CN207954717U - A kind of PE pipes full circle tool - Google Patents
A kind of PE pipes full circle tool Download PDFInfo
- Publication number
- CN207954717U CN207954717U CN201820358011.0U CN201820358011U CN207954717U CN 207954717 U CN207954717 U CN 207954717U CN 201820358011 U CN201820358011 U CN 201820358011U CN 207954717 U CN207954717 U CN 207954717U
- Authority
- CN
- China
- Prior art keywords
- full circle
- curved portion
- circle tool
- scallop
- pipes
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Meat, Egg Or Seafood Products (AREA)
Abstract
The utility model discloses a kind of PE pipes full circle tools, belong to PE pipeline processing mounting techniques field.The full circle tool includes the curved portion with lower arcuate surface and non-arc top surface, the stretching structure on the non-arc top surface that is set to curved portion, the scallop and operating lever being connected at the top of telescoping mechanism.The scallop is equipped with handle hole, and the operating lever is connected with handle hole when in use.PE pipes full circle tool provided by the utility model is by curved portion and scallop inner support in PE pipes, and the adjustable interior inner support of telescoping mechanism is in the length of full circle tool in pipe, to which the PE for enabling the full circle tool to be suitable for different bores is managed.Handle hole is equipped in scallop or curved portion, by the handle hole that is inserted into operating lever, entire full circle tool being made circumferentially to move the amendment that PE pipe roundness can be realized.Full circle tool construction is simple, easy to operate, applied widely.
Description
Technical field
The utility model is related to a kind of PE pipes full circle tools, belong to PE pipeline processing mounting techniques field.
Background technology
Polyethylene PE pipe is widely used in city gas pipe network, but in the connection procedure for carrying out new and old pipeline, behaviour
Make personnel to find that the original PE pipelines for being partially buried in underground are cut off to be that nozzle is extremely easy to happen deformation, causes crossing ellipsization
Degree causes electric melting sleeve can not be successfully and packs into old pipe nozzle beyond the case where requiring.Therefore, it is necessary to the nozzle of PE pipes into
Capable full circle again, in order to efficiently carry out the smooth connection that PE manages new and old pipeline.
Existing full circle tool is mostly to arrange the larger metal pipe material design of intensity, there are complicated, to PE pipes etc.
The not applicable problem of the lower tubing of intensity.
Utility model content
The operation of PE pipe full circle is not adapted to to solve existing full circle tool, and full circle tool construction is complicated, high processing costs
The technical issues of, the utility model provides a kind of PE pipes full circle tool, and the technical solution taken is as follows:
A kind of PE pipes full circle tool, the full circle tool include having lower arcuate surface and the curved portion of non-arc top surface 1, setting
In on 1 non-arc top surface of curved portion stretching structure 2, be connected to the scallop 4 and operating lever 3 at the top of telescoping mechanism 2;It is described
Scallop 4 is equipped with handle hole 5, and the operating lever 3 is connected with handle hole 5 when in use.
Preferably, the stretching structure 2 is equipped with and is connected thereto and controls flexible control-rod 3.
It is highly preferred that the control-rod 3 is set on the non-arc top surface of curved portion 1.
Preferably, the telescoping mechanism 2 is located at the middle part of 1 non-arcwall face of curved portion.
Preferably, the curved portion curvature of the curved portion 1 is identical as the curvature of the scallop 4.
Preferably, the telescoping mechanism 2 is jack or other can realize the existing apparatus of Telescopic.
Compared with the existing technology, the advantageous effect of the utility model acquisition is:
By curved portion and scallop inner support in PE pipes, the adjustable interior inner support of telescoping mechanism is in the length of full circle tool in pipe
Degree, to which the PE for enabling the full circle tool to be suitable for different bores is managed.
Handle hole is equipped in scallop or curved portion, by the handle hole that is inserted into operating lever, making entire full circle work
Tool circumferentially moves the amendment that PE pipe roundness can be realized.Full circle tool construction is simple, easy to operate, applied widely.
Description of the drawings
Fig. 1 is the structural schematic diagram of PE pipe full circle tools in a kind of preferred embodiment of the utility model.
Fig. 2 is the structural schematic diagram during full circle tool use shown in Fig. 1.
Fig. 3 is the structural schematic diagram of PE pipe full circle tools in a kind of preferred embodiment of the utility model.
In figure:1, curved portion;2, telescoping mechanism;3, control-rod;4, scallop;5, handle hole;6, operating lever;7, PE pipes.
Specific implementation mode
Following embodiment material therefor, method and instrument, without specified otherwise, be this field conventional material, method and
Instrument, those of ordinary skill in the art can be obtained by commercial channel.
The utility model in following description, it should be noted that term "center", " longitudinal direction ", " transverse direction ", "upper",
The indicating positions such as "lower", "front", "rear", "left", "right", "top", "bottom", "inner", "outside" and " endways " or position relationship are base
In orientation or positional relationship shown in the drawings, be merely for convenience of describing the present invention and simplifying the description, rather than indicate or
Imply that signified device or element must have a particular orientation, with specific azimuth configuration and operation, it is thus impossible to be interpreted as
Limitations of the present invention.
The utility model in following description, it should be noted that unless otherwise expressly provided with limit, term " peace
Dress ", " connected ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integrally
Connection;Can be directly connected to, can also be to be indirectly connected with by intermediate medium, can be the connection of two components interiors.It is right
Can be that concrete condition understands that term in the present invention specific of submitting a written statement to a higher authority contains for those skilled in the art
Justice.
In addition, the utility model in following description, unless otherwise indicated, " multiple ", " multigroup ", " more " meaning
It is two or more.
The utility model is described in further details below in conjunction with the accompanying drawings, but following detailed description is not intended as to this practicality
Novel restriction.
Fig. 1 is the structural schematic diagram of PE pipe full circle tools in a kind of preferred embodiment of the utility model.From fig. 1, it can be seen that
The full circle tool of the PE pipes includes the curved portion 1 that a bottom surface is arc-shaped curved surface, 2 He of telescoping mechanism being mounted in curved portion 1
Control-rod 3 and operating lever 6.Wherein, telescoping mechanism 2 is jack.It is fixed there are one scallop 4 on the top of telescoping mechanism 2,
Scallop 4 is equipped with perforative handle hole 5.Handle hole 5 can coordinate with operating lever 6.Operating lever 6 is cylindrical straight-bar, convenient to turn
Dynamic operating lever can be equipped with the existing known mechanism convenient for rotation.Meanwhile in the non-arcwall face on 1 top of curved portion(Plane)Upper fixation
There are one the operating levers 6 of operation jack.
Fig. 2 is the structural schematic diagram during full circle tool use shown in Fig. 1.In use, staff can lead to
Adjustment operating lever 6 is crossed, the diameter of entire full circle tool is shortened, and is put it into inside the PE pipes for waiting for full circle.Then, it will grasp
Make bar 6 to be inserted into handle hole 5, firmly rotation or passes through curved portion 1 and scallop 4 by connecting other actuating units rotation
The roundness of PE nozzle diameters is corrected in arcwall face rotation.
Fig. 3 is the structural schematic diagram of PE pipe full circle tools in a kind of preferred embodiment of the utility model.As can be seen from Figure 3,
This embodiment and a upper embodiment difference lies in:The position of telescoping mechanism 2 is the centre of curved portion 1.Two arcs
The round of shape face overlaps.
Although the utility model is disclosed as above with preferred embodiment, it is not limited to the utility model, appoints
What person skilled in the art can do various changes and modification, therefore without departing from the spirit and scope of the utility model
The scope of protection of the utility model should be subject to what claims were defined.
Claims (6)
1. a kind of PE pipes full circle tool, which is characterized in that include the curved portion with lower arcuate surface and non-arc top surface(1), set
It is placed in curved portion(1)Telescoping mechanism on non-arc top surface(2), be connected to telescoping mechanism(2)The scallop at top(4)And behaviour
Make bar(6);The scallop(4)It is equipped with handle hole(5), the operating lever(6)When in use with handle hole(5)Cooperation connects
It connects.
2. PE pipes full circle tool according to claim 1, which is characterized in that the telescoping mechanism(2)Equipped with being connected thereto
And control flexible control-rod(3).
3. PE pipes full circle tool according to claim 2, which is characterized in that the control-rod(3)It is set to curved portion(1)
Non- arc top surface on.
4. PE pipes full circle tool according to claim 1, which is characterized in that the telescoping mechanism(2)Positioned at curved portion(1)
The middle part of non-arcwall face.
5. PE pipes full circle tool according to claim 1, which is characterized in that the curved portion(1)Curved portion curvature with
The scallop(4)Curvature it is identical.
6. PE pipes full circle tool according to claim 1, which is characterized in that the telescoping mechanism(2)For jack.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820358011.0U CN207954717U (en) | 2018-03-16 | 2018-03-16 | A kind of PE pipes full circle tool |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820358011.0U CN207954717U (en) | 2018-03-16 | 2018-03-16 | A kind of PE pipes full circle tool |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207954717U true CN207954717U (en) | 2018-10-12 |
Family
ID=63743120
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820358011.0U Expired - Fee Related CN207954717U (en) | 2018-03-16 | 2018-03-16 | A kind of PE pipes full circle tool |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207954717U (en) |
-
2018
- 2018-03-16 CN CN201820358011.0U patent/CN207954717U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8091197B2 (en) | Device and process for assembling oriented objects | |
CN101961810A (en) | Construction method for manufacturing multi-pipe intersecting steel pipe component | |
CN204951099U (en) | Visual guiding device is intervene to supersound | |
CN109654297A (en) | Prevent the support ring and its application method of pipe deforming | |
CN207954717U (en) | A kind of PE pipes full circle tool | |
CN107378097A (en) | A kind of compression-resistant type metal hose cutter device | |
CN206343486U (en) | Full angle pipe welds swan neck system | |
CN209372666U (en) | The peel strength testing device of lining material for repairing pipelines and pipeline | |
CN103817183A (en) | Manual pipe bender | |
CN208099203U (en) | A kind of reinforced mesh bending apparatus | |
CN206225311U (en) | A kind of fuse switch | |
CN208067632U (en) | A kind of construction pipe connecting device | |
CN205369957U (en) | A condenser tube and bulky concrete for bulky concrete | |
CN208195295U (en) | A kind of electrical spool bending system | |
CN201535071U (en) | Retractor for quickly adjusting verticality of steel column | |
CN207378293U (en) | A kind of steel sleeve steel insulating tube sliding support | |
CN103752665B (en) | A kind of differential temperature shears multi-curvature bend pipe compensation equipment and technique | |
CN206943663U (en) | A kind of seamless steel alloy HTHP elbow of the butt welding with straight length | |
CN208421278U (en) | A kind of dynamic sounding device for Electromagnetic Survey of Underground Pipelines | |
CN211807945U (en) | Auxiliary tool for sleeving rigid elbow | |
CN211681048U (en) | Pipe diameter adjustable positioning device for water supply pipe production | |
CN205851735U (en) | Reinforcing bar bending tool | |
CN213144999U (en) | Spacing effectual hemisphere welded tube | |
CN110242813A (en) | A kind of method of water pipe connected positioning plate and its connecting pipe | |
CN2245540Y (en) | Pipe mouth angle drawing apparatus |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20181012 Termination date: 20190316 |
|
CF01 | Termination of patent right due to non-payment of annual fee |