CN207944554U - A kind of concrete frame bean column node steel pipe bundle reinforcing sleeve - Google Patents

A kind of concrete frame bean column node steel pipe bundle reinforcing sleeve Download PDF

Info

Publication number
CN207944554U
CN207944554U CN201720714406.5U CN201720714406U CN207944554U CN 207944554 U CN207944554 U CN 207944554U CN 201720714406 U CN201720714406 U CN 201720714406U CN 207944554 U CN207944554 U CN 207944554U
Authority
CN
China
Prior art keywords
steel pipe
pipe bundle
concrete
connecting plate
quadrangle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720714406.5U
Other languages
Chinese (zh)
Inventor
陈明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI OPEN STEEL JOIST CO Ltd
Original Assignee
SHANGHAI OPEN STEEL JOIST CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI OPEN STEEL JOIST CO Ltd filed Critical SHANGHAI OPEN STEEL JOIST CO Ltd
Priority to CN201720714406.5U priority Critical patent/CN207944554U/en
Application granted granted Critical
Publication of CN207944554U publication Critical patent/CN207944554U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

The utility model proposes a kind of concrete frame bean column node steel pipe bundle reinforcing sleeves, including quadrangle steel pipe bundle, bracket, steel pipe bundle connecting plate, cover board, concrete prefabricated beam, concrete column and joint bar;Wherein, the upper and lower ends of quadrangle steel pipe bundle are provided with steel pipe bundle connecting plate, and each two quadrangle steel pipe bundle is attached by the steel pipe bundle connecting plate, to form a cuboid casing;Bracket is placed on the steel pipe bundle connecting plate;Concrete prefabricated beam is inserted into the gap between two steel pipe bundle connecting plates up and down, is connect with the concrete prefabricated beam of the other end, and be held on bracket;The top and bottom of casing and the joint face of concrete column are both provided with cover board;The joint face of concrete column is provided with joint bar, and sizing punching block is connected to sleeve by cover board and joint bar, the problems such as conflict with the cumbersome and reinforcement location that solves to construct in background technology.

Description

A kind of concrete frame bean column node steel pipe bundle reinforcing sleeve
Technical field
The utility model is related to build, the field of engineering technology such as civilian, municipal, industrial, and in particular to a kind of concrete frame It sets a roof beam in place Column border node steel pipe bundle reinforcing sleeve.
Background technology
One of traditional architectural structural system is usually taken and is connect with grid beam for pure concrete frame trestle, and construction is existing A large amount of scaffolding work is set up as template system in field, and each formwork structure is all independently formed, and is only poured in concrete The stage of building works, and a large amount of manpower and materials is caused to waste;Especially large span, in big load structure engineering, concrete frame Column reinforcing bar needs thick with get Mi according to stress, and concrete frame beam is also, especially in negative moment area, usual steel reinforcement cage Muscle is indulged in the placement at beam-column connection of binding needs, thus the vertical muscle position appearance of easy and concrete frame beam is conflicting Phenomenon;Have again notably, it may appear that beam-to-column joint region concrete pours to go down or pour uncompacted situation, to reduce structure Safe class, be easy to form hidden danger;
In construction technology, traditional template system needs a large amount of flitch, and scaffold tube is poured as template system Build supporting member when concrete.And each formwork structure is all independently formed, and is only worked in the concreting stage;
In conclusion a kind of new building system and construction method are provided, to solve traditional concrete pouring construction The drawbacks of, it appears it is particularly important.
Utility model content
The purpose of this utility model is that a kind of concrete frame bean column node steel pipe bundle reinforcing sleeve is proposed, to solve to carry on the back The problems such as cumbersome and reinforcement location of constructing in scape technology conflicts.
To achieve the above object, the utility model proposes a kind of concrete frame bean column node steel pipe bundle reinforcing sleeve, packets Include quadrangle steel pipe bundle, bracket, steel pipe bundle connecting plate, cover board, concrete prefabricated beam, concrete column and joint bar;Wherein, the quadrangle The upper and lower ends of steel pipe bundle are provided with the steel pipe bundle connecting plate, and quadrangle steel pipe bundle described in each two passes through the steel pipe bundle Connecting plate is attached, to form a cuboid casing;The bracket is placed on the steel pipe bundle connecting plate;The coagulation Native precast beam is inserted into the gap between two steel pipe bundle connecting plates up and down, connects with the concrete prefabricated beam of the other end It connects, and is held on the bracket;The joint face of the top and bottom of described sleeve pipe and the concrete column is both provided with the cover board; The joint face of the concrete column is provided with the joint bar, and the sizing punching block is connected to institute by the cover board and the joint bar State sleeve.
Preferably, the quadrangle steel pipe bundle is arranged in the four corners of described sleeve pipe, generally use steel-tube construction.
Preferably, the quadrangle steel pipe is cavity structure.
Preferably, the concrete prefabricated beam is mounted with negative reinforcement.
Preferably, the concrete prefabricated beam is mounted with negative reinforcement, and the concrete prefabricated beam passes through between negative reinforcement Connection is connect with the concrete prefabricated beam of the other end.
Preferably, it is connected between the capping by connecting bolt.
Compared with prior art, the beneficial effects of the utility model are mainly reflected in:The concrete prefabricated beam is inserted into Gap between lower two steel pipe bundle connecting plates, connect with the concrete prefabricated beam of the other end, and is held on described On bracket, passed through convenient for beam steel;Quadrangle steel pipe bundle instead of part of nodes region part pillar longitudinal reinforcement;Negative reinforcement is set Count the stirrup instead of beams of concrete column connected node region;The setting of bracket avoids biography convenient for shelving concrete prefabricated beam The built-in fitting for way of uniting, it is firmer, it is more reliable;Due to the confined effect of node region so that joints ability greatly enhances, Monolithic architecture is set to have better shock resistance;It is factory produced, size is accurate, on-site hoisting, convenient and safe;It is connected with column Beam can be precast concrete beam, can also be girder steel.Actual selection can be carried out according to actual conditions.
Description of the drawings
Fig. 1 is a kind of example schematic diagram of concrete frame bean column node steel pipe bundle reinforcing sleeve;
Fig. 2 is that a kind of concrete frame bean column node steel pipe bundle reinforcing sleeve is connect with concrete column and concrete prefabricated beam Whole stereoscopic schematic diagram.
Specific implementation mode
It, below will be to technical scheme of the present invention to keep the purpose of this utility model, technical solution and advantage clearer It is further described.
As shown in Figure 1 to Figure 2, a kind of concrete frame bean column node steel pipe bundle reinforcement has been embodied in the present invention Casing, including quadrangle steel pipe bundle 1, bracket 2, cover board 3, connection bolt 4, steel pipe bundle connecting plate 5, concrete prefabricated beam 6, negative reinforcement 7, Joint bar 8, sizing 9 concrete column 10 of punching block;
Wherein, the upper and lower ends of the quadrangle steel pipe bundle 1 are provided with the steel pipe bundle connecting plate 5, and described in each two Quadrangle steel pipe bundle 1 is attached by the steel pipe bundle connecting plate 5, to form a cuboid casing;The bracket 2 is placed in On the steel pipe bundle connecting plate 5;Convenient for shelving concrete prefabricated beam, the built-in fitting of traditional method is avoided, it is firmer, more may be used It leans on.The concrete prefabricated beam 6 is inserted into the gap between the upper and lower two steel pipe bundle connecting plates 5, described mixed with the other end Solidifying soil precast beam 6 connects, and is held on the bracket 2, is passed through convenient for negative reinforcement 7, conflicting until preventing vertical muscle Phenomenon;The joint face of the top and bottom of described sleeve pipe and the concrete column 10 is both provided with the cover board 3;The concrete column 10 Joint face be provided with the joint bar, the concrete column 10 first passes through the sizing punching block 9 and molding is pre-machined as needed, The sleeve is connected to by the cover board 3 and the joint bar 8 again.Its node region forms confined effect so that joints Ability greatly enhances, and monolithic architecture is made to have better shock resistance.
In the present embodiment, the quadrangle steel pipe bundle 1 is arranged in the four corners of described sleeve pipe, generally use steel pipe knot Structure.
In the present embodiment, the quadrangle steel pipe bundle 1 is cavity structure.
In the present embodiment, the concrete prefabricated beam 6 is mounted with negative reinforcement 7, and the design of negative reinforcement 7 is instead of beam column built from concrete The stirrup in connecting node region.
In the present embodiment, a kind of assembly method of concrete frame bean column node steel pipe bundle reinforcing sleeve is further comprised, For assembling the concrete frame bean column node steel pipe bundle reinforcing sleeve, the method includes:
(1), the lower upper end of quadrangle steel pipe bundle 1 is connected two-by-two using steel pipe bundle connecting plate 5, it is rectangular to form one Body sleeve;
(2), bracket 2, and the sleeve are disposed respectively on the steel pipe bundle connecting plate 5 of four sides of the sleeve Top and bottom dispose cover board 3 respectively;
(3), joint bar 8 and the cover board 3 are disposed in the joint face for the concrete column 10 for pouring completion in advance.
(4), by the linking joint bar 8 is inserted between the quadrangle steel pipe bundle 1 and capping 3 by the coagulation Earth pillar 10 and described sleeve pipe are attached.
(5), concrete prefabricated beam 6 is inserted into the gap between the upper and lower two steel pipe bundle connecting plates 5, with the other end The concrete prefabricated beam 6 connects, and is held on the bracket 2.
(6), concreting is carried out to whole.
In the present embodiment, it in step (4), is connected between the capping 3 by connecting bolt 4.
In the present embodiment, in step (5), the concrete prefabricated beam 6 by connection between negative reinforcement 7 with it is another The concrete prefabricated beam 6 at end connects.
The preferred embodiment of the present invention is above are only, does not play the role of any restrictions to the utility model.It is any Person of ordinary skill in the field discloses the utility model in the range of not departing from the technical solution of the utility model Technical solution and technology contents make the variations such as any type of equivalent replacement or modification, belong to the skill without departing from the utility model The content of art scheme, still falls within the scope of protection of the utility model.

Claims (5)

1. a kind of concrete frame bean column node steel pipe bundle reinforcing sleeve, which is characterized in that including quadrangle steel pipe bundle, bracket, steel Restrain connecting plate, cover board, concrete prefabricated beam, concrete column and joint bar;Wherein, the upper and lower ends setting of the quadrangle steel pipe bundle There is the steel pipe bundle connecting plate, and quadrangle steel pipe bundle described in each two is attached by the steel pipe bundle connecting plate, to Form a cuboid casing;The bracket is placed on the steel pipe bundle connecting plate;Two above and below the concrete prefabricated beam insertion Gap between a steel pipe bundle connecting plate connect with the concrete prefabricated beam of the other end, and is held on the bracket On;The joint face of the top and bottom of described sleeve pipe and the concrete column is both provided with the cover board;The connection of the concrete column Face is provided with the joint bar, and sizing punching block is connected to sleeve by the cover board and the joint bar.
2. concrete frame bean column node steel pipe bundle reinforcing sleeve according to claim 1, which is characterized in that the quadrangle Steel pipe bundle is arranged in the four corners of described sleeve pipe, using steel-tube construction.
3. concrete frame bean column node steel pipe bundle reinforcing sleeve according to claim 1, which is characterized in that the quadrangle Steel pipe bundle is cavity structure.
4. concrete frame bean column node steel pipe bundle reinforcing sleeve according to claim 1, which is characterized in that the coagulation Native precast beam is mounted with negative reinforcement, and the concrete prefabricated beam passes through the concrete prefabricated of connection between negative reinforcement and the other end Beam connects.
5. a kind of concrete frame bean column node steel pipe bundle reinforcing sleeve according to claim 1, which is characterized in that described It is connected between cover board by connecting bolt.
CN201720714406.5U 2017-06-19 2017-06-19 A kind of concrete frame bean column node steel pipe bundle reinforcing sleeve Expired - Fee Related CN207944554U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720714406.5U CN207944554U (en) 2017-06-19 2017-06-19 A kind of concrete frame bean column node steel pipe bundle reinforcing sleeve

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720714406.5U CN207944554U (en) 2017-06-19 2017-06-19 A kind of concrete frame bean column node steel pipe bundle reinforcing sleeve

Publications (1)

Publication Number Publication Date
CN207944554U true CN207944554U (en) 2018-10-09

Family

ID=63702984

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720714406.5U Expired - Fee Related CN207944554U (en) 2017-06-19 2017-06-19 A kind of concrete frame bean column node steel pipe bundle reinforcing sleeve

Country Status (1)

Country Link
CN (1) CN207944554U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107090909A (en) * 2017-06-19 2017-08-25 上海欧本钢结构有限公司 A kind of concrete frame bean column node steel pipe bundle reinforcing sleeve and its assembly method
CN109162353A (en) * 2018-10-25 2019-01-08 安徽建筑大学 Steel concrete assembled connected node
CN111456256A (en) * 2020-05-12 2020-07-28 黑龙江宇辉新型建筑材料有限公司 Reinforced concrete prefabricated column type steel connecting joint and connecting method
CN111502034A (en) * 2020-04-27 2020-08-07 江南大学 Joint connecting device of steel-concrete combined column and beam and application thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107090909A (en) * 2017-06-19 2017-08-25 上海欧本钢结构有限公司 A kind of concrete frame bean column node steel pipe bundle reinforcing sleeve and its assembly method
CN107090909B (en) * 2017-06-19 2023-08-15 上海欧本钢结构有限公司 Reinforced sleeve of concrete frame beam column node steel tube bundle and assembly method thereof
CN109162353A (en) * 2018-10-25 2019-01-08 安徽建筑大学 Steel concrete assembled connected node
CN111502034A (en) * 2020-04-27 2020-08-07 江南大学 Joint connecting device of steel-concrete combined column and beam and application thereof
CN111456256A (en) * 2020-05-12 2020-07-28 黑龙江宇辉新型建筑材料有限公司 Reinforced concrete prefabricated column type steel connecting joint and connecting method

Similar Documents

Publication Publication Date Title
CN207944554U (en) A kind of concrete frame bean column node steel pipe bundle reinforcing sleeve
CN107090909A (en) A kind of concrete frame bean column node steel pipe bundle reinforcing sleeve and its assembly method
CN107143034A (en) A kind of assembly concrete frame structure beam column rigid connection node
CN101967851A (en) Board-mixing structure assembly type house and building method thereof
CN108412122A (en) Double web H shaped steel and its connecting node with concrete prefabricated board
CN102505849B (en) Construction method of membrane shell ribbed floor formwork supporting system
CN101021088A (en) Steel reinforcement assembling integral structural vertical pole hollow rack building floor slab structure
CN107060112A (en) A kind of steel pipe bundle concrete column is connected with floor beam uses combed connector
CN102322144A (en) Straw wall body-based frame column/beam template-less construction technology
CN108978996B (en) Outrigger added in existing brick-concrete structure and construction method thereof
CN111411693A (en) Assembly and pouring integrated shear wall structure building system
CN204715764U (en) The structure that a kind of constructional column and agent structure are constructed simultaneously
CN108775086A (en) The additional assembled integral beam-column node structure and construction method for being closed connection reinforcing bar
CN212453063U (en) Assembly and pouring integrated shear wall structure building system
CN205348390U (en) Connection structure of precast concrete roof beam and cast -in -place post
CN209179177U (en) A kind of prefabricated column component, assembled combine prefabricated post
CN210151995U (en) Assembled shear force wall flexible connection device
CN208763207U (en) The assembled integral beam-column node structure of additional closure connection reinforcing bar
CN107401215A (en) Assembled architecture and construction process
CN206143914U (en) SC fabricated frame bearing structure system
CN210104953U (en) Assembly type building with hollow small building blocks for building corners
CN106869331A (en) The connection method of precast shear wall composite beam in assembled RC frame-shear structures
CN106759882A (en) Prefabricated post composite beam top story exterior joints connection method in assembled RC frame-shear structures
CN208441257U (en) A kind of mounting structure of assembling-type precast hybrid beam and stiffened column
CN208121961U (en) A kind of assembling frame corner node structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181009