CN207764328U CN201820156183.XU CN201820156183U CN207764328U CN 207764328 U CN207764328 U CN 207764328U CN 201820156183 U CN201820156183 U CN 201820156183U CN 207764328 U CN207764328 U CN 207764328U
Authority
CN
China
Prior art keywords
charging pile
charging
test
bms
simulators
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820156183.XU
Other languages
Chinese (zh)
Inventor
黄成达
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Blue Technology Co Ltd
Original Assignee
Chengdu Blue Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Blue Technology Co Ltd filed Critical Chengdu Blue Technology Co Ltd
Priority to CN201820156183.XU priority Critical patent/CN207764328U/en
Application granted granted Critical
Publication of CN207764328U publication Critical patent/CN207764328U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of charging pile charging simulated testing system, the test system includes at least charging pile, output unit, cloud control platform and handheld test equipment;The charging pile is connected through cable with the output unit, and the charging pile is connected through mode wiredly and/or wirelessly with the cloud control platform, and the cloud control platform is connected through mode wiredly and/or wirelessly with the handheld test equipment.The true charging pile run on line of this charging pile test system complete simulation test is from starting to charge up, the information reporting of charge data and displaying, to finally terminating to charge, the whole flow process of charging disbursement and sattlement, dependence test not only has been carried out to charging pile hardware, and entire charging flow has been tested.

Description

A kind of charging pile charging simulated testing system
Technical field
The utility model is related to test system regions, especially a kind of charging pile charging simulated testing system.
Background technology
Some current existing charging pile automatic test devices are all the scheme of a whole set of test charging pile, test dress Set it is excessively huge, not only need load, BMS simulators also need to human-computer interaction host computer PC terminal.All it is mostly directly to pass through Charging pile is started up the test automated by test equipment.The charging pile test system of such pattern can not be real One true user of simulation fills the test for starting the flow to charge using App clients, being capable of not test network Some charging pile working conditions in the case of bad.Some test platform equipment have battery simulator, BMS moulds in society at present A series of equipment such as quasi- device, power analysis, oscillograph, multimeter, infrared thermography.What it was tested is also only charging pile An internal working condition.
Current most of charging pile test equipments are rested on accumulator or resistive load, this is for enterprise either from grinding It is all extremely inconvenient on functional trial or batch production detection efficiency to send out.
Our the charging pile equipment of platform production manufacture are required for carrying out detailed test at present, need accurately to go to simulate The detection for some problems that charging pile is formally runed on line.The problem of wherein mainly detecting charging pile metering and billing, with And working condition of charging pile in the case of network condition difference can be simulated.
Then it is exactly that, if some exceptions occurs in the charging pile run on line, O&M is in the later stage to also have a bit Maintenance needs to do charging pile the thing for needing band when some tests and just compares more, but also excessively heaviness.
Utility model content
The purpose of the utility model is to overcome the deficiencies in the prior art, provide a kind of charging pile charging simulation test system System, the test system include at least charging pile, output unit, cloud control platform and handheld test equipment;The charging pile Be connected with the output unit through cable, the charging pile through wiredly and/or wirelessly mode and the cloud control platform phase Even, the cloud control platform is connected through mode wiredly and/or wirelessly with the handheld test equipment.
According to a preferred embodiment, the output unit includes at least BMS simulators and load port, described The output unit component of BMS simulators and the becoming one of load port, the BMS simulators include at least agreement mould Quasi- device, voltage simulator and control unit.
According to a preferred embodiment, the BMS simulators are also equipped with the man-machine interactive screen of visualization.
According to a preferred embodiment, the handheld test equipment is for Portable DC stake tester and/or just Take formula exchange stake tester.
The utility model has the beneficial effects that:This set charging pile is tested the complete simulation test of system and is really transported on line Capable charging pile is from starting to charge up, the information reporting of charge data and displaying, to finally terminating to charge, the disbursement and sattlement that charges it is whole A flow.Dependence test not only has been carried out to charging pile hardware, and entire charging flow has been tested.
Description of the drawings
Fig. 1 is the structural schematic diagram of the utility model.
Specific implementation mode
Illustrate that the embodiment of the utility model, those skilled in the art can be by this theorys below by way of specific specific example Content disclosed by bright book understands other advantages and effect of the utility model easily.The utility model can also be by addition Different specific implementation modes are embodied or practiced, and the various details in this specification can also be based on different viewpoints and answer With carrying out various modifications or alterations under the spirit without departing from the utility model.It should be noted that the case where not conflicting Under, the feature in following embodiment and embodiment can be combined with each other.
It should be noted that the diagram provided in following embodiment only illustrates the basic of the utility model in a schematic way Conception, component count, shape when only display is with related component in the utility model rather than according to actual implementation in schema then And size is drawn, when actual implementation kenel, quantity and the ratio of each component can be a kind of random change, and its assembly layout Kenel may also be increasingly complex.
Embodiment:
A kind of charging pile charging simulated testing system, as shown in Figure 1.The test system includes at least charging pile, output Unit, cloud control platform and handheld test equipment.
The charging pile is connected through cable with the output unit, the output for completing electric energy and output test. Preferably, the output unit includes at least BMS simulators and load port, the BMS simulators and the load port collection The output unit component for being integrally formed.
The BMS simulators include at least protocol simulator, voltage simulator and control unit.The protocol simulator is used In simulation BMS messages communicated with charging pile, such as certain company CANScope simulators, not only have protocol simulator Function can also synchronize and carry out the sophisticated functions such as protocol conformance monitoring, fault simulation, Signal quality assessment.
The voltage simulator is attempted by charging pile DC+ and DC-, and centre is gated by relay, for simulating Cell voltage, in the electric stake charge arrangement stage, charging pile needs to monitor that vehicle end cell voltage normally can just enter charging rank Section, otherwise will stop charging.It is direct that the arbitrary exportable minimum and maximum voltage of charging pile can be simulated by voltage simulator DC power supply.
Described control unit enters charge arrangement for driving aforementioned relay to coordinate with protocol simulator in charging process It realizes that relay is attracted when the stage, and then charging pile is made to monitor simulated battery voltage, so that charging pile can carry out just Normal electric energy output.
Preferably, the BMS simulators are also equipped with the man-machine interactive screen of visualization.User can be based on visualizing man-machine Interactive screen observes the charge data when charge data or analog charge of charging pile, such as electric current, voltage, power in real time.
BMS battery simulators are developed on the basis of high-precision bidirectional, dc source, and DC side has high-precision and height Dynamic response characteristic, and with the function to power grid feedback energy.Output of products has simulation multiple battery charge-discharge characteristic.Production Product use all-digitized demodulator, and control accuracy height, fast response time, DC voltage adjustable range are wide.BMS simulators can simulate Various data of the charging pile in charging process are tested, and reporting for various exception informations can be simulated.
It, can be in the case of ensureing that charging pile is connected to background server in connection after BMS simulators and load Charging pile is directly directly initiated by hand-held terminal device, carries out the debugging of charging pile.Hand-held terminal device client is used Instead of traditional upper seat in the plane equipment so that the test of charging pile is more convenient.
Meanwhile passing through the setting of BMS simulators in this test system so that user does not have to carry out real vehicle during the test Charging may be implemented to simulate the battery system of different motor-cars to be charged, avoids and filled with real vehicle by this BMS simulators Since test sample is smaller in Electrical Test Procedure, the under-represented problem occurred, and in each real vehicle charging measurement The power generation of mesuring battary system is slower, the problem of to influence charging pile testing efficiency.
Preferably, the charging pile is connected through mode wiredly and/or wirelessly with the cloud control platform.The cloud control Platform can control startup and stopping and the final clearing of charging pile of charging pile, that is, complete the survey of entire charging flow Examination.Charging pile runs the problem of may existing on line, can formally be put into charging pile by the cloud control platform It can comprehensively be tested before operation.
Preferably, the cloud control platform is connected through mode wiredly and/or wirelessly with the handheld test equipment.Into One step, the handheld test equipment is Portable DC stake tester and/or Portable AC stake tester.It is described hand-held The information data that formula test equipment is transmitted to the cloud control platform based on charging pile completes the monitoring of charging pile charged state.
Charging pile status information of the user based on handheld test monitoring of equipment completes the charging pile with the monitoring of BMS simulators The comparison of status information is monitored the charged state of charging pile to realize.And based on the shifting of handheld test equipment Dynamic characteristic, user can use the device to complete to carry out state verification to different regions difference charging pile.
This set charging pile tests the true charging pile run on line of the complete simulation test of system from starting to charge up, and fills The information reporting of electric data and displaying, to finally terminating to charge, the whole flow process for the disbursement and sattlement that charges.It is not only hard to charging pile Part has carried out dependence test, and is tested to entire charging flow.
Specific embodiment of the present utility model above described embodiment only expresses, the description thereof is more specific and detailed, But it should not be understood as limiting the scope of the patent of the utility model.It should be pointed out that for the common of this field For technical staff, without departing from the concept of the premise utility, various modifications and improvements can be made, these all belong to In the scope of protection of the utility model.

Claims (4)

  1. The simulated testing system 1. a kind of charging pile charges, which is characterized in that the test system includes at least charging pile, output list Member, cloud control platform and handheld test equipment;
    The charging pile is connected through cable with the output unit, the charging pile through wiredly and/or wirelessly mode and institute It states cloud control platform to be connected, the cloud control platform is connected through mode wiredly and/or wirelessly with the handheld test equipment.
  2. The simulated testing system 2. charging pile as described in claim 1 charges, which is characterized in that the output unit includes at least BMS simulators and load port, the output unit component of the BMS simulators and the becoming one of load port, institute It states BMS simulators and includes at least protocol simulator, voltage simulator and control unit.
  3. The simulated testing system 3. charging pile as claimed in claim 2 charges, which is characterized in that the BMS simulators also carry There is the man-machine interactive screen of visualization.
  4. The simulated testing system 4. charging pile as claimed in claim 3 charges, which is characterized in that the handheld test equipment is Portable DC stake tester and/or Portable AC stake tester.
CN201820156183.XU 2018-01-30 2018-01-30 A kind of charging pile charging simulated testing system Expired - Fee Related CN207764328U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820156183.XU CN207764328U (en) 2018-01-30 2018-01-30 A kind of charging pile charging simulated testing system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820156183.XU CN207764328U (en) 2018-01-30 2018-01-30 A kind of charging pile charging simulated testing system

Publications (1)

Publication Number Publication Date
CN207764328U true CN207764328U (en) 2018-08-24

Family

ID=63182345

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820156183.XU Expired - Fee Related CN207764328U (en) 2018-01-30 2018-01-30 A kind of charging pile charging simulated testing system

Country Status (1)

Country Link
CN (1) CN207764328U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110537879A (en) * 2019-09-29 2019-12-06 北京石头世纪科技股份有限公司 Fill electric pile testing arrangement
CN114089718A (en) * 2021-10-26 2022-02-25 许继电源有限公司 Ordered charging control terminal test method and system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110537879A (en) * 2019-09-29 2019-12-06 北京石头世纪科技股份有限公司 Fill electric pile testing arrangement
CN114089718A (en) * 2021-10-26 2022-02-25 许继电源有限公司 Ordered charging control terminal test method and system
CN114089718B (en) * 2021-10-26 2023-10-27 许继电源有限公司 Ordered charging control terminal testing method and system

Similar Documents

Publication Publication Date Title
CN108398611B (en) Function test system based on minimum battery management system and test method thereof
CN109444566B (en) Electric automobile charging facility detection equipment and method
CN103454522B (en) Based on electronics spare part state of the art automatic checkout system and the method for PXI bus
CN203689120U (en) New energy vehicle battery management system master and slave control board hardware-in-the-loop test system
CN104714177A (en) Detection method and system for lithium battery management system
CN106771701A (en) A kind of electric vehicle charge interface uniformity automated detection system and method
CN106443545B (en) Fault diagnosis and positioning system and method for battery management system of pure electric vehicle
CN103019940B (en) A kind of electric energy meter embedded software half simulation testing device
CN207335757U (en) A kind of test system of automobile combination meter
CN103019902A (en) Automatic testing device and automatic testing method of ARINC 429 bus signal performance parameters
CN203287504U (en) Testing apparatus for battery performances under simulated working condition
CN110187299A (en) A kind of aviation Support Equipment electrical parameter generic calibration system
CN207764328U (en) A kind of charging pile charging simulated testing system
CN105467355A (en) Automatic testing method of electric energy meter and automatic testing device of same
CN202815579U (en) Pure electric automobile whole-vehicle controller laboratory test system
CN105242134A (en) Distributed test method suitable for system-grade test of intelligent high-voltage equipment
CN203616466U (en) Comprehensive tester and test equipment of battery management system
CN207380211U (en) A kind of device of detecting magnetic holding relays in batches
CN104977554A (en) Detection device for storage battery internal resistance tester
CN203689146U (en) New energy vehicle battery management system master and slave control board hardware-in-the-loop test system
CN106093664B (en) Conduction charging test system for electric automobile
CN109596915A (en) A kind of remote calibration system and method for electric automobile charging pile
CN208156105U (en) Function test system based on minimum battery management system
CN103064054A (en) Electric energy measure device simulation system and wiring matrix control method thereof
CN207218691U (en) A kind of electric energy metrical carrier communication module device for detecting performance

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180824

Termination date: 20210130