Aggregate water content automatic checkout system
Technical field
The utility model is related to monitoring fields when concrete production, and in particular to a kind of aggregate water content is automatic
Detecting system.
Background technology
Chinese patent disclose it is a kind of application No. is the sandstone aggregate of CN201410526241.X produce detection device, it wrap
Include the pan feeding belt set gradually from top to bottom, splicing turntable, pan feeding hopper, drier and screening plant, splicing turntable outside
Equipped with controller, screening plant side is equipped with meausring apparatus, and controller enters for sending out command signal, control splicing driven by rotary disc
Material hopper rotates together, and is turned to the underface of pan feeding belt discharge port, carries out splicing action, and drier is used for discharging
It is dried, screening plant is for sieving the material after drying.Although the detection device realizes concrete gravel aggregate
The moisture content of sandstone aggregate is detected during online production, but the shortcomings that detection device still has is:
Since splicing turntable is the aggregate for accepting the output of pan feeding belt output end, then in aggregate normally conveys, it can not
Realize the aggregate for taking pan feeding belt middle, therefore this detection can influence the normal conveying of aggregate.
Utility model content
The utility model will provide a kind of aggregate water content automatic checkout system, and solution in the prior art can be because only
The aggregate of pan feeding belt discharge end can be accepted and the aggregate in the middle part of conveyer belt is caused to cannot achieve the problem of taking.
To achieve the above object, the utility model uses the following technical solution:
A kind of aggregate water content automatic checkout system, including:
Take-off assembly comprising:Mounting bracket, two sliding rails, two mounting rods, the first spring, the first cylinder, pushing plate, shovel with
And installing mechanism, mounting bracket are stood on ground, and two sliding rails being mutually parallel are equipped on mounting bracket, are pacified on each sliding rail
The mounting rod that lower slider can be oriented in sliding rail equipped with one, two mounting rods are respectively positioned on vertical direction, are arranged between two mounting rods
There is a shovel, the feed inlet of shovel can be towards the conveyer belt of conveying aggregate, and end of the back-off from feed inlet is mounted on by installing mechanism
Between two mounting rods, and shovel can opposite two mounting rods rotate, elastic component is provided in installing mechanism so that shovel can keep into
End where material mouth tilts down state, and end face of the back-off from feed inlet is emerged when end where the feed inlet shoveled tilts down
Two mounting rods deviate from the face of conveyer belt, and the first cylinder from conveyer belt side, the first gas positioned at back-off are equipped on mounting bracket
The telescopic direction of cylinder is parallel with sliding rail, and the piston rod of the first cylinder is fixed with the pushing plate between shovel and the first cylinder, pushes away
Movable plate is located on vertical direction, when pushing plate is pressed on mounting rod end face of the back-off from feed inlet do not emerge two mounting rods the back of the body
Face from the conveyer belt and bottom plate shoveled at this time is located on horizontal plane, conveyer belt can be pushed under the promotion of the first cylinder by shovel
On, it is connected with the first spring between mounting rod and the first cylinder, can keep shovel close to the first cylinder under the first spring force;
Charge cask, underface when being located at shovel close to the first cylinder location, to accept the aggregate that shovel is put down;
Component is dried, is used to dry aggregate in charge cask;
Component is weighed, charge cask is supported, bone after the total weight and drying of aggregate and charge cask before being dried with measurement
The total weight of material and charge cask;And
Control circuit, the first cylinder and weighing component are connect with control circuit.
Preferably, installing mechanism includes mounting cylinder, two first wind springs and two first newels, and mounting cylinder is through shovel
Top, mounting cylinder both ends are inserted into mounting rod and can be rotated relative to mounting rod respectively, and the first wind spring is the elasticity of installing mechanism
Part, mounting cylinder both ends end face, which is recessed, forms a mounting hole, and the first center being inserted into mounting hole is equipped in mounting rod
Column, convolution has the first wind spring, the first wind spring inner end to be fixed with the first newel between the first newel and mounting cylinder, the first wind spring
Outer end is fixed with mounting cylinder inner wall.
