CN208039708U - A kind of revetment board mounting structure without pre-leveling - Google Patents

A kind of revetment board mounting structure without pre-leveling Download PDF

Info

Publication number
CN208039708U
CN208039708U CN201721757389.XU CN201721757389U CN208039708U CN 208039708 U CN208039708 U CN 208039708U CN 201721757389 U CN201721757389 U CN 201721757389U CN 208039708 U CN208039708 U CN 208039708U
Authority
CN
China
Prior art keywords
adjustment
leveling
mounting structure
installing matrix
board mounting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721757389.XU
Other languages
Chinese (zh)
Inventor
余文明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuzhou Kai Chen Sunshine Building Materials Co Ltd
Original Assignee
Fuzhou Kai Chen Sunshine Building Materials Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuzhou Kai Chen Sunshine Building Materials Co Ltd filed Critical Fuzhou Kai Chen Sunshine Building Materials Co Ltd
Priority to CN201721757389.XU priority Critical patent/CN208039708U/en
Application granted granted Critical
Publication of CN208039708U publication Critical patent/CN208039708U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A kind of revetment board mounting structure without pre-leveling, including installing matrix, mounting plate, multiple adjustment channels, if multiple insertion columns on a mounting board, the oil pocket with hydraulic oil is provided in installing matrix, it is provided with multiple multiple squeezing passage groups for prolonging its axial directional distribution around each adjustment channel, each squeezing passage group includes annularly being arranged being connected to oil pocket and adjust multiple radial compression channels in channel, extrusion ball is provided in squeezing passage, the connecting rod connected with extrusion ball, and connecting rod connection to the push plate for squeezing hydraulic oil in oil pocket and the fixed postive stop baffle between push plate and extrusion ball being located on squeezing passage inner wall, pump nozzle and oil extraction mouth are additionally provided in installing matrix.The utility model is levelling without being carried out to wall before installing skirting, can be directly realized by the leveling to skirting during the installation process, and conveniently leveling, leveling is efficient, and the mounting structure bonding strength is big, easy for installation, repeats and utilizes, and service life is long.

