CN208073513U - A kind of tunnel lining trolley of included sprinkling curing system - Google Patents

A kind of tunnel lining trolley of included sprinkling curing system Download PDF

Info

Publication number
CN208073513U
CN208073513U CN201820489555.0U CN201820489555U CN208073513U CN 208073513 U CN208073513 U CN 208073513U CN 201820489555 U CN201820489555 U CN 201820489555U CN 208073513 U CN208073513 U CN 208073513U
Authority
CN
China
Prior art keywords
trolley
lining
water tank
spray
spray tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820489555.0U
Other languages
Chinese (zh)
Inventor
陈阳
谭磊
郭宏
孙茂
周亮
赵振兴
王坤华
陈宜保
蒲学斌
郝建波
朱永平
王建业
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Railway Group Co Ltd Traffic Engineering Branch
Traffic Engineering Branch of China Railway Sixth Group Co Ltd
Original Assignee
Railway Group Co Ltd Traffic Engineering Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Railway Group Co Ltd Traffic Engineering Branch filed Critical Railway Group Co Ltd Traffic Engineering Branch
Priority to CN201820489555.0U priority Critical patent/CN208073513U/en
Application granted granted Critical
Publication of CN208073513U publication Critical patent/CN208073513U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses a kind of tunnel lining trolley of included sprinkling curing system, it is fixedly connected with water tank on trolley, water inlet pipe is communicated to the top of water tank by water inlet switch;One end of booster pump is communicated to the lower part of water tank by outlet pipe, and spray tube is supported in the rear of trolley by being connected to the holder of trolley and is communicated to the other end of booster pump;The side towards tunnel vault is connected with multiple rotary nozzles on spray tube.The utility model realizes that the spray of lining cutting conserves by the spray tube set on trolley rear, while trolley carries out current station lining construction, spray tube positioned at trolley rear can carry out spray maintenance to the lining cutting of a upper station, to realize that the automatic spray to rigid form removal lining cutting conserves, the maintenance quality of lining concrete is improved;Automatic water supplement is realized by the floating-ball level switch in water tank, improves the degree of automation, reduces labor intensity.

Description

A kind of tunnel lining trolley of included sprinkling curing system
Technical field
The utility model is related to lining construction fields, and in particular to be served as a contrast to a kind of tunnel of included sprinkling curing system Platform building cart.
Background technology
It is shown according to related data, China's current tunnel lining cutting mainly uses formwork jumbo to carry out form concrete construction work Industry, it is less using shield duct piece splicing construction lining cutting application example.Lining concrete maintenance is the weight of lining construction 1-7 days after the completion of wanting process, lining cutting to pour are the concrete hydrating exothermic heat maximum stage, while being also the intensity of concrete Rising stage, in place whether to the generation of tunnel lining concrete intensity and crack, there are critical shadows for lining concrete maintenance It rings, and then influences the construction quality of tunnel-liner, be the very important component part of lining construction.
In terms of lining cutting maintenance construction scene, there are the following problems:(1) concrete pump is placed at lining trolley position, is passed System lining cutting maintenance trolley serves as a contrast position because delivery pump influence can not reach new form removal two.And in view of next mould two serves as a contrast splash guard paving It hangs and reinforcing bar binds the time, can not carry out lining concrete maintenance in the average 3 day time, concrete curing early period is caused to lack. (2) using manually being conserved, can not ensure to conserve the frequency and maintenance quality, regular to cause the maintenance frequency insufficient, maintenance is not In place, operating worker there are one and accounting for for a long time, increases lining construction cost.(3) because lining concrete maintenance is not in place, especially It is in the period after the completion of tunnel-liner pours demoulding, and generality generates lining concrete intensity deficiency and because of lining cutting aquation Heat causes Lining cracks greatly.(4) at initial stage after the completion of lining cutting pours, hydration heat of concrete is very big, causes in concrete construction region Temperature is excessively high, influences in-cavity construction operating environment, reduces the efficiency of operating personnel.
Utility model content
The utility model provides a kind of tunnel lining trolley of included sprinkling curing system, to realize lining construction with Lining cutting operates while maintenance, is conserved to the automatic spray of rigid form removal lining cutting, improves the maintenance quality of lining concrete.
In order to solve the above technical problems, technical solution used by the utility model is:
A kind of tunnel lining trolley of included sprinkling curing system is fixedly connected with water tank on trolley, and water inlet pipe passes through Water inlet switch is communicated to the top of water tank;One end of booster pump is communicated to the lower part of water tank by outlet pipe, and spray tube is logical It crosses and is connected to the holder of trolley and is supported in the rear of trolley and is communicated to the other end of booster pump;Towards tunnel vault on spray tube Side be connected with multiple rotary nozzles.
Water inlet switch change-over switch state can be triggered according to height of water level by being equipped with according to said program, in the water tank Floating-ball level switch.
Compared with prior art, the utility model has the beneficial effects that:Lining is realized by the spray tube set on trolley rear The spray of block conserves;While trolley carries out current station lining construction, the spray tube for being located at trolley rear can be to a upper work The lining cutting of position carries out spray maintenance, to realize that the automatic spray to rigid form removal lining cutting conserves, improves the maintenance of lining concrete Quality;Automatic water supplement is realized by the floating-ball level switch in water tank, improves the degree of automation, reduces labor intensity.
Description of the drawings
Fig. 1 is the structural schematic diagram of the utility model.
Specific implementation mode
Specific embodiment of the present utility model is described further below in conjunction with the accompanying drawings, the paraphrase of each label in figure For:1- spray tubes, 2- booster pumps, 3- outlet pipes, 4- floating-ball level switch, 5- water tanks, 6- water inlet switch, 7 water inlet pipes, 8- platforms Vehicle, 9- holders.
The utility model is mainly to ensure lining construction and lining cutting maintenance by installing spray tube 1 additional on trolley 8 It is carried out at the same time.Specifically, one volume of upper weld in trolley 8 is 1m3Water tank 5, water tank by 5mm thickness steel plate weld It connects.Water inlet pipe 7 is communicated to the top of water tank 5 by electromagnetism water inlet switch 6, and one end of booster pump 2 is connected by outlet pipe 7 The lower part of water tank 5 is led to, the other end of booster pump 2 is communicated to spray tube 1.Spray tube 1 is located at the rear of trolley and by connecting It is supported in the holder 9 of trolley 8.The side towards tunnel vault offers multiple through-holes on spray tube 1, connects in each through-hole It connects there are one rotary nozzle, rotary nozzle can will spray to lining cutting after the water atomization in spray tube 1.
It supplies water in use, being realized by the high-pressure water pipe for the diameter 125mm being connected to in tunnel and with water inlet pipe 7, The high-pressure water pipe is connected to water supply with the head-tank outside tunnel.After the completion of originally touching the construction of two linings, trolley 8 moves forward to next A station carries out lining construction, and can be served as a contrast to new form removal two positioned at the spray tube 1 at trolley rear and carry out automatic spray maintenance, from And it realizes operation while lining construction is conserved with lining cutting and the automatic spray of rigid form removal lining cutting is conserved.Booster pump 2 can be with Improve the hydraulic pressure in spray tube 1 so that the water mist sprayed by rotary nozzle more refines, and jet length is farther, and spray area is more Greatly.
To improve the automation efficiency of the utility model, floating-ball level switch 4 is set in water tank 5, and Floating Ball Liquid Level is opened The working condition of water inlet switch 6 can be triggered according to the height of water level in water tank 5 by closing 4:When moisture storage capacity is relatively low, trigger into Taps 6 are at opening state, to be 5 moisturizing of water tank;When moisture storage capacity is higher, triggering water inlet switch 6 makes at its In closed state, avoids filling into excessive water and cause to waste.

Claims (2)

1. a kind of tunnel lining trolley of included sprinkling curing system, it is characterised in that:Trolley is fixedly connected with water tank on (8) (5), water inlet pipe (7) is communicated to the top of water tank (5) by water inlet switch (6);One end of booster pump (2) passes through outlet pipe (3) it is communicated to the lower part of water tank (5), spray tube (1) is supported in the rear of trolley by being connected to the holder (9) of trolley (8) And it is communicated to the other end of booster pump (2);The side towards tunnel vault is connected with multiple rotary nozzles on spray tube (1).
2. a kind of tunnel lining trolley of included sprinkling curing system according to claim 1, it is characterised in that:The storage The floating-ball level switch (4) of water inlet switch (6) change-over switch state can be triggered according to height of water level by being equipped in water tank (5).
CN201820489555.0U 2018-04-08 2018-04-08 A kind of tunnel lining trolley of included sprinkling curing system Expired - Fee Related CN208073513U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820489555.0U CN208073513U (en) 2018-04-08 2018-04-08 A kind of tunnel lining trolley of included sprinkling curing system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820489555.0U CN208073513U (en) 2018-04-08 2018-04-08 A kind of tunnel lining trolley of included sprinkling curing system

Publications (1)

Publication Number Publication Date
CN208073513U true CN208073513U (en) 2018-11-09

Family

ID=64043735

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820489555.0U Expired - Fee Related CN208073513U (en) 2018-04-08 2018-04-08 A kind of tunnel lining trolley of included sprinkling curing system

Country Status (1)

Country Link
CN (1) CN208073513U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111002453A (en) * 2019-12-30 2020-04-14 成都银线电杆有限公司 Pole sprays curing means
CN115341925A (en) * 2022-09-01 2022-11-15 中铁五局集团第一工程有限责任公司 Concrete area mould sprays maintenance system based on two lining platform trucks in tunnel

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111002453A (en) * 2019-12-30 2020-04-14 成都银线电杆有限公司 Pole sprays curing means
CN115341925A (en) * 2022-09-01 2022-11-15 中铁五局集团第一工程有限责任公司 Concrete area mould sprays maintenance system based on two lining platform trucks in tunnel

Similar Documents

Publication Publication Date Title
CN203417793U (en) Multi-functional pneumatic airless coating or oil paint spraying machine
CN208073513U (en) A kind of tunnel lining trolley of included sprinkling curing system
CN208778004U (en) A kind of tunnel automatic spray maintenance trolley
CN210215183U (en) Water-saving spray curing device for concrete building structure
CN210343374U (en) Tunnel secondary lining concrete sprays curing means
CN206688976U (en) A kind of retracting device for glass showering
CN207844547U (en) A kind of stock yard heap material strip sprinkling dust-removing device
CN201133252Y (en) Wet concrete jetting apparatus
CN216515024U (en) Concrete curing means that highway engineering construction was used
CN206438737U (en) A kind of high-effective water-proof material elevation construction spraying equipment
CN205190995U (en) PCCP steel wire tube core cement paste spraying device
CN201520976U (en) Auto-traveling multifunctional wet spraying machine
CN201669782U (en) Concrete automatic drip irrigation and maintenance device
CN209633450U (en) A kind of concrete mixing plant
CN104060805A (en) Overpressure automatic return device for mortar spraying distribution systems
CN203878515U (en) Novel electric water collecting sprinkler
CN208934418U (en) Pump concrete discharge port anti-throw device
CN204638410U (en) A kind of coating jeting device
CN108301844B (en) Tunnel is with spraying maintenance support
CN203266934U (en) Comprehensive main building platform washing device and concrete mixing plant
CN208885309U (en) A kind of inverted arch casting concrete product word trunk-type guiding device
CN219848750U (en) A dust device for hydraulic and hydroelectric engineering construction
CN214104314U (en) Cleaning and watering device for building service
CN211116024U (en) A concrete maintenance platform truck for circular tunnel
CN209097424U (en) A kind of poor resin storage tank

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181109

Termination date: 20190408

CF01 Termination of patent right due to non-payment of annual fee