CN208059166U - A kind of constant pressure arrangement for air conditioner water circulating system - Google Patents
A kind of constant pressure arrangement for air conditioner water circulating system Download PDFInfo
- Publication number
- CN208059166U CN208059166U CN201820280063.0U CN201820280063U CN208059166U CN 208059166 U CN208059166 U CN 208059166U CN 201820280063 U CN201820280063 U CN 201820280063U CN 208059166 U CN208059166 U CN 208059166U
- Authority
- CN
- China
- Prior art keywords
- water
- pressure
- constant pressure
- valve
- tank
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The purpose of the utility model is just to provide a kind of constant pressure arrangement for air conditioner water circulating system, it is improved in the existing closed water circulation system of refrigeration unit cold water, by improving the pressure of refrigeration unit cold water water outlet to constant pressure water compensation apparatus is increased on cold-water return pipeline to hydraulic pressure is increased on water return pipeline, and then the working efficiency of water outlet pump is promoted, reach the ability of long-range conveying cold water;The utility model structure novel is unique, it is easy to install and use, it can effectively solve to be pressurized moisturizing in refrigeration unit cold water closed-cycle system, the pressure of water outlet pump is improved by pressurizeing to water return pipeline, the pipeline pressure for increasing water outlet, enables cold water to transmit purpose at a distance, safe and reliable, the level pressure supply that can be widely used for various pipeline liquid injecting devices, there is significant economic and social benefit.
Description
Technical field
The utility model is related to air-conditioning equipments, especially a kind of constant pressure arrangement for air conditioner water circulating system.
Background technology
In pharmaceutical production, it is matter of frequent occurrence to carry out air-conditioning to workshop, especially in hot summer or hot car
Between, air-conditioning is even more essential, but since the area of plant area is big and the distance between each workshop and handpiece Water Chilling Units are remote, passes through
The cold water of refrigeration unit effectively can not be sent to each workshop by the force (forcing) pump of handpiece Water Chilling Units itself, influence the system in each workshop
Cold effect, workshop temperature drop, which is not got off, indirectly affects product quality and work task efficiency.Therefore, how to original
The closed loop system of refrigeration unit cold water be improved and innovation be those skilled in the art wish always solve the technical issues of.
Utility model content
For the above situation, to overcome the deficiency of the prior art, the purpose of the utility model to be just to provide one kind for sky
The constant pressure arrangement of the water transfer circulatory system can effectively solve to increase constant pressure supply water in original closed loop system of refrigeration unit cold water
Device improves the pressure of water outlet pump by pressurizeing to water return pipeline, increases the pipeline pressure of water outlet, realizes that cold water can
Transmission purpose at a distance.
The technical solution that the utility model solves is a kind of constant pressure arrangement for air conditioner water circulating system, existing
It is improved in the closed water circulation system of refrigeration unit cold water, by being given back to increase constant pressure water compensation apparatus on cold-water return pipeline
Increase hydraulic pressure in water lines to improve the pressure of refrigeration unit cold water water outlet, and then promote the working efficiency of water outlet pump, reaches
To the ability of long-range conveying cold water;Accordingly, the technical solution of the utility model is, including switch board, solenoid valve, pressure sensor
And water pump, the first water return pipeline of workshop, the second water return pipeline are connected with water-storage pressure tank, water-storage pressure tank is through cold-water return pipe
Road is connected with refrigeration unit, and cold-water return pipeline is connected through first pipe with constant pressure supply water tank, from water storage pressure in first pipe
Power tank side rises and is sequentially arranged with the first valve, the 4th valve, first pressure sensor and the first solenoid valve, and water-storage pressure tank is through second
Pipeline is connected with constant pressure supply water tank, equipped with the first water pump and the second water pump in parallel communicated, the first solenoid valve on second pipe
The water supply pipe being connected is housed on the pipeline section being connected with constant pressure supply water tank, second solenoid valve is housed on water supply pipe,
Blow-off line is housed on constant pressure supply water tank, third solenoid valve is housed on blow-off line, between third solenoid valve and constant pressure supply water tank
Blow-off line pipeline section on be equipped with second pressure sensor, switch board through conducting wire respectively with the first solenoid valve, second solenoid valve,
Third solenoid valve, first pressure sensor, second pressure sensor, the first water pump, the second water pump are connected, and constitute constant pressure arrangement work
Make control structure.
The utility model structure novel is unique, easy to install and use, can effectively solve refrigeration unit cold water sealing and circulating system
It is pressurized moisturizing in system, improves the pressure of water outlet pump by pressurizeing to water return pipeline, increases the pipeline pressure of water outlet, make cold
Water can transmit purpose at a distance, safe and reliable, can be widely used for the level pressure supply of various pipeline liquid injecting devices, have significant
Economic and social benefit.
Description of the drawings
Fig. 1 is the structural front view of the utility model.
Specific implementation mode
It elaborates to specific embodiment of the present utility model below in conjunction with attached drawing.
As shown in Figure 1, a kind of constant pressure arrangement for air conditioner water circulating system of the utility model, including switch board 5, electromagnetism
Valve, pressure sensor and water pump, workshop the first water return pipeline 1, the second water return pipeline 2 are connected with water-storage pressure tank 4, water storage pressure
Power tank 4 is connected through cold-water return pipeline 3 with refrigeration unit, and cold-water return pipeline 3 is through first pipe 16 and 13 phase of constant pressure supply water tank
It is connected to, the first valve 19-1, the 4th valve 19-4, first pressure is sequentially arranged with from 4 side of water-storage pressure tank in first pipe 16
Sensor 7 and the first solenoid valve 8, water-storage pressure tank 4 is connected through second pipe 15 with constant pressure supply water tank 13, on second pipe 15
Equipped with the first water pump 10 and the second water pump 11 that parallel connection communicates, on the pipeline section that the first solenoid valve 8 is connected with constant pressure supply water tank 13
Equipped with the water supply pipe 6 being connected, second solenoid valve 9 is housed on water supply pipe 6, discharge tube is housed on constant pressure supply water tank 13
Road 17 is equipped with third solenoid valve 12, the blow-off line 17 between third solenoid valve 12 and constant pressure supply water tank 13 on blow-off line 17
Pipeline section on second pressure sensor 14 is housed, switch board 5 through conducting wire 18 respectively with the first solenoid valve 8, second solenoid valve 9, the
Three solenoid valves 12, first pressure sensor 7, second pressure sensor 14, the first water pump 10, the second water pump 11 are connected, and it is fixed to constitute
Pressure device job control structure.
In order to ensure using effect and easy to use,
The switch board 5 is PLC control cabinet(Commercial product).
First water return pipeline 1 is equipped with third valve 19-3, and second valve 19-2 is housed on the second water return pipeline 2,
5th valve 19-5 is housed on water supply pipe 6.
The lower part of the water-storage pressure tank 4 is equipped with the first delivery pipe 20 with valve, and the lower part of constant pressure supply water tank 13 is equipped with
The second delivery pipe 21 with valve.
From the above, it is seen that the utility model conveys the situation of cold water capacity deficiency according to existing refrigeration unit,
It is improved in the existing closed water circulation system of refrigeration unit cold water, increases constant pressure supply water dress by giving on cold-water return pipeline
It sets and improves the pressure of refrigeration unit cold water water outlet to hydraulic pressure is increased on water return pipeline, and then promote the work effect of water outlet pump
Rate reaches the ability of long-range conveying cold water.
The present apparatus is mainly by switch board, solenoid valve, pressure sensor and water pump, the compositions such as constant pressure supply water fills;It is to pass through pressure
Pressure feedback on cold-water return pipeline to switch board, is controlled whether to give cold-water return pipeline by force snesor by switch board
Pressurization, meanwhile, cold-water return pipeline pressure is excessive and damage pipeline in order to prevent, has installed an electricity additional on cold-water return pipeline
For magnet valve when cold-water return pipeline pressure is excessive, switch board starts solenoid valve by the water sluice way constant pressure supply water of cold-water return pipeline
In filling.Constant pressure supply water filling also has resistance to pressure request, therefore, fills lower end in constant pressure supply water and has installed a pressure sensor and electromagnetism additional
The pressure value of valve, the pressure sensor feedback filled by constant pressure supply water controls whether that starting constant pressure supply water fills by switch board
Solenoid valve to fill pressure release to constant pressure supply water.
Specific works situation is that after refrigeration unit unlatching, have certain pressure on cold-water return pipeline, this pressure value
Switch board is fed back to by first pressure sensor, when the setting value of switch board is less than the pressure that first pressure sensor is fed back to
When value, the first water pump is started by switch board and fills progress constant pressure supply water to water-storage pressure, until the hydraulic pressure pressure value in first pipe
After reaching setting value, the first water pump is stopped, during this period, if the water storage that constant pressure supply water fills is not enough to cold water constant pressure supply water
When, the pressure value that constant pressure supply water fills is fed back to by switch board by second pressure sensor, at this moment switch board can start tap water
Second solenoid valve on pipeline gives constant pressure supply water to fill and carries out moisturizing, ensures the pressure on cold-water return pipeline with this;Work as control
When the setting value of cabinet is more than the pressure value of first pressure sensor feedback, switch board will start the first solenoid valve by cold-water return
Water in pipeline is discharged in constant pressure supply water filling, after the hydraulic pressure pressure value in first pipe reaches setting value, closes the first electricity
Magnet valve, during this period, if the water storage that fills of constant pressure supply water is excessive, the pressure that is filled constant pressure supply water by second pressure sensor
Value feeds back to switch board, and at this moment switch board can start third solenoid valve, is filled to constant pressure supply water and carries out pressure release through blow-off line, until
After hydraulic pressure pressure value in first pipe reaches setting value, the first solenoid valve and third solenoid valve are closed;First is used when moisturizing
Water pump and the second water pump, the first water pump make feed pump, and the second water pump makees reserve pump, when feed pump damages, pass through switch board
Quickly start the second pump, to ensure effective use of the utility model.
In short, the utility model novel and unique simple in structure, use easy to install, work efficiency is high, securely and reliably, can be to existing
There is refrigeration unit to be transformed, improves the pressure of water outlet pump by pressurizeing to water return pipeline, increase the pipeline pressure of water outlet
Power enables cold water to transmit purpose at a distance, can be widely used for the level pressure supply of various pipeline liquid injecting devices, wide application is pair
Innovation on existing air conditioner water circulating system, economic and social benefit are notable.
Claims (4)
1. a kind of constant pressure arrangement for air conditioner water circulating system, including switch board(5), solenoid valve, pressure sensor and water pump,
It is characterized in that:The first water return pipeline of workshop(1), the second water return pipeline(2)With water-storage pressure tank(4)It is connected, water-storage pressure tank
(4)Through cold-water return pipeline(3)It is connected with refrigeration unit, cold-water return pipeline(3)Through first pipe(16)With constant pressure supply water tank
(13)It is connected, first pipe(16)On from water-storage pressure tank(4)It rises and is sequentially arranged with the first valve in side(19-1), the 4th valve
(19-4), first pressure sensor(7)With the first solenoid valve(8), water-storage pressure tank(4)Through second pipe(15)With constant pressure supply water
Tank(13)It is connected, second pipe(15)Upper the first water pump communicated equipped with parallel connection(10)With the second water pump(11), the first electromagnetism
Valve(8)With constant pressure supply water tank(13)Equipped with the water supply pipe being connected on the pipeline section being connected(6), water supply pipe(6)On
Equipped with second solenoid valve(9), constant pressure supply water tank(13)It is upper that blow-off line is housed(17), blow-off line(17)It is upper that third electromagnetism is housed
Valve(12), third solenoid valve(12)With constant pressure supply water tank(13)Between blow-off line(17)Pipeline section on equipped with second pressure pass
Sensor(14), switch board(5)Through conducting wire(18)Respectively with the first solenoid valve(8), second solenoid valve(9), third solenoid valve(12),
First pressure sensor(7), second pressure sensor(14), the first water pump(10), the second water pump(11)It is connected, constitutes level pressure dress
Set job control structure.
2. the constant pressure arrangement according to claim 1 for air conditioner water circulating system, it is characterized in that:The switch board
(5)For PLC control cabinet.
3. the constant pressure arrangement according to claim 1 for air conditioner water circulating system, it is characterized in that:First return water
Pipeline(1)Equipped with third valve(19-3), the second water return pipeline(2)It is upper that second valve is housed(19-2), water supply pipe(6)On
Equipped with the 5th valve(19-5).
4. the constant pressure arrangement according to claim 1 for air conditioner water circulating system, it is characterized in that:The water-storage pressure tank
(4)Lower part be equipped with the first delivery pipe with valve(20), constant pressure supply water tank(13)Lower part equipped with valve second discharge
Pipe(21).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820280063.0U CN208059166U (en) | 2018-02-28 | 2018-02-28 | A kind of constant pressure arrangement for air conditioner water circulating system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820280063.0U CN208059166U (en) | 2018-02-28 | 2018-02-28 | A kind of constant pressure arrangement for air conditioner water circulating system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208059166U true CN208059166U (en) | 2018-11-06 |
Family
ID=63991380
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820280063.0U Active CN208059166U (en) | 2018-02-28 | 2018-02-28 | A kind of constant pressure arrangement for air conditioner water circulating system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208059166U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110567201A (en) * | 2019-09-06 | 2019-12-13 | 天津大学 | Hydraulic module device for movable indirect refrigeration system |
CN112197374A (en) * | 2020-09-03 | 2021-01-08 | 刘赛龙 | Air conditioner water charging system with low-level water charging tank |
-
2018
- 2018-02-28 CN CN201820280063.0U patent/CN208059166U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110567201A (en) * | 2019-09-06 | 2019-12-13 | 天津大学 | Hydraulic module device for movable indirect refrigeration system |
CN112197374A (en) * | 2020-09-03 | 2021-01-08 | 刘赛龙 | Air conditioner water charging system with low-level water charging tank |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208059166U (en) | A kind of constant pressure arrangement for air conditioner water circulating system | |
CN201919613U (en) | Minerals machine | |
CN103398011B (en) | Waste heat | |
CN207568956U (en) | Deflect the hydraulic system of pulse test bench | |
CN202913028U (en) | Water quenching control device for steel pipe | |
CN208454913U (en) | A kind of automatic water supplement heat preservation water system for grease production line | |
CN101885548B (en) | Low-temperature multi-effect seawater desalting inter-regenerative multi-stage spraying water supply system for raw material | |
CN201724389U (en) | Heat pump water heater | |
CN204239195U (en) | Mine residual heat of air compressor reutilization system | |
CN102322414A (en) | The air compressor unit that the cold and hot amount HQ high quality of a kind of inter-stage reclaims and stores | |
CN202228310U (en) | Air compressor set for recycling and storing interstage cooling heat | |
CN204973921U (en) | Pre -polymerization reation kettle sprays EG circulation supply control device | |
CN205475413U (en) | Anhydrous energy -saving water supply equipment of frequency conversion control that water factory was suitable for | |
CN205261923U (en) | Air can positive displacement hot -water heating system | |
CN202952416U (en) | Conduction oil heat supplying system of open mill | |
CN203716221U (en) | Network pressure-superposition cold and hot water domestic water supply system | |
CN206376865U (en) | A kind of built-in cooling back installation of continuous miner | |
CN206128170U (en) | Online intelligent water supply installation | |
CN206607635U (en) | A kind of farm's water system | |
CN111256360A (en) | Water storage type water heater capable of fully utilizing hot water | |
CN203980426U (en) | antifreeze boiler | |
CN106197068B (en) | A kind of Multistage wastewater recycling hot water supply system | |
CN203940640U (en) | House solar water heating system | |
CN204943934U (en) | The solar water heater that open type thermal-arrest enclosed supplies water | |
CN204720523U (en) | A kind of refrigerating device of accumulator |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP02 | Change in the address of a patent holder |
Address after: 465550 No. 666 General Road, Xinxian County, Xinyang City, Henan Province Patentee after: Henan Lingrui Pharmaceutical Co., Ltd. Address before: 465550 No. 232 Xiangyang Road, Xinxian County, Xinyang City, Henan Province Patentee before: Henan Lingrui Pharmaceutical Co., Ltd. |
|
CP02 | Change in the address of a patent holder |