum bag (not shown) is laid on the outer surface of magnetic pole 43, to form bonding agent perfusion die cavity.In magnetic The radial limited support component 100 of setting first at the radially inner side preset distance of pole 43, in the first radial limited support component 100 First flexible cavity component 200 is set between magnetic pole 43.First radial limited support component 100 is rigid element, for branch It supports and keeps the first flexible cavity component 200.When being filled with the fluid media (medium) of pressurization into the first flexible cavity component 200, the The expansion of one flexible cavity component 200 closely squeezes vacuum bag to flexible.
First radial limited support component 100 is ring-type, the annular gaps such as formation between magnetic pole 43, that is, first accommodates Space, thus for the reserved installation of cricoid first flexible cavity component 200, expansion space.First radial limited support component 100 It can be made of the lower material of heat transfer coefficient, for example, can be using plank, hard plastic plate etc., for preventing heat edge Radially outward transmit.Further, it is also possible to exhausted to further increase in the external laying heat-insulating material of radial limited support component 100 Hot property.First radial limited support component 100 can also be formed by rigid backbone and filling heat insulator.In order to install Convenient, the first radial limited support component 100 can along the circumferential direction be divided at least two panels, preferably be divided into four.Adjacent two Modular subs can be formed between piece.Further, it is also possible to left end and right end setting limit pressing plate 110 in the equal annular gaps (Fig. 9 is referred to) with 120, to limit the expansion axially outward and heat transfer of the first flexible cavity component 200.It is installed in magnetic pole 43 On the inner wall of rotor rim 41, that is, and in the case that rotor 40 is outer rotor, the first radial limited support component 100 Periphery be convex surface, the first flexible cavity component 100 is arranged on the external peripheral surface of the first radial limited support component 100. In the case that rotor 40 is internal rotor, the inner circle of the first limited support component 100 is then arranged in the first flexible cavity component 200 In perimeter surface.
First flexible cavity component 200 can be hermetic bag made of flexible rubber or flexiplast, be arranged in radial limit In first receiving space between position support member 100 and vacuum bag.First flexible cavity component 200 can have the first side wall 210 and second sidewall 220, the first side wall 210 is radial outside wall, for contacting with the vacuum bag laid on magnetic pole 23, to squeeze Press the bonding agent in vacuum bag.Second sidewall 220 is radially inner side wall, is connect with the surface of the first radial limited support component 100 Touching.First flexible cavity component 200 can be supported by the first radial limited support component 100.It can be to the first flexible cavity component The pressurized fluid media of predetermined temperature is filled in 200, for example, empty gas and water, oil etc..It is filled in the first flexible cavity component 200 In the case where the fluid media (medium) of pressurization, the first flexible cavity component 200 can with the rigid surface flexible contact of vacuum bag, to true Bonding agent in empty bag carries out flexible extruding, spreads bonding agent, well into the gap between magnetic pole 43 and magnetic pole 43, magnetic Gap between gap, magnetic pole 43 between pole 43 and press strip 42 and the gap between magnetic yoke 41, press strip 42 and magnetic yoke 41, sufficiently The surface for infiltrating, impregnating glued solid, sufficiently infiltrates with the cloth of reinforcement fibers of laying and mixes.Meanwhile so that bonding agent whole Thickness uniformity in a magnetic pole surfaces.In addition, bonding agent is constantly squeezed by flexible cavity component 200, so that Aqueous vapor in bonding agent blending space and the bubble generated due to polymerization reaction and in bonding agent blending space can be driven It drives away, to avoid in the protection coating of formation that there are bubble or holes.
The case where making the first flexible cavity component 200 using flexible rubber material (for example, PVDF) or plastic material Under, the sensing parts such as temperature sensor 510, piezoelectric transducer 520 can be buried, in the first flexible cavity component 200 with inspection Fluid measured medium temperature and pressure.Temperature sensor 510, the piezoelectric sensing of different location can will be set by data/address bus Device 520 is connected to controller 500 (with reference to Fig. 8 and Figure 13), and temperature signal, pressure signal are sent to controller 500, from And the whole heating temperature and pressure for controlling different piece.First flexible cavity component 200 can all be made of PVDF material, With piezoelectric transducer 520 easy to form.However, in order to save cost, it can also be only in the position for needing to arrange piezoelectric transducer 520 PVDF material is installed, and other parts are made of lower-cost rubber or plastics.
The inner space of first flexible cavity component 200 can be individual ring cavity, that is, inner space does not separate. However, it is also possible to which the internal cavity of first flexible cavity component 200 is divided into multiple annular channels 240 by dividing strip 230. Dividing strip 230, which can be, has certain flexible soft band of rib shape, and two sides are connected respectively to the first side of flexible cavity component 200 On wall 210 and second sidewall 220.Multiple annular channels 240 can be independent from each other, and be also possible to interconnected.Change sentence It talks about, each channel 240 can be parallel with one another, be also possible to be serially connected.Fig. 7-12 shows the first flexible cavity The example of each Tandem connection of component 200.Each channel that Figure 14 shows the first flexible cavity component 200 is in parallel The example of connection.In the following, being described in detail with initial reference to Fig. 7-12 pairs of technological equipments according to the utility model first embodiment.
In the case where each annular channel 240 is serially connected, one can be formed around the first radial limited support portion The helical fluid medium channel of the lateral wall coiling of part 100.The fluid medium channel can be according to substantially spiral-shaped one end It is coiled towards the other end.Fluid media (medium) entrance can be formed in axial one end of the first flexible cavity component 200, and fluid media (medium) goes out Mouth may be formed at the axial other end of the first flexible cavity component 200, so that fluid media (medium) is from the first flexible cavity component 200 One end enters helical fluid medium channel, from the another of the first flexible cavity component 200 after the surface coil of magnetic pole 43 End outflow.Can by dividing strip 230 in the first flexible cavity component 200 along the axial direction coiled coil of rotor, come The inner space of first flexible cavity component 200 is divided into the spiral-shaped fluid medium channel of serial communication.
As shown in figure 9, in the case where not being filled with fluid media (medium) in the first flexible cavity component 200, the first elastic cavity Body component 200 is maintained at pre-expansion initial position, i.e. dotted line position 250 shown in Fig. 9.Pre-expansion is also shown in Figure 12 just Beginning position is indicated by label 250.When the fluid for being filled with pressurized fluid media or pressurized, heated in the first flexible cavity component 200 After medium, the first flexible cavity component 200 is full of cyclic expansion extendable room, contacts with the vacuum bag of covering adhesive layer, from And circumferentially the direction 360o to bonding agent blending space transmit energy.
The fluid media (medium) being filled in the first flexible cavity component 200 can be liquid, or gas.According to this reality It include the first hot fluid medium supply system with the magnetic pole protection coating cure process equipment of novel exemplary embodiment 600, the fluid media (medium) for fluid media (medium) or pressurized, heated to the supply pressurization of the first flexible cavity component 200.It is first-class Body medium supply system 600 may include fluid media (medium) pressuring machine and heater, and pressuring machine pressurizes for fluid medium, heating Device is for heating fluid media (medium).In the case where fluid media (medium) is liquid (for example, water, oil etc.), pressuring machine can be liquid Pressure pump.In the case where fluid media (medium) is gas, pressuring machine can be compressor.
In the embodiments of the present invention, come the implementation that describes the utility model by taking heated fluid medium is air as an example Example.Figure 10 shows first fluid medium supply system.As shown in Figure 10, supplying fluid medium system 600 includes compressor 610, heater 620, the first connecting line 630, fluid delivery pipeline 640, fluid recovery pipeline 650, bypass line 660.Pressure Mechanism of qi 610 is used to convey forced air to the first flexible cavity component 200.Forced air is in the first flexible cavity component 200 Compressor 610 is returned to by fluid recovery pipeline 650 after circulation.Air after compressor 610 pressurizes can be by the first connection Pipeline 630 flows to heater 620, and forced air is heated to be supplied to the first flexible cavity portion after predetermined temperature by heater 620 In part 200.
Bypass line 660 is connected between the inlet and outlet of heater 620, when not needing through heater 620 to following When ring gas is heated, gas-pressurized can be direct supplied into the first elastic cavity from compressor 610 by bypass line 660 In body component 200.
The first valve 641 of control fluid path on-off is provided in fluid supply channel 640, the first valve 641 can To be electrically-controlled valve.The second valve 651 of control fluid path on-off, the second valve can be set on fluid recovery pipeline 650 Door 651 can be electrically-controlled valve.Third valve 652 can be set in the entrance side of compressor 610, it can be by opening third valve Door 652 supplies outside air to compressor 610.Third valve 652 can be electrically-controlled valve.4th valve 631 is arranged first On connecting line 630, the on-off of the fluid path between compressor 610 and heater 620 is controlled.5th valve 661 and the 6th Valve 662 is arranged on bypass line 660, controls the on-off of bypass line 660.
It is also provided with first pressure gauge 642 and the first temperature sensor 643 in fluid supply channel 640, uses respectively In the pressure and temperature of the air of detection supply.It is also provided with second pressure gauge 653 in fluid recovery pipeline 650, for examining The pressure of the air of survey time stream.
It, can be with into the first flexible cavity component 200 when supply pressurized gas after completing the priming by vacuum of bonding agent The first fluid medium supply system 600 according to the utility model embodiment is opened, forced air is supplied to the first elastic cavity In body component 200.When air is expanded full of the first flexible cavity component 200, occupies and be reserved in the first radial limited support Cyclic expansion extendable room between component 100 and adhesive layer.The radially inward expansion quilt of first flexible cavity component 200 Radial limited support component 100 stops, and radially outer inflatable elastomeric squeezes vacuum bag.First flexible cavity component 200 with it is true Empty bag flexibility is in close contact, and compresses vacuum bag.
Two conditions of Nian Jie needs are formed between bonding agent and magnetic pole, first is that infiltration, second is that bonding force, the two lacks one not It can.Infiltration is after bonding agent and magnetic pole, magnetic yoke wall, the contact of cloth of reinforcement fibers surface, and the process that contact surface is automatically increased is viscous Connect the intermolecular interaction occurred when agent (resin and curing agent) is contacted with magnetic pole surfaces, rotor rim wall, cloth of reinforcement fibers The phenomenon that.Therefore, in order to promote the infiltration of bonding agent and magnetic pole surfaces, be quickly filled in the first flexible cavity component 200 plus It calms the anger body, pressurizes to bonding agent, promote dipping, infiltration, the seepage flow of bonding agent.
As an example, a part of gas first can be filled in advance in the first flexible cavity component 200, so as to open After compressor 610, moment the first flexible cavity component 200 can be full of.
When by compressor 610 be filled with gas-pressurized to flexible cavity component 200 when, can first open the first valve 641, Third valve 652, the 4th valve 631, close other valves.Outside air is introduced into compressor 610 by third valve 652, Air after being pressurizeed by compressor 610 directly passes through bypass line 660 and enters the first flexible cavity component 200.It can make gas Body is directly filled in the first flexible cavity component 200 from compressor 610 by bypass line 660, and is avoided by flow resistance Big heater 620.
First flexible cavity component 200 can be with constant pressure extrusion bonding agent, can also be with the pressure extrusion of pulsation Bonding agent.In order to promote flowing, the diffusion of bonding agent, the pressure for the gas-pressurized being filled with can be periodically-varied.Therefore, First fluid medium supply system 600 is run in a manner of transformation, is glued so that the first flexible cavity component 200 is squeezed with undulating manner Connect agent.
During variable-pressure operation, the gas pressure being filled with can be made to increase by control compressor 610, can also passed through Operation third valve 652 discharges a certain amount of gas outward reduce the internal pressure of flexible cavity component 200.In pressure When change, the 4th valve 631 can be closed, opens the 5th valve 661 and the 6th valve 662 on bypass line 660, makes to add Body of calming the anger does not pass through heater 620, but is directly entered in the first flexible cavity component 200 by bypass line 660, realizes pressure The instantaneous variation of power improves the extruding to bonding agent and dispersion effect.
In first embodiment according to the present utility model, the cavity in the first flexible cavity component 200 passes through dividing strip 230 are divided into multiple annular channels.Multiple annular channels are connected in series, and form single fluid medium channel.Dividing strip 230 can be with For ribbed belt flexible, two sides are connected respectively on the first side wall 210 and second sidewall 220.When gas-pressurized is quickly filled with When one flexible cavity component 200, a wing passage instantaneous expansion forms the impact force of a moment, dividing strip to dividing strip 230 230 can be to other side bending deformation, into adjacent channel under the action of entire impact force.Dividing strip 230 be subject to this Kind impact force can tear dividing strip 230 and the first flexible cavity component 200 is detached from.Especially, during variable-pressure operation, dividing strip 230 can be repeatedly towards different direction bending deformation, this can aggravate the damage of dividing strip 230 thus with the first flexible cavity portion The side wall of part 200 is detached from.Therefore, it is torn to reduce this moment impact to caused by dividing strip 230, on dividing strip 230 Some holes are opened up, so that portion of air enters in the relatively low channel of pressure from the high channel of pressure, reduce dividing strip 230 The instantaneous pressure of two sides is poor.
