CN207794204U - A kind of safe protection of building site fire-fighting pond - Google Patents

A kind of safe protection of building site fire-fighting pond Download PDF

Info

Publication number
CN207794204U
CN207794204U CN201721664154.6U CN201721664154U CN207794204U CN 207794204 U CN207794204 U CN 207794204U CN 201721664154 U CN201721664154 U CN 201721664154U CN 207794204 U CN207794204 U CN 207794204U
Authority
CN
China
Prior art keywords
fire
water
fighting pond
fighting
water level
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721664154.6U
Other languages
Chinese (zh)
Inventor
罗炳锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shengshi Yao Lan (shenzhen) Technology Co Ltd
Original Assignee
Shengshi Yao Lan (shenzhen) Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shengshi Yao Lan (shenzhen) Technology Co Ltd filed Critical Shengshi Yao Lan (shenzhen) Technology Co Ltd
Priority to CN201721664154.6U priority Critical patent/CN207794204U/en
Application granted granted Critical
Publication of CN207794204U publication Critical patent/CN207794204U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Fire-Extinguishing By Fire Departments, And Fire-Extinguishing Equipment And Control Thereof (AREA)

Abstract

The utility model discloses a kind of safe protection of building site fire-fighting ponds, including fire-fighting pond, it is provided with water level observation hole at the top of the fire-fighting pond, and it is installed with rotation axis above water level observation hole, it is flexibly connected cover board in the rotation axis, water quantity monitoring meter is installed with inside the fire-fighting pond, and fire-fighting pond side is fixedly connected with the second water inlet pipe, it is installed with the second motor-driven valve on second water inlet pipe, and water quantity monitoring meter is connect with alarm, water outlet is fixedly installed on the fire-fighting pond.The safe protection of building site is with fire-fighting pond by the way that stormwater tank is arranged and is preferably supplemented fire-fighting pool inner water amount using rainwater, ensure minimum amount of water, the moisture storage capacity for solving current fire-fighting pond is generally supplied using domestic water, cost is higher, rainwater resource is not utilized rationally, and the minimum amount of water in fire-fighting pond can not be monitored in real time, when in case of emergency, there are some potential safety problems, the low problems of the ability to ward off risks for water shortage.

Description

A kind of safe protection of building site fire-fighting pond
Technical field
The utility model is related to fire-fighting pool technology field, specially a kind of safe protection of building site fire-fighting pond.
Background technology
Fire cistern is manually to build for fixed or movable fire-fighting water pumping water water storage facility, fire cistern it is effective Capacity should meet the requirement of the indoor fire consumption in fire life, and the moisture storage capacity in fire-fighting pond is generally using life at present It is supplied with water, cost is higher, is not utilized rationally to rainwater resource, and the minimum amount of water in fire-fighting pond can not carry out Real time monitoring, when in case of emergency, for water shortage there are some potential safety problems, the ability to ward off risks is low.
Utility model content
The purpose of this utility model is to provide a kind of safe protection of building site fire-fighting ponds, to solve to propose in above-mentioned background technology The moisture storage capacity in current fire-fighting pond generally supplied using domestic water, cost is higher, and it is reasonable to be carried out to rainwater resource It utilizes, and the minimum amount of water in fire-fighting pond can not be monitored in real time, when in case of emergency, water shortage exists certain Security risk, the low problem of the ability to ward off risks.
To achieve the above object, the utility model provides the following technical solutions:A kind of safe protection of building site fire-fighting pond, including disappear Anti- pond, the fire-fighting pond top is provided with water level observation hole, and is installed with rotation axis, the rotation above water level observation hole Be flexibly connected cover board on axis, be installed with water level indicating arm inside the fire-fighting pond, and fire-fighting pond top be provided with first into Water pipe, first water inlet pipe are fixedly connected with stormwater tank, and filter device, the filter device are fixedly mounted inside stormwater tank It is connect with the first water inlet pipe, and dismantling connection has filter screen inside the first water inlet pipe, is installed on first water inlet pipe First motor-driven valve, and flowmeter is installed with inside the first water inlet pipe, it is installed with water quantity monitoring inside the fire-fighting pond Meter, and fire-fighting pond side is fixedly connected with the second water inlet pipe, and the second motor-driven valve, and water are installed on second water inlet pipe Amount monitoring meter is connect with alarm, and water outlet is fixedly installed on the fire-fighting pond.
Preferably, the water level observation hole and cover board are circular configuration, and cover plate diameter is more than water level observation bore dia.
Preferably, the water level indicating arm is located at immediately below water level observation hole, and water level indicating arm is step structure, institute Water level indicating arm water level stake numerical digit is stated in ladder plane, and water level indicating arm is fixedly mounted perpendicular to fire-fighting bottom of pond portion.
Preferably, first water inlet pipe is arranged with stormwater tank bottom angled, and rainwater pool volume is fire-fighting pool volume one Half, the bottom plate of the stormwater tank is tilted to the first water inlet pipe side.
Preferably, it is in parallel electrically to connect between first motor-driven valve, flowmeter and the second motor-driven valve and water quantity monitoring meter It connects.
Compared with prior art, the utility model has the beneficial effects that:The safe protection of building site is with fire-fighting pond by the way that rainwater is arranged Pond and preferably fire-fighting pool inner water amount is supplemented using rainwater, ensures minimum amount of water, solve the water storage in current fire-fighting pond Amount is generally supplied using domestic water, and cost is higher, is not utilized rationally to rainwater resource, and in fire-fighting pond most Low wash water can not be monitored in real time, when in case of emergency, there are some potential safety problems, the abilities to ward off risks for water shortage Low problem.The safe protection of building site is completely covered water level observation hole by cover board with fire-fighting pond, makes external impurities that can not lead to Water level observation hole to be crossed to enter inside fire-fighting pond, polluted source, water level indicating arm is set up directly in ladder plane water level stake number, Convenient for directly observing in fire-fighting pond substantially water level, ensures that the water-holding quantity in fire-fighting pond, stormwater tank supply water to fire-fighting pond, reduce The supply of domestic water reduces storage cost, improves rainwater utilization, and rainwater pool volume is small, and construction cost is made to reduce, and saves Space, water quantity monitoring meter are monitored fire-fighting water amount, and the water in fire-fighting pond is made to ensure handling water for emergency episode It more than amount, in water shortage, is preferentially supplied water using stormwater tank, improves rainwater utilization, the apparatus structure is simple, sexual valence Than high.
Description of the drawings
FIG. 1 is a schematic structural view of the utility model;
Fig. 2 is enlarged structure schematic diagram at A in the utility model Fig. 1;
Fig. 3 is the utility model filter screen structure schematic diagram.
In figure:1, fire-fighting pond, 2, water level observation hole, 3, rotation axis, 4, cover board, 5, water level indicating arm, the 6, first water inlet pipe, 7, stormwater tank, 8, filter device, 9, filter screen, the 10, first motor-driven valve, 11, flowmeter, 12, water quantity monitoring meter, 13, second into Water pipe, the 14, second motor-driven valve, 15, alarm, 16, water outlet.
Specific implementation mode
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work The every other embodiment obtained, shall fall within the protection scope of the present invention.
- 3 are please referred to Fig.1, the utility model provides a kind of technical solution:A kind of safe protection of building site fire-fighting pond, including fire-fighting Pond 1, water level observation hole 2, rotation axis 3, cover board 4, water level indicating arm 5, the first water inlet pipe 6, stormwater tank 7, filter device 8, filtering Net 9, the first motor-driven valve 10, flowmeter 11, water quantity monitoring meter 12, the second water inlet pipe 13, the second motor-driven valve 14, alarm 15 and go out The mouth of a river 16,1 top of fire-fighting pond is provided with water level observation hole 2, and 2 top of water level observation hole is installed with rotation axis 3, and water level is seen Examine hole 2 and cover board 4 be circular configuration, and 4 diameter of cover board is more than 2 diameter of water level observation hole, cover board 4 to water level observation hole 2 into Row is completely covered, and makes external impurities that can not enter by water level observation hole inside fire-fighting pond, polluted source, activity in rotation axis 3 Connecting cover plate 4 is installed with water level indicating arm 5 inside fire-fighting pond 1, and 1 top of fire-fighting pond is provided with the first water inlet pipe 6, water Position indicating arm 5 is located at immediately below water level observation hole 2, and water level indicating arm 5 is step structure, 5 water level stake number of water level indicating arm In ladder plane, and water level indicating arm 5 is fixedly mounted perpendicular to 1 bottom of fire-fighting pond, and water level indicating arm 5 is straight to water level stake number Connect and be arranged in ladder plane, convenient for substantially water level in directly observation fire-fighting pond 1, the water-holding quantity in guarantee fire-fighting pond 1, first into Water pipe 6 is fixedly connected with stormwater tank 7, and filter device 8, filter device 8 and the first water inlet pipe 6 is fixedly mounted in 7 inside of stormwater tank Connection, and 6 inside dismantling connection of the first water inlet pipe has filter screen 9, the first water inlet pipe 6 is arranged with 7 bottom angled of stormwater tank, and rain 7 volume of pond is 1 volume half of fire-fighting pond, and the bottom plate of stormwater tank 7 is tilted to 6 side of the first water inlet pipe, and stormwater tank 7 is to fire-fighting pond 1 supplies water, and reduces the supply of domestic water, reduces storage cost, improves rainwater utilization, 7 volume of stormwater tank is small, makes to build Cost reduction is made, space is saved, the first motor-driven valve 10 is installed on the first water inlet pipe 6, and 6 inside of the first water inlet pipe is fixed Flowmeter 11 is installed, is electricity in parallel between the first motor-driven valve 10, flowmeter 11 and the second motor-driven valve 14 and water quantity monitoring meter 12 Property connection, water quantity monitoring meter 12 is monitored 1 water of fire-fighting pond, and the water in fire-fighting pond 1 is made to ensure for emergency episode Water or more is handled, in water shortage, preferentially is supplied water using stormwater tank 7, raising rainwater utilization, inside fire-fighting pond 1 It is installed with water quantity monitoring meter 12, and 1 side of fire-fighting pond is fixedly connected with the second water inlet pipe 13, it is fixed on the second water inlet pipe 13 Second motor-driven valve 14 is installed, and water quantity monitoring meter 12 is connect with alarm 15, water outlet 16 is fixedly installed on fire-fighting pond 1.
Operation principle:When using safe protection of building site fire-fighting pond, 1 inside moisture storage capacity of observation fire-fighting pond is carried out artificial When, by 3 rotating plate 4 of rotation axis, 5 subscript water filling bit value of water level indicating arm, water level instruction are seen by water level observation hole 2 Bar 5 uses ladder configuration, human eye directly to be read to water level indicating arm 5 on a vertical line, keeps quantities read more accurate Really, the water quantity monitoring meter 12 that 1 inside of fire-fighting pond is arranged calculates internal water, when 1 inside water of fire-fighting pond is less than minimum When moisture storage capacity, water quantity monitoring meter 12 carries out transmission signal to the first motor-driven valve 10, so that the first motor-driven valve 10 is opened, makes stormwater tank 7 Internal rainwater is entered by the first water inlet pipe 6 inside fire-fighting pond 1, and flowmeter 11 plays the role of detection to flow, in stormwater tank 7 Internal no rainwater stockpiles, and the first motor-driven valve 10 is opened, and when flow is not detected in flowmeter 11, water quantity monitoring meter 12 is to second Motor-driven valve 14 carries out transmission open signal, and domestic water is made to supply water fire-fighting pond 1, and when fire-fighting pond, 1 inside water is protected always When holding low water level, alarm 15 carries out alarm, and here it is the use processes in safe protection of building site fire-fighting pond.
Although the utility model is described in detail with reference to the foregoing embodiments, those skilled in the art is come Say, still can with technical scheme described in the above embodiments is modified, or to which part technical characteristic into Row equivalent replacement, within the spirit and principle of the utility model, any modification, equivalent replacement, improvement and so on should all It is included within the scope of protection of this utility model.

Claims (5)

1. a kind of safe protection of building site fire-fighting pond, including fire-fighting pond (1), it is characterised in that:It is provided with water at the top of the fire-fighting pond (1) Position peep hole (2), and rotation axis (3) is installed with above water level observation hole (2), movable connecting cover on the rotation axis (3) Plate (4), the fire-fighting pond (1) is internal to be installed with water level indicating arm (5), and fire-fighting pond (1) top is provided with the first water inlet It manages (6), first water inlet pipe (6) is fixedly connected with stormwater tank (7), and filter device is fixedly mounted inside stormwater tank (7) (8), the filter device (8) connect with the first water inlet pipe (6), and the internal dismantling connection of the first water inlet pipe (6) has filter screen (9), it is installed with the first motor-driven valve (10) on first water inlet pipe (6), and is installed with inside the first water inlet pipe (6) Flowmeter (11), is installed with water quantity monitoring meter (12) inside the fire-fighting pond (1), and fire-fighting pond (1) side with second into Water pipe (13) is fixedly connected, and the second motor-driven valve (14), and water quantity monitoring meter are installed on second water inlet pipe (13) (12) it is connect with alarm (15), water outlet (16) is fixedly installed on the fire-fighting pond (1).
2. a kind of safe protection of building site fire-fighting pond according to claim 1, it is characterised in that:The water level observation hole (2) and Cover board (4) is circular configuration, and cover board (4) diameter is more than water level observation hole (2) diameter.
3. a kind of safe protection of building site fire-fighting pond according to claim 1, it is characterised in that:Water level indicating arm (5) position Immediately below water level observation hole (2), and water level indicating arm (5) is step structure, water level indicating arm (5) the water level stake numerical digit In in ladder plane, and water level indicating arm (5) is fixedly mounted perpendicular to fire-fighting pond (1) bottom.
4. a kind of safe protection of building site fire-fighting pond according to claim 1, it is characterised in that:First water inlet pipe (6) with Stormwater tank (7) bottom angled is arranged, and stormwater tank (7) volume is fire-fighting pond (1) volume half, the bottom plate of the stormwater tank (7) It is tilted to the first water inlet pipe (6) side.
5. a kind of safe protection of building site fire-fighting pond according to claim 1, it is characterised in that:First motor-driven valve (10), It is electric connection in parallel between flowmeter (11) and the second motor-driven valve (14) and water quantity monitoring meter (12).
CN201721664154.6U 2017-12-05 2017-12-05 A kind of safe protection of building site fire-fighting pond Expired - Fee Related CN207794204U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721664154.6U CN207794204U (en) 2017-12-05 2017-12-05 A kind of safe protection of building site fire-fighting pond

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721664154.6U CN207794204U (en) 2017-12-05 2017-12-05 A kind of safe protection of building site fire-fighting pond

Publications (1)

Publication Number Publication Date
CN207794204U true CN207794204U (en) 2018-08-31

Family

ID=63285220

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721664154.6U Expired - Fee Related CN207794204U (en) 2017-12-05 2017-12-05 A kind of safe protection of building site fire-fighting pond

Country Status (1)

Country Link
CN (1) CN207794204U (en)

Similar Documents

Publication Publication Date Title
CN201952271U (en) Intelligent water treatment device
CN207396476U (en) A kind of water environment detection device
CN206941708U (en) A kind of fluid level control device for pumping plant cistern
CN103392567B (en) Irrigation system for three-dimensional greening walls
CN206399938U (en) Water dispensing apparatus and dam water quality monitoring system
CN209449427U (en) A kind of pig-breeding hog house ammonia monitoring system
CN207794204U (en) A kind of safe protection of building site fire-fighting pond
CN208981417U (en) A kind of indoor fire water supply system
CN208329058U (en) A kind of fire cistern with automatic checkout system
CN204490681U (en) A kind of wireless monitor Sewage treatment systems
CN207376797U (en) A kind of pumping plant water drainage device
CN204406177U (en) A kind of wastewater treatment supervisory system with alarm function
CN209673771U (en) Water quality detection warning device based on Internet of Things
CN217738946U (en) Waterproof performance detection device for building engineering waterproof material
CN205935177U (en) Cutting type sewage lifting device
CN209707989U (en) A kind of automatic control device of pumping station pollution discharge liquid level
CN211419715U (en) Automatic controller for MBR membrane pool unit
CN207649717U (en) A kind of precipitation Well Water Level prior-warning device
CN208202002U (en) A kind of novel flood-proof device
CN211285778U (en) Secondary water supply control system capable of predicting energy-saving efficiency
CN208363185U (en) A kind of fireproof poll under ground system
CN209669980U (en) A kind of integral intelligent pumping plant
CN216108787U (en) Inside water supply system in shelter mobile laboratory
CN207550115U (en) The vehicle mounted square cabin water drainage-supply system that extremely frigid zones use
CN208586652U (en) A kind of electricity well

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180831

Termination date: 20201205