Description

A kind of revetment board mounting structure without pre-leveling
Technical field
The utility model is related to skirting field, more specifically to a kind of skirting without pre-leveling installs knot Structure.
Background technology
Skirting is the object of indoor important decoration, and the flatness of metope can generate the installation effect of skirting great It influences, so, it must be levelling to wall progress in advance before skirting is installed, foamed glue is beaten to the wall of out-of-flatness, then will Batten is fixed on the wall, and is then fixed basal plate and batten by air gun, is finally stained with lamina rara externa, the above-mentioned levelling time Long, the size of batten is also different, applies man-hour requirement and is adjusted as the case may be so that construction drawing is with engineering drawing before It is often inconsistent, the construction time is extended, cost of labor is increased.
Also the patent application No. is CN201720311934.6 discloses a kind of mounting structure and skirting of skirting The mounting structure of structure, skirting includes:Several leveling components, are fixed on metope to be fitted up, several leveling component shapes At multirow leveling component;Multiple keel, each keel are horizontally extending and vertically removable with a line leveling component It connects with unloading, keel are connect with revetment plate body, and it is levelling so that skirting to treat finishing metope progress by adjusting leveling component The flush with outer surface of main body.Mounting structure in the patent equally need to carry out in advance before skirting is installed it is levelling, and Repeatedly being adjusted by leveling component could realize levelling, install skirting again after the leveling, influence construction efficiency.
Utility model content
In view of the deficiencies of the prior art, the utility model provides a kind of revetment board mounting structure without pre-leveling, It is levelling without being carried out to wall before skirting is installed, it can be directly realized by the leveling to skirting during the installation process, install Efficient and conveniently leveling, leveling is efficient, and the mounting structure bonding strength is big, easy for installation, repeats and utilizes, and uses Long lifespan.
The specific technical solution of the utility model is as follows:A kind of revetment board mounting structure without pre-leveling, including installation In the installing matrix on wall, the mounting plate for installing skirting, it is opened in dividing in multiple rows of multiple row in the installing matrix Cloth and cylindrical multiple adjustment channels, be located on the mounting plate it is more in the corresponding adjustment channel to be inserted into A insertion column is provided with the oil pocket with hydraulic oil in the installing matrix, is provided with around each adjustment channel more A multiple squeezing passage groups for prolonging its axial directional distribution, each squeezing passage group include annularly being arranged being connected to Multiple radial compression channels of the oil pocket and the adjustment channel are provided with extrusion ball in the squeezing passage and described squeeze The connecting rod of pressure ball connection connect with the connecting rod to squeeze hydraulic oil in the oil pocket push plate and it is fixed be located at described in The postive stop baffle between the push plate and the extrusion ball on squeezing passage inner wall is additionally provided in the installing matrix Pump nozzle and oil extraction mouth.
In the present embodiment, first installing matrix is mounted on wall, then on a mounting board by skirting installation, then will It is inserted into the corresponding adjustment channel of column alignment to be inserted into, with being deeply inserted into, the extrusion ball in all squeezing passages is completed jointly to inserting Enter the fixation of column, it is easy for installation.When wall not usually, that is, there is when vertical missing for installing matrix, it is only necessary to keep inserting Enter column and be horizontally inserted into the level fixation that can be achieved with all extrusion balls to being inserted into column, that is to say, that the nothing before installing skirting Need to be levelling to wall progress, it can be directly realized by the leveling to skirting during the installation process, and conveniently leveling, leveling is efficient, In whole installation process, installation effectiveness is high, at this point, adjustment channel and insertion column are at certain angle of inclination.In addition, passing through oil extraction The operations such as the draining the oil of mouth, the oiling of pump nozzle, can be achieved with the dismounting of skirting, realize the repetition profit of the revetment board mounting structure With the revetment board mounting structure installs skirting by the insertion column of multiple rows of multiple row, and structural strength is big, and service life is long.
Preferably, a diameter of be inserted into column diameter 1.1-1.4 times in the adjustment channel.
When installing matrix is there are when vertical missing, and completes the leveling to skirting, in this condition, it is inserted into column Its corresponding adjustment channel is to adjust the diameter in channel at an angle to must be greater than being inserted into column diameter, and adjustment is logical The diameter in road is set as being inserted into 1.1-1.4 times of column diameter being more reliable.
Preferably, the insertion entrance in the adjustment channel is set as taper.Expand the insertion entrance in adjustment channel, further Facilitate leveling.
Preferably, the bottom of the installing matrix is provided with to adjust the verticality adjustment of the installing matrix verticality Mechanism.When the vertical missing of installing matrix is larger, the verticality of installing matrix can be suitably adjusted by verticality adjustment mechanism, It is fixed to the level for being inserted into column to ensure that the extrusion ball in squeezing passage can be completed.
Preferably, the verticality adjustment mechanism includes bottom plate, multiple the first adjustment screw rods for being located on the bottom plate, sets The multiple second adjustment screw rods being located at right over the corresponding the first adjustment screw rod in the installing matrix bottom, described first Adjustment screw with its corresponding to second adjustment screw rod by connect swivel nut connection.
Preferably, the verticality adjustment mechanism includes multiple being connected with the installing matrix bottom and has sliding cavity Sliding column sleeve, the base platform that is connected with the bottom of all slide posts of the slide post that is located in each sliding cavity, Each sliding cavity is communicated with the oil pocket.The verticality adjustment mechanism adaptive can be adjusted, and regulated efficiency is high.
In conclusion the utility model has the advantages that:
It is levelling without being carried out to wall before skirting is installed, it can be directly realized by the tune to skirting during the installation process Flat and conveniently leveling, leveling is efficient, and installation effectiveness is high, and the mounting structure bonding strength is big, easy for installation, repeats profit With service life is long.
Description of the drawings
Fig. 1 is the structure schematic diagram of the utility model-embodiment;
Fig. 2 is the close-up schematic view at A in Fig. 1;
Fig. 3 is the implementation schematic diagram of verticality adjustment mechanism;
Fig. 4 is another embodiment schematic diagram of verticality adjustment mechanism.
Specific implementation mode
Below in conjunction with attached drawing, by specific embodiment, the utility model is described in further detail.
As shown in Figs. 1-2, a kind of revetment board mounting structure without pre-leveling, which is characterized in that including being installed on wall On installing matrix 1, the mounting plate 2 for installing skirting, be opened in the installing matrix 1 in multiple rows of multiple row distribution And cylindrical multiple adjustment channels 3, be located on the mounting plate 2 it is more in the corresponding adjustment channel 3 to be inserted into A insertion column 4 is provided with the oil pocket 5 with hydraulic oil in the installing matrix 1, is arranged around each adjustment channel 3 There are multiple multiple squeezing passage groups 6 for prolonging its axial directional distribution, each squeezing passage group 6 includes the use being annularly arranged To be connected to multiple radial compression channels 61 of the oil pocket 5 and the adjustment channel 3, extruding is provided in the squeezing passage 61 The connecting rod 63 and the connecting rod 63 that ball 62 and the extrusion ball 62 connect connect squeezing hydraulic oil in the oil pocket 5 Push plate 64 and the fixed limit between the push plate 64 and the extrusion ball 62 being located on 61 inner wall of the squeezing passage Position baffle 65, is additionally provided with pump nozzle 67 and oil extraction mouth 66, the position root of pump nozzle 67 and oil extraction mouth 66 in the installing matrix 1 Depending on actual conditions, it is not specifically limited herein.In the present embodiment, the quantity in channel 3 is adjusted depending on actual conditions.This In embodiment, first installing matrix is mounted on wall, then on a mounting board by skirting installation, then will be inserted into column alignment Corresponding adjustment channel is inserted into, and with being deeply inserted into, the extrusion ball in all squeezing passages completes the fixation to being inserted into column jointly, It is easy for installation.When wall not usually, that is, there is when vertical missing for installing matrix, it is only necessary to keep being inserted into column and is horizontally inserted into It is fixed to the level for being inserted into column to can be achieved with all extrusion balls, that is to say, that without being carried out to wall before installing skirting It is levelling, it can be directly realized by the leveling to skirting during the installation process, and conveniently leveling, leveling is efficient, in this condition, It adjusts channel and is inserted into column into certain angle of inclination.In addition, by operations such as the draining the oil of oil extraction mouth, the oilings of pump nozzle, just The recycling of the revetment board mounting structure is realized in the dismounting that can realize skirting, which passes through multiple rows of more The insertion column of row installs skirting, and structural strength is big, and service life is long.
Preferably, a diameter of be inserted into 4 diameter of column 1.1-1.4 times in the adjustment channel 3.It is excellent in the present embodiment Select 1.2 times.
Preferably, the insertion entrance in the adjustment channel 3 is set as taper.
Preferably, the bottom of the installing matrix 1 is provided with to adjust the verticality tune of 1 verticality of the installing matrix Complete machine structure 7.
As shown in Figure 3, it is preferred that the verticality adjustment mechanism 7 include bottom plate 71, be located at it is multiple on the bottom plate 71 The first adjustment screw rod 72 is located at the multiple right over the corresponding the first adjustment screw rod 72 of 1 bottom of the installing matrix Second adjustment screw rod 73, the first adjustment screw rod 72 with its corresponding to second adjustment screw rod 73 by connect swivel nut 74 connect It connects.
As another preferred embodiment, as shown in figure 4, the verticality adjustment mechanism 7 includes multiple and described installations Sliding column sleeve 76 that 1 bottom of matrix connects and with sliding cavity 75,77 and of slide post being located in each sliding cavity 75 The base platform 78 of the bottom connection of all slide posts 77, each sliding cavity 75 are communicated with the oil pocket 5.
Embodiment described above is only that preferred embodiments of the present invention are described, not new to this practicality The conception and scope of type is defined.Without departing from the design concept of the present utility model, ordinary people in the field is to this The all variations and modifications that the technical solution of utility model is made, should fall within the protection scope of the present utility model, this practicality Novel claimed technology contents have all been recorded in detail in the claims.

Claims (6)

1. a kind of revetment board mounting structure without pre-leveling, which is characterized in that including the installing matrix being installed on wall (1), mounting plate for installing skirting(2), be opened in the installing matrix(1)On in multiple rows of multiple row distribution and in circle Columnar multiple adjustment channels(3), be located at the mounting plate(2)On being inserted into the corresponding adjustment channel(3)In it is more A insertion column(4), the installing matrix(1)In be provided with the oil pocket with hydraulic oil(5), each adjustment channel(3)'s Surrounding is provided with multiple multiple squeezing passage groups for prolonging its axial directional distribution(6), each squeezing passage group(6)Including being in Ring-type setting being connected to the oil pocket(5)With the adjustment channel(3)Multiple radial compression channels(61), the extruding Channel(61)In be provided with extrusion ball(62)And the extrusion ball(62)The connecting rod of connection(63)And the connecting rod(63)Connection Squeezing the oil pocket(5)The push plate of middle hydraulic oil(64)And fixation is located at the squeezing passage(61)Position on inner wall In the push plate(64)With the extrusion ball(62)Between postive stop baffle(65), the installing matrix(1)On be additionally provided with note Oil nozzle(67)With oil extraction mouth(66).
2. a kind of revetment board mounting structure without pre-leveling according to claim 1, which is characterized in that the adjustment is logical Road(3)A diameter of insertion column(4)1.1-1.4 times of diameter.
3. a kind of revetment board mounting structure without pre-leveling according to claim 1, which is characterized in that the adjustment is logical Road(3)Insertion entrance be set as taper.
4. a kind of revetment board mounting structure without pre-leveling according to claim 1, which is characterized in that the installation base Body(1)Bottom be provided with to adjust the installing matrix(1)The verticality adjustment mechanism of verticality(7).
5. a kind of revetment board mounting structure without pre-leveling according to claim 4, which is characterized in that the verticality Adjustment mechanism(7)Including bottom plate(71), be located at the bottom plate(71)On multiple the first adjustment screw rods(72), be located at the installation Matrix(1)Bottom is located at the corresponding the first adjustment screw rod(72)Multiple second adjustment screw rods of surface(73), described One adjustment screw(72)With the second adjustment screw rod corresponding to it(73)By connecting swivel nut(74)Connection.
6. a kind of revetment board mounting structure without pre-leveling according to claim 4, which is characterized in that the verticality Adjustment mechanism(7)Including the multiple and described installing matrix(1)Bottom connection and have sliding cavity(75)Sliding column sleeve(76), It is located at each sliding cavity(75)In slide post(77)And all slide posts(77)Bottom connection base platform (78), each sliding cavity(75)With the oil pocket(5)It communicates.
CN201721757389.XU 2017-12-15 2017-12-15 A kind of revetment board mounting structure without pre-leveling Expired - Fee Related CN208039708U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721757389.XU CN208039708U (en) 2017-12-15 2017-12-15 A kind of revetment board mounting structure without pre-leveling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721757389.XU CN208039708U (en) 2017-12-15 2017-12-15 A kind of revetment board mounting structure without pre-leveling

Publications (1)

Publication Number Publication Date
CN208039708U true CN208039708U (en) 2018-11-02

Family

ID=63958768

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721757389.XU Expired - Fee Related CN208039708U (en) 2017-12-15 2017-12-15 A kind of revetment board mounting structure without pre-leveling

Country Status (1)

Country Link
CN (1) CN208039708U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107989316A (en) * 2017-12-15 2018-05-04 福州启辰阳光建材有限公司 A kind of revetment board mounting structure without pre-leveling

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107989316A (en) * 2017-12-15 2018-05-04 福州启辰阳光建材有限公司 A kind of revetment board mounting structure without pre-leveling
CN107989316B (en) * 2017-12-15 2023-10-10 台州博弘建设有限公司 Wallboard mounting structure without pre-leveling

Similar Documents

Publication Publication Date Title
CN208039708U (en) A kind of revetment board mounting structure without pre-leveling
CN202770600U (en) Device for testing performance of air penetration, rainwater seepage, and wind pressure resistance of building curtain wall
CN110242000A (en) A kind of assembled wall surface keel structure of levelling
CN107476586A (en) The erecting device of house PC prefabricated components and the installation method of PC prefabricated components
CN107989316A (en) A kind of revetment board mounting structure without pre-leveling
CN210105379U (en) Building template supporting device
CN207892087U (en) A kind of revetment board mounting structure
CN108967133A (en) A kind of nozzle carrier of punched irrigation stand
CN208039533U (en) A kind of revetment board mounting structure without wall
CN205357480U (en) Spout ground inserted bar a little
CN205063821U (en) Spiral oil atomizing nozzle
CN107965111B (en) A kind of decorative panel for building being easily installed
CN106613432A (en) Planting container capable of allowing plant to be planted at any angle and plant planting system
CN204023599U (en) Streetlamp foundation stake
CN107842135A (en) A kind of revetment board mounting structure without wall
CN208934345U (en) A kind of pentagon bottom whirlpool ball antistatic floor
CN107842134A (en) A kind of revetment board mounting structure
CN104032899A (en) Bonding type anchor device for FRP bars
CN210947284U (en) Leveling support member for assembly type keel partition wall ground
CN206315915U (en) A kind of ore dressing distribution box
CN106286992A (en) A kind of adjustable natural gas line supporting construction
CN208272526U (en) A kind of tunnel cable ditch bracket
CN207599144U (en) High intensity conduit saddle
CN207079953U (en) Edge protection rail structure
CN206640877U (en) A kind of material apparatus for leveling

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181102