Fig. 7 shows the example that hole is provided at the position that dividing strip 230 is connect with the first side wall 210.
Fig. 8 shows hole and starts example at the position that dividing strip 230 is connect with second sidewall 220.However, hole It can be provided with any position of dividing strip 230, for example, being provided with the middle part of dividing strip 230.Hole 240 is preferably shaped to Circle avoids local stress excessive and cracks.
Embodiment according to the present utility model, the technological equipment for magnetic pole protection coating curing molding, which may also include, to be used for The second energy delivery system that the external peripheral surface of magnetic yoke 41 is heated.As shown in figure 11, the second energy delivery system can Including the second flexible cavity component 300 and the second radial limited support component 400.Second radial limited support component 400 is circle The periphery of rotor 40 is arranged in tubular, forms annular gap between the external peripheral surface of rotor 40, that is, the second accommodation space, Second flexible cavity component 300 is arranged in the second accommodation space.Second energy delivery system can also include that second fluid is situated between Matter supply system (not shown), to be filled with heated pressurized gas into the second flexible cavity component 300.Due to magnetic yoke 41 Outer surface only needs to heat, and therefore, only can be filled with heat gas into the second flexible cavity component 300.It is preferable, however, that In order to make the outer surface of the second flexible cavity component 300 and magnetic yoke 41 be in close contact to heat magnetic yoke 41 with heat exchange pattern And the second flexible cavity component 300 is avoided to burn, the second energy delivery system can also include that the second compressor (does not show Out), to be filled with heated pressurized gas to the second flexible cavity component 300.At the both ends of annular gap, limit pressure can also be set Plate 410 and 420, to limit the expansion axially outward and heat transfer of the second flexible cavity component 200.Due to not needing to magnetic The cylindrical wall of yoke 41 carries out fluctuation pressurization.Therefore, other than fluctuating pressurization, the second energy delivery system can be with the first energy The construction of transmission system is similar, and in order to keep specification succinct, no longer the second energy delivery system is described in detail here.
As shown in figure 13, the first flexible cavity component 200 and the second flexible cavity component 300 can use flexible rubber Or flexiplast is made, and can be embedded with temperature sensor 510 and pressure sensor 520, and passes through data/address bus and control Device 500 processed connects, and pressure signal and temperature signal are passed to controller 500, supervises to realize to the totality of pressure and temperature It surveys and controls.Pressure signal deviations and magnetic pole protection coating thickness deviation are corresponding, and pressure is low then to correspond to magnetic pole protection coating thickness Greatly, it is small then to correspond to greatly magnetic pole protection coating thickness for pressure.The relationship that pressure signal deviations and thickness deviation can be established, as evaluation The index of energy delivery system working effect.Axial height pressure divergence signal can be used as vacuum system breakdown judge foundation, borrow It helps calibrator to examine, correct variable-pressure operation period and dynamics.
In addition, embodiment according to the present utility model, since flexible cavity component 200 is extruded in vacuum bag outer surface, i.e., Make to be that vacuum bag has breakage, vacuum bag can be also squeezed by the close contact with vacuum bag outer surface and tightly, prevents vacuum Vacuum failure in bag.
Figure 14 is the schematic diagram according to the first energy delivery system of the utility model second embodiment.Practical according to this In novel second embodiment, each layer channel in flexible cavity component 200 is mutually indepedent, is connected in first fluid medium in parallel Between the entrance and exit of supply system 600, therefore, each channel can individually be controlled.First energy transmission shown in Figure 14 System includes the shunting main pipe 645 connecting with fluid delivery pipeline 640 and the reflux main pipe connecting with fluid recovery pipeline 650 655.Shunt main pipe 645 and the shunting branch for being respectively delivered to air in each annular channel of flexible cavity component 200 Pipe connection, be provided on each shunt pipe shunt pipe valve 7 for controlling each shunt pipe on-off, 9,11,13, 15,17,19.Reflux main pipe 655 is connected to the reflux branch pipe for recycling the air in each annular channel, each reflux branch The reflux branch pipe valve 6,8,10,12,14,16,18 for controlling each reflux branch pipe on-off is provided on pipe.
In order to form each independent channel, by annular and separation band 230 by the inside of the first flexible cavity component 200 Space is divided into multiple circular passages along the axial direction of rotor.In order to which each circular passage to be separated from each other and reduce adjacent Interference and influence between channel, dividing strip 230 can be the annular rib shape demarcation plate with certain rigidity.In addition, each A longitudinal subdivision piece (not shown) is also set up in circular passage, and shunt pipe and reflux are set in the two sides of longitudinal subdivision piece Branch pipe, the air for flowing into circular passage are circulated up one week in whole circumference side.Circular passage is flowed by shunt pipe Air-flow circumferentially 360o degree circulation after a week by reflux branch pipe outflow.
In the example depicted in fig. 14, the space quilt along the axial direction of rotor, in the first flexible cavity component 200 It is divided into 7 circular passages, from left to right respectively first annular channel, the second circular passage, third circular passage, fourth annular Channel, the 5th circular passage, the 6th circular passage, the 7th circular passage.Valve 7,9,11,13,15,17,19 can be passed through respectively The shunt pipe for controlling each channel controls the reflux branch pipe in each channel by valve 6,8,10,12,14,16,18.On but The number of plies for stating channel is only exemplary, and the number in channel can be arranged according to the needs that the size of rotor and pressure control Amount.
Process described in 4 is similar referring to Fig.1 with front, after priming by vacuum bonding agent, first applies to bonding agent and presses Power makes the thickness uniformity of adhesive layer by squeezing, driving, while making bonding agent dipping, infiltration, seepage flow to each gap In.It can make the pressure of the first flexible cavity component 200 by the opening and closing of each valve come the pressure in each layer channel of hierarchical control Layered circulation pulsation.During variable-pressure operation, openable bypass line 660 makes gas-pressurized directly pass through shunting main pipe 645, then entered in each channel by shunt pipe.It is pressurizeed by fluctuation, can drive, push bonding agent, so that bonding Agent is axially uniformly distributed with circumferencial direction, while carrying out radial compression to bonding agent, is driven bonding agent and is overcome Radial resistant force, Seam into the gap between magnetic pole 43 and the gap between magnetic pole 43 and press strip 42, between magnetic pole 43 and magnetic yoke 42 Gap improves the full rate of filling of bonding agent.
