CN207671649U - Construction material transports lifter - Google Patents
Construction material transports lifter Download PDFInfo
- Publication number
- CN207671649U CN207671649U CN201721714134.5U CN201721714134U CN207671649U CN 207671649 U CN207671649 U CN 207671649U CN 201721714134 U CN201721714134 U CN 201721714134U CN 207671649 U CN207671649 U CN 207671649U
- Authority
- CN
- China
- Prior art keywords
- motor
- sliding block
- leading screw
- construction material
- sliding rail
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model discloses construction materials to transport lifter, including frame, first motor, first leading screw, first sliding rail, first sliding block, connecting plate, second sliding rail, second sliding block, second motor, second leading screw, the construction material transports lifter, clever structure, it is powerful, it is easy to operate, it is time saving and energy saving, by using the device, without staff using cart by construction material transports and staff manually promotes construction material mode, the processing promoted again can be first transported to construction material, greatly reduce the working strength of staff.
Description
Technical field
The utility model is related to lifters more particularly to construction material to transport lifter.
Background technology
Currently, the construction material on construction site does not have dedicated transport lifter, the traditional transport of construction material to be promoted
Mode is that staff first transports construction material using construction material cart mostly, when construction material is transported to specified
Behind region, staff carries out promotion processing by way of manually carrying to the construction material after transport again, and such mode is taken
When it is laborious, significantly increase the working strength of staff, in view of disadvantages described above, it is really necessary to design building transport of materials to carry
Rise device.
Utility model content
The technical problem to be solved by the utility model is to:Construction material is provided and transports lifter, to solve background skill
The problem of art proposes.
In order to solve the above technical problems, the technical solution of the utility model is:Construction material transports lifter, including frame
Frame, first motor, the first leading screw, the first sliding rail, the first sliding block, connecting plate, the second sliding rail, the second sliding block, the second motor, second
Leading screw, the first motor are located at left and right sides of lower portion, and the first motor is connected with frame screw thread, and described the
One leading screw is located at the top of first motor, and first leading screw is connected with first motor close-fitting, and first leading screw runs through
Frame, first leading screw are connected with frame member, and first sliding rail is located at left and right sides of frame roof, and described the
One sliding rail is connected with frame welding, and first sliding block is located on the inside of the first sliding rail, first sliding block and the first sliding rail
Sliding is connected, and first sliding block, through the first leading screw, first sliding block is connected with the first threads of lead screw, described
Connecting plate be located at the first sliding block between any two, the connecting plate is weldingly connected with the first sliding block, the second sliding rail position
At the top of connecting plate, second sliding rail is connected with connecting plate screw thread, and second sliding block is located at the top of the second sliding rail, institute
The second sliding block stated is connected with the sliding of the second sliding rail, and second motor is located at connecting plate top left side, the described second electricity
Machine is connected with connecting plate screw thread, and second leading screw is located on the right side of the second motor, and second leading screw and the second motor are tight
With being connected, and second leading screw runs through the second sliding block, and second leading screw is connected with the second sliding block screw thread.
Further, second slider top is additionally provided with placing box, and the placing box is connected with the second sliding block screw thread.
Further, the lower portion middle-end is additionally provided with transformer, and the transformer is connected with frame screw thread.
Further, it is additionally provided with plug on the right side of the transformer, the plug is connected with transformer conducting wire.
Compared with prior art, which transports lifter, in use, staff promotes required transport first
Construction material be positioned in placing box, staff again with hand open the second motor positive rotating function, at this point, the second motor drive
Dynamic second leading screw does clockwise rotation, under the action of the second leading screw and the second sliding block screw-driven so that the second sliding block
It drives placing box to do along the direction of the second sliding rail to move from left to right, in the above manner, to the construction material in placing box
Transport processing is carried out, after the distance that placing box moves from left to right reaches the demand of staff, staff is first closed with hand
The second motor is closed, then opens the positive rotating function of first motor with hand, at this point, first motor drives the first leading screw to rotate clockwise
Function, under the action of the first leading screw and the first sliding block screw-driven so that the first sliding block drives connecting plate to be done together with placing box
It moves from bottom to top, in the above manner, promotion processing is carried out to the construction material in placing box, when placing box moves from bottom to top
After dynamic distance reaches the demand of staff, staff closes first motor with hand again, in the above manner, finally
So that the device first transports construction material the processing promoted again, which transports lifter, clever structure, function
It is powerful, it is easy to operate, it is time saving and energy saving, by using the device, construction material is transported using cart without staff
And the mode that staff manually promotes construction material, you can construction material first transported and is promoted again
After processing greatly reduces the working strength of staff, while construction material after being promoted in placing box is removed, work
Make personnel again with hand open first motor reverse function, allow placing box to do with this and move from top to bottom, when placing box on to
After the distance of lower movement reaches the demand of staff, staff first closes first motor with hand, is then turned on the second motor
Reverse function allows placing box to do and moves from right to left with this, when the distance that placing box moves from right to left reaches staff's
After demand, staff closes the second motor with hand, and staff again places the construction material that promotion is transported needed for next group
In in placing box, then similarly above step is first transported the processing promoted again, plug to the construction material in placing box
It is to allow extraneous power supply to carry out energy supply to the device with this, transformer is in order to ensure the dress to connect extraneous power supply
The stability of voltage is set, the first motor and the second motor are clockwise and anticlockwise motor, and the first motor model is preferably
OKD3KW220VAC, second motor model is preferably 2IK6RGN-C+2GN3K.
Description of the drawings
Fig. 1 is the local front sectional view of construction material transport lifter;
Fig. 2 is the connection sectional view of the first sliding rail, the first sliding block and the first leading screw;
Fig. 3 is the connection sectional view of the second sliding rail, the second sliding block and the second leading screw.
Frame 1, first motor 2, the first leading screw 3, the first sliding rail 4, the first sliding block 5, connecting plate 6, the second sliding rail 7, second
Sliding block 8, the second motor 9, the second leading screw 10, transformer 101, plug 102, placing box 801.
Following specific implementation mode will be further illustrated in conjunction with above-mentioned attached drawing.
Specific implementation mode
Hereinafter, a variety of specific details are elaborated, in order to provide the saturating of the concept to constituting described embodiment basis
Thorough understanding.However, it will be apparent to those skilled in the art that described embodiment can be in these no specific details
In some or all situations get off practice.In other cases, well-known processing step is not specifically described.
As shown in Figure 1, Figure 2, Figure 3 shows, construction material transports lifter, including frame 1, first motor 2, the first leading screw 3, the
One sliding rail 4, the first sliding block 5, connecting plate 6, the second sliding rail 7, the second sliding block 8, the second motor 9, the second leading screw 10, described first
Motor 2 is located at the 1 inside left and right sides of frame, and the first motor 2 is connected with 1 screw thread of frame, and first leading screw 3 is located at
2 top of first motor, first leading screw 3 is connected with 2 close-fitting of first motor, and first leading screw 3 runs through frame 1,
First leading screw 3 is rotatedly connected with frame 1, and first sliding rail 4 is located at the top of frame 1 left and right sides, and described the
One sliding rail 4 is weldingly connected with frame 1, and first sliding block 5 is located at 4 inside of the first sliding rail, first sliding block 5 and first
The sliding of sliding rail 4 is connected, and first sliding block 5 is through the first leading screw 3,3 screw thread of the first sliding block 5 and the first leading screw
It is connected, the connecting plate 6 is located at the first sliding block 5 between any two, and the connecting plate 6 is weldingly connected with the first sliding block 5, described
The second sliding rail 7 be located at the top of connecting plate 6, second sliding rail 7 is connected with 6 screw thread of connecting plate, second sliding block 8
In 7 top of the second sliding rail, second sliding block 8 is connected with the sliding of the second sliding rail 7, and second motor 9 is located at connecting plate 6
Top left side, second motor 9 are connected with 6 screw thread of connecting plate, and second leading screw 10 is located at 9 right side of the second motor,
Second leading screw 10 is connected with 9 close-fitting of the second motor, and second leading screw 10 runs through the second sliding block 8, and described the
Two leading screws 10 are connected with 8 screw thread of the second sliding block, and 8 top of the second sliding block is additionally provided with placing box 801, the placing box
801 are connected with 8 screw thread of the second sliding block, and the 1 inside middle-end of frame is additionally provided with transformer 101, the transformer 101 and frame
1 screw thread of frame is connected, and 101 right side of transformer is additionally provided with plug 102, the plug 102 and 101 conducting wire phase of transformer
Even.
The construction material transports lifter, in use, staff places the construction material that required transport is promoted first
In in placing box 801, staff opens the positive rotating function of the second motor 9 with hand again, at this point, the second motor 9 drives second
Thick stick 10 does clockwise rotation, under the action of the second leading screw 10 and the second 8 screw-driven of sliding block so that 8 band of the second sliding block
Dynamic placing box 801 is done along the direction of the second sliding rail 7 to be moved from left to right, in the above manner, to the building in placing box 801
Material carries out transport processing, and after the distance that placing box 801 moves from left to right reaches the demand of staff, staff is first
The second motor 9 is closed with hand, is then turned on the positive rotating function of first motor 2, at this point, first motor 2 drives the first leading screw 3 to do up time
Needle rotation function, under the action of the first leading screw 3 and the first 5 screw-driven of sliding block so that the first sliding block 5 drives connecting plate 6 to connect
It does with placing box 801 and moves from bottom to top, in the above manner, promotion processing is carried out to the construction material in placing box 801, when
After the distance that placing box 801 moves from bottom to top reaches the demand of staff, staff closes first motor 2 with hand again and is
Can, in the above manner, finally the device is made first to be transported the processing promoted again to construction material, meanwhile, work as placing box
After construction material after being promoted in 801 is removed, staff opens the reverse function of first motor 2 with hand again, is allowed and is put with this
It sets case 801 and does and move from top to bottom, after the distance that placing box 801 moves from top to bottom reaches the demand of staff, work
Personnel first close first motor 2 with hand, then the reverse function of the second motor 9 is opened with hand, allow placing box 801 to do by dextrad with this
It moves left, after the distance that placing box 801 moves from right to left reaches the demand of staff, staff closes second with hand
The construction material that promotion is transported needed for next group is positioned in placing box 801 by motor 9, staff again, then the similarly above step
Suddenly the processing promoted again is first transported to the construction material in placing box 801, plug 102 is to connect extraneous electricity
Source allows extraneous power supply to carry out energy supply to the device with this, and transformer 101 is in order to ensure the stabilization of the device voltage
Property, the first motor 2 and the second motor 9 are clockwise and anticlockwise motor, and 2 model of first motor is preferably
OKD3KW220VAC, 9 model of the second motor is preferably 2IK6RGN-C+2GN3K.
The utility model is not limited to above-mentioned specific embodiment, and those skilled in the art visualize from above-mentioned
Hair, without performing creative labour, the various transformation made are all fallen within the scope of protection of the utility model.
Claims (4)
1. construction material transports lifter, it is characterised in that slided including frame, first motor, the first leading screw, the first sliding rail, first
Block, connecting plate, the second sliding rail, the second sliding block, the second motor, the second leading screw, the first motor are located at lower portion or so
Both sides, the first motor are connected with frame screw thread, and first leading screw is located at the top of first motor, described first
Thick stick is connected with first motor close-fitting, and first leading screw runs through frame, and first leading screw is connected with frame member, institute
The first sliding rail stated is located at left and right sides of frame roof, and first sliding rail is connected with frame welding, first sliding block
On the inside of the first sliding rail, first sliding block is slided with the first sliding rail to be connected, and first sliding block is through first
Leading screw, first sliding block are connected with the first threads of lead screw, and the connecting plate is located at the first sliding block between any two, described
Connecting plate is weldingly connected with the first sliding block, and second sliding rail is located at the top of connecting plate, second sliding rail and connecting plate
Screw thread is connected, and second sliding block is located at the top of the second sliding rail, and second sliding block is connected with the sliding of the second sliding rail, described
The second motor be located at connecting plate top left side, second motor is connected with connecting plate screw thread, the second leading screw position
On the right side of the second motor, second leading screw is connected with the second motor close-fitting, and second leading screw runs through the second sliding block,
Second leading screw is connected with the second sliding block screw thread.
2. construction material as described in claim 1 transports lifter, it is characterised in that second slider top is additionally provided with
Placing box, the placing box are connected with the second sliding block screw thread.
3. construction material as claimed in claim 2 transports lifter, it is characterised in that the lower portion middle-end is additionally provided with
Transformer, the transformer are connected with frame screw thread.
4. construction material as claimed in claim 3 transports lifter, it is characterised in that be additionally provided on the right side of the transformer slotting
Head, the plug are connected with transformer conducting wire.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721714134.5U CN207671649U (en) | 2017-12-11 | 2017-12-11 | Construction material transports lifter |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721714134.5U CN207671649U (en) | 2017-12-11 | 2017-12-11 | Construction material transports lifter |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207671649U true CN207671649U (en) | 2018-07-31 |
Family
ID=62967958
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721714134.5U Expired - Fee Related CN207671649U (en) | 2017-12-11 | 2017-12-11 | Construction material transports lifter |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207671649U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108868095A (en) * | 2018-08-27 | 2018-11-23 | 卢凌凌 | A kind of room building materials carrying frame |
-
2017
- 2017-12-11 CN CN201721714134.5U patent/CN207671649U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108868095A (en) * | 2018-08-27 | 2018-11-23 | 卢凌凌 | A kind of room building materials carrying frame |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206227942U (en) | A kind of adjustable study table | |
CN207671649U (en) | Construction material transports lifter | |
CN104868372A (en) | Double door for switchgear | |
CN208974353U (en) | Transfer car(buggy) in multi-functional institute | |
CN107485568A (en) | The broken medicine device of oncology | |
CN206731215U (en) | It is multi-functional to grind medicine device | |
CN204793660U (en) | A two opening door for cubical switchboard | |
CN205764504U (en) | A kind of effective integrated guard automatic cloth silk equipment | |
CN108011346A (en) | One kind has thermostatically controlled electric wire feeder pillar | |
CN207890783U (en) | Adhesive tape banding machine cutter frame mechanism | |
CN206709314U (en) | A kind of automatic air curtain device for refrigeration house | |
CN206865647U (en) | Movable type detecting CCTV camera | |
CN207189181U (en) | Precision pulling bench saw pole track-type facilities | |
CN204532014U (en) | A kind of automatic door can walked along curve track | |
CN206692282U (en) | Librarian's special lifting is taken books device | |
CN208428218U (en) | A kind of carpenter being convenient for carrying hardware tool placing box | |
CN204272828U (en) | A kind of top has the booth of ventilating opening | |
CN208093252U (en) | A kind of wire stranding machine and its automatic opening and closing door | |
CN206511434U (en) | A kind of large-size box with cap-opening mechanism | |
CN206704718U (en) | Polybasic drugs device for labeling | |
CN206667550U (en) | A kind of glass sunlight house girder adjustable connecting structure | |
CN208212836U (en) | Chinese medicine off-gas cleaning equipment | |
CN205911636U (en) | Upward -acting door block terminal | |
CN205370339U (en) | Improved generation abnormal shape translation door | |
CN206344038U (en) | A kind of mechanical electric positioner |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180731 Termination date: 20181211 |
|
CF01 | Termination of patent right due to non-payment of annual fee |