CN207865031U CN201820240398.XU CN201820240398U CN207865031U CN 207865031 U CN207865031 U CN 207865031U CN 201820240398 U CN201820240398 U CN 201820240398U CN 207865031 U CN207865031 U CN 207865031U
Authority
CN
China
Prior art keywords
gasification
tank body
outlet
lng
air supply
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201820240398.XU
Other languages
Chinese (zh)
Inventor
陈来生
张培培
樊杰
周小翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China International Marine Containers Group Co Ltd
CIMC Enric Investment Holdings Shenzhen Co Ltd
Nantong CIMC Energy Equipment Co Ltd
Original Assignee
China International Marine Containers Group Co Ltd
CIMC Enric Investment Holdings Shenzhen Co Ltd
Nantong CIMC Energy Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China International Marine Containers Group Co Ltd, CIMC Enric Investment Holdings Shenzhen Co Ltd, Nantong CIMC Energy Equipment Co Ltd filed Critical China International Marine Containers Group Co Ltd
Priority to CN201820240398.XU priority Critical patent/CN207865031U/en
Application granted granted Critical
Publication of CN207865031U publication Critical patent/CN207865031U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Filling Or Discharging Of Gas Storage Vessels (AREA)

Abstract

The utility model provides a kind of LNG fuel air supply system peculiar to vessel, including fuel tank case and gasification pry regulator;Fuel tank case includes the frame of tank body and support tank body;The pry regulator that gasifies includes skid, and the gasification installation and surge tank being installed in skid;The gasification tunnel for being equipped with the cooling duct for the host recirculated water flowing of ship in gasification installation and gasifying for LNG absorption host recirculated water heats;Gasification installation is equipped with inlet, gas outlet and supercharging gas port, the inlet of gasification installation is connected with the liquid outlet of tank body, the supercharging gas port of gasification installation is connected with the gas returning port of tank body, and the buffered tank in gas outlet of gasification installation provides gaseous fuel to the host of ship.The utility model fuel tank case is replaceable, and fuel adding is convenient;LNG gasification is carried out using ship self energy, reduces extra power consumption, while gasification also avoids the pollution to external environment, carrying out tank body using gasification natural gas increases supercharging, and system operation is more stable.

Description

LNG fuel air supply system peculiar to vessel
Technical field
The utility model is related to the fuel of LNG powered ships to supply field, more particularly to a kind of LNG fuel gas supply peculiar to vessel system System.
Background technology
The ship using LNG as fuels and energy is generally fixedly mounted on using c-type fuel tank on ship at present, when need into When row LNG fuel addings, harbour is filled or by the progress fuel adding of LNG filling landing stage by being accommodated to special LNG.
The pattern that LNG powered ship fuel addings are relatively good is carried out using LNG filling landing stage, but since LNG fills ship Cost of investment it is very high, LNG powered ships put into operation after quantity reaches a certain amount of only in navigation area, can just consider to build Fill ship.At present build up put into operation LNG filling landing stage it is considerably less, the fuel adding of LNG powered ships mainly or use former Mode, i.e. powered ship are accommodated to harbour and are filled from fuel tank of the bank base filling station on ship.But powered ship makes moist Rise, the influence of lakie, can not often determine and berth, and LNG conveyance conduits should not extend and stretch, bank base filling station adds to ship Gas is there are larger difficulty, and it is long to there is the filling time, the disadvantage more than security risk, cause the large-scale applications of LNG Power Vessels by It is serious to restrict.
To solve the above problems, there is scheme, as fuel tank, combustion to be provided for LNG powered ships using tank container at present Material, but there are itself to run consumed resource is higher, environmental pollution hidden danger is excessive etc. for existing fuel tank case air supply system Disadvantage causes LNG fuel tank case to fail to use on a large scale.
Utility model content
Based on above-mentioned background, the utility model provides a kind of LNG fuel air supply system peculiar to vessel based on fuel tank case, solves Fuel tank case air supply system self-operating consumes the problem that resource is high, environmental pollution hidden danger is big in the prior art.
In order to solve the above technical problems, the utility model adopts the following technical solution:A kind of LNG fuel gas supply peculiar to vessel system System, including fuel tank case and gasification pry regulator;Fuel tank case includes the tank body for containing LNG and the frame for supporting the tank body Frame;The pry regulator that gasifies includes skid, and the gasification installation and surge tank being installed in skid;It is equipped with and supplies in the gasification installation The cooling duct of the host recirculated water flowing of ship and the gasification tunnel to gasify for LNG absorption host recirculated water heats;Phase Cooling duct described in Ying Yu, the gasification installation are equipped with the inlet and outlet for access host circulation;Phase Gasification tunnel described in Ying Yu, gasification installation are equipped with inlet, gas outlet and supercharging gas port, the import of inlet and gasification tunnel It communicates, gas outlet is connected to the outlet of gasification tunnel with supercharging gas port;The inlet of the gasification installation goes out with the tank body Liquid mouth is connected, and the supercharging gas port of the gasification installation is connected with the gas returning port of the tank body, the outlet of the gasification installation Mouth is connected with the import of the surge tank, and the outlet of the surge tank is for connecting the host of ship to provide gaseous fuel.
More preferably, the air supply system further includes filling sled;The sled that fills is installed close to the fuel tank case;It is described to fill Dress sled includes filling frame and integrated installation in filling infusion pipeline and the first return line in frame;The woven hose It is connected by pipeline between the import on road and the liquid outlet of the tank body, the outlet of the infusion pipeline and the gasification installation Inlet between be connected by pipeline;Between the import of first return line and the supercharging gas port of the gasification installation It is connected by pipeline, the outlet of first return line is connected between the gas returning port of the tank body by pipeline.
More preferably, the sled that fills further includes charging line and the second return line;The outlet of the charging line and institute The inlet for stating tank body is connected by pipeline, and the import of the charging line is for connecting external filing provision;Described second The import of return line is connected with the gas returning port of the tank body by pipeline, and the outlet of second return line is for connecting External filing provision.
More preferably, each connecting pipe filled between sled and the tank body is used by stainless steel tube and metal hose The combined pipe of composition.
More preferably, each connecting pipe filled between sled and the gasification installation is stainless steel pipes, and stainless steel Pipeline outer wrapping flexibility cold insulation material.
More preferably, the bottom for filling frame and the bottom of the skid are equipped with insulating pad.
More preferably, the installation site of the gasification installation is less than the fuel tank case, and the gas outlet of the gasification installation is low In the liquid outlet of the tank body.
More preferably, the tank body has bottom outlet tube, and bottom outlet tube is double-wall pipe, including inner tube and is surrounded on outside inner tube Outer tube, inner tube are connected to the tank interior, and airtight cavity is formed between outer tube and inner tube.
More preferably, nitrogen is filled in the airtight cavity, the double-wall pipe is also associated with detection device, the detection dress It sets and is connected to the airtight cavity to detect whether said inner tube leaks.
More preferably, the outer tube is equipped with detection hole;The detection device includes sampling line, pressure transmitter and flammable Gas analyzer, the sampling line are installed at the detection hole, and are connected to the airtight cavity to the pressure transmitter With analysis of combustible gases instrument.
As shown from the above technical solution, the utility model has the following advantages that and good effect:The utility model it is peculiar to vessel LNG fuel air supply systems store LNG using fuel tank case, and LNG is used as marine main engine fuel after gasification, required supplementation with When LNG fuel, by the fuel tank case more renewed, old fuel tank case can be hoisted to be filled on the bank, fuel adding It is more convenient, it is filled in ship without being limited to.Wherein, gasification installation is connected to ship using inlet and outlet Host circulation, by gasification installation string access host circulation, directly providing heat using host recirculated water makes LNG gasification is recycled using ship itself clear energy sources, promotes the utilization rate of resource, reduces extra power consumption;LNG gas Change process avoids in LNG impurity component loss from being discharged into external environment with intermediate medium and causes dirt to environment not by intermediate medium Dye, reduces environmental pollution danger factors, good environmental protection.Meanwhile a part of gases of the LNG after gasification installation gasifies is through increasing Mouth of calming the anger is transmitted back to fuel tank case, is pressurized to tank body, promotes LNG stream speed, ensures the pumping rate when operation of fuel tank case, Conducive to the even running of air supply system, marine main engine fuel security of supply is improved;Tank body, from supercharging equipment, simplifies without setting Fuel tank box structure is convenient for the dismounting and transport of fuel tank case.Fuel tank case and gasification pry regulator are integrated module knot Structure, the arrangement installation on ship are more convenient.
Description of the drawings
Fig. 1 is the structural schematic diagram of the utility model LNG fuel air supply system preferred embodiment peculiar to vessel.
Fig. 2 is arrangement schematic diagram of the utility model LNG fuel air supply system preferred embodiment peculiar to vessel on ship.
Fig. 3 is the structural schematic diagram of tank body outlet tube in the utility model LNG fuel air supply system preferred embodiment peculiar to vessel.
The reference numerals are as follows:10, air supply system;1, fuel tank case;11, tank body;111, outlet tube;1111, inner tube; 1112, outer tube;115, detection device;1151, sampling line;1152, pressure transmitter;1153, pressure needle valve;1154, it follows Ring gas needle valve;12, frame;121, corner fittings;2, gasify pry regulator;21, skid;22, gasification installation;221, water inlet; 222, water outlet;23, surge tank;3, sled is filled;34, installation frame;35, pipeline valve member;301, connecting pipe;302, connecting tube Road;303, cold insulation material;50, ship;501, host;502, open deck;503, flat;505, water circulating pump;506、 Insulating pad.
Specific implementation mode
Embodying the exemplary embodiment of the utility model features and advantages will describe in detail in the following description.It should be understood that To be the utility model can have various variations in different embodiments, all do not depart from the model of the utility model It encloses, and the descriptions and illustrations are essentially for illustration purposes, rather than to limit the utility model.
Include mainly fuel tank case 1, gasify and adjust with Fig. 2, the LNG fuel air supply system peculiar to vessel 10 of the present embodiment refering to fig. 1 Pressure prizes 2 and fills sled 3.Fuel tank case 1 is replaceable tank container structure, interior to contain LNG fuel.Gasify pry regulator 2 The heat provided using the host recirculated water of ship 50 makes LNG gasification, and the natural gas after gasification is adjusted to suitable pressure The host 501 for being conveyed to ship 50 is used as fuel, to provide ship 50 power.3 integrated pipeline valve member equipment of sled are filled, The communicating passage that fuel tank case 1 is established between the pry regulator 2 that gasifies, and replaced convenient for the installation of fuel tank case 1.
Specifically, fuel tank case 1 includes for containing the tank body 11 of LNG and supporting the frame 12 of tank body 11.Utilize frame Corner fittings 121 on 12, the lifting and the locking on ship 50 that can be convenient for fuel tank case 1, realizes quickly tearing open for fuel tank case 1 It unloads, install, while also ensureing stability of the fuel tank case 1 on ship 50.
Tank body 11 is equipped with the inlet tube and outlet tube that are communicated with its internal liquid phase space, and with its internal gas-phase space The muffler communicated.Inlet tube, outlet tube and muffler are located at the corresponding feed liquor for constituting tank body 11 respectively of the nozzle outside tank body 11 Mouth, liquid outlet and gas returning port.
Refering to Fig. 3, in the present embodiment, outlet tube 111 is bottom outlet tube, i.e. outlet tube 111 goes out liquid from 11 bottom of tank body, goes out Liquid pipe 111 uses double-wall pipe structure, including inner tube 1111 and the outer tube 1112 that is surrounded on outside inner tube 1111.Inner tube 1111 and tank body 11 inside connections, airtight cavity is formed between outer tube 1112 and inner tube 1111.Such as there are LNG leak cases, LNG is first leaked to close It seals in cavity, shields the situation that cryogenic liquid is leaking directly on hull and occur, prevent Ship Structure by Cold water stress.Using this Double-wall pipe structure can exempt the airtight ice chest of fuel tank case 1, simplify 1 valve box structure of fuel tank case, meet 1 water of fuel tank case Lu Lianyun requirements.
Further, nitrogen, nitrogen pressure substantially 0.5bar~1bar are filled in airtight cavity.It is set on outer tube 1112 There are one or multiple detection holes, and by detection hole connecting detection device 115, detection device 115 is connected to airtight cavity to examine Inner tube 1111 is surveyed with the presence or absence of leakage, lifting system safety.
More preferably, detection device 115 includes sampling line 1151, pressure transmitter 1152 and analysis of combustible gases instrument (figure In be not shown), sampling line 1151 is welded at detection hole, connection airtight cavity to pressure transmitter 1152 and fuel gas point Analyzer.Pressure needle valve 1153 and recyclegas needle valve 1154 are set on sampling line 1151, to realize pressure detecting respectively Sampling and analysis of combustible gases sampling, pressure transmitter 1152 are installed on 1151 end of sampling line, monitor airtight cavity in real time Interior pressure change, analysis of combustible gases instrument tests and analyzes in due course whether there is fuel gas in sample gas.
Refering to fig. 1 and Fig. 2, gasification pry regulator 2 include skid 21, gasification installation 22, surge tank 23, voltage-regulating system (in figure Non- label) and structures such as necessary pipe-line system (non-label in figure), each structure assembly be installed in skid 21 formed it is whole Module, convenient for the installation on hull.
Cooling duct and gasification tunnel are equipped in gasification installation 22, host recirculated water flows in cooling duct, to entrance LNG in gasification tunnel provides heat, makes LNG gasification.Meanwhile host recirculated water is also cooled down, and is conveyed to master after processing Machine 501 cools down host 501, promotes the utilization rate of resource, reduces energy expenditure.
Corresponding to cooling duct, water inlet 221 and water outlet 222 are respectively equipped on gasification installation 22;Water inlet 221 is arranged In the lower part of 22 shell of gasification installation, the outlet for connecting host recirculated water;Water outlet 222 is set to 22 shell of gasification installation Top, for connecting host circulating water intake.More preferably, water inlet 221 and water outlet 222 are all made of flange arrangement, are convenient for Pass through pipeline access host circulation.The mobilization dynamic of host recirculated water is provided by water circulating pump 505.
Corresponding to gasification tunnel, gasification installation 22 is equipped with inlet, gas outlet and supercharging gas port.Inlet is logical with gasification The import in road communicates, and gas outlet is connected to the outlet of gasification tunnel with supercharging gas port.
Natural gas after the caching gasification of surge tank 23, import are connected with the gas outlet of gasification installation 22, and outlet is logical Piping is connected to the host 501 of ship 50, to provide fuel gas to the host 501 of ship 50.Voltage-regulating system is set to slow It rushes on tank 23 to the pipeline of 50 host 501 of ship, natural gas is adjusted to by suitable pressure by pressure regulator.
Referring still to Fig. 1 and Fig. 2, it includes installation frame 34 to fill sled 3, and the pipeline valve being integrated in installation frame 34 Part 35.Wherein, each pipeline includes infusion pipeline, filling pipeline, the first return line, second return line etc..Root on each pipeline According to needing that corresponding valve member is arranged.
Infusion pipeline and the first return line match, and establish the interface channel between fuel tank case 1 and gasification installation 22, Improve LNG gasification efficiency.
Wherein, infusion pipeline is by the LNG in fuel tank case 1 to be delivered to gasification installation 22, the import of infusion pipeline with The liquid outlet of tank body 11 is connected by pipeline and is connected, and the outlet of infusion pipeline passes through pipeline with the inlet of gasification installation 22 It connects and is connected.
First return line to by gasification after the defeated batch can case 1 that strile-backs of natural gas, to tank body 11 be pressurized, to improve tank Body 11 goes out liquid speed degree, promotes LNG gasification efficiency.The import of first return line passes through pipe with the supercharging gas port of gasification installation 22 Road connects and is connected, and the outlet of the first return line is connected by connection by pipeline with the gas returning port of tank body 11.
Filling pipeline and the second return line match, and the connection established between fuel tank case 1 and external filing provision is logical Road.The outside filing provision can be filling landing stage or bank base filling station, meet the filling item of external filing provision in ship 50 When part, directly fuel tank case 1 can be filled by filling pipeline and the external filing provision of the second return line connection.
Wherein, it fills by the outlet of pipeline is connect with the inlet of tank body 11 by pipeline and is connected, the second return line Import be connected by connect by pipeline with the gas returning port of tank body 11.When being filled to tank body 11, external filing provision LNG enter in tank body 11 through filling pipeline, the second return line makes real between 11 gas-phase space of tank body and external filing provision Existing pressure balance ensures filling rate.
The air supply system 10 of the present embodiment is on ship 50 in use, fuel tank case 1 is installed on ship 50 with sled 3 is filled On open deck 502, fill sled 3 close to fuel tank case 1 install, fuel tank case 1 can be arranged it is multiple, respectively with fill sled 3 phase Pipeline is answered to form connection.Gasification pry regulator 2 is installed on the flat 503 inside ship 50, and installation site is less than fuel tank Enough liquid level height difference is formed between case 1, with fuel tank case 1, the gas outlet of gasification installation 22 is less than the liquid outlet of tank body 11, protects The pumping rate for having demonstrate,proved tank body 11 when fuel tank case 1 is run, is conducive to the even running of gasification installation 22.
Fuel tank case 1 is locked by container angle lock with open deck 502.Fill sled 3 34 bottom of installation frame with And 21 bottom of skid of gasification pry regulator 2 is respectively provided with insulating pad 506, insulating pad 506 is installed on the correspondence deck of ship 50 On, transmission of the cold to 50 deck of ship is completely cut off by insulating pad 506, prevents leakage from damaging Ship Structure.
In the air supply system 10 of the present embodiment, fuel tank case 1, gasification pry regulator 2 and to fill sled 3 be integrated module Structure is respectively arranged after on ship 50, then each modular structure is connected into total system using corresponding connecting pipe, It is easy for construction.Fuel tank case 1, the pry regulator 2 that gasifies and each connecting pipe filled between sled 3 use flange docking structure, connection Simplicity installs flinger ring on each flange, prevents liquid splash.
Fill between sled 3 and gasification pry regulator 2 connecting pipe 302 (i.e. infusion pipeline and 22 inlet of gasification installation it Between pipeline and the first return line and gasification installation 22 be pressurized the pipeline between gas port) pass through the open deck of ship 50 502, stainless steel pipes can be used in each connecting pipe 302, and outer layer covers flexibility cold insulation material 303 prevents pipeline subcooled liquid from damaging Hinder hull.
Each connecting pipe 301 between sled 3 and tank body 11 is filled using the combination being made of stainless steel tube and metal hose Pipeline so that can misplace and dock between the inlet of tank body 11, liquid outlet, gas returning port and the respective line for filling sled 3, be convenient for After refuelling tank case 1 with fill sled 3 connection.
Although describing the utility model with reference to several exemplary embodiments, it is to be understood that, term used is to say Term bright and exemplary, and not restrictive.Since the utility model can in a variety of forms be embodied without departing from practicality Novel spirit or essence, it should therefore be appreciated that the above embodiment is not limited to any details above-mentioned, and should be in accompanying right Widely explained in spirit and scope defined by it is required that, thus fall into whole variations in claim or its equivalent scope and Remodeling all should be appended claims and be covered.

Claims (10)

1. a kind of LNG fuel air supply system peculiar to vessel, which is characterized in that including:
Fuel tank case includes the tank body for containing LNG and the frame for supporting the tank body;
Gasify pry regulator, including skid, and the gasification installation and surge tank being installed in skid;It is equipped in the gasification installation The cooling duct flowed for the host recirculated water of ship and the gasification tunnel to gasify for LNG absorption host recirculated water heats; Corresponding to the cooling duct, the gasification installation is equipped with the inlet and outlet for access host circulation; Corresponding to the gasification tunnel, gasification installation is equipped with inlet, gas outlet and supercharging gas port, inlet and gasification tunnel into Mouth communicates, and gas outlet is connected to the outlet of gasification tunnel with supercharging gas port;
The inlet of the gasification installation is connected with the liquid outlet of the tank body, the supercharging gas port of the gasification installation with it is described The gas returning port of tank body is connected, and the gas outlet of the gasification installation is connected with the import of the surge tank, the surge tank Outlet is for connecting the host of ship to provide gaseous fuel.
2. LNG fuel air supply system peculiar to vessel according to claim 1, which is characterized in that the air supply system further includes filling Dress sled;The sled that fills is installed close to the fuel tank case;
The sled that fills includes filling frame and integrated installation in filling infusion pipeline and the first return line in frame;
It is connected by pipeline between the import of the infusion pipeline and the liquid outlet of the tank body, the outlet of the infusion pipeline It is connected by pipeline between the inlet of the gasification installation;
It is connected by pipeline between the import of first return line and the supercharging gas port of the gasification installation, described first The outlet of return line is connected between the gas returning port of the tank body by pipeline.
3. LNG fuel air supply system peculiar to vessel according to claim 2, which is characterized in that the sled that fills further includes filling Pipeline and the second return line;
The outlet of the charging line is connected with the inlet of the tank body by pipeline, and the import of the charging line is used for The external filing provision of connection;
The import of second return line is connected with the gas returning port of the tank body by pipeline, second return line Outlet is for connecting external filing provision.
4. LNG fuel air supply system peculiar to vessel according to claim 3, which is characterized in that described to fill sled and the tank body Between each connecting pipe use the combined pipe that is made of stainless steel tube and metal hose.
5. LNG fuel air supply system peculiar to vessel according to claim 2, which is characterized in that described to fill sled and the gasification Each connecting pipe between device is stainless steel pipes, and stainless steel pipes outer wrapping flexibility cold insulation material.
6. LNG fuel air supply system peculiar to vessel according to claim 2, the bottom for filling frame and the skid Bottom is equipped with insulating pad.
7. LNG fuel air supply system peculiar to vessel according to claim 1, which is characterized in that the installation position of the gasification installation It sets low in the fuel tank case, the gas outlet of the gasification installation is less than the liquid outlet of the tank body.
8. LNG fuel air supply system peculiar to vessel according to claim 1, which is characterized in that the tank body has bottom outlet tube, Bottom outlet tube is double-wall pipe, including inner tube and the outer tube that is surrounded on outside inner tube, inner tube are connected to the tank interior, outer tube with it is interior Airtight cavity is formed between pipe.
9. LNG fuel air supply system peculiar to vessel according to claim 8, which is characterized in that be filled in the airtight cavity Nitrogen, the double-wall pipe are also associated with detection device, and the detection device is connected to the airtight cavity to detect said inner tube Whether leak.
10. LNG fuel air supply system peculiar to vessel according to claim 9, which is characterized in that the outer tube is equipped with detection Hole;The detection device includes sampling line, pressure transmitter and analysis of combustible gases instrument, and the sampling line is installed on described At detection hole, and the airtight cavity is connected to the pressure transmitter and analysis of combustible gases instrument.
CN201820240398.XU 2018-02-08 2018-02-08 LNG fuel air supply system peculiar to vessel Withdrawn - After Issue CN207865031U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820240398.XU CN207865031U (en) 2018-02-08 2018-02-08 LNG fuel air supply system peculiar to vessel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820240398.XU CN207865031U (en) 2018-02-08 2018-02-08 LNG fuel air supply system peculiar to vessel

Publications (1)

Publication Number Publication Date
CN207865031U true CN207865031U (en) 2018-09-14

Family

ID=63457025

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820240398.XU Withdrawn - After Issue CN207865031U (en) 2018-02-08 2018-02-08 LNG fuel air supply system peculiar to vessel

Country Status (1)

Country Link
CN (1) CN207865031U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108194835A (en) * 2018-02-08 2018-06-22 南通中集能源装备有限公司 LNG fuel air supply system peculiar to vessel
CN112050081A (en) * 2020-09-22 2020-12-08 华润(南京)市政设计有限公司 Movable type acceptance and feeding and discharging device for dual-fuel ship

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108194835A (en) * 2018-02-08 2018-06-22 南通中集能源装备有限公司 LNG fuel air supply system peculiar to vessel
CN108194835B (en) * 2018-02-08 2024-04-16 南通中集能源装备有限公司 Marine LNG fuel gas supply system
CN112050081A (en) * 2020-09-22 2020-12-08 华润(南京)市政设计有限公司 Movable type acceptance and feeding and discharging device for dual-fuel ship
CN112050081B (en) * 2020-09-22 2022-01-04 华润(南京)市政设计有限公司 Movable type acceptance and feeding and discharging device for dual-fuel ship

Similar Documents

Publication Publication Date Title
CN108194835A (en) LNG fuel air supply system peculiar to vessel
CN109027662B (en) LNG/L-CNG skid-mounted gas station
CN106170657B (en) Including the floating structure of sealing heat-insulation storage tank and the method for running the floating structure
CN104265512B (en) High-pressure/low-pressure gas supply system of ship power plant
CN207514561U (en) A kind of LNG fuel feeder peculiar to vessel
CN108916648B (en) LNG gas supply system on deck transport ship
CN203161377U (en) Gas fuel supply system of marine power plant
GB2419577A (en) Device for supplying fuel to an energy production installation of a ship
CN207865031U (en) LNG fuel air supply system peculiar to vessel
KR20100077194A (en) Method for operating a lng fuelled marine vessel
CN106184684A (en) Peculiar to vessel automatically control removable LNG fuel tank case air supply system
CN105889751A (en) LNG filling system, BOG processing system and mobile LNG filling ship
CN208719826U (en) Alternate form tank case with phase transformation feeder peculiar to vessel
CN113047996A (en) Methanol fuel dual-fuel supply system
CN105570665A (en) Bunkering storage tank system for ship and liquefied natural gas (LNG) bunkering pontoon with storage tank system
CN108006432A (en) A kind of LNG bank bases formula loading system peculiar to vessel
CN103867888A (en) Novel LNG gas-feeding integrated module device
CN204060975U (en) A kind of high voltage/low voltage fuel gas supply system of Ship Power Equipment
CN213065523U (en) Marine liquefied natural gas low pressure fuel supply system
CN106168328A (en) A kind of removable LNG ship fuel tank case
CN203428013U (en) LNG (liquefied natural gas) fuel storage tank structure and LNG ship
CN102494244B (en) Pontoon LNG aeration device and operation method thereof
CN105546325A (en) Filling marine liquefied natural gas storage tank
CN204176323U (en) A kind of LNG low temperature list pump sled
CN208535563U (en) A kind of LNG air supply system on deck carrier

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP02 Change in the address of a patent holder

Address after: No. 429, Chenggang Road, Chongchuan District, Nantong City, Jiangsu Province, 226000

Patentee after: NANTONG CIMC ENERGY EQUIPMENT Co.,Ltd.

Patentee after: CHINA INTERNATIONAL MARINE CONTAINERS (GROUP) Ltd.

Patentee after: CIMC ENRIC INVESTMENT HOLDINGS (SHENZHEN) Co.,Ltd.

Address before: 226003 No.155, Chenggang Road, Gangzha District, Nantong City, Jiangsu Province

Patentee before: NANTONG CIMC ENERGY EQUIPMENT Co.,Ltd.

Patentee before: CHINA INTERNATIONAL MARINE CONTAINERS (GROUP) Ltd.

Patentee before: CIMC ENRIC INVESTMENT HOLDINGS (SHENZHEN) Co.,Ltd.

CP02 Change in the address of a patent holder
AV01 Patent right actively abandoned

Granted publication date: 20180914

Effective date of abandoning: 20240416

AV01 Patent right actively abandoned

Granted publication date: 20180914

Effective date of abandoning: 20240416

AV01 Patent right actively abandoned
AV01 Patent right actively abandoned