CN207817705U - New-energy grid-connected power station relates to net performance on-line monitoring system - Google Patents

New-energy grid-connected power station relates to net performance on-line monitoring system Download PDF

Info

Publication number
CN207817705U
CN207817705U CN201721900195.0U CN201721900195U CN207817705U CN 207817705 U CN207817705 U CN 207817705U CN 201721900195 U CN201721900195 U CN 201721900195U CN 207817705 U CN207817705 U CN 207817705U
Authority
CN
China
Prior art keywords
data
new
power station
line monitoring
database server
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721900195.0U
Other languages
Chinese (zh)
Inventor
苏建军
李广磊
刘守刚
张华伟
李洪海
张荣贵
王尚斌
郝俊杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd
Shandong Luneng Software Technology Co Ltd
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd
Shandong Luneng Software Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd, Shandong Luneng Software Technology Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201721900195.0U priority Critical patent/CN207817705U/en
Application granted granted Critical
Publication of CN207817705U publication Critical patent/CN207817705U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The utility model discloses a kind of new-energy grid-connected power stations to relate to net performance on-line monitoring system, including:Main station system, dedicated transmission channel and plant stand acquisition system;The main station system and plant stand acquisition system are carried out data transmission by dedicated transmission channel;The data transmission is one-way transmission, and data transfer direction is to be transmitted to main station system by plant stand acquisition system.The utility model advantageous effect:Data one-way transmission between main station system and plant stand acquisition system, ensures the data safety of main station system.Data transmission uses dedicated transmission channel, ensures the safe and convenient of data transmission.

Description

New-energy grid-connected power station relates to net performance on-line monitoring system
Technical field
The utility model is related to new-energy grid-connected power station technology fields more particularly to a kind of new-energy grid-connected power station to relate to net It can on-line monitoring system.
Background technology
With electric power allotment between province, the rapid growth of new energy unit and power grid peak-valley difference and Power Market Construction It moves forward steadily, the difficulty and complexity of operation of power networks adjustment are significantly increased, and existing technical supervision mecha-nism mechanism can not fit Answer the needs of development of the situation.
Work is supported in order to improve intelligent power grid technology comprehensively, control centre is assisted fully to grasp new energy power station equipment fortune The real time status informations such as market condition provide strong back up information for frequency modulation scheduling and support;And improve service new energy power station Ability implements the main automatic system performance of dynamic evaluation new energy power station for the unit that generates electricity, and improves new energy power station automation Operation level and adjustment function, are active, while improving unit safety and economy in the competition for power grid electricity volume Property;Technical supervision department is can be applied to simultaneously, it is made to grasp unit automatic frequency adjustment ability in time, solution scene can be analyzed in time Problem, real-time, the automaticity of the supervisory service that develops skill.There is an urgent need for a kind of grid-connected new energy power station performance on-line monitorings of construction to answer Use system.
Utility model content
The purpose of this utility model is exactly to solve the above problems, and provides a kind of new-energy grid-connected power station and relates to net performance online Monitoring system realizes the on-line monitoring of grid-connected new energy power station using information-based means, and more accurate data branch is provided for scheduling It holds, adapts to the requirement to power grid regulation performance under global energy internet environment from now on.
To achieve the above object, the utility model uses following technical proposals, including:
A kind of new-energy grid-connected power station relates to net performance on-line monitoring system, including:Main station system, dedicated transmission channel and factory It stands acquisition system;
The main station system and plant stand acquisition system are carried out data transmission by dedicated transmission channel;The data transmission is One-way transmission, data transfer direction are to be transmitted to main station system by plant stand acquisition system.
Further, the main station system includes:
Application server, relational database server, live database server, the first interchanger, the first one-way isolation Device, convergence live database server, interface server, longitudinal decryption device and the first router;
The application server is separately connected with relational database server, live database server;The application clothes The first interchanger of business device, the first one-way isolation device, convergence live database server, interface server, longitudinal decryption device It is sequentially connected in series with the first router.
Further, the plant stand acquisition system includes:The second router, longitudinal encryption device, the data being sequentially connected in series Upload integrated terminal, second switch, the second single-phase isolating device and communication data harvester;The communication data acquisition dress It sets and is communicated with new energy power station.
Further, the communication data harvester is communicated with multiple new energy power stations simultaneously.
Further, the dedicated transmission channel is that the telecommunications that plant stand acquisition system is communicated with main station system is special logical Interrogate link.
The utility model advantageous effect:
Data one-way transmission between main station system and plant stand acquisition system, ensures the data safety of main station system.Data pass It is defeated to use dedicated transmission channel, ensure the safe and convenient of data transmission.
Communication data harvester supports MODBUS, CDT, CAN, Profibus, DL/T 634.5101-2002, DL/T 634.5104-2009, DL/T 719-2000, the communication protocols such as IEC870-5-101,103,104, IEC61850 and agreement are fitted Data exchange with the data of multiple new energy power stations, it can be achieved that communicate between answering heterogeneous system.
The communication data harvester communicatively unit data needed for acquisition system in SCADA, and energy and data It uploads integrated terminal and carries out data exchange, ensure that the authenticity of data source.
Electric Power Research Institute's acquisition new-energy grid-connected power station relates to net performance data, is then stored in real-time data base In, the supervisory service for power grid, DianKeYuan, government provides Data safeguard.
Description of the drawings
Fig. 1 is that the utility model new-energy grid-connected power station relates to net performance on-line monitoring system structure diagram;
Specific implementation mode:
The utility model is described in further detail below in conjunction with the accompanying drawings.
It is noted that following detailed description is all illustrative, it is intended to provide further instruction to the utility model.It removes Non- otherwise indicated, all technical and scientific terms that the utility model uses have general with the utility model technical field The normally understood identical meanings of logical technical staff.
The utility model discloses a kind of new-energy grid-connected power stations to relate to net performance on-line monitoring system, as shown in Figure 1, packet It includes:Main station system (hereinafter referred to as " main website "), dedicated transmission channel and plant stand acquisition system (hereinafter referred to as " substation ");System of main website Carried out data transmission by dedicated transmission channel between system and plant stand acquisition system, ensure that the safe and convenient of data transmission.Number It is one-way transmission according to transmission mode, i.e., can only main station system be transmitted to by plant stand acquisition system, ensure that the data of main station system Safety.
Main station system includes:Application server, relational database server, live database server, the first interchanger, First one-way isolation device, convergence live database server, interface server, longitudinal decryption device and the first router;
Application server is separately connected with relational database server, live database server;Application server first Interchanger, the first one-way isolation device, convergence live database server, interface server, longitudinal decryption device and the first via It is sequentially connected in series by device.
Wherein, interface server, which is used to summarize, receives the real time data that each new energy power station is sent to main website, by substation After data summarization, it is sent to convergence live database server and preserves.According to the performance of interface server can multiple substations with one Platform interface server, also can one interface server in a substation.
Convergence live database server receives the data sent from interface server and storage, converges real-time data base Relationship between server and interface server is one-to-many.It is after completing data receiver and preserving that data are unidirectional by first Isolating device is sent to live database server.
Live database server stores unit real time data, supports second grade real-time data memory;Compression storing data;Branch Hold the mirror image transmission between live database server;Data are supported to be transmitted by xegregating unit;Data are supported originally to converge reality When database mirror image transmission.
The network between main website reception data network and application database server is isolated in first one-way isolation device, ensures master Stand application safety.
The data that substation is transmitted are sent to main website by dedicated transmission channel, and data are by longitudinal decryption via interface service Device is preserved to convergence live database server;Live database server is mirrored to by one-way isolation, interchanger again.
It should be noted that application server, relational database server, real-time data base clothes that main station system includes Business device, convergence live database server and interface server be all made of existing computer system and can be realized as, without into Improvement on line program.
Data interaction is communicated by telecommunications dedicated transmission channel between substation and main website;Dedicated transmission channel refers to special Communication link is configured according to the relevant regulations of private network of electric power system.
Data upload integrated terminal, communication data harvester and the network that plant stand acquisition system is mounted in Power Plant Side are logical The set of the equipment such as road, including:The second router, longitudinal encryption device, the data being sequentially connected in series upload integrated terminal, the second friendship It changes planes, the second single-phase isolating device and communication data harvester;
Communication data harvester is communicated with new energy power station (SCADA), and communication data harvester is communicatively The unit data needed for acquisition system in SCADA, and integrated terminal can be uploaded with data and carry out data exchange, it ensure that data are come The authenticity in source.
Data acquisition modes support the communications protocol such as OPC, Modbus, 104 stipulations, CDT.Measuring point data type supports simulation The types such as amount, switching value, pulsed quantity, digital quantity, semaphore, electric flux, character amount, remote control amount, data block support initial value to set Set, rated value is handled, is taken absolute value, coefficient conversion etc. data reliabilities processing.
Using general international standard communication protocol, ensure the standardization of information exchange.Communication data harvester is supported MODBUS、CDT、CAN、Profibus、DL/T 634.5101-2002、DL/T 634.5104-2009、DL/T 719-2000, The communication protocols such as IEC870-5-101,103,104, IEC61850 and agreement, adapt to heterogeneous system between data exchange, it can be achieved that with The data of multiple new energy power stations communicate.
Data upload integrated terminal abbreviation integrated terminal, are exclusively used in the terminal device of new energy power station side information taken, complete The acquisition of net performance on-line monitoring related data, processing, storage are related at new-energy grid-connected power station and transmit information to main website.
Longitudinal encryption device and the second single-phase isolating device belong to Network Security Device, the peace for ensureing data transmission Quan Xing.
Tthe utility model system is hard in strict accordance with the related requirement of national information protection based on security rank when being worked The principle for holding " security partitioning, network-specific, lateral isolation, longitudinal certification ", ensures the safety of electric power monitoring system, is carrying out son Stand system Construction when, it is to be ensured that substation system build used by equipment meet《Electric power secondary system security protection provides》And state The related requirement of family's information protection based on security rank.
Planning is required according to state's net company information protection based on security rank system, great Qu, letter are controlled in information Intranet, production It is isolated by forward and reverse isolating device, fire wall, the special longitudinal encryption device of electric power between breath outer net.
System is forbidden selecting detecting through national regulatory authorities and be assert and through national energy in lectotype selection and configuration Office's notification is there are the system and equipment of loophole and risk, and production controls in great Qu in addition to secure accessing area, and forbidding selecting has nothing The equipment of line communication function.
Communication data harvester acquisition new energy power station SCADA system, which has, concerns net measuring point data, single-phase by second Isolating device forward direction by second switch send to data upload integrated terminal, data by longitudinal encryption device encryption after, By the second router and dedicated link, it is transmitted to main station system.
It should be noted that isolating device, the encryption device etc. that are arrived involved in main station system and plant stand acquisition system, are all The device that can be obtained on the market, without being improved.
It is above-mentioned although specific embodiments of the present invention are described with reference to the accompanying drawings, but not to this practicality newly The limitation of type protection domain, those skilled in the art should understand that, based on the technical solution of the present invention, ability Field technique personnel need not make the creative labor the various modifications or changes that can be made still in the protection model of the utility model Within enclosing.

Claims (5)

1. a kind of new-energy grid-connected power station relates to net performance on-line monitoring system, which is characterized in that including:Main station system, special biography Defeated channel and plant stand acquisition system;
The main station system and plant stand acquisition system are carried out data transmission by dedicated transmission channel;The data transmission is unidirectional Transmission, data transfer direction are to be transmitted to main station system by plant stand acquisition system.
2. a kind of new-energy grid-connected power station as described in claim 1 relates to net performance on-line monitoring system, which is characterized in that described Main station system includes:
Application server, relational database server, live database server, the first interchanger, the first one-way isolation device, Converge live database server, interface server, longitudinal decryption device and the first router;
The application server is separately connected with relational database server, live database server;The application server First interchanger, the first one-way isolation device, convergence live database server, interface server, longitudinal decryption device and the One router is sequentially connected in series.
3. a kind of new-energy grid-connected power station as described in claim 1 relates to net performance on-line monitoring system, which is characterized in that described Plant stand acquisition system includes:The second router, longitudinal encryption device, the data being sequentially connected in series upload integrated terminal, the second exchange Machine, the second single-phase isolating device and communication data harvester;The communication data harvester is communicated with new energy power station.
4. a kind of new-energy grid-connected power station as claimed in claim 3 relates to net performance on-line monitoring system, which is characterized in that described Communication data harvester is communicated with multiple new energy power stations simultaneously.
5. a kind of new-energy grid-connected power station as described in claim 1 relates to net performance on-line monitoring system, which is characterized in that described Dedicated transmission channel is the telecommunications special communication link that plant stand acquisition system is communicated with main station system.
CN201721900195.0U 2017-12-29 2017-12-29 New-energy grid-connected power station relates to net performance on-line monitoring system Expired - Fee Related CN207817705U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721900195.0U CN207817705U (en) 2017-12-29 2017-12-29 New-energy grid-connected power station relates to net performance on-line monitoring system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721900195.0U CN207817705U (en) 2017-12-29 2017-12-29 New-energy grid-connected power station relates to net performance on-line monitoring system

Publications (1)

Publication Number Publication Date
CN207817705U true CN207817705U (en) 2018-09-04

Family

ID=63328583

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721900195.0U Expired - Fee Related CN207817705U (en) 2017-12-29 2017-12-29 New-energy grid-connected power station relates to net performance on-line monitoring system

Country Status (1)

Country Link
CN (1) CN207817705U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109195156A (en) * 2018-10-17 2019-01-11 安徽立卓智能电网科技有限公司 A kind of multichannel secure accessing data collection system
CN111614626A (en) * 2020-04-26 2020-09-01 中广核风电有限公司 Data acquisition system and data acquisition method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109195156A (en) * 2018-10-17 2019-01-11 安徽立卓智能电网科技有限公司 A kind of multichannel secure accessing data collection system
CN111614626A (en) * 2020-04-26 2020-09-01 中广核风电有限公司 Data acquisition system and data acquisition method

Similar Documents

Publication Publication Date Title
CN104578422B (en) Remote maintenance method for transformer substation telecontrol forwarding table
CN109450662A (en) Ad hoc network communication manager and network-building method, ad hoc network communication system
CN103714437A (en) Power line repair commanding method based on CIS and movable operation
Yang ICT technologies standards and protocols for active distribution network
CN103026664A (en) Determining vlan-ids for a switched-based communication network of a process control system
CN104636986B (en) A kind of method that scheduling telesecurity remote control based on service is checked
KR101659113B1 (en) System for clouding service provide of power system
CN103199624A (en) Smart converting station based on international electrotechnical commission (IEC) 61850
CN207817705U (en) New-energy grid-connected power station relates to net performance on-line monitoring system
CN201163437Y (en) Automatization remote real-time monitoring system for client distribution network
CN110865621A (en) Method and system for monitoring a hydropower station
CN106230993A (en) Safety protection compliance data acquisition method and system for power monitoring system
CN103297520B (en) Operation of power networks service system and implementation method
CN207817497U (en) A kind of grid-connected unit relates to net performance on-line monitoring framework
CN204794376U (en) Intelligent substation access device
CN109587161A (en) The monitoring method of smart grid remote control command transmission overall process information
CN207817517U (en) A kind of fired power generating unit coal consumption on-line monitoring framework
CN207817953U (en) Regulating units monitor framework on-line
CN201138439Y (en) Customer integrated automation data acquisition system
CN110391985A (en) A kind of power information acquisition monitoring system
CN109754149A (en) Power communication is credible background management system, terminal and power communication trusted system
CN205812076U (en) A kind of Computer information network engineering system
CN108390738A (en) A kind of data transmission method and system based on the synchronization of intelligent substation clock
CN104301441B (en) A kind of substation equipment message transparent transmission system and transmission method
CN104378413B (en) A kind of intelligent substation simulation system data transmission method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180904

Termination date: 20211229