Preferably, further include clamping assembly, clamping assembly include maintenance bar, bayonet lock, second spring, the first block piece,
Second block piece and the second cylinder are located between shovel and the first cylinder on mounting bracket and are provided with the first block piece and the second resistance
Block piece, the first block piece is fixed with mounting bracket and the first block piece is close to the first cylinder, and the first block piece is for stopping mounting rod
It is moved to the first cylinder, mounting rod side is provided with the second block piece in the first block piece, the second block piece is fixed to one
The piston rod of second cylinder, the second cylinder are mounted on mounting bracket, and the second block piece can stop installation under the driving of the second cylinder
Bar is moved to conveyer belt, can not also stop that mounting rod is moved to conveyer belt, the second cylinder is electrically connected to control circuit, two mounting rods
Between can stretch into a maintenance bar, telescopic hole is offered on the face of maintenance bar in a mounting rod, maintenance bar is close to telescopic hole
Face offers card hole, and a bayonet lock one end stretches in telescopic hole, and the bayonet lock other end is caught in after capable of stretching out telescopic hole to card hole, card
Pins position is fixed to second spring one end in the end in telescopic hole, and the second spring other end is fixed with telescopic hole inner wall, the second bullet
The telescopic direction of spring is parallel with bayonet lock, and bayonet lock is vertical with the prolonging direction of the first cylinder.
Preferably, charge cask includes:Vessel, opening-closing plate, two mounting bases, two rotating bars, two second wind springs with
And two second newels, vessel shape are rectangular parallelepiped structure, offer material-holding chamber in vessel, material-holding chamber is funnel
Shape is equipped with two mounting bases in vessel bottom, and being placed between two mounting bases has an opening-closing plate one end, opening-closing plate both sides point
It is not fixed with two rotating bars, each rotating bar can be rotationally inserted into a mounting base, and each rotating bar is located in mounting base
Sunken end face formed recessed groove, the second newel being inserted into recessed groove is installed in mounting base, in every 1 second
Equal convolution has the second wind spring, the second wind spring outer end and rotating bar inner wall, the second wind spring inner end and second between stem and rotating bar
Newel is fixed, and opening-closing plate can be kept to be located at the state of vertical direction under volume Two spring force;
The drivening piece one end between two mounting rods is fixed on face of the pushing plate close to conveyer belt, drivening piece is another
One end is fixed with voussoir, and mounting bracket does not hinder the movement of drivening piece, voussoir to extend to opening-closing plate, when shovel be located at vessel just on
Opening-closing plate is pressed on by voussoir on vessel bottom surface when square and opening-closing plate closes accommodating chamber.
Preferably, vessel bottom is equipped with stand, and stand bottom end is fixed on the supporting plate, and it includes weight to weigh component
Quantity sensor and installation shell, installation shell are positioned on ground, and weight sensor, support plate are equipped on installation shell
It is positioned on weight sensor, weight sensor is electrically connected to control circuit.
Preferably, the picking-up container being provided with below stand immediately below vessel, picking-up container do not hinder voussoir
Movement.
Preferably, drying component includes air-heater, air jet pipe and installation part, and air-heater is placed on by vessel,
The outlet end of air-heater is connected to an air jet pipe, air jet pipe is mounted on by an installation part on vessel, and air jet pipe goes out
Mouthful end is towards aggregate in vessel.
Preferably, vibrating motor is installed outside vessel, vibrating motor is connected to control circuit.
Compared with the prior art, the utility model has the advantages that:
When work, first, start the first cylinder, the piston rod of the first cylinder extend to shovel direction (when initial position,
In the piston rod retraction to the first cylinder of first cylinder, under the elastic force of the first spring so that mounting rod close to the first cylinder, and
End where the feed inlet shoveled at this time tilts down, and two mounting rods are emerged away from the face of conveyer belt in end face of the back-off from feed inlet),
Since the elasticity rate elastic component elastic force of the first spring is big, when pushing plate starts to contact with shovel, shovel starts opposite mounting rod and revolves
Turn, shovel rotate to shovel close to the first cylinder face and mounting rod close to the face of the first cylinder in one plane, pushing plate at this time
It is pressed on mounting rod, stops that shovel rotates to the first cylinder direction and shovels bottom surface in the horizontal plane, at the same time, pushing plate
Continuation is under the promotion of the first cylinder to conveyer belt when move, and promotion and mounting rod overcome the elastic force of the first spring to conveyer belt
Direction moves, and sliding rail is oriented to mounting rod and is moved upwards in the side vertical with conveyer belt direction of transfer, final shovel be pushed to
It transmits on belt surface, aggregate is entered in shovel;Then, the first cylinder bounces back, and retracts early period, the elasticity rate elastic component of the first spring
Elastic force is big, therefore pushing plate can be close to mounting rod so that the bottom surface of shovel keeps horizontal position, does not have aggregate at this time and falls
Between conveyer belt and charge cask, when close to the first cylinder position, since the elastic force of the first spring is not big enough, in elasticity
Pushing plate is mutually disengaged with mounting rod under the elastic force of part, and shovel has been positioned above charge cask at this time, as long as charge cask is enough
Big to accept the aggregate fallen in shovel, the final feed inlet that shovels reduces so that aggregate smoothly falls in charge cask, realizes
Feeding;After again, weigh component and measure gross mass m1 above it, m1 subtract container quality m2 be equal to it is dry before aggregate matter
Amount;After again, component operation is dried, aggregate is dried 10 minutes to 30 minutes;Finally, it weighs component measurement and obtains quadrate bone material thereon
Gross mass m3 after drying, control circuit internal controller calculate water content=(m1-m3)/(m3-m2).First in the above process
It solves the problems, such as that the aggregate in the middle part of conveyer belt cannot be taken out, avoid the normal transmission for interfering aggregate, movement is toppled over and shoveled to shovel
The first cylinder is used, reduces the use of power source, has saved the energy, be good for the environment.
Part is illustrated to embody by the further advantage, target and feature of the utility model by following, and part will also pass through
Research and practice to the utility model and be understood by the person skilled in the art.
Description of the drawings
Fig. 1 is the structural schematic diagram of aggregate water content automatic checkout system;
Fig. 2 is the A-A sectional views in Fig. 1;
Fig. 3 is enlarged drawing at D in Fig. 2;
Fig. 4 is the B-B sectional views in Fig. 1;
Fig. 5 is the C-C sectional views in Fig. 1.
Reference numeral is:Take-off assembly 1, mounting bracket 11, sliding rail 12, mounting rod 13, the first spring 14, the first cylinder 15,
Pushing plate 16, shovel 17, installing mechanism 18, charge cask 2, drying component 3, weigh component 4, mounting cylinder 181, the first wind spring 182,
First newel 183, clamping assembly 5, maintenance bar 51, bayonet lock 52, second spring 53, the first block piece 54, the second block piece 55,
Second cylinder 56, vessel 21, opening-closing plate 22, mounting base 23, rotating bar 24, drivening piece 25, voussoir 26, stand 27, support
Plate 28, weight sensor 41, installation shell 42, picking-up container 6, air jet pipe 31, installation part 32, vibrating motor 7, conveyer belt 10.
Specific implementation mode
In order to make, technological means of the utility model, creation characteristic, reached purpose and effect are more clear and are easy to
Understand, the utility model is further elaborated with reference to the accompanying drawings and detailed description:
As shown in Figure 1, the utility model proposes a kind of aggregate water content automatic checkout systems, including:
Take-off assembly 1 comprising:Mounting bracket 11, two sliding rails 12, two mounting rods 13, the first spring 14, the first cylinder 15,
Pushing plate 16, shovel 17 and installing mechanism 18, mounting bracket 11 are stood on ground, and two are equipped on mounting bracket 11 and is mutually parallel
Sliding rail 12, one is mounted on each sliding rail 12 can be oriented to the mounting rod 13 of lower slider, two mounting rods, 13 equal position in sliding rail 12
In on vertical direction, a shovel 17 is provided between two mounting rods 13, the feed inlet for shoveling 17 can be towards the conveyer belt of conveying aggregate
10, between shovel 17 is mounted on two mounting rods 13 away from the end of feed inlet by installing mechanism 18, and shoveling 17 can opposite two installation
Bar 13 rotates, and elastic component is provided in installing mechanism 18 so that it is ramp-like that shovel 17 can keep end where feed inlet to dip down
State, and end where shoveling 17 feed inlet when tilting down shovel 17 emerge two mounting rods 13 away from transmission away from the end face of feed inlet
With 10 face, the first cylinder 15 that 10 side of conveyer belt is deviated from positioned at shovel 17 is installed on mounting bracket 11, the first cylinder 15
Telescopic direction is parallel with sliding rail 12, and the piston rod of the first cylinder 15 is fixed with the pushing plate between shovel 17 and the first cylinder 15
16, pushing plate 16 is located on vertical direction, and 17 are shoveled when pushing plate 16 is pressed on mounting rod 13 and deviates from the end face of feed inlet not
Two mounting rods 13 of emerging deviate from the face of conveyer belt 10 and the bottom plate of shovel 17 is located on horizontal plane at this time, in the promotion of the first cylinder 15
Under shovel 17 can be pushed on conveyer belt 10, the first spring 14 is connected between mounting rod 13 and the first cylinder 15, first
Shovel 17 can be kept close to the first cylinder 15 under 14 elastic force of spring;
Charge cask 2, underface when being located at shovel 17 close to the first 15 position of cylinder, to accept the aggregates that shovel 17 is put down;
Component 3 is dried, is used to dry aggregate in charge cask 2;
Component 4 is weighed, charge cask 2 is supported, after measuring total weight and the drying of drying preceding aggregate and charge cask 2
The total weight of aggregate and charge cask 2;And
Control circuit, the first cylinder 15 and weighing component 4 are connect with control circuit.When work, first, start first
Cylinder 15, the piston rod of the first cylinder 15 extend to 17 directions of shovel (when initial position, the piston rod retraction of the first cylinder 15
To the first cylinder 15, under the elastic force of the first spring 14 so that mounting rod 13 close to the first cylinder 15, and at this time shovel 17 into
End where material mouth tilts down, and shovel 17 emerges two mounting rods 13 away from the face of conveyer belt 10 away from the end face of feed inlet), due to
The elasticity rate elastic component elastic force of first spring 14 is big, therefore when pushing plate 16 starts to contact with shovel 17, and shovel 17 starts opposite installation
Bar 13 rotates, and shovel 17 rotates to shovel 17 and put down at one close to the face of the first cylinder 15 close to the face of the first cylinder 15 and mounting rod 13
On face, pushing plate 16 is pressed on mounting rod 13, stops that shovel 17 rotates to 15 direction of the first cylinder and shovels 17 bottom surfaces at this time
In the horizontal plane, at the same time, the continuation of pushing plate 16 is under the promotion of the first cylinder 15 to conveyer belt 10 when move, promotion and
Mounting rod 13 overcomes the elastic force of the first spring 14 to be moved to 10 direction of conveyer belt, sliding rail 12 be oriented to mounting rod 13 with transmission
It is moved upwards with the vertical side of 10 direction of transfers, final shovel 17 is pushed to 10 surface of conveyer belt, and aggregate is entered in shovel 17;So
Afterwards, the first cylinder 15 bounces back, and retracts early period, the elastic force of the elasticity rate elastic component of the first spring 14 is big, therefore pushing plate 16 can
It is close to mounting rod 13 so that the bottom surface for shoveling 17 keeps horizontal position, does not have aggregate at this time and falls and holds in conveyer belt 10 and charging
Between device 2, when close to the first 15 position of cylinder, since the elastic force of the first spring 14 is not big enough, in the elastic force of elastic component
Lower pushing plate 16 is mutually disengaged with mounting rod 13, is shoveled 17 at this time and is had been positioned at 2 top of charge cask, as long as charge cask 2 is enough
Big to accept the aggregate fallen in shovel 17, final 17 feed inlets that shovel reduce so that and aggregate smoothly falls in charge cask 2,
Realize feeding;After again, weigh component 4 and measure gross mass m1 above it, m1 subtract container quality m2 be equal to it is dry before
The quality of aggregate;After again, drying component 3 works, and aggregate is dried 10 minutes to 30 minutes;Finally, the measurement of component 4 is weighed to obtain
Gross mass m3 after quadrate bone material drying thereon, control circuit internal controller calculate water content=(m1-m3)/(m3-m2).
As shown in Figure 1, Figure 2 and shown in 3, in order to which design structure is simple and installing mechanism 18 easy to use, installing mechanism 18
Including mounting cylinder 181, two first wind springs 182 and two first newels 183, mounting cylinder 181 is through the top of shovel 17, mounting cylinder
181 both ends are inserted into mounting rod 13 and can be rotated relative to mounting rod 13 respectively, and the first wind spring 182 is the elasticity of installing mechanism 18
Part, 181 both ends end face of mounting cylinder, which is recessed, forms a mounting hole, and first be inserted into mounting hole is equipped in mounting rod 13
Newel 183, convolution has the first wind spring 182,182 inner end of the first wind spring and first between the first newel 183 and mounting cylinder 181
Newel 183 is fixed, and 182 outer end of the first wind spring is fixed with 181 inner wall of mounting cylinder.When positioned at original state, in the first wind spring
Under 182 elastic force so that shovel 17 be maintained at close to 15 side of the first cylinder leak out mounting rod 13 states so that when pushing plate 16 with
It can all pour aggregate after being detached from;When being squeezed by pushing plate 16 so that the first wind spring 182 deforms upon.
As shown in figure 5, in order to avoid causing to lead when the first cylinder 15 bounces back because of the elastic force of the first spring 14 deficiency
Pushing plate 16 is caused to be detached from mounting rod 13, and then avoid result in causes aggregate to be inclined due to shoveling 17 and not reaching above charge cask 2
Pour out, the aggregate water content automatic checkout system further includes clamping assembly 5, clamping assembly 5 include maintenance bar 51,
Bayonet lock 52, second spring 53, the first block piece 54, the second block piece 55 and the second cylinder 56 are located at shovel on mounting bracket 11
17 and first are provided with the first block piece 54 and the second block piece 55 between cylinder 15, and the first block piece 54 is fixed with mounting bracket 11
And first block piece 54 close to the first cylinder 15, the first block piece 54 for stopping that mounting rod 13 is moved to the first cylinder 15,
First block piece 54 is provided with the second block piece 55 close to 13 side of mounting rod, and the second block piece 55 is fixed to one second cylinder 56
Piston rod, the second cylinder 56 be mounted on mounting bracket 11 on, the second cylinder 56 driving under the second block piece 55 can stop installation
Bar 13 is moved to conveyer belt 10, can not also stop that mounting rod 13 is moved to conveyer belt 10, and the second cylinder 56 is electrically connected to control electricity
Road can stretch into a maintenance bar 51 between two mounting rods 13, telescopic hole is offered on the face of maintenance bar 51 in a mounting rod 13,
Maintenance bar 51 offers card hole close to the face of telescopic hole, and 52 one end of a bayonet lock stretches in telescopic hole, and 52 other end of bayonet lock can be stretched
It is caught in card hole after going out telescopic hole, bayonet lock 52 is located at the end in telescopic hole and is fixed to 53 one end of second spring, second spring
53 other ends are fixed with telescopic hole inner wall, and the telescopic direction of second spring 53 is parallel with bayonet lock 52, bayonet lock 52 and the first cylinder 15
Prolonging direction it is vertical.When original state, the second cylinder 56 elongation so that mounting rod 13 is stuck in the resistance of the first block piece 54 and second
Between block piece 55, when the first cylinder 15 reaches shovel 17, maintenance bar 51 stretches between two mounting rods 13 first, and bayonet lock 52 is close to solid
The end of position bar 51 is hemispherical, squeezes bayonet lock 52 after enabling to maintenance bar 51 to reach bayonet lock 52 so that 52 retraction of bayonet lock is extremely
In telescopic hole, second spring 53 is compressed, and final bayonet lock 52 stretches in card hole, and then the second block piece 55 is by the second cylinder 56
It retracts so that the second block piece 55 cannot stop the movement of mounting rod 13, and bayonet lock 52 is avoided to cross card hole, thus can be swimmingly
It pushes mounting rod 13 to move, the shovel 17 when the first cylinder 15 is retracted is avoided to cause aggregate to be lost without reaching above charge cask 2
Leakage so that working environment is beautiful.When mounting rod 13 is drawn back into the first block piece 54 and the second block piece 55, the second cylinder 56
Elongation is so that mounting rod 13 is stuck between the first block piece 54 and the second block piece 55, and pushing plate 16 continues to move at this time,
Under the barrier effect of first block piece 54, mounting rod 13 is not in movement, and maintenance bar 51 is moved relative to bayonet lock 52, and bayonet lock 52 skids off card
Hole, final bayonet lock 52 are detached from maintenance bar 51, and the feed inlet of shovel 17 is also rotated down at this time so that aggregate, which is dumped into charging, to be held
In device 2.
As shown in Fig. 1 and Fig. 4, in order to realize the automatic shutter of charge cask 2, and saves 2 opening and closing of charge cask and drive
Dynamic equipment, and realize and its interior aggregate all can be poured out automatically in feeding fashionable dress material container 2, when improving measurement next time
Accuracy, charge cask 2 includes:Vessel 21, opening-closing plate 22, two mounting bases 23, two rotating bars 24, two second wind springs with
And two second newels, 21 shape of vessel are rectangular parallelepiped structure, and material-holding chamber is offered in vessel 21, material-holding chamber is leakage
Bucket shape is equipped with two mounting bases 23 in 21 bottom of vessel, and being placed between two mounting bases 23 has 22 one end of an opening-closing plate, opens
22 both sides of closing plate are respectively fixed with two rotating bars 24, and each rotating bar 24 can be rotationally inserted into a mounting base 23, each
Rotating bar 24 is located at the sunken end face in mounting base 23 and forms recessed groove, is equipped with and is inserted into recessed groove in mounting base 23
Second newel, equal convolution has the second wind spring, the second wind spring outer end and rotation between every 1 second newel and rotating bar 24
24 inner wall of bar, the second wind spring inner end are fixed with the second newel, opening-closing plate 22 can be kept to be located under volume Two spring force vertical
The state in direction;
25 one end of drivening piece between two mounting rods 13 is fixed on the face of conveyer belt 10 in pushing plate 16,
25 other end of drivening piece is fixed with voussoir 26, and mounting bracket 11 does not hinder the movement of drivening piece 25, voussoir 26 to extend to opening-closing plate 22,
When shoveling 17 and being located at 21 surface of vessel, opening-closing plate 22 is pressed on by voussoir 26 on 21 bottom surface of vessel and opening-closing plate 22
Close accommodating chamber.When the initial position has been assumed, voussoir 26 is located at the underface of opening-closing plate 22, under the action of voussoir 26 so that
Opening-closing plate 22 is close to vessel 21, and vessel 21 is closed, and at this time it is ensured that accepting the aggregate slided in shovel 17, also can
Aggregate will not leak out vessel 21 when ensureing dry;When needing to take new aggregate, the first cylinder 15 elongation so that voussoir
26 far from opening-closing plate 22, under the elastic force of the second wind spring so that and opening-closing plate 22 rotates down, when shoveling 17 arrival conveyer belt 10,
Opening-closing plate 22 remains in the state on vertical direction under the elastic force of the second wind spring, and aggregate is under gravity automatically from vessel
It is skidded off in 21;Voussoir 26 is corner block shape away from the end of conveyer belt 10, when the first cylinder 15 bounces back so that voussoir 26 can
Smoothly it is located at 22 lower section of opening-closing plate so that opening-closing plate 22 can be raised to the position on horizontal plane, realize opening-closing plate
22 opening and closing.
As shown in Figure 1, in order to which design structure is simple and weighing component 4 easy to use, 21 bottom of vessel is equipped with
Stand 27,27 bottom end of stand are fixed in support plate 28, and it includes weight sensor 41 and installation shell 42, peace to weigh component 4
Dress shell 42 is positioned on ground, and weight sensor 41 is equipped on installation shell 42, and support plate 28 is positioned over weight sensing
On device 41, weight sensor 41 is electrically connected to control circuit.M2 is equal to 28 mass of support plate+27 mass of stand+charge cask, 2 matter
Amount.
As shown in Figure 1, in order to avoid the aggregate poured out of vessel 21 pollutes working environment, under stand 27
Side is provided with the picking-up container 6 immediately below vessel 21, picking-up container 6 to there is enough distances between vessel 21, with
So that picking-up container 6 does not hinder the movement of voussoir 26.
As shown in Figure 1, in order to which design structure is simple and drying component 3 easy to use, drying component 3 include air-heater,
Air jet pipe 31 and installation part 32, air-heater are placed on by vessel 21, and the outlet end of air-heater is connected to an air jet pipe 31,
Air jet pipe 31 is mounted on by an installation part 32 on vessel 21, and the outlet end of air jet pipe 31 is towards 21 in-seam of vessel
Material.
As shown in Figure 1, in order to avoid aggregate is deposited in couples in vessel 21 and causes drying effect uneven,
Vibrating motor 7 is installed outside vessel 21, vibrating motor 7 is connected to control circuit.Vibrating motor 7 is so that vessel 21 exists
It is vibrated when drying, to shake up aggregate in vessel 21, improves the effect of drying.
Finally illustrate, above example is merely intended for describing the technical solutions of the present application, but not for limiting the present application, although ginseng
The utility model is described in detail according to preferred embodiment, it will be understood by those of ordinary skill in the art that, it can be to this
The technical solution of utility model is modified or replaced equivalently, without departing from the objective and model of technical solutions of the utility model
It encloses, should all cover in the right of the utility model.