CN208074091U - A kind of rope traction folder - Google Patents

A kind of rope traction folder Download PDF

Info

Publication number
CN208074091U
CN208074091U CN201820400722.XU CN201820400722U CN208074091U CN 208074091 U CN208074091 U CN 208074091U CN 201820400722 U CN201820400722 U CN 201820400722U CN 208074091 U CN208074091 U CN 208074091U
Authority
CN
China
Prior art keywords
fixture block
swing arm
hinge joint
rope traction
steel wire
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820400722.XU
Other languages
Chinese (zh)
Inventor
陈世通
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Wall Seal Machinery Co Ltd
Original Assignee
Guangzhou Wall Seal Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Wall Seal Machinery Co Ltd filed Critical Guangzhou Wall Seal Machinery Co Ltd
Priority to CN201820400722.XU priority Critical patent/CN208074091U/en
Application granted granted Critical
Publication of CN208074091U publication Critical patent/CN208074091U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of rope traction folders, including the first fixture block and the second fixture block positioned opposite, further include being mutually parallel and the two respectively first swing arm and second swing arm hinged with first fixture block and the second fixture block, four hinge joint lines in first fixture block, the second fixture block, the first swing arm and the second swing arm are parallelogram, and at least one be equipped with makes the first fixture block and the second fixture block elastic torsion part close to each other in four hinge joints;Further include that can fix the first swing arm and the second swing arm mutual alignment and adjustable tightening device, the second fixture block are connected with the interconnecting piece for connecting steel wire ropes.Rope traction folder provided by the utility model, it is easy to operate, clamping force can be kept after clamping steel wire rope, and steel wire rope is avoided to be slided on haulage clip, it is more preferable to the connective stability of steel wire rope.

Description

A kind of rope traction folder
Technical field
The utility model is related to ship carrier equipment fields more particularly to a kind of rope traction to press from both sides.
Background technology
In ship running, it is frequently encountered the case where loading and unloading goods or material supply, when tender is to ships conveying articles, The first connecting steel wire ropes between two ships are needed, cargo then could be allowed to hang on a steel cord and be moved to another ship from a ship On.However, currently, although the steel wire rope on two ships can be linked together using common haulage clip, operation is laborious, very It uses both hands and feet to needs, also, haulage clip is not firm enough to the fixation of steel wire rope, there are security risk, is susceptible to because skidding And the case where falling off.Therefore, it is necessary to design a kind of new rope traction folder.
Utility model content
The purpose of this utility model is to provide a kind of rope traction folder, easy to operate, can be protected after clamping steel wire rope Clamping force is held, steel wire rope is avoided to be slided on haulage clip, it is more preferable to the connective stability of steel wire rope.
To achieve the above object, the utility model provides a kind of rope traction folder, including the first fixture block positioned opposite With the second fixture block, further include be mutually parallel and the two respectively first swing arm hinged with first fixture block and the second fixture block and Second swing arm, four hinge joint lines in the first fixture block, the second fixture block, the first swing arm and the second swing arm are parallel four side Shape, at least one be equipped with makes the first fixture block and the second fixture block elastic torsion part close to each other in four hinge joints;Also wrap The first swing arm and the second swing arm mutual alignment can be fixed and adjustable tightening device, the second fixture block are connected with for connecting steel by including The interconnecting piece of cord.
The tightening device includes the operation portion and screw rod being connected as a further improvement of the utility model, described Screw rod is horizontally through first swing arm and is threadedly coupled with it, and screw rod is also horizontally through the strip-shaped hole that the second swing arm is equipped with, The length direction of the strip-shaped hole is identical as the extending direction of the second swing arm, and the second swing arm is equipped with the lock being fixed on screw rod Tight mechanism.
Include the handle being an integral structure with interconnecting piece as the further improvement of the utility model, described second For fixture block between the first fixture block and the handle, first swing arm and the second swing arm are hinged with handle, the second fixture block, Four hinge joint lines in hand, the first swing arm and the second swing arm are parallelogram.
As the further improvement of the utility model, the elastic torsion part setting is put in second fixture block and first At the hinge joint of arm, the second fixture block and the second swing arm.
As the further improvement of the utility model, the hinge joint of first fixture block and the first swing arm is first hinged The hinge joint of point, second fixture block and the first swing arm is the second hinge joint, the line of the first hinge joint and the second hinge joint and The angle of the line of second hinge joint and interconnecting piece is 90-180 °.
As the further improvement of the utility model, opposite side is set respectively on first fixture block and the second fixture block There are the first concave surface and the second concave surface of arc.
As the further improvement of the utility model, it is opposite that direction is equipped on first concave surface and the second concave surface Teeth portion.
Advantageous effect
Compared with prior art, the advantages of rope traction folder of the utility model, is:
1, interconnecting piece is used to fix the steel wire rope on a ship, then makes the first folder using elastic torsion part as driving force Block and the second fixture block are close to each other, to clamp the steel wire rope on another ship;And by tightening device can be quickly effortlessly The relative position for fixing the first swing arm and the second swing arm, so as to avoid the first fixture block and the second fixture block due to relatively moving The clamping force to the second steel wire rope is reduced, the sliding of the second steel wire rope is avoided or even is fallen off, makes rope traction folder to steel The connective stability of cord is more preferable;
2, tightening device includes the operation portion and screw rod being connected, and further includes the baffle ring and nut being sleeved on screw rod, passes through Rotary screw can allow baffle ring to drive the second swing arm closer or far from the first swing arm, and simple in structure easy to operate, maintenance is also square Just;
3, the first concave surface on the first fixture block and the second fixture block and the second concave surface are adapted with the second steel wire rope, increase it The second steel wire rope is further avoided in the first fixture block and second to increase frictional force with the contact surface between the second steel wire rope The case where being had skidded between fixture block, connective stability further increase;
4, the teeth portion on the first concave surface and the second concave surface can further increase the first fixture block and second the second steel wire of fixture block pair The frictional force of rope, connective stability further increase.
By description below and in conjunction with attached drawing, the utility model will become more fully apparent, these attached drawings are for explaining this The embodiment of utility model.
Description of the drawings
In order to illustrate the embodiment of the utility model or the technical proposal in the existing technology more clearly, below will be to embodiment Or attached drawing needed to be used in the description of the prior art is briefly described, it should be apparent that, the accompanying drawings in the following description is only It is some embodiments of the utility model, for those of ordinary skill in the art, in the premise not made the creative labor Under, other drawings may also be obtained based on these drawings.
Fig. 1 is the front view of rope traction folder;
Fig. 2 is the main view partial sectional view of rope traction folder;
Fig. 3 is the close-up schematic view of strip-shaped hole;
Fig. 4 is the rearview of rope traction folder;
Fig. 5 is the schematic diagram of the first concave surface and the second concave surface;
Fig. 6 is the use state partial sectional view of rope traction folder.
Specific implementation mode
The embodiments of the present invention are described referring now to the drawings.
Embodiment
Specific embodiment of the present utility model is as shown in Figures 1 to 5, a kind of rope traction folder, including positioned opposite The first fixture block 1 and the second fixture block 2.Further include be mutually parallel and the two respectively with first fixture block, 1 and second fixture block 2 cut with scissors The first swing arm 3 and the second swing arm 4 connect, four in the first fixture block 1, the second fixture block 2, the first swing arm 3 and the second swing arm 4 four Hinge joint line is parallelogram, and at least one be equipped with makes the first fixture block 1 and the second fixture block 2 mutually in four hinge joints Close elastic torsion part;Further include that can fix the first swing arm 3 and 4 mutual alignment of the second swing arm and adjustable tightening device 5, Second fixture block 2 is connected with the interconnecting piece 6 for connecting the first steel wire rope 8.In the present embodiment, interconnecting piece 6 is shackle structure.First 8 other end of steel wire rope is located therein on a ship.First fixture block 1 and the second fixture block 2 are used to clamp one end of the second steel wire rope 9, The other end of second steel wire rope 9 is located on another ship.
After driving the first fixture block 1 and the second fixture block 2 to clamp the second steel wire rope 9 using the elastic force of elastic torsion part, pass through Tightening device can fix the relative position of the first swing arm and the second swing arm, so as to avoid the first fixture block 1 and the second fixture block 2 because going out It now relatively moves and reduces the clamping force to the second steel wire rope 9, avoid the sliding of the second steel wire rope 9 or even fall off, make steel The connective stability of the second steel wire rope of cord haulage clip pair 9 is more preferable.
The hinge joint of first fixture block, 1 and first swing arm 3 is the first hinge joint, second fixture block, 2 and first swing arm 3 Hinge joint be the second hinge joint, the line of the line and the second hinge joint and interconnecting piece 6 of the first hinge joint and the second hinge joint Angle be 90-180 °.When the direction that both the first steel wire rope 8 and second steel wire ropes 9 are pullled is opposite, the first hinge joint with The line of second hinge joint and the second hinge joint and the angle of the line of interconnecting piece 6 just have the tendency that becoming larger, to allow the first folder Block 1 and the second fixture block 2 are to the clamping force bigger of the second steel wire rope 9, frictional force also bigger, the second steel wire rope 9 of more difficult appearance The case where skidding or falling off.
The tightening device 5 includes that the operation portion 51 being connected and screw rod 52, the screw rod 52 are horizontally through described first Swing arm 3 is simultaneously threadedly coupled with it, and screw rod 52 is also horizontally through the strip-shaped hole 41 that the second swing arm 4 is equipped with, the length of the strip-shaped hole 41 Degree direction is identical as the extending direction of the second swing arm 4, and the second swing arm 4 is equipped with the retaining mechanism being fixed on screw rod 52, The side far from the first swing arm 3 is equipped with the baffle ring 54 and nut 53 being set on screw rod 52 in second swing arm 4.In the present embodiment, Baffle ring 54 there are one being also arranged on screw rod 52 between the first swing arm 3 and the second swing arm 4.The outer diameter of baffle ring 54 is more than bar shaped The width in hole 41.The length of strip-shaped hole 41 is more than the diameter of screw rod 52, then just have can be along item for the screw rod 52 for being located in strip-shaped hole 41 The space of shape hole 41 length direction movement could allow the first swing arm 3 and the second swing arm 4 opposite first fixture block 1 and the second fixture block 2 It swings.
Include the handle 7 being an integral structure with interconnecting piece 6, second fixture block 2 is located at the first fixture block 1 and the handle Between 7, first swing arm, 3 and second swing arm 4 is hinged with handle 7, the second fixture block 2, handle 7, the first swing arm 3 and second pendulum Four hinge joint lines on arm 4 four are parallelogram.
The hinge in second fixture block, 2 and first swing arm 3, the second fixture block 2 and the second swing arm 4 is arranged in the elastic torsion part Junction.Elastic torsion part is torque spring, is equipped between the second fixture block 2 and the opposite side of the first swing arm 3 for accommodating The groove of torque spring is equipped between the second fixture block 2 and the opposite side of the second swing arm 4 for accommodating the recessed of torque spring Slot.
On first fixture block, 1 and second fixture block 2 opposite side be respectively equipped with arc the first concave surface 11 and second it is recessed Face 12.First concave surface 11 and the second concave surface 12 are adapted with the second steel wire rope 9, increase its contact between the second steel wire rope Face, to increase frictional force.
Above-mentioned each hinge joint is in such a way that compatible screw bolt and nut connects.
First concave surface is equipped with the opposite teeth portion in direction on 11 and second concave surface 12, can further increase the first fixture block With the frictional force of second the second steel wire rope of fixture block pair, connective stability further increases.
In above-described embodiment, interconnecting piece 6 can be arranged directly on the second fixture block 2, and elastic torsion part can be arranged at this time At the first fixture block 1 and the hinge joint of the first swing arm 3, the first fixture block 1 and the second swing arm 4.Elastic torsion part can also be only arranged Wherein on a hinge joint, because the first fixture block 1, the second fixture block 2, the first swing arm 3 and the second swing arm 4 are hinged two-by-two, four Linkage, even if only there are one being driven flexible torsion elements on hinge joint, but it wants the technique of elastic torsion part Seek higher.
The utility model is described above in association with most preferred embodiment, but the utility model is not limited to above take off The embodiment shown, and modification, equivalent combinations that various essence according to the present utility model carry out should be covered.

Claims (7)

1. a kind of rope traction folder, including the first fixture block (1) positioned opposite and the second fixture block (2), which is characterized in that also wrap It includes and is mutually parallel and the two respectively first swing arm (3) hinged with first fixture block (1) and the second fixture block (2) and the second pendulum Arm (4), four hinge joint lines in the first fixture block (1), the second fixture block (2), the first swing arm (3) and the second swing arm (4) four For parallelogram, at least one be equipped with keeps the first fixture block (1) and the second fixture block (2) close to each other in four hinge joints Elastic torsion part;Further include that can fix the first swing arm (3) and the second swing arm (4) mutual alignment and adjustable tightening device (5), the Two fixture blocks (2) are connected with the interconnecting piece (6) for connecting steel wire ropes.
2. a kind of rope traction folder according to claim 1, which is characterized in that the tightening device (5) includes being connected The operation portion (51) and screw rod (52) connect, the screw rod (52) are horizontally through first swing arm (3) and are threadedly coupled with it, spiral shell Bar (52) is also horizontally through the strip-shaped hole (41) that the second swing arm (4) is equipped with, the length direction of the strip-shaped hole (41) and the second pendulum The extending direction of arm (4) is identical, and the second swing arm (4) is equipped with the retaining mechanism being fixed on screw rod (52).
3. a kind of rope traction folder according to claim 1 or 2, which is characterized in that including being integrated with interconnecting piece (6) The handle (7) of formula structure, second fixture block (2) is between the first fixture block (1) and the handle (7), first swing arm (3) and the second swing arm (4) is hinged with handle (7), the second fixture block (2), handle (7), the first swing arm (3) and the second swing arm (4) Four hinge joint lines on four are parallelogram.
4. a kind of rope traction folder according to claim 3, which is characterized in that the elastic torsion part is arranged described Second fixture block (2) and the first swing arm (3), the second fixture block (2) at the hinge joint of the second swing arm (4).
5. a kind of rope traction folder according to claim 1, which is characterized in that first fixture block (1) and the first pendulum The hinge joint of arm (3) is the first hinge joint, and the hinge joint of second fixture block (2) and the first swing arm (3) is the second hinge joint, the The line and the second hinge joint of one hinge joint and the second hinge joint and the angle of the line of interconnecting piece (6) are 90-180 °.
6. a kind of rope traction folder according to claim 1, which is characterized in that first fixture block (1) and the second folder Opposite side is respectively equipped with the first concave surface (11) and the second concave surface (12) of arc on block (2).
7. a kind of rope traction folder according to claim 6, which is characterized in that first concave surface (11) and second recessed The opposite teeth portion in direction is respectively equipped on face (12).
CN201820400722.XU 2018-03-23 2018-03-23 A kind of rope traction folder Active CN208074091U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820400722.XU CN208074091U (en) 2018-03-23 2018-03-23 A kind of rope traction folder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820400722.XU CN208074091U (en) 2018-03-23 2018-03-23 A kind of rope traction folder

Publications (1)

Publication Number Publication Date
CN208074091U true CN208074091U (en) 2018-11-09

Family

ID=64046699

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820400722.XU Active CN208074091U (en) 2018-03-23 2018-03-23 A kind of rope traction folder

Country Status (1)

Country Link
CN (1) CN208074091U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110332281A (en) * 2019-06-19 2019-10-15 沪东中华造船(集团)有限公司 A kind of sea transverse replenishment frame rope fixture and frame rope device
CN112120776A (en) * 2020-08-27 2020-12-25 北京市春立正达医疗器械股份有限公司 Cable fixing and bundling device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110332281A (en) * 2019-06-19 2019-10-15 沪东中华造船(集团)有限公司 A kind of sea transverse replenishment frame rope fixture and frame rope device
CN112120776A (en) * 2020-08-27 2020-12-25 北京市春立正达医疗器械股份有限公司 Cable fixing and bundling device

Similar Documents

Publication Publication Date Title
CN208074091U (en) A kind of rope traction folder
US7448608B2 (en) Foldable frame for oscillating saws
US11045940B2 (en) Devices for the support of tools
US4146941A (en) Boat bow ladder assembly
CN102422337A (en) Suspension device
ATE382004T1 (en) LOAD RACK FOR TRANSPORTING A BICYCLE
SI1515885T1 (en) Movable platform unit for a boat, particularly for hauling and launching tenders and the like
US5740591A (en) Quick release locking strap
US11235828B2 (en) Bicycle luggage rack
DE20113742U1 (en) Cable routing for an industrial robot
US6132305A (en) Portable game animal hanger
US20120067931A1 (en) Apparatus for carrying a power tool
CN206691682U (en) Transport bundled device safely
DE502006005002D1 (en) KNICKMAS FOR A NITROGEN CONVEYOR SYSTEM
US4033532A (en) Power tool support
CN210710453U (en) Fixed crane
US6176479B1 (en) Clamping device
CN210608305U (en) Tension tower pulley suspension device
KR101213686B1 (en) A garment hanger for container.
CN205592504U (en) Biaxial ferrule device for unmanned aerial vehicle
CN204454233U (en) A kind of transmission shaft suspender
US6415480B1 (en) Clip mechanism for a line
US3061350A (en) Greenhouse flat carrier
US2444450A (en) Chain tool
CN210000172U (en) Special tool for replacing and adjusting dropper

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant