Utility model content
In view of the deficiencies of the prior art, the utility model develops a kind of for the automatic clear of amine purification electrodialysis plant
Wash down electrode systems, optimization solves electrodialysis plant runner in amine purification and is easy contamination and plugging, and the cleaning frequency is short etc. to ask
Topic.
To realize goal of the invention, the technical problems to be solved by the invention:
The automatic of electrodialysis amine purification equipment cleans electrode systems, including electrodialysis plant, has two in electrodialysis plant
The import of paths, two paths is connected with two amine liquid input channels respectively, the outlets of two paths respectively with two amine liquid
Output channel is connected, and the system further includes that cleaning water tank and flushing water pump, the cleaning water tank pass through pipeline and ejected wash water
Pump is connected, and the flushing water pump is divided to two-way logical in the two-way of nearly electrodialysis plant with two amine liquid input channels respectively by pipeline
The entrance in road is connected, and is interconnected with two input bypass lines between two amine liquid input channels, described two
It is interconnected with two output bypass lines between root amine liquid output channel, operated pneumatic valve is equipped on above-mentioned each road pipeline.
Preferably, the cleaning water tank 14 is equipped with liquid level meter 13, prevents water for cleaning from overflowing, prevent water for cleaning from using
It is complete to cause to be pumped into air in flushing water pump.
Preferably, electrode systems further include electric automatic control case for the automatic cleaning of the electrodialysis amine purification equipment
16, the electric automatic control case 16 is connected by cable with each operated pneumatic valve, flushing water pump, liquid level meter, flushing water pump, gas
The startup closing of movable valve is executed by PLC automatic control system, avoids manual operation.
Preferably, fire-proof motor of the flushing water pump 11 using ExIIBT4 grades, to be suitable for petroleum and petrochemical industry
It uses.
Preferably, being equipped with air manometer, the pressure for measuring electric automatic control case on electric automatic control case
Power.
The beneficial effects of the utility model are embodied in:
1, it can effectively slow down electrodialysis plant internal contamination, extend the electrodialytic cleaning frequency, extend electrodialysis plant
Service life.
2, amine liquid will not be mixed in the flow of pole with concentrated water, extra amine liquid will not be discharged, having for concentrated water will not be made
Machine object content rises, and causes processing/discharge difficult.
3, the system is automatically controlled by PLC realizations, and self-controlled platform can be by the probe mounted on each position, to each
Position liquid level, valve switch, pump switch etc. are automatically controlled in real time, are accomplished the all-weather monitoring run to device and realized
The unmanned management of equipment operation.
Specific implementation mode
The utility model is illustrated with reference to specific embodiment.
The automatic cleaning electrode systems, including electrodialysis plant 12 of electrodialysis amine purification equipment as shown in Figure 1, electric osmose
There are two paths, the import of two paths to be connected respectively with two amine liquid input channels 17 in desorption device 12, two paths go out
Mouth is connected with two amine liquid output channels 18 respectively, and the system further includes cleaning water tank 14 and flushing water pump 11, described clear
Water tank 14 is connected by pipeline with flushing water pump 11, and the flushing water pump 11 is divided to two-way defeated with two amine liquid respectively by pipeline
The entrance for entering pipeline 17 in the two paths of nearly electrodialysis plant 12 is connected, and is used between two amine liquid input channels 17
Two input bypass lines 19 interconnect, mutual with two output bypass lines 20 between described two amine liquid output channels 18
It is connected, operated pneumatic valve 1-10 is equipped on above-mentioned each road pipeline, air manometer is equipped on electric automatic control case 16
15, the pressure for measuring electric automatic control case.
The cleaning water tank 14 is equipped with liquid level meter 13, prevents water for cleaning from overflowing, and preventing water for cleaning to be finished causes clearly
It is pumped into air in wash water pump;Electrode systems further include electric automatic control case for the automatic cleaning of the electrodialysis amine purification equipment
16, the electric automatic control case 16 is connected by cable with each operated pneumatic valve, flushing water pump, liquid level meter, flushing water pump, gas
The startup closing of movable valve is executed by PLC automatic control system, avoids manual operation;The flushing water pump 11 uses Ex II
The fire-proof motor of BT4 grades, to be suitable for petroleum and petrochemical industry use.
The automatic workflow for cleaning electrode systems of the electrodialysis amine purification equipment includes the following steps:
1, when electrodialysis plant normal operation, this system is in halted state, and air-operated bi-directional valve 2,3,8,9 is in Fig. 1
Opening state, air-operated bi-directional valve 1,4,5,6,7,10 are closed.
2, membrane stack wash phase.
Electrodialysis plant, which enters, cleans the when of falling polar period, first closes electrodialysis plant, closes air-operated bi-directional valve 1,2,3,4,
Air-operated bi-directional valve 5,6 is opened, air-operated bi-directional valve 8,9 is still in opening state, and air-operated bi-directional valve 7,10 is still in closed state.So
Start flushing water pump 11 afterwards, the liquid level of cleaning water tank 14 is monitored by liquid level gauge 13, it is pneumatically double by 16 coordinated signals of PLC control cabinet
Cleaning water tank 14 is kept to be constantly in intermediate liquid level in this stage to valve 6 and flushing water pump 11.
Membrane stack scavenging period is determined that general cleaning to membrane stack exports water quality Ph close to 7, and conductance is less than by membrane stack outlet water quality
Subject to 50us/cm, equipment debugging period can attempt to obtain the average value of this time, then be reached by the way that PLC control cabinet 16 is written
AutoPlay function.
3, the stage of falling pole.
After the completion of membrane stack wash phase, air-operated bi-directional valve 6 is closed, closes flushing water pump 11, air-operated bi-directional valve 5 is closed, beats
Air-operated bi-directional valve 1,4,7,10 is opened, air-operated bi-directional valve 8,9 is closed, starts electrodialysis plant operation, you can reach the operation of falling pole mesh
's.
4, after the completion of the stage of falling pole, this system, which is in, closes halted state, and electrodialysis plant enters the normal operation period.
5, the when of falling polar period is cleaned into second, first closes electrodialysis plant, air-operated bi-directional valve 1,2,3,4 is closed, beats
Air-operated bi-directional valve 5,6 is opened, air-operated bi-directional valve 7,10 is still in opening state, and air-operated bi-directional valve 8,9 is still in closed state.Then
Start flushing water pump 11, the liquid level of cleaning water tank 14 is monitored by liquid level gauge 13, it is pneumatically two-way by 16 coordinated signals of PLC control cabinet
Valve 6 and flushing water pump 11 are constantly in intermediate liquid level to keep cleaning water tank 14 in this stage.
6, after the completion of membrane stack wash phase, air-operated bi-directional valve 6 is closed, closes flushing water pump 11, closes air-operated bi-directional valve 5,
Air-operated bi-directional valve 2,3,8,9 is opened, air-operated bi-directional valve 7,10 is closed, starts electrodialysis plant operation.So far, electrodialysis plant
Operating status is consistent with initial operating state.
7, it is recycled according to the above process cycle, can achieve the purpose that clean pole automatically.
The above description is only the embodiments of the present invention, and it does not limit the scope of the patent of the present invention, every
Using equivalent structure or equivalent flow shift made by the utility model description, or it is used in other relevant skills indirectly