Figure 15 A and 15B show the sectional view of main view and press strip according to the rotor of the utility model embodiment. As shown in figs. 15a and 15b, it is arranged alternately along the circumferencial direction of rotor 40, magnetic pole 43 and press strip 42, by press strip 42 by magnetic Pole 43 is fixed on the inner wall of rotor rim 41.Unlike the prior art, in embodiment according to the present utility model, Vertical passage 421 and interconnection 422, vertical passage 421 and interconnection 422 are formed in press strip 42 to be interconnected, shape Structure is reticulated, so that bonding agent can be interconnected in different directions and flow.In the embodiments of the present invention, Vertical passage 421 is axially formed in press strip 42 along rotor, can be along rotor axially through press strip 42.Interconnection 422 can form along the circumferencial direction of rotor 40 and run through press strip 42.Vertical passage 421 and interconnection 422 can by The back side of press strip 42 forms groove to be formed.In this case, more bonding agents enter between press strip 42 and magnetic yoke 41, from And increase the binding force between press strip 42 and magnetic yoke 41.
The flow characteristics of 16A-18B description bonding agent at different location in bonding agent mixing cavity with reference to the accompanying drawings. For the ease of stating the bonding agent for being located at rotor different location, in the case where rotor 40 is axial horizontal positioned, definition electricity The bottommost of machine rotor 40 is 6 o'clock position, and top is 12 o'clock position.
Figure 16 A and 16B show near 6 o'clock of clock (for example, in 4-5-6-7-8 o'clock position range) bonding agent Flow characteristics.As shown in figure 16 a and 16b, the position near six o'clock of clock, on the one hand, in the first flexible cavity component Under the action of 200 extruding forces applied, bonding agent circumferentially flows with axial direction, is unfolded.Specifically, in magnetic pole 43 Upper surface, bonding agent under the guidance of fluid conducting material, sufficiently infiltrate reinforcing material 51, in the lower surface of magnetic pole 43, bonding agent Along the gap between magnetic pole 43 and magnetic yoke 41, the gap between press strip 42 and magnetic yoke 41 is flowed towards all directions.Another party Work is combined with bonding agent self gravity in face, radially, the radial pressure that the first flexible cavity component 200 applies bonding agent For bonding agent, so that bonding agent is in radial clearance, magnetic pole 43 and the press strip entered between magnetic pole 43 under double action power drive In 42 gap.Due to the opposite setback in gap between radial clearance very little, especially magnetic pole 43 and press strip 42, bonding agent along Resistance into radial clearance is very big, if only leaning on the effect of flow by gravity, is difficult to go deep into radial clearance completely.However, Embodiment according to the present utility model applies bonding agent by being filled with pressurized fluid media in the first flexible cavity component 200 Add flexible extruding force, penetrated into radial gap for bonding agent along radial direction and provide sufficient driving force, so that bonding Agent can be flowed along radial clearance, so that each gap be filled up.
Figure 17 A and 17B show bonding agent near 12 o'clock position (for example, in 10-11-12-13-14 o'clock range It is interior) flow characteristics.In the position, similar with flow characteristics shown in Figure 16 A and 16B, bonding agent is two-way in a circumferential direction Expansion flowing, two dimensional development flows in the axial direction.In radial directions, gravity direction is downward, with the first flexible cavity component 200 The radial compression power of application is contrary, unfavorable to bonding agent Radial Flow Through Porous Media.However the application of the first flexible cavity component 200 is crowded Pressure is far longer than gravity, and therefore, bonding agent can overcome diameter under the action of the radial pressure that elastic strong component 200 applies To resistance, along seepage flow, dipping in gap of the radial direction between magnetic pole 43 and between magnetic pole 43 and press strip 42.
Figure 18 A and 18B show (within the scope of clock 2-3-4) or (clock 8-9-10 near 9 o'clock near corresponding 3 o'clock In range) flow characteristics of position.It is similar with flow characteristics shown in prior figures 16A, 16B, 17A and 17B, in the first elasticity Under the action of the extruding force that capsule components 200 apply, two dimensional development flows bonding agent in a circumferential direction, exhibition two-way in the axial direction Open flowing.At the same time, bonding agent is under the action of the radial pressure that the strong component 200 of the first elasticity applies, along radial direction Seepage flow, dipping in gap between magnetic pole 43 and between magnetic pole 43 and press strip 42.Although gravity direction and radial direction are hung down Directly, it is unfavorable for bonding agent radially to enter in radial clearance, however, embodiment according to the present utility model, due to setting Flexible cavity component 200 enables the bonding agent resistance is overcome to cross magnetic pole 43 and press strip by applying flexible extruding force 42, it is flowed along radial clearance, into magnetic pole and press strip behind.
In the prior art, each row's magnetic pole is along the circumferential direction spaced from each other by press strip 42, in press strip and not formed makes circumference side The channel that bonding agent between upward magnetic pole mutually circulates so that bonding agent extra between magnetic pole can not add to it is adjacent In magnetic pole gap.However, embodiment according to the present utility model, due to being provided with fluid channel in 42 behind of press strip, so that viscous The flowing of press strip 42 can circumferentially be passed through by connecing agent, so that the bonding agent of different zones is interconnected, is complementary to one another, from And it is sufficient filling with each gap.
Figure 19 and 20 shows the external structure diagram according to the technological equipment of the utility model embodiment.
As shown in figure 19, further include the second energy delivery system according to the technological equipment of the utility model embodiment, be used for Magnetic yoke 41 is heated from outside.In embodiment according to the present utility model, the second energy delivery system includes the first electricity Magnetic induction heating unit 800.The radial outside of rotor rim 41 is arranged in first electromagnetic induction heating unit 800, is used for from outer Rotor rim 41 is heated in side, to heat from the other side to magnetic pole.
First electromagnetic induction heating unit 800 may include the electromagnetic induction heating coil being wrapped on the outer wall of magnetic yoke 41 801, the induction heating power 802 of alternating current is provided for electromagnetic induction heating coil 801 and sense 41 outside wall temperature of magnetic yoke Temperature sensor 803.First electromagnetic induction heating unit 800 may also include outside heat insulating member 804, be centered around the outer of magnetic yoke 41 Side prevents the heat of magnetic yoke 41 from distributing outward.Outside heat insulating member 804 include radially around cylinder and axial end portion baffle, To carry out radial limit and axial limiting to electromagnetic coil 801.
The outside of rotor rim 41 is arranged in outside heat insulating member 804, and pre- with the lateral wall interval of rotor rim 41 Set a distance, to form annular housing between 41 lateral wall of heat insulating member 804 and rotor rim on the outside.Electromagnetic coil 801 exists It is wrapped in the annular housing on the outer wall of magnetic yoke 41.Air is full of in the annular housing, since air is with lower thermally conductive Coefficient, to can be further improved heat-insulating property by the air in the annular housing.On the other hand, due to entire annular housing Interior air mutually circulates, so that the temperature uniformity of the entire outer surface of the outer wall of rotor rim 41.If The temperature of the outer wall of rotor rim 41 everywhere is inconsistent, then is easy to cause the torsional deformation of rotor 40 in expansion process.However, Embodiment according to the present utility model, due to the presence of annular housing, so that the temperature of the outer surface of rotor rim 41 uniform one It causes, avoids due to the inconsistent caused torsional deformation of temperature.
In addition, the outside heat insultating cavity 804 there can also be electromagnetic shielding action, the electromagnetic wave of electromagnetic coil 801 is avoided To external radiation, Contamination of Electromagnetic Wave is caused to environment, radiation injury is caused to worker.It can be enclosed on the inner wall of the heat insultating cavity One layer of aluminium foil.On the one hand, electromagnetic wave is shielded by the aluminium foil layer, on the other hand, aluminium foil layer can reduce radiance, into One step enhances thermal insulation property.
It can also include end thermal insulation board 805 according to the utility model embodiment technological equipment.End thermal insulation board 805 is circle One end of rotor is arranged in shape, for blocking rotor internal cavity, rotor 40 is avoided to distribute heat outward from axial end portion.End every Hot plate 805 also has the function of sound insulation and electromagnetic shielding, for completely cutting off the noise for the component being arranged in rotor internal cavity and preventing Only interfering with each other between each electromagnetic component.
As illustrated in figures 19 and 20, technological equipment according to the present utility model further includes rotary drive unit 900, is used for Driving motor rotor along the circumferential direction rotates.
Rotary drive unit 900 may include servo drive component 901 and conversion section 904, and servo drive component 901 can wrap Servo drive motor and retarder are included, servo drive unit 901 can be turned by drive shaft 902 and the connection of flexible clutch 903 Change section 904.Conversion section 904 includes small end and big end, and small end is connect with the power output end of flexible clutch 903, greatly The flange 47 of end and rotor is cooperatively connected, and completes major diameter rotary part with the conversion of minor diameter rotary part and connect function Energy.
Rotary drive unit 900 further includes SERVO CONTROL power supply 905, servo sensor 906 and support base 908.It watches Sensor 906 is taken for detecting the rotation angle of conversion section 904, servo drive motor is detected according to servo sensor 906 Rotational angle signal determines rotation direction and rotational angle.
Controller 500 can control rotary drive unit 900, according to the seepage flow situation of bonding agent, rotate rotor 40 pre- The predetermined time is stopped after determining angle.For example, making rotor 40 stop the predetermined time, so that bonding agent after the completion of bonding agent perfusion Abundant seepage flow, dipping.Since the bonding agent in 6 o'clock position is more advantageous under the double action of gravity and radial compression power Magnetic pole gap is filled, in order to enable the formation thickness uniformity of each position filling rate of rotor and protection coating, Ke Yi After the static predetermined time, the 6 o'clock position of rotor is rotated into predetermined angular, so that each position of rotor is in 6 o'clock position The predetermined time is stopped, to the abundant seepage flow of bonding agent at different location, be filled into magnetic pole gap.
It can also include the second electromagnetic induction heating unit 700 according to the technological equipment of the utility model embodiment.Figure 21 Show the schematic diagram of the second electromagnetic induction heating unit according to the utility model embodiment.Second electromagnetic induction heating unit 700 for heating magnetic pole 43 from the inside of rotor, so that magnetic yoke 43 takes the lead in warming up, to reduce bonding agent and consolidate Infiltration angle between body component, realizes bonding between the two.It is situated between in the hot fluid only passed through in the first flexible cavity component 200 Matter carries out heating and by the first electromagnetic induction heating unit 800 from the outside of magnetic yoke 41 on the inside of bonding agent blending space When heating to magnetic yoke 41, magnetic pole 43 can only be heated by way of heat transfer, between magnetic yoke 41 and magnetic pole 43 The temperature of bonding agent is lower than the temperature of the radially inner side bonding agent positioned at magnetic pole 43, therefore, the bonding agent temperature of 43 two sides of magnetic pole It is inconsistent.On the other hand, in the case where heating magnetic pole 43 from inside in thermo-conducting manner by flexible cavity component, magnetic pole 43 temperature is lower than the temperature of bonding agent, is unfavorable for realizing bonding between bonding agent and magnetic pole.However, according to the utility model Embodiment, bonding agent can be crossed to heat to magnetic pole 43 by the second electromagnetic induction heating unit 700, magnetic can be made The temperature of pole 43 takes the lead in warming up, its temperature is made to be higher than the temperature of bonding agent, reduces the surface energy of magnetic pole 43, reduces bonding agent Infiltration angle between magnetic pole 43, improves bonding force between the two.On the other hand, by making the temperature of magnetic pole 43 be higher than bonding The temperature of agent can guarantee bonding agent blending space from two sides thermally equivalent.
As shown in figure 21, the second electromagnetic induction heating unit 700 may include supportive body 701, supporting cantilever 702, electromagnetism Induction heating cylinder 703, induction heating power 704.Electromagnetic induction heating cylinder 703 is online by cylindrical wires ring framework 7031 and winding The formation of electromagnetic coil 7032 on ring framework 7031.In order to enable electromagnetic coil 7032 is equably wrapped in coil rack 7031 On, coil holding tank can be previously provided on coil rack 7031, by accommodating the setting of electromagnetic coil 7032 in coil In slot, effectively to control density and the interval of electromagnetic coil 7032.
Electromagnetic induction heating cylinder 703 is fixed on one end of supporting cantilever 702, by the other end of supporting cantilever 702 by propping up Main body 701 is supportted to support.Supporting cantilever 702 on the whole can be with linear expansion, integral elevating, to adjust electricity according to the position of rotor The height of magnetic induction cartridge heater 703 and horizontal position, to be accurately placed in rotor internal cavity.
Supporting cantilever 702 can be at least two, symmetrically be supported on the two sides of electromagnetic induction heating cylinder 703.In this reality With in novel embodiment shown in the drawings, supporting cantilever 702 is four, is symmetricly set on electromagnetic induction heating cylinder 703.
Supporting cantilever 702 can be driven flexible by driving part 705, turned so that electromagnetic induction heating cylinder 703 is put into It is taken out in sub- inner cavity or from rotor internal cavity.When electromagnetic induction heating cylinder 703 is put into rotor, electromagnetic induction heating cylinder 703 are located at the radially inner side of radial support member 100.
In the case where heating using 703 pairs of magnetic poles of electromagnetic induction heating cylinder, need to guarantee electromagnetic induction heating cylinder 703 are symmetrical arranged with rotor, so that the induced current uniformity generated on magnetic pole, therefore, it is necessary to by adjusting electricity The position of magnetic induction cartridge heater 703, so that the gap uniformity between electromagnetic induction heating cylinder 703 and rotor rim inner wall. Supporting cantilever 703 is set at least four by embodiment according to the present utility model, and makes supporting cantilever 702 not only can be with The horizontal position of electromagnetic induction heating cylinder 703 is adjusted relative to rotor rim, left-right position, upper and lower position can also adjust electricity 703 tilt angle of magnetic induction cartridge heater.However, in this case, the cost of supporting cantilever 702 is relatively high.
In order to save the manufacturing cost of entire technological equipment, the technological equipment of embodiment according to the present utility model further includes Laser centring device 907.Laser centring device 907 may include laser emitter and laser pickoff.Laser emitter can be with It is mounted on reference axis, laser pickoff may be mounted on adjustment axis.
For example, in the case where rotor, which remains stationary, makes the second electromagnetic induction heating unit 700 towards rotor movement, it can Laser emitter to be mounted on rotor 40, and laser pickoff is mounted on electromagnetic induction heating cylinder 703.In addition, In the case that rotor can also be moved along track, two laser centring devices 907 can be set, so that rotor is relative to second Electromagnetic induction heating unit 700 is adjustment axis.In such a case, it is possible to keep the first electromagnetic induction heating unit 700 not It is dynamic, and keep rotor mobile towards the first electromagnetic induction heating unit 700.By laser centring device 907, electromagnetism sense can be adjusted Cartridge heater 703 is answered to be placed in rotor axially alignedly.Guaranteeing the circularity of rotor 40 and electromagnetic induction heating cylinder 703 simultaneously And in the case that rotor and electromagnetic induction heating cylinder 703 are horizontally mounted, it is only necessary to adjust the two by laser centring device Between it is axially aligned, without be arranged the higher mechanical arm of cost, to save manufacturing cost.
As shown in figure 23, in addition, in order to further confirm that the gap between electromagnetic induction heating cylinder 703 and rotor is No along the circumferential direction uniformity, can also rotor inner wall or electromagnetic induction heating cylinder 703 outer wall setting away from From sensor 808.Range sensor 808 can be at least four, evenly distributed in the circumferential direction in the described first radial limit The radially inner side of support member 100 or the outside for being arranged in the electromagnetic induction heating cylinder 703.
Embodiment according to the present utility model, for the ease of mobile second electromagnetic induction heating unit 700, and convenient for adjusting The position of economize on electricity magnetic induction cartridge heater 703 can be arranged idler wheel in the lower part of supportive body 701, be also provided with moving rail Road 706 avoids the deflection in moving process so that supportive body 701 is moved along the track 706 of setting.
Figure 23 shows the isometric exploded view of a part of the technological equipment according to the utility model embodiment.As schemed Show, in the case where electromagnetic induction heating cylinder 703 is put into rotor inner cavity by laser centring device 907, Ke Yitong End thermal insulation board 805 is crossed by the end part seal of rotor inner cavity, on the one hand prevents heat from distributing outward, on the other hand to electromagnetism Wave is shielded, and electromagnetic wave outside radiation is avoided to cause environmental pollution.In addition, end thermal insulation board 805 can also play the work of sound insulation With the Noise upon Environment for avoiding the component in rotor inner cavity from issuing when operating causes noise pollution.According to the utility model Embodiment, can by priming by vacuum equipment be arranged in rotor internal cavity.As shown in figure 21, vacuum pump 53, resin container 54, resin The components such as system collecting tank 57 can be set in rotor internal cavity, and is closed by end thermal insulation board 805, on the one hand can be with Thermal loss is avoided, on the other hand, the running noise of all parts can be shielded by end thermal insulation board 805, is realized Energy conservation and environmental protection and green manufacturing.
Embodiment according to the present utility model, in vacuum infusion process, the first flexible cavity component 200 of setting is to viscous It connects agent blending space and applies radial compression power, the driving force missing of bonding agent Radial Flow Through Porous Media is solved the problems, such as, to solve magnetic pole The filling problem in the gap between magnetic yoke parietal suture gap, magnetic pole and magnetic pole, between magnetic pole and press strip.Especially by press strip Fluid channel is set, so that bonding agent is interconnected by the fluid channel in press strip, keeps the bonding agent of different zones mutual Supplement, is sufficient filling with each gap.In the case where rotor is horizontal positioned, rotor can also be made to rotate to a certain position and kept Predetermined time, so that bonding agent is under the effect of gravity, under the action of radial pressure gradient, axial pressure gradient, be sufficiently impregnated, seep Stream, filling protection coating form space.
By being full of pressurized fluid media in flexible cavity component 200, bonding agent is applied and is adequately squeezed, it can be abundant Drive, squeeze out gas, bubble in bonding agent etc., it avoids forming bubble and hole in protection coating.
When bonding agent is perfused to a certain extent, it may be difficult to continue to supplement bonding agent into vacuum bag.However, according to this reality Binder can be perfused to vacuum bag 50 under positive pressure due to the presence of flexible cavity component with novel embodiment.? The pressure in vacuum bag can be suitably reduced, so that more bonding agents are supplemented in and.In other words, bonding agent can be improved Pressure supplements bonding agent into vacuum bag by force, to guarantee that each gap guarantees full of bonding agent in bonding agent filling space The full rate of filling in coating filling space is protected, so that each surface of magnetic pole being capable of glued dose of covering.
Magnetic pole is heated by electromagnetic induction heating unit 700, magnetic pole is made to take the lead in warming up, temperature is higher than bonding agent Temperature, reduce the infiltration angle of magnetic pole, improve the engaging force between solid-liquid.
Since the volume of the first flexible cavity component 200 is very small, by being filled with hot-air pair in flexible cavity component In the case that bonding agent is heated, air caloric receptivity is small, and air stream cyclic process cost is small, consuming little energy, temperature rise transition Process is of short duration, and temperature rise rate controllability is high, quick requirement of the resin filling process easy to accomplish to temperature rise.
Thermal current continuously flows in the annular space on the outside of rotor and thermal current continuous flow in flexible cavity component It is dynamic, it ensure that the Temperature Distribution homogenization of temperature field circumferencial direction, axial direction, so that the dilatancy of rotor is consistent, Rotor expansion is avoided to be distorted in the process.
By controlling the heating device of the magnetic yoke two sides of rotor, the temperature one of bonding agent blending space two sides is enabled to It causes, temperature rise rate is consistent.Temperature is the cured principal element of bonding agent, not only determines to solidify the degree completed, but also determine The speed that solidification process carries out.Curing time is too long or curing time is too short, can all adhesive property be made to decline.Temperature is excessively high, because React too fast, viscosity rises rapidly the diffusion that will affect bonding agent to bonded object surface, it will also result in the decline of adhesive property, Therefore, in bonding agent solidification process, strict control bonding agent solidification temperature.It is viscous that bonding agent used at present belongs to reactivity Agent is connect, after the two component mixing of resin and curing agent, crosslinks reaction, it is also necessary to remain necessary in solidification bonding temp Hourage solidifies the intensity requirement reached during obtaining caking.
After bonding agent to be maintained to the time that preferably bonding solidification temperature is persistently set, bonding agent is substantially It is fully cured, therefore enters cooling and stress relaxation stage.In cooling and stress relaxation stage, keep bonding agent mixed to set rate Space cooling is closed, correspondingly, the pressure in the first flexible cavity component 200 is also gradually reduced.It can be by controlling heater 620 Power reduced to make the temperature for the gas being filled with the rate that sets.
Process equipment and process according to the utility model embodiment for magnetic pole protection coating curing molding, It can be improved the reliability of technology of the permanent magnetism magnetic pole manufacturing, to improve magnetic pole protection Forming Quality.It is according to the present utility model Embodiment makes thermal current from continuously flowing in entire elastic cavity, guarantees by controlling the energy delivery system of magnetic pole two sides Temperature field circumferential orientation, the Temperature Distribution homogenization of different height are controllable, can be realized temperature rise control unification, Temperature Distribution Homogenization, temperature rise rate controllability are exceedingly fast, and solve in the protection coating forming process of permanent magnet motor magnetic pole in 360 degree of ranges of circumference Heated unification problem, magnetic pole and the heated unification problem of magnetic yoke short transverse.
By being filled with gas-pressurized in the first flexible cavity component 200, vacuum bagging skin is adapted to flexible material surface The comparatively rigid outer surface formed after vacuumizing, objectively it is easy to accomplish with vacuum bagging skin is seamless is bonded, realize close Contact.Realizing close contact could be with heat-conducting mode transferring heat energy, to improve heat transfer efficiency.It is pressurizeed, is promoted by fluctuation The infiltration of bonding agent, seepage flow, for the formation of bonding force provide abundant guarantee.Meanwhile by applying extruding force to bonding agent, The gas in bonding agent can be sufficiently driven, avoids forming bubble and hole in protection coating.
Due to the heat-blocking action by the first radial limiting component 100, so that the first flexible cavity component 200 can only be to The heat transfer of bonding agent blending space, thermal loss is small, and avoids other component and absorb heat, reduces in entire technical process Thermal loss and heat consumption.
Further, since not using the blower for forced-convection heat transfer, and generation is made an uproar in entire heating process The component of sound is enclosed in rotor internal cavity, is placed noise insulation by sound-insulating member, is exchanged heat with cross-ventilation in the prior art Mode compare, reduce noise pollution, be advantageously implemented green manufacturing.At the same time, by being provided simultaneously with heat insulating member Electro-magnetic screen function can prevent electromagenetic wave radiation injury caused by worker.
Embodiment according to the present utility model, by making magnetic pole protect temperature rise rate unification, temperature in coating forming process Degree is distributed homogenization, so that magnetic pole protection coating self-formed shaping process stress is eliminated, guarantees Forming Quality, the reduction later period used Removing caused by Cheng Yingli is broken, and magnetic pole protects the generation of coating phenomenon of rupture, improves unit service life.
Embodiment according to the present utility model is not limited to the solidification of the magnetic pole protection coating applied to wind power generator rotor Molding can also be applied to other and need to lay adhesive layer and make the occasion of bonding agent curing molding, equally may be implemented similar Technical effect.Although in addition, above simultaneously using the first energy delivery system, the second energy delivery system and internal electricity Magnetic induction heaters, the example that binder blending space is symmetrically heated from the two sides of bonding agent blending space, still, It selects to be heated in bonding agent blending space side due to process conditions limitation or the structure limitation of component itself etc. When, using the utility model the first energy transmission when also can be realized corresponding technical effect.
In addition, being not limited to solidify applied to the protection coating of outer rotor according to the technological equipment of the utility model embodiment Moulding process can be used for the protection coating cure process of internal rotor.In addition, in addition to the protection of the rotor for motor Except coating cure process, any similar applications for making bonding agent curing molding can also be applied to.In addition it is also possible to sharp With technological equipment according to the present utility model, pressurization only is carried out to adhesive layer or only adhesive layer is heated.In addition to this is practical Except the cylindrical rotor of new embodiment, the technological equipment of the utility model does not have the surface shape of protection coating curing molding It is restricted, this is because the flexible cavity component of the utility model is flexible, thus be it is profile-followed, so as to for each The surface of the component of kind irregular shape or regular shape forms protection coating.
Although describing the utility model referring to preferred embodiment, the description of above embodiments is only intended to help Assistant solves the principles of the present invention and spirit.It should be pointed out that for those of ordinary skill in the art, not departing from this Under the premise of the principle of utility model, various improvement can be carried out to the utility model, these improvement will fall into the utility model Scope of protection of the claims in.

Claims (11)

1. a kind of technological equipment for magnetic pole protection coating curing molding, rotor (40) includes magnetic yoke (41) and magnetic pole (43), the magnetic pole (43) is fixedly mounted on the radial first surface of the magnetic yoke (41), which is characterized in that the work Skill equipment includes the first electromagnetic induction heating unit (800) being arranged on the radial second surface of the magnetic yoke (41), described First electromagnetic induction heating unit (800) includes the first electromagnetic induction heating coil (801) being wrapped on the magnetic yoke (41) And the outside heat insulating member (804) being arranged on the outside of the electromagnetic induction heating coil (801), heat insulating member (804) and institute It states second surface to be spaced a predetermined distance, to form the annulus for surrounding the magnetic yoke (41).
2. technological equipment as described in claim 1, which is characterized in that the outside heat insulating member (804) further includes electromagnetic screen Component is covered, for shielding to electromagnetic wave.
3. technological equipment as claimed in claim 2, which is characterized in that the outside heat insulating member (804) includes around described Magnetic yoke (41) radially around cylinder and the axial limiting baffle of the end radially around cylinder, the electromagnetism be set Shield member is the aluminium foil being attached on the inside of the heat insulating member.
4. technological equipment as claimed in any one of claims 1-3, which is characterized in that the technological equipment further includes:
First radial limited support component (100), faces the first surface of the magnetic yoke (41), pre- with the magnetic pole (43) interval Set a distance, to form first receiving space between the described first radial limited support component (100) and the first surface;
First flexible cavity component (200) is flexible encapsulated cavity, and setting is in the described first radial limited support component (100) On, and be located in the first receiving space;
First fluid medium supply system (600) is connected to the first flexible cavity component (200), is used for described first Flexible cavity component (200) supplies pressurized fluid media or pressurized, heated fluid media (medium), makes the first flexible cavity component (200) bonding agent being perfused in the vacuum bag (50) being covered on the magnetic pole (43) surface is squeezed.
5. technological equipment as claimed in claim 4, which is characterized in that the technological equipment further includes the second electromagnetic induction heating Unit (700) carries out electromagnetism to the magnetic pole (43) from internal rotor for being arranged in the rotor internal cavity of the rotor (40) Induction heating.
6. technological equipment as claimed in claim 5, which is characterized in that the second electromagnetic induction heating unit (700) includes Supportive body (701), supporting cantilever (702), electromagnetic induction heating cylinder (703) and induction heating power (704), the branch One end of support cantilever (702) is fixed on the supportive body (701), described in the other end support of the supporting cantilever (702) Electromagnetic induction heating cylinder (703), by the way that the electromagnetic induction heating cylinder (703) is placed on the described first radial limited support portion The radially inner side of part (100) to carry out electromagnetic induction heating to the magnetic pole (43).
7. technological equipment as claimed in claim 6, which is characterized in that the electromagnetic induction heating cylinder (703) is cylindrical shape, packet The second electromagnetic induction heating coil for including coil rack (7031) and being equably wrapped on the coil rack (7031) (7032), the technological equipment further includes laser centring device (907), for making the electromagnetic induction heating cylinder (703) and institute State that rotor (40) is axially aligned, so that the circumferential gap between the electromagnetic induction heating cylinder (703) and the rotor (40) is equal It is even consistent.
8. technological equipment as claimed in claim 7, which is characterized in that the technological equipment further includes range sensor (808), For detecting the gap between the electromagnetic induction heating cylinder (703) and the rotor, the range sensor (808) is at least It four, radially inner side evenly distributed in the circumferential direction in the described first radial limited support component (100) or is arranged in described The outside of electromagnetic induction heating cylinder (703).
9. technological equipment as claimed in claim 7, which is characterized in that the supporting cantilever (702) can be relative to the branch Support main body (701) horizontal extension and oscilaltion;
The laser centring device (907) includes laser emitter and laser pickoff, be separately mounted to the rotor (40) and On the electromagnetic induction heating cylinder (703).
10. technological equipment as claimed in claim 7, which is characterized in that the technological equipment further includes end thermal insulation board (805), the end thermal insulation board (805) has heat-insulated, sound insulation and electro-magnetic screen function, end thermal insulation board (805) setting In the end of the rotor (40), the rotor internal cavity of the rotor (40) is sealed.
11. technological equipment as claimed in claim 10, which is characterized in that the technological equipment further includes rotary drive unit (900), the rotary drive unit (900) connect with the rotor (40), and the rotor (40) is driven to rotate.
CN201820174303.9U 2018-01-31 2018-01-31 Technological equipment for magnetic pole protection coating curing molding Active CN208101106U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820174303.9U CN208101106U (en) 2018-01-31 2018-01-31 Technological equipment for magnetic pole protection coating curing molding

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820174303.9U CN208101106U (en) 2018-01-31 2018-01-31 Technological equipment for magnetic pole protection coating curing molding

Publications (1)

Publication Number Publication Date
CN208101106U true CN208101106U (en) 2018-11-16

Family

ID=64129507

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820174303.9U Active CN208101106U (en) 2018-01-31 2018-01-31 Technological equipment for magnetic pole protection coating curing molding

Country Status (1)

Country Link
CN (1) CN208101106U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110091524A (en) * 2018-01-31 2019-08-06 北京金风科创风电设备有限公司 Technological equipment for curing and molding magnetic pole protective coating
CN112737241A (en) * 2020-12-18 2021-04-30 浙江英洛华磁业有限公司 Method of manufacturing a rotor assembly

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110091524A (en) * 2018-01-31 2019-08-06 北京金风科创风电设备有限公司 Technological equipment for curing and molding magnetic pole protective coating
CN110091524B (en) * 2018-01-31 2024-08-23 北京金风科创风电设备有限公司 Process equipment for curing and forming magnetic pole protective coating
CN112737241A (en) * 2020-12-18 2021-04-30 浙江英洛华磁业有限公司 Method of manufacturing a rotor assembly

Similar Documents

Publication Publication Date Title
CN108011481B (en) Process equipment and method for curing and forming magnetic pole protective coating
CN208101106U (en) Technological equipment for magnetic pole protection coating curing molding
CN101365580B (en) Bulk resin infusion system apparatus and method
WO2018076959A1 (en) Process and process apparatus for forming protective coating on magnetic pole of permanent magnet motor
CN104260328B (en) A kind of Electromagnetic Heating solidifying and molding device and use it to prepare the method for filament wound composite body
CN109067119B (en) Process equipment and method for filling motor parts with liquid medium
CN108000906B (en) Process equipment and method for curing and forming magnetic pole protective coating
CN106426978A (en) Flexible molding process and molding system for magnetic pole protective layer
CA2731753A1 (en) Mould for manufacturing a composite part including at least one fibre reinforced matrix
CN102114710B (en) Method for preparing large-scale composite-material aerogenerator blade
CN103107662A (en) Heating device and method for bonding magnet yoke and magnet using the same
BR112020009494A2 (en) apparatus for making a composite component and method for making a composite component
CN110091524A (en) Technological equipment for curing and molding magnetic pole protective coating
US20130270729A1 (en) Resin flow control in vartm process
CN207077774U (en) A kind of 3D printing consumption material box with auxiliary discharging and moisture-proof function
CN103939682B (en) A kind of preparation method of the steel-plastics composite pipe at steel pipe inner wall rotational moulding outer wall composite glass fiber
CN112078096A (en) High-efficient environment-friendly plastics injection molding machine
US11732687B2 (en) Manufacturing of a wind turbine rotor blade
CN110907331A (en) Simulation device for one-dimensional heat seepage transfer of soil body and implementation method
CN101367267B (en) Composite metal component production, forming and bonding system
CN115940456A (en) Surface-mounted permanent magnet motor rotor permanent magnet fixing device and method
CN108501290B (en) A kind of prefabricated plate forming device of steel plastic compount
CN204773659U (en) Pultrude moulding equipment of solidifiable composite fiber board after pultrusion
CN213055693U (en) Quick injection structure of injection molding machine
CN219237469U (en) Automatic equipment of filling UV glue

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant