CN207641743U - Spraying drying environmental protection equipment and spray equipment - Google Patents

Spraying drying environmental protection equipment and spray equipment Download PDF

Info

Publication number
CN207641743U
CN207641743U CN201721737558.3U CN201721737558U CN207641743U CN 207641743 U CN207641743 U CN 207641743U CN 201721737558 U CN201721737558 U CN 201721737558U CN 207641743 U CN207641743 U CN 207641743U
Authority
CN
China
Prior art keywords
water
spray
spray booth
paint spray
gas
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721737558.3U
Other languages
Chinese (zh)
Inventor
徐万付
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Valence Coating Machinery Co Ltd
Original Assignee
Guiyang Valence Coating Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Valence Coating Machinery Co Ltd filed Critical Guiyang Valence Coating Machinery Co Ltd
Priority to CN201721737558.3U priority Critical patent/CN207641743U/en
Application granted granted Critical
Publication of CN207641743U publication Critical patent/CN207641743U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P70/00Climate change mitigation technologies in the production process for final industrial or consumer products
    • Y02P70/10Greenhouse gas [GHG] capture, material saving, heat recovery or other energy efficient measures, e.g. motor control, characterised by manufacturing processes, e.g. for rolling metal or metal working

Landscapes

  • Details Or Accessories Of Spraying Plant Or Apparatus (AREA)
  • Application Of Or Painting With Fluid Materials (AREA)

Abstract

The utility model is related to spray-painting plant fields, and environmental protection equipment and spray equipment are dried in particular to a kind of spraying.Spraying drying environmental protection equipment includes the paint spray booth for spray painting, sink, water treatment system, water channel pipe-line system, the gas cleaning plant that the gas of useless coating cloud is purified, cascade component and gas delivery system, sink is set to paint spray booth bottom and is connected to paint spray booth, sink, water treatment system, water channel pipe-line system and cascade component are sequentially connected, cascade component is set in paint spray booth and is connect with paint spray booth, and useless coating cloud is reentered by gas cleaning plant purification in paint spray booth.The aqueous solution and residual gas for the coating cloud that gives up can be further processed in it, and water, gas can be recycled, and reduce the wasting of resources, water process and residual gas in combination with processing, accelerate the rate of useless coating cloud purification, and clean-up effect is more thorough, more environmentally-friendly.

Description

Spraying drying environmental protection equipment and spray equipment
Technical field
The utility model is related to spray-painting plant fields, and environmental protection equipment and spraying are dried in particular to a kind of spraying Device.
Background technology
All be in the lacquer spraying technique of the existing object larger to vehicle or volume manually carried out in closed environment, and The useless coating cloud that spray painting generates is extracted afterwards, was being painted when then handling again useless coating cloud, but using this method The useless coating cloud generated in journey may loss everywhere, then flow to human body side, absorbed by human body, be easy to cause personnel health Damage, while polluting air quality in spray painting.Meanwhile it is less for the purified treatment for the coating cloud that gives up, often direct emission, influences Environment.
Utility model content
The purpose of this utility model is to provide a kind of sprayings to dry environmental protection equipment, can quickly generate spray painting useless Coating cloud is quickly infiltrated so that useless coating cloud can rapidly dissolve in water, and respectively to the aqueous solution and residual gas of the coating cloud that gives up Body is further processed, and water can be recycled, and reduces the wasting of resources, water process and residual gas add in combination with processing The rate of the useless coating cloud purification of speed, and clean-up effect is more thorough.
The another object of the utility model is to provide a kind of spray equipment, the waste water that can be quickly generated to the coating cloud that gives up It is recycled with exhaust gas, reduces damage of the coating cloud to human body of giving up, reduce the wasting of resources.
What the embodiments of the present invention were realized in:
Environmental protection equipment is dried in a kind of spraying comprising for the paint spray booth of spray painting, in putting the liquid for being impregnated with useless coating cloud Sink, the water in sink is handled water treatment system, the water of water treatment system introduced into paint spray booth to carrying out useless paint The water channel pipe-line system of the absorption of mist, the gas cleaning plant that the gas of useless coating cloud is purified, by water channel pipe-line system Water forms the cascade component of flowing water curtain in paint spray booth and conveys the gas delivery system of gas, and sink is set to paint spray booth Bottom is simultaneously connected to paint spray booth, and sink, water treatment system, water channel pipe-line system and cascade component are sequentially connected, cascade component It is set in paint spray booth and is connect with paint spray booth, useless coating cloud is reentered by gas cleaning plant purification in paint spray booth.
In the utility model preferred embodiment, above-mentioned water treatment system includes sequentially connected cesspool, sedimentation basin, net Change pond and clear water reserviors, cesspool are connect with sink, clear water reserviors are connect with water channel pipe-line system.
In the utility model preferred embodiment, above-mentioned gas purifier includes activated carbon filter component and photooxidation catalysis Component, one end of activated carbon filter component and one end of photooxidation catalytic module are connect with gas delivery system respectively, activated carbon mistake The other end of filter component is connect with the other end of photooxidation catalytic module.
In the utility model preferred embodiment, it further includes being adsorbed to useless coating cloud that above-mentioned ring spray, which applies drying environmental protection equipment, Spray chamber, spray chamber is connected to sink, and spray chamber is connect with gas delivery system.
In the utility model preferred embodiment, above-mentioned spray chamber includes multiple spray systems, and multiple spray systems are all provided with It is placed in spray chamber and is connect with spray chamber.
In the utility model preferred embodiment, above-mentioned multiple spray systems are staggered from top to bottom in spray chamber.
In the utility model preferred embodiment, above-mentioned each spray system includes water fender and multiple spray heads, water blocking Plate and multiple spray heads may be contained in spray chamber, and water fender is connect with spray chamber, and multiple spray heads are connect with water fender, gear Water plate is obliquely installed, and the free end of two adjacent water fenders overlaps.
In the utility model preferred embodiment, above-mentioned cascade component includes baffle plate and drainage plate, baffle plate and drainage Plate may be contained within connecting in paint spray booth and with the inner wall of paint spray booth, and baffle plate is set gradually from top to bottom with drainage plate, and drain The distance between free end and paint spray booth of plate are more than the distance between free end and paint spray booth of baffle plate.
In the utility model preferred embodiment, the free end of above-mentioned drainage plate and the free end of baffle plate offer more A flowing through-hole.
A kind of spray equipment comprising environmental protection equipment is dried in above-mentioned spraying.
The advantageous effect of the utility model embodiment is:The utility model to paint indoor by setting cascade component Useless coating cloud can carry out contact infiltration with liquid, prevent useless coating cloud loss everywhere in paint spray booth, promote the safety of operating personnel, Meanwhile cascade component is obliquely installed and increases the area and time that coating cloud is contacted with liquid that give up, and further promotes its infiltration absorption effect Fruit.Equal fluid layer is formed in paint spray booth by gas delivery system, and useless coating cloud is pressed into sink, and is conveyed, into one Step optimizes painting environment.And gas delivery system, gas cleaning plant realize the purification of useless coating cloud and recycle, at water Reason system and water channel pipe-line system and cascade component also achieve the purification of water and recycle, and further save resource, make It must paint more environmentally-friendly.
Description of the drawings
It, below will be to required use in embodiment in order to illustrate more clearly of the technical solution of the utility model embodiment Attached drawing be briefly described, it should be understood that the following drawings illustrates only some embodiments of the utility model, therefore should not be by Regard the restriction to range as, for those of ordinary skill in the art, without creative efforts, may be used also To obtain other relevant attached drawings according to these attached drawings.
Fig. 1 is the structural schematic diagram for the spraying drying environmental protection equipment that the utility model embodiment provides;
Fig. 2 is the structural schematic diagram for the baffle plate that the utility model embodiment provides;
Fig. 3 is the structural schematic diagram for the spray chamber that the utility model embodiment provides;
Fig. 4 is the attachment structure schematic diagram for the water treatment system that the utility model embodiment provides.
Icon:100- spraying drying environmental protection equipments;The paint spray booths 110-;120- water channel pipe-line systems;130- cascade components; 140- sinks;150- gas delivery systems;111- grids;113- filter devices;131- baffle plates;133- drainage plates;135- flows Dynamic through-hole;160- spray chambers;161- spray systems;161a- water fenders;161b- spray heads;170- water treatment systems;171- is dirty Pond;173- sedimentation basins;175- clarifier-tanks;177- clear water reserviors;180- gas cleaning plants;181- activated carbon filter components; 183- photooxidation catalytic modules;141- supply air systems;141a- ajutages;141b- pressure fan;141c- heat exchangers;143- transmission system System;143a- air pumps;The first conveyance conduits of 143b-;The second conveyance conduits of 143c-.
Specific implementation mode
It is new below in conjunction with this practicality to keep the purpose, technical scheme and advantage of the utility model embodiment clearer Attached drawing in type embodiment, the technical scheme in the utility model embodiment is clearly and completely described, it is clear that is retouched The embodiment stated is the utility model a part of the embodiment, instead of all the embodiments.Usually here described in attached drawing and The component of the utility model embodiment shown can be arranged and be designed with a variety of different configurations.
Therefore, the detailed description of the embodiments of the present invention to providing in the accompanying drawings is not intended to limit requirement below The scope of the utility model of protection, but it is merely representative of the selected embodiment of the utility model.Based in the utility model Embodiment, the every other embodiment that those of ordinary skill in the art are obtained without creative efforts, all Belong to the range of the utility model protection.
It should be noted that:Similar label and letter indicate similar terms in following attached drawing, therefore, once a certain Xiang Yi It is defined, then it further need not be defined and explained in subsequent attached drawing in a attached drawing.
In the description of the present invention, it should be noted that term " first ", " second " etc. are only used for distinguishing description, It is not understood to indicate or imply relative importance.
In the description of the present invention, it should also be noted that, unless otherwise clearly defined and limited, term " is set Set ", " connection ", " connected ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, Or it is integrally connected;It can be mechanical connection, can also be electrical connection;It can be directly connected, intermediary can also be passed through It is indirectly connected, can be the connection inside two elements.For the ordinary skill in the art, it can be managed with concrete condition Solve the concrete meaning of above-mentioned term in the present invention.
Below in conjunction with the accompanying drawings, it elaborates to some embodiments of the utility model.In the absence of conflict, under Feature in the embodiment and embodiment stated can be combined with each other.
As shown in Figure 1, the present embodiment provides a kind of sprayings to dry environmental protection equipment 100 comprising the paint spray booth for spray painting 110, in put the sink 140 for the liquid for being impregnated with useless coating cloud, the water treatment system 170 that the water in sink 140 is handled, By the water of water treatment system 170 introduce paint spray booth 110 to carrying out the water channel pipe-line system 120 of the absorption of useless coating cloud, by useless coating cloud Gas purified gas cleaning plant 180, the water of water channel pipe-line system 120 formed into flowing in the paint spray booth 110 The cascade component 130 of cascade and the gas delivery system 150 for conveying gas, sink 140 be set to 110 bottom of paint spray booth and with spray Paint room 110 is connected to, and sink 140, water treatment system 170, water channel pipe-line system 120 and cascade component 130 are sequentially connected, cascade Component 130 is set in paint spray booth 110 and connect with paint spray booth 110, give up coating cloud by the purification of gas cleaning plant 180 again into Enter in paint spray booth 110.
Construction personnel paints to vehicle in paint spray booth 110, and paint spray booth 110 is cube or cylinder.Paint spray booth 110 tops are provided with gas feed, are connected to gas delivery system 150 so that external air can enter paint spray booth 110 It is interior, equal fluid layer is then formed in paint spray booth 110, and useless coating cloud is pressed into sink 140.Not only working environment is improved, but also is ensured Coating quality.
Spraying drying environmental protection equipment 100 further includes the mistake for filtering the gas that gas delivery system 150 is conveyed to paint spray booth 110 Device 113 is filtered, filter device 113 is set to the top of the outside of paint spray booth 110, and is connect with paint spray booth 110.Filter device 113 can be filter screen either high efficiency filter cotton or other filter elements with purification.Using filter device 113 to input The air of paint spray booth 110 is purified, and ensures spray painting effect, prevents the Cucumber in air from influencing spray painting effect, such as oxygen Gas can cause Cucumber to aoxidize, and then reduce spray painting effect.Filter device 113 can also play certain control gas simultaneously The effect of flow velocity can then ensure that air forms stable equal fluid layer in paint spray booth 110.
Further, 110 bottom of paint spray booth is provided with grid 111, can the liquid that cascade component 130 drains be flowed into water In slot 140, prevents the liquid that cascade component 130 drains from being put aside for a long time in 110 bottom of paint spray booth, prevent containing benzene, formaldehyde etc. The liquid of organic substance for a long time corrodes human body.
It will produce largely useless coating cloud after spray painting, useless coating cloud extracted only with gas delivery system 150, Bu Nengbao Useless coating cloud in card paint spray booth 110 is quickly extracted completion, meanwhile, conveying is gas, is easy to cause gas escape, reduces it Safety, therefore in order to solve this technical problem, useless coating cloud is infiltrated at once after the completion of spray painting so that useless coating cloud energy It is enough quickly to be infiltrated, reduce the loss for the coating cloud that gives up.Specifically, cascade component 130 is set in paint spray booth 110 and and paint spray booth 110 connections, then form flowing water curtain in paint spray booth 110, can quickly introduce the liquid in water channel pipe-line system 120 It is contacted into paint spray booth 110, and with the useless coating cloud in paint spray booth 110, further the air in purification paint spray booth 110, and cascade After the liquid of component 130 is contacted with the useless coating cloud in paint spray booth 110, liquid flows into sink 140.
Further, referring back to Fig. 2, cascade component 130 includes baffle plate 131 and drainage plate 133, baffle plate 131 and is drawn Flowing plate 133 may be contained within connect in paint spray booth 110 and with the inner wall of paint spray booth 110, baffle plate 131 and drainage plate 133 from up to Under set gradually, and the distance between the free end of drainage plate 133 and paint spray booth 110 be more than baffle plate 131 free end and spray The distance between paint room 110.Baffle plate 131 can put aside a small amount of water, can increase the time of contact of water and useless coating cloud, increase simultaneously Add active force of the water to the coating cloud that gives up so that more useless coating cloud can be pressed into water, and the cross section of baffle plate 131 is " V " word Shape.And drainage plate 133 can be the baffle plate 131 of " V " font, can also be the hang plate to 110 top droop of paint spray booth.
It should be noted that the number of drainage plate 133 is rationally added according to production requirement, it should be noted that more lean on The distance between the drainage plate 133 of 110 bottom of nearly paint spray booth and paint spray booth 110 more arrive, that is, ensure that the cascade to be formed is stairstepping Cascade.
And the distance between the free end of drainage plate 133 and paint spray booth 110 are more than the free end and paint spray booth of baffle plate 131 The distance between 110.Step-like cascade can be formed, the time of useless coating cloud and cascade effect is further increased, promotes purification effect Fruit.
Further, the free end of drainage plate 133 and the free end of baffle plate 131 offer multiple flowing through-holes 135. Recirculation hole is set so that the liquid of 131 free end of overflow to drainage plate 133 and baffle plate can be made by flow orifice and useless coating cloud With.
Further, the liquid for having moieties to be flowed out by water channel pipe-line system 120 in useless coating cloud infiltrates, subsequently into water In slot 140, but also portion gas cannot be dissolved in the liquid flowed out in water channel pipe-line system 120, need to add other Ingredient could be absorbed, and therefore, spraying drying environmental protection equipment 100 further includes the spray chamber 160 adsorbed to the coating cloud that gives up, spray Leaching room 160 is connected to sink 140, and spray chamber 160 is connect with gas delivery system 150.Gas delivery system 150 is by paint spray booth The useless coating cloud generated in 110 is further absorbed into spray chamber 160, different chemical substances is sprayed by spray chamber 160, into one Step handles useless coating cloud, ensures that the gas of discharge meets discharge standard.
Specifically, in conjunction with Fig. 1 and Fig. 3, spray chamber 160 includes multiple spray systems 161, and multiple spray systems 161 are all provided with It is placed in spray chamber 160 and is connect with spray chamber 160.Spray system 161 can carry out the useless coating cloud by infiltration further Ground adsorbs, and reduces the content of pernicious gas in the coating cloud that gives up.And multiple spray systems 161 can spray identical liquid, then inhale Attached identical impurity can also spray different liquid, remove exhaust gas different in giving up coating cloud.
Preferably, multiple spray systems 161 are staggered from top to bottom in spray chamber 160.Multiple spray systems 161 are handed over Mistake setting can limit the running orbit for the coating cloud that gives up, increase and give up what coating cloud was contacted with the liquid that spray system 161 sprays Time then promotes the removal efficiency of pernicious gas in giving up coating cloud.
Further, each spray system 161 includes water fender 161a and multiple spray head 161b, water fender 161a and more A spray head 161b may be contained in spray chamber 160, and water fender 161a is connect with spray chamber 160, multiple spray head 161b with Water fender 161a connections, water fender 161a are obliquely installed.Water fender 161a is obliquely installed to the direction close to 160 bottom of spray chamber The area that ejecting liquid is contacted with useless coating cloud can be increased, further promote clean-up effect, and water fender 161a being capable of anti-stop bit The liquid that spray system 161 to its upper is sprayed is put aside on water fender 161a for a long time, increases the use of spray system 161 Service life accelerates the flowing of liquid, but can increase the time of contact of liquid and useless coating cloud again, further promotes purification efficiency.
Preferably, the free end of two adjacent water fender 161a overlaps, i.e., two neighboring water fender 161a's View field overlaps, and is then limited the track of the flowing for the coating cloud that gives up, and extend useless coating cloud in spray chamber The distance of 160 flowings, increases the basal latency of useless coating cloud and ejecting liquid, further improves clean-up effect.
Further, the liquid referring to Fig. 4,160 spray-absorption of spray chamber pernicious gas to give up in coating cloud and paint spray booth 110 The liquid that coating cloud acts on that gives up in interior cascade component 130 is collected in sink 140, and the water harmful substance in the sink 140 contains Amount is high, is unable to direct emission, needs to be discharged after carrying out water process, but for resource-effective and recycling, and reduce Production cost considers, the water Jing Guo water process is drained into again in cascade component 130 and carries out secondary use, specifically, sink 140, water treatment system 170, water channel pipe-line system 120 and cascade component 130 are sequentially connected, water treatment system 170 include according to Cesspool 171, sedimentation basin 173, clarifier-tank 175 and the clear water reserviors 177 of secondary connection, cesspool 171 are connect with sink 140, clear water Pond 177 is connect with water channel pipe-line system 120.Various liquid in sink 140 flow into cesspool 171, then successively by precipitation Pond 173, clarifier-tank 175 carry out purified treatment, obtain clear water, then water channel pipe-line system 120 transports clear water again to cascade Cascade is formed in component 130, and the useless coating cloud in paint spray booth 110 is infiltrated.
Sedimentation basin 173, clarifier-tank 175 recorded in the utility model are the common sedimentation basins of water process in the prior art 173 and clarifier-tank 175.
Further, referring back to Fig. 1, may contain some chemical methodes of part by the useless coating cloud of spray chamber 160 cannot Either therefore, it is necessary to further be purified by the way of Physical entrapment or biology retention for other impurities for the hazardous solid of removal Useless coating cloud.Therefore, the gas cleaning plant 180 that spraying drying environmental protection equipment 100 further purifies the coating cloud that gives up, gas is net Makeup is set 180 and is connect with gas delivery system 150.Specifically, gas cleaning plant 180 is set to outside spray chamber 160, and gas is net Makeup is set 180 and is connected to spray chamber 160 by gas delivery system 150, and gas delivery system 150 will be by spray chamber 160 Useless coating cloud is transported to being purified in purifier, then again will by purifier the useless coating cloud for meeting discharge standard again It inputs in paint spray booth 110.
Further, gas cleaning plant 180 includes activated carbon filter component 181 and photooxidation catalytic module 183, activated carbon One end of filter assemblies 181 and one end of photooxidation catalytic module 183 are connect with gas delivery system 150 respectively, activated carbon filtering The other end of component 181 is connect with the other end of photooxidation catalytic module 183.That is one end of activated carbon filter component 181 passes through gas Body conveying system 150 is connected to spray chamber 160, and one end and the paint spray booth 110 of photooxidation catalytic module 183 pass through gas delivery system 150 connections, and activated carbon component is connect with photooxidation catalytic module 183.Activated carbon is passed sequentially through by the gas of spray chamber 160 Filter assemblies 181 and photooxidation catalytic module 183 are passed through after purifying to paint spray booth 110 again.
Further, gas delivery system 150 includes the supply air system 141 that gas is conveyed to paint spray booth 110, supply air system 141 are connected to paint spray booth 110, and equal fluid layer is formed in paint spray booth 110, and useless coating cloud is pressed into sink 140.That is supply air system 141 are located at the top of paint spray booth 110, can the top-down transport in paint spray booth 110 by wind (air), prevent useless coating cloud to Upper loss, advanced optimizes painting environment.
Supply air system 141 includes ajutage 141a, pressure fan 141b and heat exchanger 141c, and pressure fan 141b is by paint spray booth Air (or gas by gas cleaning plant 180) outside 110 is compressed and is conveyed into ajutage 141a, and laggard Entering in paint spray booth 110, air is equably sent into chamber body by ajutage 141a with the end face wind speed of 0.3m/s, from top to bottom, spray Paint process carries out in the equal fluid layer with certain wind speed so that in the useless coating cloud indentation sink 140 of splashing, both improves work Environment in turn ensures coating quality, while useless coating cloud being transported downwards, then transports to spray chamber 160.Heat exchanger 141c can It is dried to conveying into the air in paint spray booth 110, prevents air from excessively moistening and influence effect of painting.
, referring back to Fig. 1, gas delivery system 150 further includes that the gas containing useless coating cloud in paint spray booth 110 is delivered to spray The Transmission system 143 of room 160 is drenched, spray chamber 160 and paint spray booth 110 are connected to Transmission system 143 respectively.Further, it transmits System 143 includes aspiration pump 143a and the first conveyance conduit 143b, and aspiration pump 143a settings are relatively distant from sink with spray chamber 160 140 side is simultaneously connect with spray chamber 160, and the both ends of the first conveyance conduit 143b connect with spray chamber 160 and paint spray booth 110 respectively It is logical.Aspiration pump 143a provides power for gas to the movement of spray chamber 160, realizes the flowing of gas, and then can realize useless coating cloud Purification.
Further, aspiration pump 143a is set to the side that gas cleaning plant 180 is relatively distant from spray chamber 160, and first The both ends of conveyance conduit 143b are connect with paint spray booth 110 and purifier respectively so that useless coating cloud can be quickly cleaned.
Gas delivery system 150 further include the second conveyance conduit 143c, the second conveyance conduit 143c both ends respectively with gas The gas outlet of body purifier 180 is connect with ajutage 141a, then so that passing through the useless coating cloud (being pure air) of purification Paint spray booth 110 is returned to once again, and infiltration absorption is carried out to newly generated useless coating cloud.
The power of the mechanical organs such as the aspiration pump 143a and pressure fan 141b of the utility model is by external power supply reality Existing.
The utility model also provides a kind of spray equipment (not shown) comprising environmental protection equipment 100 is dried in above-mentioned spraying.
In the present embodiment, the operating method and principle of spraying drying environmental protection equipment:
First, pressure fan is opened, gas is constantly conveyed into paint spray booth and forms equal fluid layer, and vehicle is positioned over It paints in paint spray booth, meanwhile, in the useless coating cloud indentation sink that the gas of conveying is obtained spray painting, and cascade component will In liquid drain to paint spray booth in water channel pipe-line system, infiltration and preliminary absorption are carried out to the useless coating cloud that spray painting generates.And And liquid enters sink.Meanwhile aspiration pump is also opened, by the extra gas transport that do not adsorbed by liquid infiltration to spray chamber, and Gas is absorbed in spray indoor moveable and by the liquid that spray system sprays afterwards, and the liquid sprayed converges in sink, It is then handled to obtain clear water by water treatment system, then clear water is returned into cascade component by water channel pipeline system transfer. It is transmitted back in paint spray booth by second pipe again after the gas of spray chamber is purified using gas cleaning plant.
To sum up, the utility model enables the indoor useless coating cloud that paints to be contacted with liquid by the way that cascade component is arranged Infiltration prevents useless coating cloud loss everywhere in paint spray booth, promotes the safety of operating personnel, meanwhile, cascade component is obliquely installed increasing Add the area and time that useless coating cloud is contacted with liquid, further promotes it and infiltrate adsorption effect.It is being sprayed by gas delivery system Equal fluid layer is formed in paint room, and useless coating cloud is pressed into sink, and is conveyed, and painting environment has been advanced optimized.And gas Transport system, gas cleaning plant realize the purification of useless coating cloud and recycle, water treatment system and water channel pipe-line system with And cascade component also achieves the purification of water and recycles, and further saves resource so that spray painting is more environmentally-friendly.
The preferred embodiment that these are only the utility model, is not intended to limit the utility model, for this field Technical staff for, various modifications and changes may be made to the present invention.Within the spirit and principle of the utility model, Any modification, equivalent replacement, improvement and so on should be included within the scope of protection of this utility model.

Claims (10)

1. environmental protection equipment is dried in a kind of spraying, which is characterized in that it includes being impregnated with useless paint for the paint spray booth of spray painting, in putting The sink of the liquid of mist, the water treatment system handled to the water in the sink introduce the water of the water treatment system The paint spray booth to carrying out the water channel pipe-line system of the absorption of useless coating cloud, the gas purification for purifying the gas of useless coating cloud fills It sets, the water of the water channel pipe-line system is formed to the cascade component of flowing water curtain in the paint spray booth and conveys gas Gas delivery system, the sink are set to the paint spray booth bottom and are connected to the paint spray booth, the sink, the water process System, the water channel pipe-line system and the cascade component are sequentially connected, and the cascade component is set in the paint spray booth And connect with the paint spray booth, the useless coating cloud is reentered by gas cleaning plant purification in paint spray booth.
2. environmental protection equipment is dried in spraying according to claim 1, which is characterized in that the water treatment system includes connecting successively Cesspool, sedimentation basin, clarifier-tank and the clear water reserviors connect, the cesspool are connect with the sink, the clear water reserviors and the water Road pipe-line system connection.
3. environmental protection equipment is dried in spraying according to claim 1, which is characterized in that the gas cleaning plant includes activity Distinguish one end of charcoal filter assemblies and photooxidation catalytic module, one end of the activated carbon filter component and the photooxidation catalytic module It is connect with the gas delivery system, the other end of the activated carbon filter component and the other end of the photooxidation catalytic module connect It connects.
4. environmental protection equipment is dried in spraying according to claim 1, which is characterized in that the spraying drying environmental protection equipment also wraps The spray chamber adsorbed to the useless coating cloud is included, the spray chamber is connected to the sink, the spray chamber and the gas Transport system connects.
5. environmental protection equipment is dried in spraying according to claim 4, which is characterized in that the spray chamber includes multiple spray systems System, multiple spray systems may be contained within connecting in the spray chamber and with the spray chamber.
6. environmental protection equipment is dried in spraying according to claim 5, which is characterized in that multiple spray systems are in the spray Leaching interior is staggered from top to bottom.
7. environmental protection equipment is dried in spraying according to claim 6, which is characterized in that each spray system includes water blocking Plate and multiple spray heads, the water fender and multiple spray heads may be contained in the spray chamber, the water fender and institute Spray chamber connection is stated, multiple spray heads are connect with the water fender, and the water fender is obliquely installed, and adjacent two The free end of the water fender overlaps.
8. environmental protection equipment is dried in spraying according to claim 7, which is characterized in that the cascade component include baffle plate and Drainage plate, the baffle plate and the drainage plate may be contained within connecting in paint spray booth and with the inner wall of the paint spray booth, the folding Flowing plate is set gradually from top to bottom with the drainage plate, and the distance between the free end of the drainage plate and the paint spray booth are big In the distance between the free end of the baffle plate and the paint spray booth.
9. environmental protection equipment is dried in spraying according to claim 8, which is characterized in that the free end of the drainage plate and described The free end of baffle plate offers multiple flowing through-holes.
10. a kind of spray equipment, which is characterized in that dry environmental protection equipment including spraying described in any one of claim 1-9.
CN201721737558.3U 2017-12-13 2017-12-13 Spraying drying environmental protection equipment and spray equipment Expired - Fee Related CN207641743U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721737558.3U CN207641743U (en) 2017-12-13 2017-12-13 Spraying drying environmental protection equipment and spray equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721737558.3U CN207641743U (en) 2017-12-13 2017-12-13 Spraying drying environmental protection equipment and spray equipment

Publications (1)

Publication Number Publication Date
CN207641743U true CN207641743U (en) 2018-07-24

Family

ID=62880184

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721737558.3U Expired - Fee Related CN207641743U (en) 2017-12-13 2017-12-13 Spraying drying environmental protection equipment and spray equipment

Country Status (1)

Country Link
CN (1) CN207641743U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109433501A (en) * 2018-12-24 2019-03-08 永康市恒久涂装设备有限公司 A kind of multi-level water whirling paint-spraying cabinet
CN114177736A (en) * 2021-12-14 2022-03-15 宁波广昊环保设备有限公司 Purifier that coating cloud was handled

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109433501A (en) * 2018-12-24 2019-03-08 永康市恒久涂装设备有限公司 A kind of multi-level water whirling paint-spraying cabinet
CN114177736A (en) * 2021-12-14 2022-03-15 宁波广昊环保设备有限公司 Purifier that coating cloud was handled

Similar Documents

Publication Publication Date Title
CN207641743U (en) Spraying drying environmental protection equipment and spray equipment
CN204874120U (en) Waste gas waste water that sprays paint integration processing system
CN108543366A (en) The environmental protection equipment of paint spray booth exhaust-gas treatment
CN207271499U (en) Environmentally friendly side curtain oil curtain machine and oil curtain device
CN207085586U (en) A kind of filtration, purification system
CN213193182U (en) Waste gas purification washing tower
CN204911229U (en) Spraying waste gas treatment system
CN108905460A (en) A kind of purification device and purification method of painting workshop exhaust-gas treatment
CN104549862B (en) A kind of furniture spray paint after the processing means of coating cloud
CN202427304U (en) Integrated treatment tank for coating exhaust
CN206642518U (en) A kind of 10,000 air quantity spray columns
CN106039886A (en) Painting waste gas treatment equipment
CN209934351U (en) Paint mist waste gas purification device
CN204469523U (en) A kind of industrial foul waste gas purifier
CN208229661U (en) A kind of novel bacteria bed emission-control equipment
CN106111424A (en) A kind of dope room air cleaner
CN202427592U (en) Single-step back-to-back spraying room
CN207786907U (en) paint spray booth
CN205886471U (en) Horizontal washing tower
CN210057745U (en) Etching exhaust-gas treatment equipment
CN109603368A (en) Spray waste gas treatment equipment
CN108355437A (en) Spray system for settling paint spray booth exhaust gas particle object
CN218307131U (en) Energy-saving circulating fluorine absorption tower
CN211936374U (en) Coal chemical waste gas treatment atomizing humidification circulating device
CN206911097U (en) Paint waste gas treatment equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180724

Termination date: 20191213

CF01 Termination of patent right due to non-payment of annual fee