CN207686144U - A kind of high stress steel strand integral bundle extruding drag-line - Google Patents

A kind of high stress steel strand integral bundle extruding drag-line Download PDF

Info

Publication number
CN207686144U
CN207686144U CN201721828093.2U CN201721828093U CN207686144U CN 207686144 U CN207686144 U CN 207686144U CN 201721828093 U CN201721828093 U CN 201721828093U CN 207686144 U CN207686144 U CN 207686144U
Authority
CN
China
Prior art keywords
sealing drum
anchor head
guy
sleeve
steel cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721828093.2U
Other languages
Chinese (zh)
Inventor
苏桥
陈贵鹏
韦飞
韦覃茂
黄世祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liuzhou Gui Bridge Cable Co Ltd
Original Assignee
Liuzhou Gui Bridge Cable Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Liuzhou Gui Bridge Cable Co Ltd filed Critical Liuzhou Gui Bridge Cable Co Ltd
Priority to CN201721828093.2U priority Critical patent/CN207686144U/en
Application granted granted Critical
Publication of CN207686144U publication Critical patent/CN207686144U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model is related to a kind of high stress steel strand integral bundles to squeeze drag-line, two anchorages including guy of twisted steel cable and mounted on guy of twisted steel cable both ends, anchorage includes squeezing anchor head, nut, sealing drum, seal assembly, buffer sleeve and damper, nut, which is mounted on, to be squeezed on anchor head, buffering sleeve one end is connect with anchor head is squeezed, the buffering sleeve other end is connect with sealing drum, damper is mounted in sealing drum and is close to buffer sleeve end face, guy of twisted steel cable end penetrates sealing drum, guy of twisted steel cable end divests PE steel strand wires across damper and buffering sleeve and is fixed in extruding anchor head, extruding anchor cephalic par is sealed by anchor head seal cover board, it buffers and is filled with epoxy resin mortar in sleeve, anti-corrosion packing material is perfused in sealing drum, it is sealed by seal assembly between sealing drum end and guy of twisted steel cable.The utility model can meet the fatigue behaviour of 400MPa stress amplitudes, can bear the stress variation amplitude of bigger.

Description

A kind of high stress steel strand integral bundle extruding drag-line
Technical field
The utility model is related to a kind of drag-line, more particularly to a kind of high stress steel strand integral bundle squeezes drag-line.
Background technology
At present country's bridge and the application of building construction drag-line it is most be that steel strand integral bundle squeezes drag-line, the stayed structure ruler Very little small, drag-line intensity is high, is largely applied in bridge and building construction.
The design Suo Li of drag-line(Drag-line allows the maximum pull used on bridge, generally considers 2~2.5 times of safety systems Number)Generally the 0.4~0.45 of drag-line limit fracture Suo Li, while drag-line should also meet the requirement of fatigue behaviour.Fatigue behaviour It is required that it is 0.45 times of drag-line ultimate tension that drag-line, which should be able to meet upper threshold force, stress amplitude 200MPa is recycled 2,000,000 times, and drag-line is not Allow have 2%~5% fracture of wire.Popular says, 0.45 times that drag-line is exactly moved to ultimate tension.Then power is lowered again, Range of decrease intensity is 200MPa, then moves 0.45 times of ultimate tension to again, is repeated 2,000,000 times.It is influenced by material and structure, at present The stress amplitude of this drag-line is very low, is no more than 200MPa.Main cause is caused by the structure of anchorage, steel strand wires extruding anchor, steel Twisted wire is directly extruded in anchor cup from finished product rope to anchor cup, the process of neither one transition, steel strand wires are squeezed, and stress is too big, steel For twisted wire when being shaken, power is directly delivered to steel strand wires extruded parts, is easy fatigue break.
In recent years, the increasing of infrastructure, various special bridges and building increase.Both existing drag-lines have been expired The needs that foot is not built, the drag-lines of more requirement of engineering high stress width.Especially in coastal waters or bridge over strait, disliked The influence of bad weather, drag-line moment stress change very greatly, it is desirable that drag-line can bear the stress variation amplitude of bigger.
Invention content
The technical problems to be solved in the utility model is:A kind of high stress steel strand integral bundle extruding drag-line, the drag-line are provided The fatigue behaviour of 400MPa stress amplitudes can be met, the stress variation amplitude of bigger can be born.
Solving the technical solution of above-mentioned technical problem is:A kind of high stress steel strand integral bundle extruding drag-line, including steel strand wires Drag-line and two anchorages mounted on guy of twisted steel cable both ends, the anchorage include squeezing anchor head, nut, sealing drum and sealing Component, the anchorage further include having buffering sleeve and damper, and nut, which is mounted on, to be squeezed on anchor head, is buffered sleeve one end and is squeezed Anchor head connection, the buffering sleeve other end is pressed to be connect with sealing drum, damper is mounted in sealing drum and is close to buffer sleeve end face, Guy of twisted steel cable end penetrates sealing drum, and guy of twisted steel cable end divests PE steel strand wires across damper and buffering sleeve and consolidates It is scheduled on and squeezes in anchor head, extruding anchor cephalic par is sealed by anchor head seal cover board, and epoxy resin mortar, sealing are filled in buffering sleeve It is perfused with anti-corrosion packing material in cylinder, is sealed by seal assembly between sealing drum end and guy of twisted steel cable.
The both ends of the buffering sleeve are that the mode being connected through a screw thread is connect with extruding anchor head, sealing drum respectively.
The cross sectional shape of the buffering sleeve lining is dentation.
The utility model is characterized in that:1, a buffering sleeve is increased, high-strength epoxy mortar is perfused in buffering sleeve Inner, Effectively reduce the vibrations that steel strand wires are generated in stress alternation variation;2, damper is increased, steel strand wires are effectively eliminated Vibrations.
For drag-line when stress, steel strand wires will produce vibrations, when especially stress amplitude generation alternately changes, vibrations It can be more severe.Drag-line of the present invention and conventional extruding drag-line compare, more buffering sleeve, epoxy resin mortar and dampers, drag-line Vibrations major part is eliminated by damper, be then passed on the epoxy resin mortar of solidification, then by buffer sleeve, be transmitted to crowded Anchor head, the steel strand wires position being finally easily broken off are pressed, that is, the steel strand wires position that anchor head Inner is extruded, the vibrations being subject to are Very little.So, the fatigue behaviour of drag-line is significantly improved, and can hold the lotus for can standing high stress amplitude variation It carries.
It is detected according to method specified in People's Republic of China (PRC) traffic transport industry standard JT/T 850-2013, this reality Reach 400MPa with novel stress amplitude.
In the following, squeezing a kind of high stress steel strand integral bundle of the utility model the technology of drag-line in conjunction with the accompanying drawings and embodiments Feature is further described.
Description of the drawings
Fig. 1:The high stress steel strand integral bundle of the utility model squeezes stayed structure schematic diagram.
Fig. 2:When the utility model makes, the pre-installed position schematic diagram of each parts.
Fig. 3:When the utility model makes, steel strand wires, which penetrate to squeeze, squeezes tight schematic diagram in anchor head.
Fig. 4:When the utility model makes, the schematic diagram of buffering sleeve Inner perfusion epoxy resin mortars.
In figure:1- anchor head seal cover boards, 2- extruding anchor heads, 3- nuts, 4- buffering sleeves, 5- epoxy resin mortars, 6- dampers, 7- guy of twisted steel cable, 8- anti-corrosion packing materials, 9- sealing drums, 10- seal assemblies.
P indicates extrusion die core in Fig. 3.
Specific implementation mode
Embodiment 1:A kind of high stress steel strand integral bundle extruding drag-line, as shown in Figure 1, including guy of twisted steel cable 7 and installation Two anchorages at guy of twisted steel cable both ends, the anchorage include squeezing anchor head 2, nut 3, sealing drum 9 and seal assembly 10, The anchorage further includes having buffering sleeve 4 and damper 6, and damper 6 is made of rubber material, and nut is mounted on extruding anchor On head, buffering sleeve one end is connect with anchor head is squeezed, and the buffering sleeve other end is connect with sealing drum, and damper is mounted on sealing drum Interior and be close to buffer sleeve end face, guy of twisted steel cable end penetrates sealing drum, and the PE steel strand wires that divest of guy of twisted steel cable end are worn It crosses damper and buffering sleeve and is fixed on and squeeze in anchor head, extruding anchor cephalic par is sealed by anchor head seal cover board 1, cushion collar It is filled with epoxy resin mortar 5 in cylinder, anti-corrosion packing material 8 is perfused in sealing drum, leads between sealing drum end and guy of twisted steel cable Cross seal assembly sealing.
In the present embodiment, the both ends of the buffering sleeve be the mode that is connected through a screw thread respectively with squeeze anchor head, close Sealed tube connects.
In the present embodiment, the cross sectional shape of the buffering sleeve lining is the dentation with multiple trapezoidal grooves, to increase Add epoxy resin mortar and buffer the contact area of sleeve, epoxy resin mortar is enable to be firmly fixed in buffering sleeve.
The production process of the utility model is as follows:
1, the prepackage of parts is installed each part by Fig. 2.
2, steel strand wires are penetrated into extruding anchor head, by extruder, drag-line steel strand wires is squeezed to tight, as shown in Figure 3
3, after squeezing, by cushion collar wound packages on squeezing anchor head, drag-line is placed vertically, as shown in figure 4, in buffering sleeve Epoxy resin mortar is perfused in Inner, and epoxy resin mortar intensity is very high, has 100MPa or more after solidification, energy is effective and steel strand wires are bonded to one It rises, prevents steel strand wires from generating vibrations after entering to squeeze anchor head.
4, after epoxy resin mortar solidification, damper is pushed to come, has refilled sealing drum, seal assembly, sealing drum Inner perfusions are anti- Rotten packing material, then processing squeeze the external screw thread of anchor head, and whole drag-line is with regard to completion of processing.

Claims (3)

1. a kind of high stress steel strand integral bundle squeezes drag-line, including guy of twisted steel cable(7)With mounted on guy of twisted steel cable both ends Two anchorages, the anchorage include squeezing anchor head(2), nut(3), sealing drum(9)And seal assembly(10), feature exists In:The anchorage further includes having buffering sleeve(4)And damper(6), nut, which is mounted on, to be squeezed on anchor head, and sleeve one end is buffered It is connect with anchor head is squeezed, the buffering sleeve other end is connect with sealing drum, and damper is mounted in sealing drum and is close to buffer sleeve End face, guy of twisted steel cable end penetrate sealing drum, and the PE steel strand wires that divest of guy of twisted steel cable end pass through damper and cushion collar Cylinder is simultaneously fixed in extruding anchor head, and extruding anchor cephalic par passes through anchor head seal cover board(1)Sealing, buffering sleeve is interior to be filled with epoxy Mortar(5), anti-corrosion packing material is perfused in sealing drum(8), pass through seal assembly between sealing drum end and guy of twisted steel cable Sealing.
2. a kind of high stress steel strand integral bundle according to claim 1 squeezes drag-line, it is characterised in that:The cushion collar The both ends of cylinder are that the mode being connected through a screw thread is connect with extruding anchor head, sealing drum respectively.
3. a kind of high stress steel strand integral bundle according to claim 1 or 2 squeezes drag-line, it is characterised in that:Described is slow The cross sectional shape for rushing sleeve lining is dentation.
CN201721828093.2U 2017-12-22 2017-12-22 A kind of high stress steel strand integral bundle extruding drag-line Active CN207686144U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721828093.2U CN207686144U (en) 2017-12-22 2017-12-22 A kind of high stress steel strand integral bundle extruding drag-line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721828093.2U CN207686144U (en) 2017-12-22 2017-12-22 A kind of high stress steel strand integral bundle extruding drag-line

Publications (1)

Publication Number Publication Date
CN207686144U true CN207686144U (en) 2018-08-03

Family

ID=62995958

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721828093.2U Active CN207686144U (en) 2017-12-22 2017-12-22 A kind of high stress steel strand integral bundle extruding drag-line

Country Status (1)

Country Link
CN (1) CN207686144U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110725547A (en) * 2019-10-17 2020-01-24 柳州欧维姆机械股份有限公司 Compact steel strand inhaul cable and manufacturing method thereof
CN112942102A (en) * 2021-02-03 2021-06-11 柳州欧维姆机械股份有限公司 Prestressed inhaul cable anchorage device with elastic sealing cylinder

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110725547A (en) * 2019-10-17 2020-01-24 柳州欧维姆机械股份有限公司 Compact steel strand inhaul cable and manufacturing method thereof
CN110725547B (en) * 2019-10-17 2023-08-11 柳州欧维姆机械股份有限公司 Compact steel strand inhaul cable and manufacturing method thereof
CN112942102A (en) * 2021-02-03 2021-06-11 柳州欧维姆机械股份有限公司 Prestressed inhaul cable anchorage device with elastic sealing cylinder

Similar Documents

Publication Publication Date Title
CN103669208B (en) A kind of anchoring process being applicable to large-tonnage FRP inhaul cable
CN108004926B (en) Large-tonnage FRP inhaul cable anchoring process
CN207686144U (en) A kind of high stress steel strand integral bundle extruding drag-line
CN101210447B (en) Steel strand integral bundle extrusion anchor cable guy cable
CN202450444U (en) Cross-ear type steel-strand stay cable anchor
CN103147440A (en) Construction method of prestressed anchor cable
CN101235663A (en) Clip type anchorage applying to carbon fiber reinforced polymeric material prestressing force rib
CN212641209U (en) Steel strand inhaul cable steering anchoring structure with complete reeving pore channel
CN207828785U (en) A kind of high stress steel strand wires extruding drag-line
CN107447757A (en) The Extruded anchoring tool and anchoring process of a kind of FRP tendons
CN205134756U (en) Steel strand wires connector
US10570992B2 (en) Coupler for stranded rope
CN200999418Y (en) Steel strand hank extruding anchor wire bracing cable
CN205529907U (en) P -type anchorage device at fixed end
CN112458898A (en) Corrosion-resistant fatigue-resistant chilled casting anchorage device for ultra-high-strength and ultra-long stay cable
CN203603061U (en) Carbon fiber composite inhaul cable
CN108532335A (en) A kind of high stress width squeezes anchoring guy of twisted steel cable and preparation method thereof
CN201738241U (en) FRP rib and steel strand connector and composite inhaul cable
CN101864725B (en) FRP (Fiber Reinforce Plastic) tendon and steel strand connector and compound stay cable
CN202299136U (en) Dispersion type anchored prestressed carbon fiber stranded wire anchorage system
CN210713525U (en) High-strength wear-resistant slow-bonding prestressed steel strand
CN209100064U (en) A kind of high bond stress anchor cable structure
CN2573774Y (en) Resin filled extrusion fastening body device
CN209100066U (en) A kind of quick tensioning anchor cable structure
CN106192764A (en) A kind of pre-stress FRP concrete box type girder and production technology

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A high stress steel strand whole bundle extrusion cable

Effective date of registration: 20220412

Granted publication date: 20180803

Pledgee: Guangxi Guihui Financing Guarantee Co.,Ltd.

Pledgor: LIUZHOU GUIQIAO CABLE Co.,Ltd.

Registration number: Y2022450000041