CN207952565U - A kind of preparation facilities of semi-solid metal slurry - Google Patents

A kind of preparation facilities of semi-solid metal slurry Download PDF

Info

Publication number
CN207952565U
CN207952565U CN201720444078.1U CN201720444078U CN207952565U CN 207952565 U CN207952565 U CN 207952565U CN 201720444078 U CN201720444078 U CN 201720444078U CN 207952565 U CN207952565 U CN 207952565U
Authority
CN
China
Prior art keywords
sleeve
temperature adjustment
diversion pipe
semi
preparation facilities
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720444078.1U
Other languages
Chinese (zh)
Inventor
蔡中法
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SUZHOU CHUNXING PRECISION MECHANICAL CO Ltd
Original Assignee
SUZHOU CHUNXING PRECISION MECHANICAL CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SUZHOU CHUNXING PRECISION MECHANICAL CO Ltd filed Critical SUZHOU CHUNXING PRECISION MECHANICAL CO Ltd
Priority to CN201720444078.1U priority Critical patent/CN207952565U/en
Application granted granted Critical
Publication of CN207952565U publication Critical patent/CN207952565U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model is related to a kind of preparation facilities of semi-solid metal slurry;Including holding furnace, holder, casting machine, temperature adjustment sleeve and air deflector, air deflector is arranged on holder, air deflector includes diversion pipe and the sprue cup in diversion pipe one end is arranged, the top of sprue cup is equipped with holding furnace, the other end of diversion pipe is set as discharge port, discharge outlet is equipped with casting machine, thermostat kit jacket casing is located at formation temperature adjustment chamber on diversion pipe, temperature adjustment chamber is between temperature adjustment sleeve and diversion pipe, temperature adjustment sleeve includes the first sleeve and second sleeve of detachable-type sealed connection, first sleeve outer wall is equipped with the heat conduction matchmaker's entrance communicated with temperature adjustment chamber, second sleeve outer wall is equipped with the heat conduction matchmaker outlet communicated with temperature adjustment chamber;A kind of preparation facilities of semi-solid metal slurry provided by the utility model can be applied widely while ensureing cooling or heating precision.

Description

A kind of preparation facilities of semi-solid metal slurry
Technical field
The utility model is related to one kind belonging to Semi-solid Metals Forming Techniques field more particularly to a kind of semi-solid metal slurry The preparation facilities of material.
Background technology
It is well known that Semi-solid Metals Forming Techniques be will the solidliquid mixture containing n on-dendritic solid phase in setting temperature model A kind of material forming techniques shaped in enclosing, are mainly used in the alloy system that wider liquid consolidates coexistence, as aluminium alloy, Magnesium alloy, kirsite, nickel alloy, copper alloy and steel and alloy, wherein aluminium alloy, magnesium alloy because its fusing point it is low, industrial production It is easily achieved, is especially most widely used in automobile manufacturing field;Due in semi-solid-state metal preparation process in the prior art The problems such as there are deformation resistances greatly, high energy consumption and deformation are uneven, it is difficult to the advantage of semi-soild-state technology be brought into play, in this way Just to the Preparation equipment of Semi-Solid Metals Forming, more stringent requirements are proposed.
Utility model content
In order to solve the above technical problems, the utility model aim is to provide, a kind of energy consumption is easily controllable and purposes is wide half The preparation facilities of solid metal slurry.
To achieve the goals above, the utility model provides a kind of preparation facilities of semi-solid metal slurry, including protects Warm stove, holder, casting machine, temperature adjustment sleeve and air deflector, on the bracket, the air deflector includes leading for the air deflector setting Flow tube is equipped with the holding furnace, the diversion pipe with the sprue cup in described diversion pipe one end, the top of the sprue cup is arranged The other end be set as discharge port, the discharge outlet is equipped with the casting machine, and the thermostat kit jacket casing is located on the diversion pipe Temperature adjustment chamber is formed, for the temperature adjustment chamber between the temperature adjustment sleeve and diversion pipe, the temperature adjustment sleeve includes detachable close The first sleeve and second sleeve of connection are sealed, first sleeve outer wall is equipped with the heat conduction matchmaker communicated with the temperature adjustment chamber and enters Mouthful, the second sleeve outer wall is equipped with the heat conduction matchmaker outlet communicated with the temperature adjustment chamber.
Further, first sleeve is equipped with fixed flange, and the second sleeve is equipped with mounting flange, institute State detachable connection between fixed flange and mounting flange.
Further, further include the sealing ring being arranged on the fixed flange.
Further, first sleeve is connected with second sleeve by internal and external threads removable seal.
Further, the diversion pipe is conical flow guiding pipe or hook-type diversion pipe.
Further, heat conduction matchmaker inlet is equipped with the first temperature sensor, and heat conduction matchmaker exit is equipped with second Temperature sensor.
Further, further include being arranged in heat conduction matchmaker inlet and the micropump that is communicated with the temperature adjustment chamber.
According to the above aspect of the present invention, the utility model has at least the following advantages:While ensureing semi-solid-state metal form, expand The big scope of application of the preparation facilities of semi-solid metal slurry.
The above description is merely an outline of the technical solution of the present invention, in order to better understand the skill of the utility model Art means, and can be implemented in accordance with the contents of the specification, below on the preferred embodiment of the present invention and the accompanying drawings in detail It describes in detail bright as after.
Description of the drawings
Fig. 1 shows a kind of structural schematic diagram of the preparation facilities of semi-solid metal slurry of the utility model.
Specific implementation mode
With reference to the accompanying drawings and examples, specific embodiment of the present utility model is described in further detail.Below Embodiment is not intended to limit the scope of the present invention for illustrating the utility model.
Referring to Fig. 1, the utility model provides a kind of preparation facilities of semi-solid metal slurry, including holding furnace 1, holder 2, casting machine 3, temperature adjustment sleeve and air deflector, air deflector are arranged on holder 2, and air deflector includes diversion pipe 4 and is arranged in water conservancy diversion The top of the sprue cup 5 of 4 one end of pipe, sprue cup 5 is equipped with holding furnace 1, and the other end of diversion pipe 4 is set as discharge port 6, discharge port 6 Place is equipped with casting machine 3, and thermostat kit jacket casing, which is located on diversion pipe 4, forms temperature adjustment chamber 7, and temperature adjustment chamber 7 is located at temperature adjustment sleeve and diversion pipe 4 Between, temperature adjustment sleeve include detachable-type sealed connection the first sleeve 8 and second sleeve 9,8 outer wall of the first sleeve be equipped with Heat conduction matchmaker's entrance that temperature adjustment chamber 7 communicates, 9 outer wall of second sleeve are equipped with the heat conduction matchmaker outlet communicated with temperature adjustment chamber 7.
A kind of preparation facilities operation principle of semi-solid metal slurry provided by the utility model is as follows:
During preparing semi-solid-state metal with inclined cooling plate formula, the master that molten metal is changed into semi-solid-state metal is influenced It will be because being known as pouring temperature, cooling length and angle of inclination, the preparation facilities of semi-solid metal slurry provided by the utility model By air deflector and mating temperature adjustment sleeve to realize the control to these three principal elements;Wherein, the metal in holding furnace 1 Liquid flows into diversion pipe 4 by the sprue cup 5 of 4 one end of diversion pipe, and the temperature adjustment sleeve being arranged on 4 outer wall of diversion pipe can be passed through difference The heat conduction matchmaker of temperature realizes temperature adjustment to the molten metal in diversion pipe 4, since temperature adjustment sleeve includes the of detachable-type sealed connection One sleeve 8 and second sleeve 9 can carry out temperature adjustment to diversion pipe 4 of different shapes;In addition, air deflector is fixed on holder 2, The transformation of differing tilt angles may be implemented;It is final to realize to the accurate control of the solid phase mass fraction in semi-solid-state metal simultaneously The mechanical performance for improving semi-solid metal slurry, meets the needs of client and market.
Dismounting and sealing between first sleeve 8 and second sleeve 9 for convenience, the first sleeve 8 are equipped with mounting flange Disk 10, second sleeve are equipped with mounting flange 11, and detachable connection between fixed flange 10 and mounting flange 11 is gone back Including the sealing ring on fixed flange 10 is arranged.
In order to facilitate dismantling and fix the temperature adjustment sleeve that the first sleeve 8 and second sleeve 9 form, the first sleeve 8 and second Sleeve 9 is connected by internal and external threads removable seal.
In order to carry out temperature adjustment and deformation to different types of molten metal, diversion pipe 4 is conical flow guiding pipe or hook-type water conservancy diversion Pipe.
In order to keep the temperature change of heat conduction matchmaker more intuitive, heat conduction matchmaker inlet is equipped with the first temperature sensor 12, heat conduction Matchmaker exit is equipped with second temperature sensor 13.
In order to accelerate temperature adjustment intracavitary heat transmission, further include being arranged to communicate in heat conduction matchmaker inlet and with temperature adjustment chamber 7 Micropump 14.
The above is only the preferred embodiment of the utility model, is not intended to limit the utility model, it is noted that For those skilled in the art, without deviating from the technical principle of the utility model, it can also do Go out several improvements and modifications, these improvements and modifications also should be regarded as the scope of protection of the utility model.

Claims (7)

1. a kind of preparation facilities of semi-solid metal slurry, it is characterised in that:Including holding furnace, holder, casting machine, temperature adjustment sleeve And air deflector, on the bracket, the air deflector includes diversion pipe and is arranged in the diversion pipe one for the air deflector setting The sprue cup at end, the top of the sprue cup are equipped with the holding furnace, and the other end of the diversion pipe is set as discharge port, it is described go out The casting machine is equipped at material mouth, the thermostat kit jacket casing is located at formation temperature adjustment chamber, the temperature adjustment chamber on the diversion pipe and is located at Between the temperature adjustment sleeve and diversion pipe, the temperature adjustment sleeve includes the first sleeve that detachable-type sealed connects and second set Cylinder, first sleeve outer wall are equipped with the heat conduction matchmaker's entrance communicated with the temperature adjustment chamber, and the second sleeve outer wall is equipped with The heat conduction matchmaker outlet communicated with the temperature adjustment chamber.
2. the preparation facilities of semi-solid metal slurry according to claim 1, it is characterised in that:It is set on first sleeve There is fixed flange, the second sleeve is equipped with mounting flange, removable between the fixed flange and mounting flange Unload formula connection.
3. the preparation facilities of semi-solid metal slurry according to claim 2, it is characterised in that:Further include being arranged described Sealing ring on fixed flange.
4. the preparation facilities of semi-solid metal slurry according to claim 1, it is characterised in that:First sleeve and Two sleeves are connected by internal and external threads removable seal.
5. the preparation facilities of semi-solid metal slurry according to claim 1, it is characterised in that:The diversion pipe is taper Diversion pipe or hook-type diversion pipe.
6. the preparation facilities of semi-solid metal slurry according to claim 1, it is characterised in that:Heat conduction matchmaker inlet Equipped with the first temperature sensor, heat conduction matchmaker exit is equipped with second temperature sensor.
7. the preparation facilities of semi-solid metal slurry according to claim 1, it is characterised in that:Further include being arranged described Heat conduction matchmaker inlet and the micropump communicated with the temperature adjustment chamber.
CN201720444078.1U 2017-04-25 2017-04-25 A kind of preparation facilities of semi-solid metal slurry Expired - Fee Related CN207952565U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720444078.1U CN207952565U (en) 2017-04-25 2017-04-25 A kind of preparation facilities of semi-solid metal slurry

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720444078.1U CN207952565U (en) 2017-04-25 2017-04-25 A kind of preparation facilities of semi-solid metal slurry

Publications (1)

Publication Number Publication Date
CN207952565U true CN207952565U (en) 2018-10-12

Family

ID=63723909

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720444078.1U Expired - Fee Related CN207952565U (en) 2017-04-25 2017-04-25 A kind of preparation facilities of semi-solid metal slurry

Country Status (1)

Country Link
CN (1) CN207952565U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109848390A (en) * 2019-01-28 2019-06-07 浙江大学宁波理工学院 The preparation of low-melting alloy semi solid slurry and recovery valve island heat supply integrated system
CN111304519A (en) * 2020-04-16 2020-06-19 重庆大学 Preparation method and device of steel blank for semi-solid thixoforming
CN114101647A (en) * 2021-11-24 2022-03-01 安徽省巢湖市宏顺机械铸造有限公司 One-man operation safety type casting machine

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109848390A (en) * 2019-01-28 2019-06-07 浙江大学宁波理工学院 The preparation of low-melting alloy semi solid slurry and recovery valve island heat supply integrated system
CN109848390B (en) * 2019-01-28 2021-01-01 浙江大学宁波理工学院 Low-melting-point alloy semi-solid slurry preparation and recovery valve island type heat supply integrated system
CN111304519A (en) * 2020-04-16 2020-06-19 重庆大学 Preparation method and device of steel blank for semi-solid thixoforming
CN111304519B (en) * 2020-04-16 2021-09-14 重庆大学 Preparation method and device of steel blank for semi-solid thixoforming
CN114101647A (en) * 2021-11-24 2022-03-01 安徽省巢湖市宏顺机械铸造有限公司 One-man operation safety type casting machine

Similar Documents

Publication Publication Date Title
CN207952565U (en) A kind of preparation facilities of semi-solid metal slurry
WO2016115954A1 (en) Device and method for preparing semi-solid metal slurry
CN203508950U (en) Device for inducing molten metal to carry out rapid and mass nucleation through rotary rod
CN205603660U (en) Aluminum alloy and magnesium alloy vacuum melting pouring device
CN101745629A (en) Method for preparing semi-solid alloy rheological slurry or billet through annular-gap type electromagnetic stirring
CN103978187A (en) Device and method for counter-gravity casting of solidification process controlled titanium-based alloy
CN206083784U (en) A heat preservation stove that is used for preparing in succession half solid -state thick liquids of aluminum alloy
CN107790669B (en) Semi-solid slurry preparation and die-casting integrated rheologic die-casting method
CN102358922B (en) Light alloy semi-solid slurry preparation device
CN108097882A (en) Riser component
CN205917321U (en) Novel square crystallizer that electroslag used
CN107498010B (en) A kind of preparation process of light alloy semisolid slurry
CN109604550B (en) Magnesium alloy vertical semi-continuous casting device
CN106834762B (en) A kind of vacuum melting device of intermetallic Ni-Al compound
CN109513890B (en) Preparation method of hollow cast iron pipe with A-type graphite structure
CN206083783U (en) Prepare temperature control system of half solid -state thick liquids heat preservation stove of aluminum alloy in succession
CN101347833A (en) Sine waveform device for preparing semi-solid metal slurry
CN205262181U (en) Excel in production facility of aluminum alloy of tombarthite
CN205183728U (en) A cold chamber die casting molding machine open type feed cylinder that is used for half solid -state die -casting to take shape
CN209363579U (en) A kind of metal semicontinuous casting crystallizer melting bath stirring device
CN202861355U (en) Automatic feeding device for cold-chamber die-casting machine
CN107957193A (en) A kind of Automatic-temperature holding furnace for being used to continuously prepare aluminium alloy semi-solid slurry
CN102343422B (en) Device for preparing semisolid alloy slurry
CN105605918B (en) A kind of smelting furnace diversion pipe
CN217492625U (en) Electromagnetic heating and water cooling dual-function casting mold

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181012

Termination date: 20190425

CF01 Termination of patent right due to non-payment of annual fee