CN207745704U - Double-wall spray equipment for smoke absorption - Google Patents

Double-wall spray equipment for smoke absorption Download PDF

Info

Publication number
CN207745704U
CN207745704U CN201721869403.5U CN201721869403U CN207745704U CN 207745704 U CN207745704 U CN 207745704U CN 201721869403 U CN201721869403 U CN 201721869403U CN 207745704 U CN207745704 U CN 207745704U
Authority
CN
China
Prior art keywords
absorption
wall
spraying mechanism
flow
double
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721869403.5U
Other languages
Chinese (zh)
Inventor
姬亚沣
王豪仁
武华山
郑胜杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou Kimcheon Mining And Metallurgy Equipment Co Ltd
Original Assignee
Zhengzhou Kimcheon Mining And Metallurgy Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou Kimcheon Mining And Metallurgy Equipment Co Ltd filed Critical Zhengzhou Kimcheon Mining And Metallurgy Equipment Co Ltd
Priority to CN201721869403.5U priority Critical patent/CN207745704U/en
Application granted granted Critical
Publication of CN207745704U publication Critical patent/CN207745704U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model is related to a kind of double-wall spray equipments for smoke absorption, including absorption tower, absorb tower side wall and are equipped with gas inlet;Exhanst gas outlet is equipped at the top of absorption tower;Interlayer is equipped in absorption tower;Channel is equipped between interlayer bottom and the inner wall on absorption tower;Interlayer outer wall and the first flow for absorbing formation flue gas circulation between inner wall of tower;First flow is connected to gas inlet;It is the second flow channel of flue gas circulation in interlayer;Second flow channel is connected to exhanst gas outlet;First flow is connected to second flow channel by channel;The first spraying mechanism is equipped in first flow;The second spraying mechanism is equipped in second flow channel.The double-wall spray equipment for being used for smoke absorption carries out flue gas the absorption of uniform and complete, fume treatment efficiency can be improved, while improving the utilization rate of medicament, and less medicament loss reduces production cost.

Description

Double-wall spray equipment for smoke absorption
Technical field
The utility model belongs to the waste gas pollution control and treatment technical field of noble metal purification, and in particular to a kind of for smoke absorption Double-wall spray equipment.
Background technology
As national environmental protection policy is more and more stringent, the exhaust gas that many precious metal smelting enterprises generate becomes government's emphasis prison The object of control, by this device, in addition medicament, according to certain absorbing reaction process so that exhaust gas concentration drop to country or Person's professional standard is discharged, and atmosphere pollution is avoided.
Existing absorption tower collocation centrifugal blower uses, and flue gas only simply enters from absorption tower side, then up moves By the subsequent sucking centrifugal blower of 2-3 grades of sprays, such fume treatment mode there are fume treatments uneven, halfway disadvantage End, fume treatment is less efficient, and application in actual production causes medicament loss excessive, and the practical performance effect of medicament is insufficient, makes Increase at every operation cost.
Utility model content
The purpose of this utility model be to provide it is a kind of for the double-wall spray equipment of smoke absorption to solve existing cigarette The less efficient technical problem of aspiration receiving apparatus fume treatment.
In order to achieve the goal above, the technical solution that the utility model is taken is:Double-wall for smoke absorption sprays Device, including absorption tower absorb tower side wall and are equipped with gas inlet;Exhanst gas outlet is equipped at the top of absorption tower;It is equipped with and uses in absorption tower In the interlayer for forcing that flue gas is made to spread;The channel led to for plume is equipped between interlayer bottom and the inner wall on absorption tower;Folder Layer outer wall and the first flow for absorbing formation flue gas circulation between inner wall of tower;First flow is connected to gas inlet;It is in interlayer The second flow channel of flue gas circulation;Second flow channel is connected to exhanst gas outlet;First flow is connected to second flow channel by channel;First The first spraying mechanism for absorbing medicament to the flue gas sprinkling flowed in first flow is equipped in runner;It is set in second flow channel It is useful for absorbing the second spraying mechanism of medicament to the flue gas sprinkling flowed in second flow channel.
The double-wall spray equipment for smoke absorption of the utility model, absorption tower are internally provided with interlayer, and interlayer will be inhaled It receives tower section and is divided into two channels of first flow and second flow channel, the first spray is respectively equipped in first flow and second flow channel Device and the second spray equipment.Flue gas enters first flow from absorption tower top, and flue gas flows downward, and flue gas is narrow in first flow More disperse in narrow space, flue gas carries out after hitting strongly, and the medicament sprayed with the first spraying mechanism is sufficiently mixed and occurs Reaction.Subsequent smoke movement is entered by channel inside second flow channel to first flow bottom, and flue gas changes direction and transports upwards It is dynamic, flow out absorption tower after being mixed with the medicament that the second spraying mechanism sprays.Flue gas is reacted through multistage absorption with hybrid concurrency life, right Flue gas carries out the absorption of uniform and complete, fume treatment efficiency can be improved, while improving the utilization rate of medicament, less medicament loss, Reduce production cost.
Further, first spraying mechanism sprays the injection direction of medicament upward;Second spraying mechanism sprays medicament Injection direction downward.The direction of spray head and the direction of flow of flue gas are oppositely arranged, and are uniformly mixed, are carried with medicament convenient for flue gas High smoke absorption rate.
Further, the first flow is in the circular passage of interlayer, circular passage equipped with described in two groups first Spraying mechanism, the first spraying mechanism include spraying mechanism and first time spraying mechanism on first, and two group of first spraying mechanism can be right Flue gas in first flow carries out fully absorbing processing.
Further, spraying mechanism is located at the middle and upper part of first flow on described first, and first time spraying mechanism is located at the The bottom of one runner.A distance is equipped on first between spraying mechanism and gas inlet, can be reserved to entering in first flow Smoke absorption space.First time spraying mechanism position is relatively low, it is possible to increase the sphere of action of first time spraying mechanism.
Further, equipped with the second spraying mechanism described in two groups in the second flow channel, the second spraying mechanism includes second Upper spraying mechanism and second time spraying mechanism.Two group of second spraying mechanism can carry out the flue gas in second flow channel to fully absorb place Reason.
Further, spraying mechanism is located at the top of second flow channel on described second, and second time spraying mechanism is located at second The middle part of runner.Spraying mechanism can cover the flue gas in second flow channel complete on second.Second time spraying mechanism can be to second The flue gas of runner lower part is absorbed.
Further, first spraying mechanism is spray head;Second spraying mechanism is swirling jet spray head.It is first-class Space in road is more narrow, is applicable in spray head.Second flow channel space is larger, and swirling jet spray head can overall absorption and processing Flue gas.
Further, first spraying mechanism and the second spraying mechanism are respectively connected with medicament conveyance conduit, medicament conveying Pipeline is connected with medicament circulating pump.
Further, the double-wall spray equipment includes two absorption towers, and two absorption towers are connected in series with, absorption tower Outlet is connected with the wind turbine for extracting flue gas.Two concatenated absorption towers fully absorb and handle flue gas.
Description of the drawings
Fig. 1 is the double-wall spray equipment structural schematic diagram that smoke absorption is used in embodiment 1.
In figure:1, left absorption tower;2, right absorption tower;3, the first gas inlet;4, the first exhanst gas outlet;5, the second flue gas into Mouthful;6, the second exhanst gas outlet;7, wind turbine;8, interlayer;9, channel;10, first flow;11, second flow channel;12, spray head; 1201, upper spray head;1202, lower spray head;13, swirling jet spray head;1301, upper swirling jet spray head;1302, lower whirlpool Revolve jet stream spray head;14, medicament conveyance conduit;15, medicament circulating pump.
Specific implementation mode
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, the every other embodiment that those of ordinary skill in the art are obtained all belongs to In the range of the utility model protection.
The embodiment of double-wall spray equipment in the utility model for smoke absorption is as shown in Figure 1.
Embodiment 1
The double-wall spray equipment for smoke absorption of the present embodiment, including left absorption tower 1 and the suction of 2 two, right absorption tower Tower is received, two absorption towers are connected in series with by pipeline.1 side wall of left absorption tower is equipped with the first gas inlet 3, the first gas inlet 3 Top on left absorption tower 1 is set.1 top of left absorption tower is equipped with the first exhanst gas outlet 4.2 side wall of right absorption tower is equipped with the second cigarette Gas import 5, the second gas inlet 5 are arranged on the top on right absorption tower 2.2 top of right absorption tower is equipped with the second exhanst gas outlet 6.The Two exhanst gas outlets 6 are connected with the wind turbine 7 for extracting flue gas.
It is equipped in left absorption tower 1 and right absorption tower 2 for the interlayer 8 for forcing that flue gas is made to spread.8 bottom of interlayer with The channel 9 led to for plume is equipped between the inner wall on absorption tower.Flue gas circulation is formed between 8 outer wall of interlayer and absorption inner wall of tower First flow 10.First flow is connected to gas inlet.It is the second flow channel 11 of flue gas circulation in interlayer 8.Second flow channel and cigarette Gas outlet.First flow 10 is connected to second flow channel 11 by channel.
The first spray for absorbing medicament to the flue gas sprinkling flowed in first flow 10 is equipped in first flow 10 Mechanism.First spraying mechanism is spray head 12.Spray head 12 sprays the injection direction of medicament upward, i.e. the direction court of spray head On.First flow is that two groups of spray heads are equipped in the circular passage of interlayer, circular passage, respectively 1201 He of upper spray head Lower spray head 1202.Upper spray head 1201 and lower spray head 1202 include a ring around the injection direction spray upward of interlayer Head.Upper spray head 1201 is located at the middle and upper part of first flow 10, and lower spray head 1202 is located at the bottom of first flow 10.
The second spray for absorbing medicament to the flue gas sprinkling flowed in second flow channel 11 is equipped in second flow channel 11 Mechanism.Second spraying mechanism is swirling jet spray head 13.Swirling jet spray head 13 sprays the injection direction of medicament downward.The Two groups of swirling jet spray heads are equipped in two runners 11, respectively upper swirling jet spray head 1301 and lower swirling jet spray head 1302.Upper swirling jet spray head 1301 is located at the top of second flow channel, and lower swirling jet spray head 1302 is located at second flow channel 11 middle part.
First spraying mechanism and the second spraying mechanism are respectively connected with medicament conveyance conduit 14, and medicament conveyance conduit is connected with medicine Agent circulating pump 15.
Embodiment 2
The described double-wall spray equipment for being used for smoke absorption of the present embodiment, general configuration is consistent with embodiment 1, But it is not both with embodiment 1:It is provided only with an absorption tower.
Embodiment 3
The described double-wall spray equipment for being used for smoke absorption of the present embodiment, general configuration is consistent with embodiment 1, But it is not both with embodiment 1:First spraying mechanism is provided with one group, is located at the bottom of first flow.
Embodiment 4
The described double-wall spray equipment for being used for smoke absorption of the present embodiment, general configuration is consistent with embodiment 1, But it is not both with embodiment 1:Second spraying mechanism is provided with one group, is located at the top of second flow channel.

Claims (9)

1. for the double-wall spray equipment of smoke absorption, including absorption tower, it is characterised in that:Absorb tower side wall be equipped with flue gas into Mouthful, exhanst gas outlet is equipped at the top of absorption tower;The interlayer for forcing that flue gas is made to spread is equipped in absorption tower;Interlayer bottom and absorption The channel for flue gas circulation is equipped between the inner wall of tower;The first of flue gas circulation is formed between interlayer outer wall and absorption inner wall of tower Runner;First flow is connected to gas inlet;It is the second flow channel of flue gas circulation in interlayer;Second flow channel connects with exhanst gas outlet It is logical;First flow is connected to second flow channel by channel;It is equipped in first flow for the flue gas flowed in first flow Sprinkling absorbs the first spraying mechanism of medicament;It is equipped in second flow channel and is absorbed for being sprayed to the flue gas flowed in second flow channel Second spraying mechanism of medicament.
2. the double-wall spray equipment according to claim 1 for smoke absorption, it is characterised in that:First spray Mechanism sprays the injection direction of medicament upward;Second spraying mechanism sprays the injection direction of medicament downward.
3. the double-wall spray equipment according to claim 1 or 2 for smoke absorption, it is characterised in that:Described first Runner is in the circular passage of interlayer, circular passage Spraying mechanism and first time spraying mechanism on first.
4. the double-wall spray equipment according to claim 3 for smoke absorption, it is characterised in that:It is sprayed on described first Leaching mechanism is located at the middle and upper part of first flow, and first time spraying mechanism is located at the bottom of first flow.
5. the double-wall spray equipment according to claim 1 or 2 for smoke absorption, it is characterised in that:Described second Second spraying mechanism described in being equipped with two groups in runner, the second spraying mechanism include spraying mechanism and second time spray thrower on second Structure.
6. the double-wall spray equipment according to claim 5 for smoke absorption, it is characterised in that:It is sprayed on described second Leaching mechanism is located at the top of second flow channel, and second time spraying mechanism is located at the middle part of second flow channel.
7. the double-wall spray equipment according to claim 1 for smoke absorption, it is characterised in that:First spray Mechanism is spray head;Second spraying mechanism is swirling jet spray head.
8. the double-wall spray equipment according to claim 1 for smoke absorption, it is characterised in that:First spray Mechanism and the second spraying mechanism are respectively connected with medicament conveyance conduit, and medicament conveyance conduit is connected with medicament circulating pump.
9. the double-wall spray equipment according to claim 1 for smoke absorption, it is characterised in that:The double-wall spray Shower device includes two absorption towers, and two absorption towers are connected in series with, and the outlet on absorption tower is connected with the wind turbine for extracting flue gas.
CN201721869403.5U 2017-12-27 2017-12-27 Double-wall spray equipment for smoke absorption Expired - Fee Related CN207745704U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721869403.5U CN207745704U (en) 2017-12-27 2017-12-27 Double-wall spray equipment for smoke absorption

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721869403.5U CN207745704U (en) 2017-12-27 2017-12-27 Double-wall spray equipment for smoke absorption

Publications (1)

Publication Number Publication Date
CN207745704U true CN207745704U (en) 2018-08-21

Family

ID=63150881

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721869403.5U Expired - Fee Related CN207745704U (en) 2017-12-27 2017-12-27 Double-wall spray equipment for smoke absorption

Country Status (1)

Country Link
CN (1) CN207745704U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117358054A (en) * 2023-11-27 2024-01-09 北京实力伟业环保科技有限公司 Waste gas biological treatment device based on high acid-resistant desulfurization strain

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117358054A (en) * 2023-11-27 2024-01-09 北京实力伟业环保科技有限公司 Waste gas biological treatment device based on high acid-resistant desulfurization strain
CN117358054B (en) * 2023-11-27 2024-03-19 北京实力伟业环保科技有限公司 Waste gas biological treatment device based on high acid-resistant desulfurization strain

Similar Documents

Publication Publication Date Title
CN104259040B (en) A kind of water curtain type paint line paint spray booth
CN206587560U (en) The simple emission-control equipment in laboratory
CN205886486U (en) Spray paint waste gas treatment system
CN206492367U (en) Exhaust-gas treatment spray column in a kind of coating equipment
CN207745704U (en) Double-wall spray equipment for smoke absorption
CN202893166U (en) Flue gas denitration device
CN203678203U (en) Tristate purifier
CN208436641U (en) A kind of elution device of efficient removal tantalum niobium waste gas decomposition
CN204996289U (en) Waste gas treatment system sprays paint based on plasma purification techniques
CN204051315U (en) A kind of water spray cleaner
CN207187510U (en) A kind of vortex mixed SCR denitration device
CN206404504U (en) A kind of emission-control equipment painted for hardware
CN206593127U (en) No smoke environmental protection and energy conservation chimney device
CN202410469U (en) Dust collection system for dried adipic acid
CN207745682U (en) Dynamic wave spray equipment for smoke absorption
CN205517145U (en) A gas collection discharging equipment for copper -plating production line
CN207221653U (en) A kind of processing unit of organic exhaust gas
CN206823505U (en) A kind of efficient desulfurizing tower for smoke gas treatment
CN203569055U (en) Water scrubber applied to coke oven gas purification system
CN204093295U (en) A kind of desulfurizing tower import sprayer unit
CN208406456U (en) A kind of Venturi wet-process dust-extraction unit
CN210751966U (en) Compound fertilizer production tail gas processing apparatus
CN211328825U (en) Waste gas treatment system in production of reinforced water reducing agent
CN109603478A (en) A kind of environmentally protective arc tunnel nitrogen oxides exhaust gas processing device and processing method
CN202044892U (en) Reverse-umbrella type directional liquid film smoke-elimination dust-collection desulfurization and denitrification unit

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180821

Termination date: 20201227

CF01 Termination of patent right due to non-payment of annual fee