CN207919773U - A kind of assembled toilet dash lead wall - Google Patents

A kind of assembled toilet dash lead wall Download PDF

Info

Publication number
CN207919773U
CN207919773U CN201721856440.2U CN201721856440U CN207919773U CN 207919773 U CN207919773 U CN 207919773U CN 201721856440 U CN201721856440 U CN 201721856440U CN 207919773 U CN207919773 U CN 207919773U
Authority
CN
China
Prior art keywords
wall
steel bar
reserved
ground
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721856440.2U
Other languages
Chinese (zh)
Inventor
李康
张西祥
何明东
侯国伟
李东雷
靳文奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ANGANG REAL ESTATE DEVELOPMENT (GROUP) Co Ltd
Original Assignee
ANGANG REAL ESTATE DEVELOPMENT (GROUP) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ANGANG REAL ESTATE DEVELOPMENT (GROUP) Co Ltd filed Critical ANGANG REAL ESTATE DEVELOPMENT (GROUP) Co Ltd
Priority to CN201721856440.2U priority Critical patent/CN207919773U/en
Application granted granted Critical
Publication of CN207919773U publication Critical patent/CN207919773U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model is related to a kind of assembled toilet dash lead walls, the water blocking is led wall and is arranged above the ground beam reinforced steel bar of toilet, it is prefabricated component that water blocking, which leads wall, wall including concreting, reserved wall steel bar and reserved assembling reinforcement are equipped in wall, reserved assembling reinforcement is stretched out from wall bottom surface, with ground beam reinforced steel bar banding fixed, wall bottom surface is equipped with waterproof groove, water-swellable adhesive tape is fixed in waterproof groove, casting concrete on the beam reinforced steel bar of ground makes wall form entirety with ground.The utility model can save traditional cast in place concrete form assembling and disassembling process, effectively accelerate speed of application, save the duration.Can be in workshop processing and fabricating, precision controlling is higher, and Forming Quality is preferable.Good water-proof effect, and water blocking leads being firmly combined between wall and concrete floor, good integrity.

Description

A kind of assembled toilet dash lead wall
Technical field
The utility model is related to toilet dash lead wall construction fields, are led more particularly, to a kind of assembled toilet water blocking Wall.
Background technology
When existing toilet drop plate construction, surrounding should pour concrete guide wall of the circle not less than C20,150mm high, often Rule construction technology is molded with bathroom floor primary concreting, and hoisting die construction is difficult in the construction process for this technique, technique It is cumbersome, be easy to walk, Forming Quality is poor.And general floorslab concrete design strength is higher than the intensity of concrete guide wall, once Property pouring molding causes waste of material to a certain extent.And during long-term use, water blocking is led between wall and floor Faying face be easy to seep water, cause the permeable mouldy and coating for wall surface of wall to peel off, seriously affect the use in house.
Invention content
Technical problem to be solved in the utility model be for existing toilet dash lead wall and concrete floor it Between faying face be easy infiltration, waterproof effect is bad, and construct when be not easy to formwork, water blocking is led between wall and concrete wall Combination not enough defect and deficiency securely, a kind of assembly concrete water blocking is provided and leads wall, solves wall between conventional sanitation The problem of being easy infiltration, good water-proof effect, and water blocking lead being firmly combined between wall and concrete floor, good integrity, just In construction.
To achieve the above object, the utility model is realized using following technical scheme:
A kind of assembled toilet dash lead wall, the water blocking are led wall and are arranged above the ground beam reinforced steel bar of toilet, It is prefabricated component that water blocking, which leads wall, includes the wall of concreting, reserved wall steel bar and reserved assembling reinforcement are equipped in wall, Reserved assembling reinforcement is stretched out from wall bottom surface, and with ground beam reinforced steel bar banding fixed, wall bottom surface is equipped with waterproof groove, and waterproof is recessed Fix water-swellable adhesive tape in slot, casting concrete on the beam reinforced steel bar of ground makes wall form entirety with ground.
The length that wall bottom surface is stretched out in the reserved assembling reinforcement is 180-230mm.
The water-swellable adhesive tape is fixed on the wall by fastening nail.
Compared with prior art, the utility model has the beneficial effects that:
1, assembled toilet dash lead wall can save traditional cast in place concrete form assembling and disassembling process, effectively accelerate to apply Work speed saves the duration.
2, assembled toilet dash lead wall can be in workshop processing and fabricating, and precision controlling is higher, and Forming Quality is preferable.
3, remaining concrete is made when assembled toilet dash lead wall can be using concrete work, avoids Concrete wastes.
4, the lifting of assembled toilet dash lead wall is convenient, can directly be lifted using live tower crane, convenient for construction.
5, assembled toilet dash lead wall good water-proof effect, and water blocking leads the jail of the combination between wall and concrete floor Gu good integrity.
Description of the drawings
Fig. 1 is the structural schematic diagram that water blocking leads wall.
Fig. 2 is the utility model construction schematic diagram.
In figure:Wall 1, wall steel bar 2, reserved assembling reinforcement 3, water-swellable adhesive tape 4, beam-slab template 5, ground beam slab steel Muscle 6, iron nail 7, steel wire 8, timber wedge 9.
Specific implementation mode
Specific embodiment of the present utility model is further illustrated below in conjunction with the accompanying drawings:
Such as Fig. 1-Fig. 2, a kind of assembled toilet dash lead wall, the water blocking leads wall and ground beam slab in toilet is arranged The top of reinforcing bar 6, it is prefabricated component that water blocking, which leads wall, includes the wall 1 of concreting, be equipped in wall 1 reserved wall steel bar 2 and Reserved assembling reinforcement 3 is reserved assembling reinforcement 3 and is stretched out from 1 bottom surface of wall, and the length that 1 bottom surface of wall is stretched out in reserved assembling reinforcement 3 is 180-230mm.The reserved assembling reinforcement 3 stretched out and 6 banding fixed of ground beam reinforced steel bar, 1 bottom surface of wall are equipped with waterproof groove, prevent It is followed closely by fastening in water groove and fixes water-swellable adhesive tape 4, casting concrete on ground beam reinforced steel bar 6 makes wall 1 be formed with ground It is whole.
Embodiment
A kind of assembled toilet dash lead wall, water blocking lead wall shop-fabricated, including C20 concretings wall 1, 20mm wide is reserved in high 150mm, 1 bottom surface of wall, and 15mm depth waterproof grooves, waterproof groove is interior to fix 20mm × 30mm chance water by steel nail Expand adhesive tape 4.
Reserved wall steel bar 2 and reserved assembling reinforcement 3 are equipped in wall 1, reserved assembling reinforcement 3 is stretched from 1 bottom surface of wall Go out, it is 200mm to reserve assembling reinforcement 3 to stretch out the length of 1 bottom surface of wall.Pre- guidance wall positioning is positioned on beam reinforced steel bar, in advance It stays assembling reinforcement 3 to be inserted into ground beam steel 6, binds reserved assembling reinforcement 3 and ground beam reinforced steel bar 6 after positioning, utilize Steel wire 8 makes 1 fixed position of wall, while steel wire 8 being fixed on beam-slab template 5 with iron nail 7, keeps wall position solid with timber wedge 9 It is fixed secured.It is poured together when pouring floorslab concrete, it is ensured that globality, and meet seepage resistance demand
Described above is only the basic principle of the utility model, is not imposed any restrictions to the utility model, every foundation The utility model carries out it equivalent variations and modification, within the scope of the art of this patent protection scheme.

Claims (3)

1. a kind of assembled toilet dash lead wall, which is characterized in that the water blocking leads wall and ground beam slab in toilet is arranged Above reinforcing bar, it is prefabricated component that water blocking, which leads wall, includes the wall of concreting, and wall is interior equipped with the wall steel bar reserved and reserved Assembling reinforcement is reserved assembling reinforcement and is stretched out from wall bottom surface, and with ground beam reinforced steel bar banding fixed, it is recessed that wall bottom surface is equipped with waterproof Slot, fixes water-swellable adhesive tape in waterproof groove, and casting concrete on the beam reinforced steel bar of ground makes wall form entirety with ground.
2. a kind of assembled toilet dash lead wall according to claim 1, which is characterized in that the reserved binding steel The length that muscle stretches out wall bottom surface is 180-230mm.
3. a kind of assembled toilet dash lead wall according to claim 1, which is characterized in that the water-swellable glue Item is fixed on the wall by fastening nail.
CN201721856440.2U 2017-12-27 2017-12-27 A kind of assembled toilet dash lead wall Active CN207919773U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721856440.2U CN207919773U (en) 2017-12-27 2017-12-27 A kind of assembled toilet dash lead wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721856440.2U CN207919773U (en) 2017-12-27 2017-12-27 A kind of assembled toilet dash lead wall

Publications (1)

Publication Number Publication Date
CN207919773U true CN207919773U (en) 2018-09-28

Family

ID=63608092

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721856440.2U Active CN207919773U (en) 2017-12-27 2017-12-27 A kind of assembled toilet dash lead wall

Country Status (1)

Country Link
CN (1) CN207919773U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109723186A (en) * 2019-01-05 2019-05-07 中国十七冶集团有限公司 A kind of prefabricated components of sealing reversed beam and the construction method of sealing reversed beam
CN110258602A (en) * 2019-06-27 2019-09-20 中铁第四勘察设计院集团有限公司 Prefabricated water-blocking bank segment, the construction method from wall discharge structure and from wall ditch
CN113529974A (en) * 2021-06-17 2021-10-22 中建一局集团建设发展有限公司 Embedded fastening bolt wall guide system and construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109723186A (en) * 2019-01-05 2019-05-07 中国十七冶集团有限公司 A kind of prefabricated components of sealing reversed beam and the construction method of sealing reversed beam
CN109723186B (en) * 2019-01-05 2020-11-24 中国十七冶集团有限公司 Prefabricated part of water-stop back beam and construction method of water-stop back beam
CN110258602A (en) * 2019-06-27 2019-09-20 中铁第四勘察设计院集团有限公司 Prefabricated water-blocking bank segment, the construction method from wall discharge structure and from wall ditch
CN113529974A (en) * 2021-06-17 2021-10-22 中建一局集团建设发展有限公司 Embedded fastening bolt wall guide system and construction method

Similar Documents

Publication Publication Date Title
CN207919773U (en) A kind of assembled toilet dash lead wall
CN108086582A (en) A kind of prefabricated assembled concrete wallboard for fabricated construction
CN205296388U (en) Apron is sealed to garage wall post -cast strip
CN110056190A (en) A kind of two-part slab thickness control sealing up screw
CN212896486U (en) Waterproof device for side edge of post-cast strip
CN210552011U (en) Take precast stair mould of concrete maintenance function
CN208168084U (en) A kind of plate end and plate side do not go out the bidirectional laminated slab bottom plate of muscle
CN1978819B (en) Poured-in-place concrete hollow board
CN206220057U (en) Open drain one-time-shaped mould
CN214195552U (en) Combined core mould
CN204098286U (en) A kind of washroom dash leads wall
CN1970933B (en) Cast-in-situ concrete hollow slab
CN102251612A (en) Reinforced concrete hollow floor slab and construction method thereof
CN1970939B (en) Cast-in-situ concrete hollow slab
CN101387146A (en) Concrete full built-in core mould
CN203004038U (en) Profiling reinforced concrete tool type roof board forming die
CN206360331U (en) One kind is exempted to be stripped building template
CN1975024B (en) Cast-in-place hollow slab
CN1978817B (en) Cast-in-situ concrete hollow slab
CN100999935B (en) Cast-in-situ concrete hollow board
CN100545390C (en) A kind of cast-in-place concrete cored
CN101196032B (en) Cast-in-situ concrete hollow slab
CN101196035B (en) Cast-in-situ concrete hollow slab
CN101196031B (en) Cast-in-situ concrete hollow slab
CN100999936A (en) Cast-in-situ concrete hollow board

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant