CN207780122U - Nuclear phase assisting device of 10kV Barrow type switchgears - Google Patents
Nuclear phase assisting device of 10kV Barrow type switchgears Download PDFInfo
- Publication number
- CN207780122U CN207780122U CN201721924849.3U CN201721924849U CN207780122U CN 207780122 U CN207780122 U CN 207780122U CN 201721924849 U CN201721924849 U CN 201721924849U CN 207780122 U CN207780122 U CN 207780122U
- Authority
- CN
- China
- Prior art keywords
- baffle
- auxiliary
- insulator
- nuclear phase
- guiding
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000012212 insulator Substances 0.000 claims abstract description 51
- 230000005611 electricity Effects 0.000 claims abstract description 25
- 230000003068 static effect Effects 0.000 claims abstract description 12
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims description 5
- 230000000694 effects Effects 0.000 claims description 2
- 239000000523 sample Substances 0.000 abstract description 6
- 238000005192 partition Methods 0.000 abstract description 4
- 238000000819 phase cycle Methods 0.000 description 11
- 230000005540 biological transmission Effects 0.000 description 6
- 238000012360 testing method Methods 0.000 description 6
- 238000012423 maintenance Methods 0.000 description 5
- 238000010586 diagram Methods 0.000 description 4
- 238000009413 insulation Methods 0.000 description 4
- 230000002159 abnormal effect Effects 0.000 description 3
- 238000004880 explosion Methods 0.000 description 3
- 238000012795 verification Methods 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 239000012141 concentrate Substances 0.000 description 2
- 238000010891 electric arc Methods 0.000 description 2
- 238000002474 experimental method Methods 0.000 description 2
- 239000011521 glass Substances 0.000 description 2
- 230000005484 gravity Effects 0.000 description 2
- 239000002184 metal Substances 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 238000004804 winding Methods 0.000 description 2
- 230000015556 catabolic process Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000004744 fabric Substances 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000011810 insulating material Substances 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 238000011089 mechanical engineering Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000002265 prevention Effects 0.000 description 1
Abstract
The utility model provides a kind of nuclear phase assisting device of 10kV Barrow type switchgears, including electricity check trolley and auxiliary sub-device, the auxiliary sub-device are located on electricity check trolley, and the auxiliary sub-device includes baffle and multiple guiding insulators;The multiple guiding insulator is located on the baffle, and each insulator that is oriented to is connect with a circuit breaker static contact and wireless core phase instrument respectively.It includes electricity check trolley that the utility model, which is provided by the way that auxiliary device is arranged, can solve staff and separate baffle, the close problem of safe distance with hand.By the way that baffle is arranged, human body and switch cabinet electrified part are artificially kept apart into guarantee safe distance, lower baffle plate folding is not in place when being gone up in the partition shelf of part, when staff is adjusted, operating personnel's body is prevented to probe into cabinet, safe distance when ensureing not have a power failure with equipment.It is oriented to insulator by setting, fixed nuclear phase lever gos deep into direction, and is effectively increased creeping discharge distance and ensures electric clearance.
Description
Technical field
The utility model is related to mechanical engineering technical fields, more particularly, to a kind of core of 10kV Barrow type switchgears
Phase auxiliary device.
Background technology
Nuclear phase refers to checking two power supplys or loop phase, phase sequence with phasing tester or other means in electric system electric operation
It is whether identical.That is in practical operation power, the measurement to phase difference.If phase sequence is inconsistent, phase fault can be caused
Accident influences normal power transmission.The abnormal running of three-phase equipment, such as the reversion of motor can also be caused.Therefore, it creates, change
Build, extend after substation and transmission line of electricity, and finish in line maintenance, to before client's power transmission, it is necessary to carry out three-phase electricity
The nuclear phase on road is tested.Ensure that transmission line of electricity phase sequence is consistent with the phase sequence needed for user's threephase load.
Currently, expanding with capital construction, distribution automation, industry, bar moves the unusual fluctuation work of isocorrelate road and carries out, a large amount of high-voltage nuclear phase works
It concentrates in substation carrying out, due to transformer substation power distribution unit structural factor, concentrates on contact box in 10kV middle-placed switch cabinets substantially
Place carries out, and between switchgear upper and lower static contact, busbar is checked with line Phases, is goed deep into using high-voltage radio nuclear phase instrument transmitter
In contact box nuclear phase is contacted with electrification static contact.The secondary nuclear phase at electrification display is because there is many switch cabinet electrified displays
Place cannot carry out nuclear phase, electrification display secondary connection mistake will lead to nuclear phase mistake and due to electrification display without jack
The capacitance partial pressure of support insulator than, capacitance difference there are will be had when bigger difference variation there are larger amplitude with
And phase deviation, it may cause to measure and judge by accident.Therefore, primarily now high-pressure side nuclear phase is carried out using wireless nuclear phase mode.
At present for fixed (middle) 10 KV switch cabinet, in nuclear phase, nuclear phase instrument can be in direct contact
The Naked of two electrical bodies reveals part above and below to switch, and operation is very easy.And it is complete close to be mostly for trolley type 10kV switchgears
Equipment is sealed, no electrical body is exposed outside, therefore when carrying out nuclear phase to circuit by switch, needs staff artificially to use double
Hand separates the movable doorboard in switchgear, and fracture contact is exposed, and could carry out nuclear phase work later.
When wireless phasing tester nuclear phase, it can not ensure that phasing tester metal part keeps enough electricity with trolley divider metal part
It is split to there is nuclear phase lever in the nuclear phase work of 10 kilovolts of trolley type switchs at present for gas safe distance or creeping discharge distance
Steel plate electric discharge in cabinet is closed, making the person, equipment that cannot be ensured in safety causes staff's personal safety accident to occur.
In separated dodge gate baffle, the body of operating personnel may probe into cabinet, with 10kV electrical bodies safety away from
From deficiency, it can not ensure the personal safety of staff, there are security risks, also, overhead gage presence falls risk.Wireless
During nuclear phase instrument transmitter contact buses side (upside) static contact, however not excluded that overhead gage machinery positioner failure, gravity factor
It falls.
Utility model content
It is hidden in the presence of safety that the utility model provides staff when one kind overcoming an above-mentioned nuclear phase of 10kV Barrow type switchgears
A kind of nuclear phase assisting device of 10kV Barrow type switchgears for the problem of suffering from.
One side according to the present utility model provides a kind of nuclear phase assisting device of 10kV Barrow type switchgears, including
Electricity check trolley and auxiliary sub-device, the auxiliary sub-device is located on electricity check trolley, the auxiliary sub-device include baffle with it is more
A guiding insulator;The multiple guiding insulator is located on the baffle, it is each be oriented to insulator respectively with a circuit breaker static contact
It is connected with wireless core phase instrument.
Preferably, the auxiliary sub-device includes 6 guiding insulators;The baffle includes two and is oriented to insulator row, each
It includes 3 equally distributed guiding insulators to be oriented to insulator row.
Preferably, the baffle is made of implosion guard.
Preferably, the surrounding of the baffle is disposed with insulating frame.
Preferably, the auxiliary sub-device further includes at least one mobile base.
Preferably, the mobile base is electromagnetic base, and each electromagnetic base includes an electromagnetism conducting switch.
Preferably, the auxiliary sub-device includes 6 guiding insulators;The baffle includes two and is oriented to insulator row, each
It includes 3 equally distributed guiding insulators to be oriented to insulator row;The baffle is made of implosion guard;The surrounding of the baffle is arranged
There is insulating frame;The auxiliary sub-device further includes at least one mobile base, and the mobile base is electromagnetic base, Mei Yi electricity
Magnetic pedestal includes an electromagnetism conducting switch.
Nuclear phase assisting device of 10kV Barrow type switchgears provided by the utility model includes testing by the way that auxiliary device is arranged
Electric trolley can solve staff and separate baffle, the close problem of safe distance with hand.By the way that baffle is arranged, artificially by human body
Keep apart guarantee safe distance with switch cabinet electrified part, when upper lower baffle plate opens and closes not in place, staff in the partition shelf of part
When being adjusted, operating personnel's body is prevented to probe into cabinet, safe distance when ensureing not have a power failure with equipment.It is oriented to by being arranged
Insulator, fixed nuclear phase lever go deep into direction, and are effectively increased creeping discharge distance and ensure electric clearance, while the baffle can prevent
Overhead gage falls to the risk of nuclear phase instrument.
Description of the drawings
Fig. 1 is a kind of signal of the nuclear phase auxiliary sub-device of 10kV Barrow type switchgears in the utility model embodiment
Figure;
Fig. 2 is a kind of schematic diagram of electricity check trolley in the utility model embodiment;
Fig. 3 is a kind of schematic diagram of the nuclear phase assisting device of 10kV Barrow type switchgears in the utility model embodiment;
Wherein,
1-baffle;2-are oriented to insulator;3-insulating frames;
4-mobile bases;5-door openers;6-handle apparatus;
7-forward devices;8-telescopic positioning devices;9-auxiliary sub-devices.
Specific implementation mode
With reference to the accompanying drawings and examples, specific embodiment of the present utility model is described in further detail.Below
Embodiment is not intended to limit the scope of the present invention for illustrating the utility model.
When existing 10kV Barrow type switchgears carry out a nuclear phase, in separated dodge gate baffle, the body of operating personnel
Body may probe into cabinet, insufficient with the safe distance of 10kV electrical bodies, can not ensure the personal safety of staff, there is peace
Full hidden danger, also, overhead gage presence falls risk.During wireless core phase instrument transmitter contact buses side (upside) static contact,
It is not excluded for overhead gage machinery positioner failure, gravity factor falls, and due to the non-all insulation part of baffle perimeter connecting component, it can
Busbar grounding short circuit accident can be caused to occur.
And upper lower baffle plate folding is not in place in the partition shelf of part.Infull in the case of nuclear phase is opened in lower baffle plate, by pole
Easily lead to high-voltage potential by nuclear phase instrument transmitter to baffle to form weak insulation galvanic circle.Wireless phasing tester nuclear phase
When, cause arc discharge, no isolating device that may lead to electric arc or high pressure steel plate electric discharge in switchgear just in case nuclear phase lever occurs
Electric casualty accident occurs.To solve problems of the prior art, the utility model proposes a kind of 10kV Barrow type switchgears
Nuclear phase assisting device.
Fig. 1 is a kind of signal of the nuclear phase auxiliary sub-device of 10kV Barrow type switchgears in the utility model embodiment
Figure, as shown in Figure 1, the auxiliary device includes electricity check trolley and auxiliary sub-device 9, it is small that the auxiliary sub-device 9 is located at electrical verification
Che Shang, the auxiliary sub-device 9 include baffle 1 and multiple guiding insulators 2;The multiple guiding insulator 2 is located at the baffle 1
On, each insulator 2 that is oriented to is connect with a circuit breaker static contact and wireless core phase instrument respectively.
Further, Fig. 2 is a kind of schematic diagram of electricity check trolley in the utility model embodiment, and Fig. 3 is that this practicality is new
A kind of schematic diagram of nuclear phase assisting device of 10kV Barrow type switchgears in type embodiment, the present embodiment also please refer to Fig.2 and
Fig. 3.
As shown in Figures 2 and 3, electricity check trolley includes door opener 5, handle apparatus 6, move ahead device 7 and flexible positioning dress
Set 8.
It should be noted that nuclear phase is an essential job in the experiment of electrical system effect, mainly for verification
Whether the actual installations such as busbar, cable phase sequence is consistent with design phase sequence and PT phase sequences.Secondary nuclear phase be primary system power transmission after adopt
With secondary nuclear phase instrument in PT secondary side Check Phase Sequences, general secondary nuclear phase instrument can measure three-phase three winding PT signals, pass through signal
Lamp come indicate three groups of windings respectively phase sequence, answer split-phase normally to show as phase sequence is errorless.Nuclear phase is using a nuclear phase stick
Primary side distinguish each two-phase (both sides be all power supply then answer A to A, B to B) verification phase angle, and with secondary device (it is comprehensive protect, it is same
Phase) it compares and carrys out Check Phase Sequence.The relatively secondary nuclear phase of nuclear phase answers first and second nuclear phase closer to system source, more accurate
It is used cooperatively.Nuclear phase is the important experiment of electric system, and the operations such as back brake power transmission, the grid-connected same period could be carried out after needing nuclear phase errorless,
Otherwise there may be the serious consequences such as non-Switching Synchronization, false protection, motor insulation breakdown.
Further, it is as follows to carry out the step of auxiliary nuclear phase for auxiliary device provided by the utility model:
Trolley type breaker is pulled to maintenance position.
Auxiliary sub-device 9 is mounted on electricity check trolley, good position is adjusted according to size.
By in electricity check trolley push-on switch cabinet, circuit breaker trolley cabinet Internal baffle is opened, insulator 2 will be oriented to and be inserted into breaker cabinet
Inner breaker static contact.
Wireless core phase instrument is inserted into and is oriented to the progress nuclear phase of insulator 2, in nuclear phase, auxiliary device can prevent staff from leaning on
Nearly electrification position, when nuclear phase, carry out importing orientation, increase creeping discharge distance.
After the completion of nuclear phase, electricity check trolley is pulled to maintenance position.
Auxiliary sub-device 9 is removed from electricity check trolley.
Further, the material for being oriented to insulator is King or other high-strength insulating materials.
Nuclear phase assisting device of 10kV Barrow type switchgears provided by the utility model includes testing by the way that auxiliary device is arranged
Electric trolley can solve staff and separate baffle, the close problem of safe distance with hand.By the way that baffle 1 is arranged, artificially by human body
Keep apart guarantee safe distance with switch cabinet electrified part, when upper lower baffle plate 1 opens and closes not in place, staff in the partition shelf of part
When being adjusted, operating personnel's body is prevented to probe into cabinet, safe distance when ensureing not have a power failure with equipment.It is oriented to by being arranged
Insulator 2, fixed nuclear phase lever go deep into direction, and are effectively increased creeping discharge distance and ensure electric clearance, while the baffle 1 can be to prevent
Only overhead gage falls to the risk of nuclear phase instrument.
The utility model can increase nuclear phase Security of test, and operating personnel's body is prevented to probe into cabinet, guarantee and equipment
Safe distance when not having a power failure, the person, equipment safety can be ensured by being abnormal the when of the accidents such as setting off an explosion.Nuclear phase can be increased
Test accuracy reduces the probability that service personnel misjudges equipment state.The person is ensured when suitable for trolley type switch nuclear phase, is set
Standby safety, work efficiency is high, a few nuclear phase assisting device of input manpower.
It should be noted that the auxiliary device in the utility model embodiment does not change breaker electricity check trolley structure
Become.
Based on above-described embodiment, for the present embodiment referring also to Fig. 1, the auxiliary sub-device 9 includes 6 guiding insulators 2;Institute
It includes two guiding insulator rows to state baffle 1, and each guiding insulator row includes 3 equally distributed guiding insulators 2.
Specifically, switchgear includes 6 circuit breaker static contacts, so being corresponding with 6 guiding insulators 2, circuit breaker static contact
It is also corresponded with the position relationship for being oriented to insulator 2.
Based on above-described embodiment, the present embodiment is made referring also to Fig. 1, the baffle 1 of implosion guard.
Nuclear phase assisting device of 10kV Barrow type switchgears provided by the utility model, by the way that baffle 1 is arranged by explosion-proof glass
Glass is made, and has explosion prevention function and pressure release passage, just in case being abnormal the when of the accidents such as setting off an explosion can ensure personal safety.
Based on above-described embodiment, the present embodiment is disposed with insulating frame 3 referring also to Fig. 1, the surrounding of the baffle 1.
Nuclear phase assisting device of 10kV Barrow type switchgears provided by the utility model, by the surrounding cloth that baffle 1 is arranged
It is equipped with insulating frame 3, solves in the prior art due to the non-all insulation part of baffle perimeter connecting component, busbar may be caused to connect
The problem of ground short circuit accident occurs.
Based on above-described embodiment, for the present embodiment referring also to Fig. 1, the auxiliary sub-device further includes at least one dump bottom
Seat 4.
Based on above-described embodiment, for the present embodiment referring also to Fig. 1, the mobile base 4 is electromagnetic base, each electromagnetism bottom
Seat includes an electromagnetism conducting switch.
Nuclear phase assisting device of 10kV Barrow type switchgears provided by the utility model, by the way that mobile base 4 is arranged, and should
Pedestal 4 is electromagnetic base, which just has magnetic field when the switch is opened there are one electromagnetism conducting switch, installed convenient for baffle,
It carries.
The testing auxiliary device is with energy suitable for multiple sizes breaker as a further improvement of the utility model,
2 diameter of guiding insulator of trolley, guiding 2 diameter of insulator is small therefore the circuit breaker trolley of various models can be inserted.10kV at present
High-voltage chamber switch cabinet huge number, trolley breaker outgoing line seat size is varied, and the guiding insulator 2 of minor diameter adapts to a variety of
The trolley type breaker of structure type.
Based on above-described embodiment, for the present embodiment referring also to Fig. 1, the auxiliary sub-device 9 includes 6 guiding insulators 2;Institute
It includes two guiding insulator rows to state baffle 1, and each guiding insulator row includes 3 equally distributed guiding insulators 2;The baffle 1
It is made of implosion guard;The surrounding of the baffle 1 is disposed with insulating frame 3;The auxiliary sub-device 9 further includes at least one work
Dynamic pedestal 4, the mobile base 4 are electromagnetic base, and each electromagnetic base includes an electromagnetism conducting switch.
Further, it is as follows to carry out the step of auxiliary nuclear phase for auxiliary device provided by the utility model:
Trolley type breaker is pulled to maintenance position.
Will auxiliary sub-device 9 be mounted on electricity check trolley on, according to size adjust good position after, open electromagnetic base switch into
Row is fixed.
By in electricity check trolley push-on switch cabinet, circuit breaker trolley cabinet Internal baffle is opened, insulator will be oriented to and be inserted into breaker cabinet
Inner breaker static contact.
Wireless core phase instrument is inserted into and is oriented to the progress nuclear phase of insulator 2, in nuclear phase, auxiliary device can prevent staff from leaning on
Nearly electrification position, when nuclear phase, carry out importing orientation, increase creeping discharge distance, there is implosion guard and relief hole can effectively prevent
Only ensured personal safety when something unexpected happened when nuclear phase.
After the completion of nuclear phase, electricity check trolley is pulled to maintenance position.
Auxiliary sub-device 9 is removed from electricity check trolley.
Nuclear phase assisting device of 10kV Barrow type switchgears provided by the utility model can improve the accurate of nuclear phase test
Property and safety.
Finally, the device of the utility model is only preferable embodiment, is not intended to limit the protection of the utility model
Range.Within the spirit and principle of the utility model, any modification, equivalent replacement, improvement and so on should be included in
Within the scope of protection of the utility model.
Claims (7)
1. a kind of nuclear phase assisting device of 10kV Barrow type switchgears, which is characterized in that including electricity check trolley and sub-device is assisted,
The auxiliary sub-device is located on electricity check trolley, and the auxiliary sub-device includes baffle and multiple guiding insulators;
The multiple guiding insulator is located on the baffle, and each insulator that is oriented to is respectively with a circuit breaker static contact and without line core
Phase instrument connects.
2. auxiliary device according to claim 1, which is characterized in that the auxiliary sub-device includes 6 guiding insulators;
The baffle includes two and is oriented to insulator row, and each guiding insulator row includes 3 equally distributed guiding insulators.
3. auxiliary device according to claim 1, which is characterized in that the baffle is made of implosion guard.
4. auxiliary device according to claim 1, which is characterized in that the surrounding of the baffle is disposed with insulating frame.
5. auxiliary device according to claim 1, which is characterized in that the auxiliary sub-device further includes at least one activity
Pedestal.
6. auxiliary device according to claim 5, which is characterized in that the mobile base is electromagnetic base, each electromagnetism
Pedestal includes an electromagnetism conducting switch.
7. auxiliary device according to claim 1, which is characterized in that the auxiliary sub-device includes 6 guiding insulators;
The baffle includes two and is oriented to insulator row, and each guiding insulator row includes 3 equally distributed guiding insulators;
The baffle is made of implosion guard;
The surrounding of the baffle is disposed with insulating frame;
The auxiliary sub-device further includes at least one mobile base, and the mobile base is electromagnetic base, each electromagnetic base
Including an electromagnetism conducting switch.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721924849.3U CN207780122U (en) | 2017-12-29 | 2017-12-29 | Nuclear phase assisting device of 10kV Barrow type switchgears |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721924849.3U CN207780122U (en) | 2017-12-29 | 2017-12-29 | Nuclear phase assisting device of 10kV Barrow type switchgears |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207780122U true CN207780122U (en) | 2018-08-28 |
Family
ID=63222389
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721924849.3U Active CN207780122U (en) | 2017-12-29 | 2017-12-29 | Nuclear phase assisting device of 10kV Barrow type switchgears |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207780122U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110058090A (en) * | 2019-06-05 | 2019-07-26 | 衢州代宇商务咨询有限公司 | A kind of detection device for reducing electromagnetic radiation and electromagnetic radiation being detected |
CN112366524A (en) * | 2020-10-31 | 2021-02-12 | 贵州电网有限责任公司 | Adjustable multipurpose cubical switchboard contact baffle auxiliary stay frame |
CN112670874A (en) * | 2019-10-15 | 2021-04-16 | 国网湖北省电力有限公司襄阳供电公司 | Electricity-testing and phase-checking integrated trolley |
-
2017
- 2017-12-29 CN CN201721924849.3U patent/CN207780122U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110058090A (en) * | 2019-06-05 | 2019-07-26 | 衢州代宇商务咨询有限公司 | A kind of detection device for reducing electromagnetic radiation and electromagnetic radiation being detected |
CN112670874A (en) * | 2019-10-15 | 2021-04-16 | 国网湖北省电力有限公司襄阳供电公司 | Electricity-testing and phase-checking integrated trolley |
CN112366524A (en) * | 2020-10-31 | 2021-02-12 | 贵州电网有限责任公司 | Adjustable multipurpose cubical switchboard contact baffle auxiliary stay frame |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207780122U (en) | Nuclear phase assisting device of 10kV Barrow type switchgears | |
CN103904578B (en) | For high-tension switch cabinet nuclear phase, busbar grounding function solid type handcart | |
CN103364648B (en) | Nuclear phase device and electroscope used in cooperation with nuclear phase device | |
CN206431235U (en) | A kind of industrial frequency withstand voltage detection device | |
CN201590615U (en) | High-pressure nuclear phase device for central-positioned high-voltage switch cabinets | |
US20150015234A1 (en) | Contact voltage detection system and method | |
CN201892700U (en) | Secondary side electricity-testing and nuclear-phase handcart of central switch cabinet | |
CN201514437U (en) | Distribution network capacitance current test instrument | |
CN107086537B (en) | Prevent the disconnecting device and cutting-off method of the debugging primary equipment electrification of substation's relay protection | |
CN207440195U (en) | A kind of multi-functional energizing test platform | |
Boboev et al. | Evaluation of indirect methods for determining the isolation parameters of the network phases relative to the ground on a computer model | |
CN204190234U (en) | High-tension switch cabinet ground connection and Test Integrated dolly | |
CN104505863B (en) | A method for determining and adjusting wireless phase detection | |
CN102565614B (en) | Alternating voltage loop test method | |
CN202256512U (en) | Multifunctional phase check instrument | |
CN203337743U (en) | Phase checking device and electroscope used with the same | |
CN204719085U (en) | A kind of electric energy quality test device being applicable to underground coal mine low voltage electric network | |
CN103743977A (en) | High-voltage heavy-current combined temperature rise verification platform for equipotential temperature measuring device | |
CN102832554B (en) | A kind of electric power apparatus examination test ground connection mechanical locking device | |
CN107579471A (en) | A kind of handcart switch cabinet CT rising test short-circuit devices | |
CN209784496U (en) | Withstand voltage tester | |
CN104020325A (en) | High-voltage test shielding cover for 10kV ring main unit | |
CN102611019B (en) | Method for charged replacement of isolating switch and current guide device thereof | |
CN102508010A (en) | Electricity testing method of high voltage switch cabinet | |
CN216285604U (en) | Subway GIS high tension switchgear system detection device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |