CN208092160U - A kind of starting spare transformer open phase detection system based on optical ct - Google Patents
A kind of starting spare transformer open phase detection system based on optical ct Download PDFInfo
- Publication number
- CN208092160U CN208092160U CN201820248557.0U CN201820248557U CN208092160U CN 208092160 U CN208092160 U CN 208092160U CN 201820248557 U CN201820248557 U CN 201820248557U CN 208092160 U CN208092160 U CN 208092160U
- Authority
- CN
- China
- Prior art keywords
- phase
- optical
- spare transformer
- testing device
- current
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The starting spare transformer open phase detection system based on optical ct that the utility model discloses a kind of, including optical ct and phase interruption testing device.The phase interruption testing device of the utility model accesses optical ct current signal, it calculates in real time and starts spare transformer high-pressure side three-phase current fundamental voltage amplitude, when any phase current is less than its no-load current, then it is judged to that open phase fault occurs, alarm signal is provided through delay and notifies operating personnel's timely processing, improves the operational reliability that power plant starts standby power system.
Description
Technical field
The utility model is related to the monitoring for protection fields that power plant starts spare transformer system, relate more specifically to generate electricity
Factory starts the detecting system of spare transformer system open phase fault.
Background technology
World nuclear runs Experience Feedback (SOER 2015-1Safety of the NAB National Association 0f Broadcasters (WANO) in 2015
Challenges from Open Phase Events) in refer to the disconnection faults of several nuclear power stations emphatically, and thus lead
The serious consequence of cause, it is desirable to cause to pay attention in the industry, make corresponding safe precaution measure.
Such as on January 30th, 2012, No. 2 units of human relations nuclear power station were visitd due on the porcelain insulating casing of 345kV switchyards by the U.S.
Lead is fallen, and causes to start the on high-tension side high resistance earthing fault of spare transformer, this failure causes two and starts spare change
Depressor C phase single-phase wire breaks.C phase decompressions cause starting spare transformer to produce unbalance voltage, and reactor protection system is correct
The imbalance for having differentiated 6.9kV busbar voltages, reactor shutdown.It also results in by the several of starting spare transformer SAT power supplies
Platform large-size machine is tripped due to phase current overcurrent, including essential service water pump, component cooling pump etc..8 points are about crossed
Clock, the abnormal instruction of voltage and on the spot report find that No. 2 starting spare transformers are smoldered, and master control room operator disconnects manually
The lead-in circuit breaker of the 4kV safety level busbares of dynamic spare transformer institute band, and then Emergency diesel is made to be supplied to 4kV safety level busbares
Electricity.The equipment fault that the event exposes switchyard causes disconnected phase, protection and automatic device not to be alarmed accordingly, not quilt in time
Operations staff has found, causes reactor shutdown occur and starts the accident of spare transformer damage.
There is also such as Bruce A1 units, No. 3 units of Forsmark, No. 2 units of Vandellos are several in the past
The open phase fault that severity differs all occurred between year, has caused a series of event, has seriously threatened the safety of nuclear power station
Operation.
Up to now, it yet there are no the open report for starting spare transformer high-pressure side open phase detection system Related product.For
This, the utility model proposes a kind of the starting spare transformer open phase detection system based on optical ct, Sensitive Detection idle condition
The on high-tension side open phase fault of lower starting spare transformer reminds operations staff's timely processing.
Utility model content
The purpose of this utility model is:To solve the spare change of starting to power plant zero load proposed in above application practice
The demand of depressor open phase fault Sensitive Detection devises a kind of starting spare transformer open phase detection system based on optical ct.
The technical solution of the utility model is:
A kind of starting spare transformer open phase detection system based on optical ct includes phase interruption testing device and is installed on
Play the standby on high-tension side optical ct of change;Wherein phase interruption testing device access optical ct current signal and breaker aided location;It is described
Phase interruption testing device includes analog acquisition unit AC_I, digital signal processing unit DSP, it is mono- into collecting unit BI, MON to open
Member, signal relay;
Optical ct acquisition starts spare transformer high-pressure side three-phase current, and current signal enters phase interruption testing device analog quantity
Collecting unit AC_I is then output to digital signal processing unit DSP;
Opening into collecting unit BI for intake signal access phase interruption testing device, is then output to digital signal processing unit
DSP;
Digital signal processing unit DSP is connected by internal bus with AC_I and BI units;
MON units are connected by internal bus with DSP unit and signal relay.
Further, the MON units by internal bus and LCD MODULE and debugging module, communication module, beat
Impression block, clock synchronization module are connected.
The beneficial effects of the utility model:It is to be detected by the way that optical ct is applied to starting spare transformer open phase fault,
Monitoring starts each phase current in spare transformer high-pressure side in real time, can differentiate the starting spare transformer in the case of no-load current is smaller
Open phase fault solves the difficulty that can not be reacted under idle condition and start spare transformer open phase fault.
Description of the drawings
Fig. 1 is a kind of starting spare transformer open phase detection system construction drawing based on optical ct.
Specific implementation mode
A kind of starting spare transformer open phase detection system based on optical ct, including phase interruption testing device and be installed on
The on high-tension side optical ct of dynamic spare transformer.Wherein optical ct parameter need according to start spare transformer rated voltage,
Electric current, in-site installation condition, starts spare transformer no-load current to determine at environment temperature.
The utility model starts spare transformer high-pressure side three-phase current amplitude by the application of optical ct, in real time monitoring,
It can differentiate the starting spare transformer open phase fault in the case of smaller no-load current, starting can not be reacted by solving under idle condition
The problem of spare transformer open phase fault.
Below in conjunction with attached drawing, the utility model is described in further detail:
As shown in Figure 1, a kind of starting spare transformer open phase detection system based on optical ct, including phase interruption testing device
The on high-tension side optical ct of spare transformer is started with being installed on.Wherein phase interruption testing device access optical ct current signal and open circuit
Device aided location when any phase current is less than its no-load current under grid-connected state, then is judged to that open phase fault occurs, through prolonging
When provide alarm signal.
The parameter of optical ct is needed according to the rated voltage of starting spare transformer, electric current, environment temperature, in-site installation item
Part starts spare transformer no-load current to determine.According to the statistics to multiple scenes, standby change high-pressure side no-load current range is played
In 0.2~0.5A ranges, then optical ct will ensure accurately measure in the range, could meet started under idle condition it is spare
The needs of transformer open phase detection.In order to provide the separate equal signals of open phase fault, the generally installation 3 of spare transformer high-pressure side is started
Group optical ct, detects A, B, C three-phase current respectively.
Phase interruption testing device operation principle is as follows:
Optical ct acquisition starts spare transformer high-pressure side three-phase current, and current signal enters phase interruption testing device analog quantity
Collecting unit AC_I is exported after shaping filter is handled and is given digital signal processing unit DSP;
Intake signal access phase interruption testing device is opened into collecting unit BI, and output is to number after light-coupled isolation is handled
Word signal processing unit DSP;
Digital signal processing unit DSP receives AC_I and BI element output signals by internal bus, carries out Fourier's meter
Calculation and logic judgment calculate and start spare transformer high-pressure side three-phase current amplitude, and provide circuit breaker position;
MON units receive the starting spare transformer three-phase current amplitude and open circuit that DSP unit provides by internal bus
Device aided location carries out logic decision;If meeting the phase decision condition of breaking, through the output contact that is delayed to signal relay and same
When light open-phase indicting lamp.
MON units connect LCD MODULE by internal bus, for showing starting on phase interruption testing device liquid crystal
Each phase current in spare transformer high-pressure side and other real-time status;
MON units are also connected with debugging module, the debugging for starting spare transformer open phase detection system;
MON units are also connected with communication module, print module, clock synchronization module, provide printing, clock synchronization and Communications service.
Claims (2)
1. a kind of starting spare transformer open phase detection system based on optical ct, it is characterised in that:It include open phase detection dress
Set and be installed on the standby on high-tension side optical ct of change;Wherein phase interruption testing device access optical ct current signal and breaker auxiliary
Position;The phase interruption testing device includes analog acquisition unit AC_I, digital signal processing unit DSP, opens into collecting unit
BI, MON unit, signal relay;
Optical ct acquisition starts spare transformer high-pressure side three-phase current, and current signal enters phase interruption testing device analog acquisition
Unit AC_I is then output to digital signal processing unit DSP;
Opening into collecting unit BI for intake signal access phase interruption testing device, is then output to digital signal processing unit DSP;
Digital signal processing unit DSP is connected by internal bus with AC_I and BI units;
MON units are connected by internal bus with DSP unit and signal relay.
2. a kind of starting spare transformer open phase detection system based on optical ct as described in claim 1, it is characterised in that:
The MON units pass through internal bus and LCD MODULE and debugging module, communication module, print module, clock synchronization module phase
Even.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820248557.0U CN208092160U (en) | 2018-02-11 | 2018-02-11 | A kind of starting spare transformer open phase detection system based on optical ct |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820248557.0U CN208092160U (en) | 2018-02-11 | 2018-02-11 | A kind of starting spare transformer open phase detection system based on optical ct |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208092160U true CN208092160U (en) | 2018-11-13 |
Family
ID=64064539
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820248557.0U Active CN208092160U (en) | 2018-02-11 | 2018-02-11 | A kind of starting spare transformer open phase detection system based on optical ct |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208092160U (en) |
-
2018
- 2018-02-11 CN CN201820248557.0U patent/CN208092160U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108169615B (en) | Optical CT-based phase failure detection method for starting standby transformer | |
CN203071571U (en) | Intelligent monitoring device for distributed boundary switches | |
CN110554234A (en) | Zero-sequence current loop inspection method for in-service switch cabinet | |
CN107884645A (en) | Based on voltage ratio compared with power capacitor method for monitoring operation states | |
CN101931172A (en) | Electric debugging method of dry-quenching power distribution system | |
CN114563670A (en) | On-line monitoring device and method for insulation of impact capacitor in generator outlet circuit breaker | |
CN106058893A (en) | High-voltage and high-capacity chain-type STATCOM device protection system | |
CN109932601A (en) | The method that the grid-connected circuit of star-like statodyne group is detected with anti-power transmission | |
CN105391033A (en) | Layered domain-partitioned anti-islanding protection method for large-scale wind power generation | |
CN108710040A (en) | Shunt capacitor is protected and monitoring integration method | |
CN208092160U (en) | A kind of starting spare transformer open phase detection system based on optical ct | |
CN202840494U (en) | Transformer high-voltage side backup protection and monitoring device for railway power substation | |
CN107732971A (en) | A kind of band bidirectional current protection distributed grid-connected access case | |
CN209329687U (en) | A kind of traction substation emergency protection system | |
CN207851205U (en) | Converter Station electricity consumption fault monitoring device | |
CN201450318U (en) | Automatic false ground preventive low-voltage power distribution device | |
CN109449898A (en) | Solve the method and system of load direct supply system generator unit stator Xuhanting oral solution failure | |
CN109683044A (en) | Power switchgear malfunction judgment method based on multi-source information | |
CN218958623U (en) | Power microcomputer monitoring fault disconnection device | |
CN216056316U (en) | Line microcomputer protection system | |
CN114123131B (en) | Function optimization's quick cut system | |
CN214409251U (en) | Grounding fault alarm device for low-voltage side of transformer for high-temperature gas cooled reactor high-voltage station | |
CN2397599Y (en) | Double system relay protector for distribution equipment | |
CN108183464A (en) | A kind of judgement system and method for generator start and stop protection automatic switching | |
CN215833580U (en) | Short circuit detection device for power system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |