CN207944455U - Remove mudcake device - Google Patents

Remove mudcake device Download PDF

Info

Publication number
CN207944455U
CN207944455U CN201721831614.XU CN201721831614U CN207944455U CN 207944455 U CN207944455 U CN 207944455U CN 201721831614 U CN201721831614 U CN 201721831614U CN 207944455 U CN207944455 U CN 207944455U
Authority
CN
China
Prior art keywords
tube body
outer shroud
cavity
mudcake
pile foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721831614.XU
Other languages
Chinese (zh)
Inventor
刘思谋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mcc Communication Construction Group Co Ltd
Original Assignee
Mcc Communication Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mcc Communication Construction Group Co Ltd filed Critical Mcc Communication Construction Group Co Ltd
Priority to CN201721831614.XU priority Critical patent/CN207944455U/en
Application granted granted Critical
Publication of CN207944455U publication Critical patent/CN207944455U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model provides one kind and removing mudcake device, including interior tube body and the outer shroud tube body being arranged outside said inner tube body, there is a closed cavity on the outer shroud tube body, the cavity is connect by water pipe with high-pressure hydraulic pump, the outer wall upper edge of the outer shroud tube body is circumferentially provided with multiple nozzles, and the multiple nozzle is connected to the cavity.The utility model substantially increases the frictional resistance between entire friction pile and the soil body applied to cast-in-situ bored pile, reduce or eliminate the sedimentation of pile foundation in the future, and pile foundation cures combination with pile foundation surrounding soil and is formed as well-set entirety well, this bearing capacity for allowing for pile foundation has obtained greatly being promoted, and reduces the transversely deforming and linear deformation of pile foundation.

Description

Remove mudcake device
Technical field
The utility model is related to Construction Technology fields, more specifically, are related to a kind of going for cast-in-situ bored pile hole wall Mudcake device.
Background technology
Bored concrete pile is the pile foundation structure that the buildings such as house, bridge, water conservancy dam generally use.Existing cast-in-situ bored pile Construction method be:First, measurement and positioning buries steel pile casting, then middle drill bit is started drilling machine and tunneled downwards in steel pile casting Pore-forming well, after stake holes is formed, first time borehole cleaning;Then it is put into steel reinforcement cage in stake holes, after the completion of steel reinforcement cage, second of borehole cleaning; Conduit is placed in steel reinforcement cage later, concrete funnel is installed, then the first batch of concrete of Reperfu- sion controls concrete pouring height by lining rope, tears open Except conduit is up to the elevation of concrete pouring to design requirement;Pile crown laitance layer thickness is normally controlled in 0.5-1m, extracts casing, construction It completes.
The construction method of above-mentioned cast-in-situ bored pile is primarily present following disadvantage:First, in drilled pile pore forming process, Carry out mud off.If without mud off, drill around the soil body will collapse hole fall into stake holes, it is therefore necessary to Mud off is used to form mudcake on stake holes wall.Mudcake exists always during pile foundation concrete pouring, and concrete and stake has been isolated The consolidation of surrounding soil affects the bearing capacity of pile foundation, reduces the service life of pile foundation;Second, steel reinforcement cage is during the installation process It is possible that smearing hole wall, it is stained with soil on steel reinforcement cage, reduces the quality of stake;Third, friction pile are possible to because of Lack of support And post jacking measure must be used.Post-mud-jacking bored pile is not only of high cost, larger mixed with the usage amount of additive cement mortar, Er Qieqi The effect for improving the bearing capacity of friction pile is little, can also cause the waste of raw material.
Utility model content
In view of the above problems, the purpose of this utility model is to provide one kind and removing mudcake device, to solve prior art drilling Bored concrete pile influences pouring pile bearing capacity because of there are problems that for mudcake.
To achieve the goals above, the present invention is realized by technical solution below:
One kind removing mudcake device, including interior tube body and the outer shroud tube body being arranged outside said inner tube body, the outer endless tube There is a closed cavity, the cavity to be connect with high-pressure hydraulic pump by water pipe, the outer wall upper edge week of the outer shroud tube body on body To multiple nozzles are provided with, the multiple nozzle is connected to the cavity.
Preferably, the outer shroud tube body is connect with said inner tube body by multigroup reinforcing rib group, reinforcing rib described in every group Group includes two symmetrically set reinforcing rib.
Preferably, the multiple nozzle be set in qually spaced on the outer shroud tube body and the nozzle be bore by it is interior extremely Outer gradually increased horn-like nozzle.
Preferably, it is symmetrically provided with multigroup hanging ring group on the lateral surface of the outer shroud tube body, hanging ring group described in every group Including two symmetrically arranged hanging rings.
Preferably, more water pipes are provided in the cavity, the more water pipes are along the circumferential equidistant of the cavity Setting.
Compared with prior art, the utility model at least has the advantages that:The utility model removes mudcake device Mudcake on pile foundation hole wall can be rinsed out, rinse the mudcake got off and be discharged as the concrete face of rising rises at the top of pile foundation hole, This allows for periphery of pile foundation and cures combinations well with pile foundation hole wall soil loading body, substantially increase entire friction pile and the soil body it Between frictional resistance, reduce or eliminate the sedimentation of pile foundation in the future, improve the durability of pile foundation structure object structure;The present invention Pile foundation obtained cures well with pile foundation surrounding soil in conjunction with well-set entirety is formed as, this allows for the carrying of pile foundation Power has obtained greatly being promoted, and reduces the transversely deforming and linear deformation of pile foundation, greatly improves the service life of pile foundation, And the bearing power increase of the pile foundation of the bigger method preparation with the present invention of diameter of pile foundation is bigger.
Description of the drawings
By reference to the description below in conjunction with attached drawing, and with the utility model is more fully understood, this reality It will be more clearly understood and understood with novel other purposes and result.In the accompanying drawings:
Fig. 1 is the structural schematic diagram of the utility model embodiment.
Identical label indicates similar or corresponding feature or function in all the appended drawings.
Specific implementation mode
Specific embodiment of the utility model is described in detail below with reference to attached drawing.
Go mudcake device, including interior tube body 101 and setting in interior tube body 101 as shown in Figure 1, the utility model provides one kind External outer shroud tube body 102.Outer shroud tube body 102 includes inner ring pipeline and the outer shroud pipeline being arranged outside interior endless tube road, interior endless tube The both ends in road between interior endless tube road and inner ring pipeline respectively with the connection closed at both ends of outer shroud pipeline to form a closed sky Chamber 103.Interior tube body 101 is connect with outer shroud tube body 102 by multigroup reinforcing rib group, and every group of reinforcing rib group includes two and be symmetrical arranged Reinforcing rib 104, in the present embodiment, which can be made of reinforcing bar, i.e., by one end of reinforcing bar and outer shroud tube body 102 The inner wall of inner ring pipeline weld together, the other end outer wall corresponding on interior tube body 101 of reinforcing bar welds together.Cavity High pressure resistant water pipe 105 is provided in 103, high pressure resistant water pipe 105 is stretched to from 103 top of cavity in cavity 103, high pressure resistant water pipe 105 connect with high-pressure hydraulic pump.In actual use, can more high pressure resistant water pipes 105 be set according to Pile Diameter size, it is more Circumferential spaced set of the high pressure resistant water pipe 105 of root along cavity 103.The outer tube wall upper edge of outer shroud tube body 102 is circumferentially provided with more A nozzle 106, the spaced set on outer tube body 101 of multiple nozzles 106, multiple nozzles 106 are connected to cavity 103.In order to make The area bigger for the water column radiation that each nozzle 106 sprays is obtained, nozzle 106 is set as bore gradual increased loudspeaker from the inside to the outside Shape nozzle.Multigroup hanging ring group is additionally provided on the top surface of outer tube body 102, every group of hanging ring group includes two symmetrically arranged hanging rings 107.Multigroup hanging ring group is connect by steel wire rope with boom hoisting to facilitate boom hoisting that mudcake device will gone to sling rising Or decline when keep go mudcake device always with horizontal direction keeping parallelism.
Apply when removing mudcake device of the present embodiment, by two hanging rings 107 gone on mudcake device respectively with a steel Cord connects, and every steel wire rope is connect with one end of the fringed iris herb on hoist engine respectively again, and two steel wire ropes of adjustment so that iron is flat Carry on a shoulder pole and go mudcake device to remain parallel with horizontal direction.Start hoist engine to be set in the interior tube body 101 for removing mudcake device On conduit in pile foundation hole, mudcake device is gone to be put into pile foundation hole along conduit.Funnel is installed on the top of conduit, by pump truck In concrete be perfused from funnel into conduit, first batch of concrete enters the bottom hole of pile foundation hole until by conduit along conduit Bottom is embedded wherein.At this moment high-pressure hydraulic pump is opened, high pressure water is pumped into mudcake by high pressure resistant water pipe 105 and filled by high-pressure hydraulic pump In the cavity 103 set, the water in cavity 103 sprays horn-like water column from multiple nozzles 106 on outer shroud tube body 102 again and rinses stake Mudcake on datum hole hole wall.Mudcake device is gone to rise as the concrete face in pile foundation hole rises when rinsing.Through removing mudcake device The mudcake and mud rinsed become the concrete face pushing tow that pile crown laitance layer is constantly risen and rise together.Continuously filled into conduit Note concrete stops concrete perfusion until when concrete face is risen at the elevation of design, closes high-pressure hydraulic pump immediately, stops spray Water removes the conduit of funnel and top.Start hoist engine, mudcake device will be gone to be promoted to outside pile foundation hole, construction terminates.
It describes according to the present utility model to remove mudcake device in an illustrative manner above with reference to attached drawing.But this field skill Art personnel should be appreciated that removes mudcake device for what above-mentioned the utility model was proposed, can also not depart from the utility model Various improvement are made on the basis of content.Therefore, the scope of protection of the utility model should be by appended claims Hold and determines.

Claims (5)

1. one kind removing mudcake device, which is characterized in that including interior tube body and the outer shroud tube body being arranged outside said inner tube body, institute Stating, there is a closed cavity, the cavity to be connect with high-pressure hydraulic pump by water pipe on outer shroud tube body, outside the outer shroud tube body Wall upper edge is circumferentially provided with multiple nozzles, and the multiple nozzle is connected to the cavity.
2. removing mudcake device as described in claim 1, which is characterized in that the outer shroud tube body passes through multigroup with said inner tube body Reinforcing rib group connects, and reinforcing rib group described in every group includes two symmetrically set reinforcing rib.
3. removing mudcake device as described in claim 1, which is characterized in that the multiple nozzle is set in qually spaced in the outer shroud On tube body and the nozzle is bore gradual increased horn-like nozzle from the inside to the outside.
4. removing mudcake device as described in claim 1, which is characterized in that be symmetrically arranged on the lateral surface of the outer shroud tube body There is multigroup hanging ring group, hanging ring group described in every group includes two symmetrically arranged hanging rings.
5. removing mudcake device as described in claim 1, which is characterized in that more water pipes are provided in the cavity, it is described more Circumferential spaced set of the root water pipe along the cavity.
CN201721831614.XU 2017-12-25 2017-12-25 Remove mudcake device Active CN207944455U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721831614.XU CN207944455U (en) 2017-12-25 2017-12-25 Remove mudcake device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721831614.XU CN207944455U (en) 2017-12-25 2017-12-25 Remove mudcake device

Publications (1)

Publication Number Publication Date
CN207944455U true CN207944455U (en) 2018-10-09

Family

ID=63704252

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721831614.XU Active CN207944455U (en) 2017-12-25 2017-12-25 Remove mudcake device

Country Status (1)

Country Link
CN (1) CN207944455U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108086322A (en) * 2017-12-25 2018-05-29 中冶交通建设集团有限公司 The method removed mudcake device and pouring pile bearing capacity is improved using the device
CN111734387A (en) * 2020-06-18 2020-10-02 浙江化工工程地质勘察院有限公司 Hydraulic pressure-induced plug drilling and water pressure test method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108086322A (en) * 2017-12-25 2018-05-29 中冶交通建设集团有限公司 The method removed mudcake device and pouring pile bearing capacity is improved using the device
CN108086322B (en) * 2017-12-25 2024-01-26 中冶交通建设集团有限公司 Mud skin removing device and method for improving bearing capacity of cast-in-place pile by using same
CN111734387A (en) * 2020-06-18 2020-10-02 浙江化工工程地质勘察院有限公司 Hydraulic pressure-induced plug drilling and water pressure test method

Similar Documents

Publication Publication Date Title
CN207079577U (en) Pile for prestressed pipe
CN102286970B (en) Whole process construction method of driven cast-in-place piles and special purpose device thereof
CN105220714B (en) Built-in anchor cable fills core compound prestress pile tube float Structure construction method
CN108978644A (en) Energy saving and environment friendly bored pile construction method
CN207944455U (en) Remove mudcake device
CN206143757U (en) It expands bored concrete pile stake pipe and pile driver to add elongated immersed tube rammer
CN108842758A (en) Rotary digging drilling hole bored concrete pile construction method
CN105464122A (en) Construction method for major-diameter hollow pile sinking foundation
CN111719568A (en) Anchor-spraying supporting method for man-cut pile retaining wall
CN103603337A (en) Grouting precast pile and grouting method
CN104314075A (en) Conical concrete pile tip, tubular pile provided with pile tip and production method of tubular pile
CN209339156U (en) The embedding rock foot pilework of anchor tube formula in a kind of Extra-Deep Foundation Pit
CN103911989A (en) Underwater pouring root type foundation with retaining wall and construction method thereof
CN107254872B (en) Prestressed pipe pile bottom floating and fixing sealing device and control method thereof
CN203782691U (en) Underwater pouring type pipe column provided with retaining wall and internal mold system thereof
CN112647495A (en) Construction method of prefabricated end-bearing tubular pile
CN106836215B (en) Inside and outside hydraulic pressure autobalance steel pile casting
CN105544551B (en) A kind of super-long filling pile quickly transfers the construction method of steel reinforcement cage
CN108086322B (en) Mud skin removing device and method for improving bearing capacity of cast-in-place pile by using same
CN114960715A (en) Underground engineering surge treatment device and control method
CN108360524A (en) One kind preventing superfilled device and its application method
CN109137924B (en) Structure for reducing pile length of deep soft soil layer by forming composite foundation and construction method
CN114232611A (en) Filling device and filling method for karst cave in pile hole
CN204326072U (en) A kind of anti-float anchor rod node
CN206233243U (en) After-teeming sizing device after a kind of stake holes

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant