CN207618113U - A kind of twoport alternating blanking device - Google Patents

A kind of twoport alternating blanking device Download PDF

Info

Publication number
CN207618113U
CN207618113U CN201721227299.XU CN201721227299U CN207618113U CN 207618113 U CN207618113 U CN 207618113U CN 201721227299 U CN201721227299 U CN 201721227299U CN 207618113 U CN207618113 U CN 207618113U
Authority
CN
China
Prior art keywords
storage bin
bin hopper
pneumatic unit
controller
discharge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721227299.XU
Other languages
Chinese (zh)
Inventor
李怀前
刘树利
王昊
申黎明
张园园
李怀志
张意敏
刘志潜
李凯
刘新宇
周跃峰
毕巧珍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIAOZUO YELLOW RIVER ENGINEERING BUREAU HENAN YELLOW RIVER ENGINEERING BUREAU
Original Assignee
JIAOZUO YELLOW RIVER ENGINEERING BUREAU HENAN YELLOW RIVER ENGINEERING BUREAU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIAOZUO YELLOW RIVER ENGINEERING BUREAU HENAN YELLOW RIVER ENGINEERING BUREAU filed Critical JIAOZUO YELLOW RIVER ENGINEERING BUREAU HENAN YELLOW RIVER ENGINEERING BUREAU
Priority to CN201721227299.XU priority Critical patent/CN207618113U/en
Application granted granted Critical
Publication of CN207618113U publication Critical patent/CN207618113U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Basic Packing Technique (AREA)

Abstract

The utility model provides a kind of twoport alternating blanking device, including:Two discharge ports for being installed in sack filling machine side;For storing sandstone material, and the storage bin hopper of sandstone material is exported under the control of pneumatic unit at regular time and quantity;For under the control of pneumatic unit timesharing convey to two discharge ports the discharge bucket of sandstone material;For presetting activity duration, work schedule, timing sends operational order to storage bin hopper after opening operation according to enabled instruction, expire signal according to storing and sent stopping conveying sandstone material instruction to sack filling machine, periodically sends the controller of alternate instruction to pneumatic unit according to discharging time;The operational order control storage bin hopper sent according to controller discharges at regular time and quantity, and the alternate instruction control discharge bucket sent according to controller alternately exports the pneumatic unit of sandstone material to two discharge ports timings.The utility model has the characteristics that efficient, simple in structure, at low cost, can be widely applied to the fields such as flood-fighting.

Description

A kind of twoport alternating blanking device
Technical field
The utility model is related to a kind of discharging technologies, replace blanking device more particularly to a kind of twoport.
Background technology
In recent years, flood occurs again and again, and flood-fighting scene needs a large amount of sandstone material carrying out pack operation. Currently, Jiaozhuo Middle Yellow River business office is using its Patent No. ZL2013205863380, entitled " emergency flood fighting joint sack filling machine " Technology described in Chinese utility model patent greatly increases working efficiency instead of handwork, in flood-fighting critical period Important function is played.In the utility model patent, after sandstone material is loaded into feed hopper, ribbon conveyer conveys sandstone material It feeds to discharge bucket.But in practical application, although respectively there are one discharge buckets at the sack filling machine both ends, in an object After material bag is filled, when replacing another material bag, it is still desirable to spend and replace the time.With the accumulation of activity duration, the time is replaced An important factor for just being had to take into account that at one.
It can be seen that in the prior art, sack filling machine still has the problem that working efficiency is low, of high cost.
Invention content
In view of this, the main purpose of the utility model is to provide a kind of efficient, simple in structure, at low cost twoports Alternately blanking device.
In order to achieve the above object, the utility model proposes technical solution be:
A kind of twoport alternating blanking device, including two provided besides are in the discharge port (6) of sack filling machine side;For to coming It is stored from the sandstone material of sack filling machine feed hopper, and defeated at regular time and quantity to discharge bucket (3) under the control of pneumatic unit (7) Send the storage bin hopper (2) of sandstone material;For under the control of pneumatic unit (7) timesharing convey sandstone material to two discharge ports Discharge bucket (3);For presetting activity duration, work schedule, after opening operation from the enabled instruction of discharge port (6) Timing sends operational order to storage bin hopper (2), and it is defeated to sack filling machine transmission stopping to have expired signal according to the storing from storage bin hopper (2) It send sandstone material to instruct, alternate instruction is periodically sent to pneumatic unit according to preset each discharge hole for discharge time Controller (5);The operational order control storage bin hopper (2) sent according to controller (5) discharges to discharge bucket (3) at regular time and quantity, The alternate instruction control discharge bucket (3) sent according to controller (5) alternately exports sandstone material to two discharge port (6) timings Pneumatic unit (7);Wherein,
Discharge bucket (3) is located at the lower section of storage bin hopper (2), and two discharge ports (6) are installed side by side below discharge bucket (3);Storage Hopper (2) one end is connected to the feed hopper (1) of sack filling machine, and storage bin hopper (2) other end is connected to discharge bucket (3) one end;Discharge bucket (3) other end is connected to two discharge ports (6);Controller (5) first input end is connect with any discharge port (6), controller (5) Second input terminal is connect with storage bin hopper (2), the belt conveyor control terminal connection of (5) first output end of controller and sack filling machine, control Device (5) second output terminal processed is connect with pneumatic unit (7) control terminal;(7) first input/output terminal of pneumatic unit and storage bin hopper (2) it connects, (7) second input/output terminal of pneumatic unit is connect with discharge bucket (3).
In conclusion twoport blanking device described in the utility model is installed in sack filling machine side, it, can also be same in practical application When the twoport blanking device is symmetrically installed in the sack filling machine other side, such sack filling machine both sides share 4 discharge ports, into one Step improves the pack efficiency of sack filling machine.Twoport blanking device described in the utility model to two by alternately going out at regular time and quantity Material mouth discharges so that sack filling machine is always in running order, and pack worker also improves the efficiency of set folder bag, to greatly improve The pack efficiency of sack filling machine.In addition, twoport blanking device described in the utility model also have it is simple in structure, at low cost excellent Point.
Description of the drawings
Fig. 1 is the front view that twoport described in the utility model replaces blanking device.
Fig. 2 is the left view that twoport described in the utility model replaces blanking device.
Fig. 3 is the connection operating schematic diagram of storage bin hopper described in the utility model and pneumatic unit.
Fig. 4 is the connection operating schematic diagram of discharge bucket described in the utility model and pneumatic unit.
Specific implementation mode
To keep the purpose of this utility model, technical solution and advantage clearer, below in conjunction with attached drawing and specific implementation Example is described in further detail the utility model.
Fig. 1 is the front view that twoport described in the utility model replaces blanking device.Fig. 2 hands over for twoport described in the utility model For the left view of blanking device.As shown in Figure 1 and Figure 2, twoport alternating blanking device described in the utility model includes:Two side by side It is installed in the discharge port 6 of sack filling machine side;For being stored to the sandstone material from sack filling machine feed hopper, and pneumatic single Convey the storage bin hopper 2 of sandstone material under the control of member 7 at regular time and quantity to discharge bucket 3;For the timesharing under the control of pneumatic unit 7 The discharge bucket 3 of sandstone material is conveyed to two discharge ports 6;For presetting activity duration, work schedule, according to from discharging Timing sends operational order to storage bin hopper 2 after operation is opened in the enabled instruction of mouth 6, has completely been believed according to the storing from storage bin hopper 2 It number is sent to sack filling machine and to stop conveying sandstone material instruction, according to preset each discharge hole for discharge time to pneumatic unit Periodically send the controller 5 of alternate instruction;According to controller 5 send operational order control storage bin hopper 2 at regular time and quantity to Discharge bucket 3 discharges, and control discharge bucket 3 according to the alternate instruction that controller 5 is sent periodically alternately exports sand to two discharge ports 6 The pneumatic unit 7 of stone material;Wherein,
Discharge bucket 3 is located at the lower section of storage bin hopper 2, and two discharge ports are installed side by side in 3 lower section of discharge bucket;2 one end of storage bin hopper It is connected to the feed hopper 1 of sack filling machine, 2 other end of storage bin hopper is connected to 3 one end of discharge bucket;3 other end of discharge bucket and two dischargings Mouth connection;5 first input end of controller is connect with any discharge port 6, and 5 second input terminal of controller is connect with storage bin hopper 2, control The belt conveyor control terminal of 5 first output end of device and sack filling machine connects, 5 second output terminal of controller and 7 control terminal of pneumatic unit Connection;7 first input/output terminal of pneumatic unit is connect with storage bin hopper 2,7 second input/output terminal of pneumatic unit and discharge bucket 3 Connection.
In the utility model, storage bin hopper 2 periodically convey sandstone material activity duration be 700 milliseconds, 900 milliseconds, 1200 Millisecond.In practical application, which can specifically be set according to material bag size.By the setting of activity duration, The utility model realizes the control of load.
In the utility model, two provided besides are in the application number of the discharge port and application before applicant of sack filling machine side A kind of Chinese utility model application for " 2017205967814 ", entitled " discharge system " is almost the same.Institute's difference exists In, be provided in aforementioned utility model application, on discharge port for measure output sandstone weight of material weighing sensor;And In the utility model, weighing sensor is no longer set, the weight of the sandstone material of output is controlled by controller on discharge port.
In practical application, the soft-touch control 61 for starting operation for controlling sack filling machine is additionally provided on discharge port 6.This practicality In novel, since there are two discharge ports 6 for the same side installing, therefore soft-touch control 61 is installed in any one of two discharge ports 6 On.
In practical application, 5 first input end of the controller is connect with any discharge port 6 is specially:Controller 5 first is defeated Enter end to connect with 61 output end of soft-touch control.
In practical application, signal is expired according to the storing from storage bin hopper 2 and has sent stopping conveying sandstone material to sack filling machine After instruction, the belt feeder 4 on sack filling machine is out of service.
In short, twoport blanking device described in the utility model is installed in sack filling machine side, in practical application, can also simultaneously by The twoport blanking device is symmetrically installed in the sack filling machine other side, and such sack filling machine both sides share 4 discharge ports, further carry The high pack efficiency of sack filling machine.Twoport blanking device described in the utility model passes through at regular time and quantity alternately to two discharge ports Discharging so that sack filling machine is always in running order, and pack worker also improves the efficiency of set folder bag, to greatly increase dress The pack efficiency of bag machine.In addition, twoport blanking device described in the utility model also have the advantages that it is simple in structure, at low cost.
In the utility model, pneumatic unit 7 include for filtering air in impurity and moisture air filter, for compressing The air compressor of air, the driving motor for driving air compressor, the operational order for being sent according to controller 5 are fixed When open or close the first cylinder 7111 of open-close sluice gate 21, the alternate instruction timing for being sent according to controller 5 is alternately turned over Second cylinder 721 of dynamic flag gate;Wherein, driving motor is connect with air compressor, and air compressor is connected by air filter It is connected to the first cylinder 711, the second cylinder 721.
In practical application, pneumatic unit 7 further includes for controlling clamping device folder bag or loose bag on two discharge ports respectively Clamping piece third cylinder and the 4th cylinder.
Fig. 3 is the connection operating schematic diagram of storage bin hopper described in the utility model and pneumatic unit.As shown in figure 3, storage bin hopper 2 ForHole capital after selling all securities formula structure in type, 2 right output port of storage bin hopper are connected to sack filling machine feed hopper, in 2 lower port of storage bin hopper and discharge bucket 3 Port is connected to;Storage bin hopper 2 is installed on the belt conveying frame 4 of sack filling machine, and the live roller 41 on belt conveying frame is located at storage 2 knee of hopper;It is provided in storage bin hopper 2 and periodically closes or open opening for 2 lower port of storage bin hopper under the control of pneumatic unit 7 Closing gate 21, there are one sent to controller 5 when sandstone material reaches 2 limit position of storage bin hopper for the installing of 2 upper inside wall of storage bin hopper Storing has expired the limit sensor of signal.
In the utility model, 7 first input/output terminal of the pneumatic unit is connect with storage bin hopper 2 is specially:Pneumatic unit 7 first input/output terminals are connect with open-close sluice gate 21;
In the utility model, 5 second input terminal of the controller is connect with storage bin hopper 2 is specially:Controller 5 second is defeated Enter end to connect with limit switch.
In the utility model, open-close sluice gate 21 is one piece of iron plate.
In practical application, operational order that the first cylinder 711 is sent according to controller 5 drive open-close sluice gate 21 open or It closes.As shown in figure 3, when open-close sluice gate opens 3 lower port of storage bin hopper, the first cylinder 5 is in position a with open-close sluice gate 21; When open-close sluice gate closes 3 lower port of storage bin hopper, the first cylinder 5 is in position b with open-close sluice gate 21.
Fig. 4 is the connection operating schematic diagram of discharge bucket described in the utility model and pneumatic unit.As shown in figure 4, this practicality The novel discharge bucket 3 is square hollow storehouse formula structure;Discharge bucket 3 is internally provided with for making under the control of pneumatic unit 7 The flap gate 31 of 3 lower port of discharge bucket and two 6 timing alternate communications of discharge port;3 side of discharge bucket is additionally provided with observation window 32;
In the utility model, 7 second input/output terminal of the pneumatic unit is connect with discharge bucket 3 is specially:Pneumatic unit 7 second input/output terminals are connect with flap gate 31.
In the utility model, flap gate 31 is welded by two blocks of steel plates for forming herringbone structure 311~312, and two There are one the door-hinges 313 that bottom end is thick, top is thin for setting between a steel plate, and door-hinge 313 and two welding of steel plate 311~312 are solid It is fixed.In practical application, flap gate 31 also plays a part of that sandstone material is guided to discharge by which discharge port 6.
In practical application, 7211 ontology upper end of the second cylinder by 7211 storage bin hopper 3 of cylinder block outside, the second cylinder 721 Cylinder axis be fixedly connected with the door-hinge bottom end of flap gate 31 by connecting rod 7212.In Fig. 4, position c, position d are turned over respectively Two positions after the alternating overturning of plate gate 31.
In conclusion twoport blanking device described in the utility model is installed in sack filling machine side, it, can also be same in practical application When the twoport blanking device is symmetrically installed in the sack filling machine other side, such sack filling machine both sides share 4 discharge ports, into one Step improves the pack efficiency of sack filling machine.It brings into operation after sack filling machine power-up, this moment, open-close sluice gate, flap gate are in just The initial position of beginning position, open-close sluice gate is close stance, and the initial position of flap gate is to open storage bin hopper with acquiescence first to go out The discharge port channel of material and block the discharging of the second tagmeme discharge port channel position, the belt feeder of operation by sandstone material from Feed hopper is delivered in storage bin hopper.Soft-touch control is touched, is started after 600 milliseconds of twoport blanking device delay described in the utility model Operation, this 600 milliseconds for completing set folder material bag;First cylinder is opened according to the operational order that controller is sent and opens and closes lock Door closes open-close sluice gate after a certain period of time, and during this, a certain amount of sandstone material enters storage bin hopper in storage bin hopper, and according to The guiding function of flag gate, the discharge hole for discharge pack in the first discharging tagmeme, completes the first process.First process packs It is delayed 600 milliseconds after the completion, during being delayed herein, flag gate blocks the discharge port of the first discharging tagmeme, and opens second The discharge port of discharging tagmeme is completed at the same time set folder material bag;First cylinder is opened according to the operational order that controller is sent and is opened and closed Gate closes open-close sluice gate after a certain period of time, and during this, a certain amount of sandstone material enters storage bin hopper, and root in storage bin hopper According to the guiding function of flag gate, the second process is completed in the discharge hole for discharge pack in the second discharging tagmeme.Above-mentioned first mistake Journey is recycled with the primary complete discharging of the second process composition, and primary complete discharging cycle only needs 1200 milliseconds in total.By turning over The switching of plate gate in cycles repeats above-mentioned discharging cycle, completes pack.As it can be seen that passing through the work of the twoport blanking device The working efficiency of function, sack filling machine substantially increases;Moreover, the twoport blanking device is simple in structure, at low cost.
The above is only the preferred embodiments of the present utility model only, is not intended to limit the scope of protection of the utility model. Within the spirit and principle of the utility model, any modification, equivalent replacement, improvement and so on should be included in this reality Within novel protection domain.

Claims (6)

1. a kind of twoport replaces blanking device, including two provided besides, in the discharge port (6) of sack filling machine side, feature exists In the blanking device further includes:For being stored to the sandstone material from sack filling machine feed hopper, and in pneumatic unit (7) storage bin hopper (2) of sandstone material is conveyed under control at regular time and quantity to discharge bucket (3);For the control in pneumatic unit (7) Lower timesharing conveys the discharge bucket (3) of sandstone material to two discharge ports;For presetting activity duration, work schedule, according to Timing sends operational order to storage bin hopper (2) after operation is opened in enabled instruction from discharge port (6), according to from storage bin hopper (2) storing has expired signal and has sent stopping conveying sandstone material instruction to sack filling machine, is gone out according to preset each discharge port The material time periodically sends the controller (5) of alternate instruction to pneumatic unit;The operational order control sent according to controller (5) Storage bin hopper (2) processed at regular time and quantity to discharge bucket (3) discharge, according to controller (5) send alternate instruction control discharge bucket (3) to Two discharge port (6) timings alternately export the pneumatic unit (7) of sandstone material;Wherein,
Discharge bucket (3) is located at the lower section of storage bin hopper (2), and two discharge ports (6) are installed side by side below discharge bucket (3);Storage bin hopper (2) one end is connected to the feed hopper (1) of sack filling machine, and storage bin hopper (2) other end is connected to discharge bucket (3) one end;Discharge bucket (3) is another One end is connected to two discharge ports (6);Controller (5) first input end is connect with any discharge port (6), controller (5) second Input terminal is connect with storage bin hopper (2), the belt conveyor control terminal connection of (5) first output end of controller and sack filling machine, controller (5) second output terminal is connect with pneumatic unit (7) control terminal;(7) first input/output terminal of pneumatic unit connects with storage bin hopper (2) It connects, (7) second input/output terminal of pneumatic unit is connect with discharge bucket (3).
2. twoport according to claim 1 replaces blanking device, which is characterized in that the storage bin hopper (2) isIn type Hole capital after selling all securities formula structure, storage bin hopper (2) right output port are connected to sack filling machine feed hopper, storage bin hopper (2) lower port with it is described go out Hopper (3) upper port is connected to;The storage bin hopper (2) is installed on the belt conveying frame (4) of sack filling machine, and on belt conveying frame Live roller (41) is located at the storage bin hopper (2) knee;It is provided in the storage bin hopper (2) and is controlled in the pneumatic unit (7) The open-close sluice gate (21) of the storage bin hopper (2) lower port is periodically closed or opened under system, and storage bin hopper (2) upper inside wall is installed with One sends storing to the controller (5) when sandstone material reaches storage bin hopper (2) limit position and has expired the limit of signal Sensor;
(7) first input/output terminal of the pneumatic unit is connect with storage bin hopper (2) is specially:The pneumatic unit (7) first is defeated Enter/output end connect with open-close sluice gate (21);
(5) second input terminal of the controller is connect with storage bin hopper (2) is specially:(5) second input terminal of the controller and pole Limit switch connection.
3. twoport according to claim 2 replaces blanking device, which is characterized in that the open-close sluice gate (21) is one block of iron Plate.
4. twoport according to claim 1 replaces blanking device, which is characterized in that the discharge bucket (3) is square hollow Storehouse formula structure;The discharge bucket (3) is internally provided with for making the discharge bucket (3) under the control of the pneumatic unit (7) The flap gate (31) of lower port and two discharge port timing alternate communications;Discharge bucket (3) side is additionally provided with observation window (32);
(7) second input/output terminal of the pneumatic unit is connect with discharge bucket (3) is specially:The pneumatic unit (7) second is defeated Enter/output end connect with flap gate (31).
5. twoport according to claim 4 replaces blanking device, which is characterized in that the flap gate (31) is by two pieces of groups It is welded at the steel plate (311~312) of herringbone structure, there are one bottom end is thick, the thin door-hinge in top for setting between two steel plates (313), and door-hinge (313) is bonded with two steel plates (311~312) and is welded and fixed.
6. twoport according to claim 1 replaces blanking device, which is characterized in that the pneumatic unit (7) includes being used for The air filter of the impurity and moisture in air filtering is crossed, the air compressor of compressed air is used for, for driving air compressor Driving motor, the operational order timing for being sent according to the controller (5) open or close the first of open-close sluice gate (21) The second cylinder of flag gate is alternately stirred in cylinder (711), the alternate instruction timing for being sent according to the controller (5) (721);Wherein, driving motor is connect with air compressor, air compressor by air filter be connected to the first cylinder (711), Second cylinder (721).
CN201721227299.XU 2017-09-25 2017-09-25 A kind of twoport alternating blanking device Active CN207618113U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721227299.XU CN207618113U (en) 2017-09-25 2017-09-25 A kind of twoport alternating blanking device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721227299.XU CN207618113U (en) 2017-09-25 2017-09-25 A kind of twoport alternating blanking device

Publications (1)

Publication Number Publication Date
CN207618113U true CN207618113U (en) 2018-07-17

Family

ID=62818303

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721227299.XU Active CN207618113U (en) 2017-09-25 2017-09-25 A kind of twoport alternating blanking device

Country Status (1)

Country Link
CN (1) CN207618113U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108974460A (en) * 2018-08-21 2018-12-11 合肥天业智能装备有限公司 Boiling cray automatic gauge, mounted box, dress basket production line

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108974460A (en) * 2018-08-21 2018-12-11 合肥天业智能装备有限公司 Boiling cray automatic gauge, mounted box, dress basket production line

Similar Documents

Publication Publication Date Title
CN207618113U (en) A kind of twoport alternating blanking device
CN106268400A (en) Automatic batching system
CN203753891U (en) Bidirectional blanking device for mixing stock bin
CN209567105U (en) Bilateral double-station special-shaped cigarette packing machine
CN101135586A (en) Measurement control method of hopper scale used for feeding revolving furnace
CN208576793U (en) A kind of plastic grains feeding-distribution device
CN206395413U (en) A kind of vertical hand over expects tilting plate type separatory funnel
CN202828106U (en) Feeding device for bag feeding type full-automatic packaging machine
CN202805426U (en) Continuous asphalt mixture agitating equipment
CN216613223U (en) Direct-throw blanking device
CN205293733U (en) Vibrating feeder
CN209720771U (en) A kind of anti-clogging flour sub-packaging system
CN211521012U (en) Blanking control device
CN208868437U (en) A kind of jumbo bag packaging opens bag station
CN107813997A (en) A kind of Kiwi berry formula fertilizer special production equipment
CN202317467U (en) Power addition control device of power adding machine
CN203727715U (en) Multi-port bagging mixer discharge device
CN208994492U (en) Bucket elevator with material-blockage preventing device
CN206954549U (en) One kind is weighed packing device
CN206767167U (en) A kind of device for discharging with ingoldsby car
CN206766475U (en) A kind of screw mounted box baling press
CN210854410U (en) Eccentric pneumatic feeding device and feeding system
CN207191608U (en) Aquatic feeds baling press
CN202492176U (en) Material feeding tank of oscillating conveyor in double-channel material distribution
CN204568072U (en) Eight mouth swinging wrapping machine

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant