CN207605781U - A kind of metallurgical Large Fe ore crushing equipment - Google Patents
A kind of metallurgical Large Fe ore crushing equipment Download PDFInfo
- Publication number
- CN207605781U CN207605781U CN201721514199.5U CN201721514199U CN207605781U CN 207605781 U CN207605781 U CN 207605781U CN 201721514199 U CN201721514199 U CN 201721514199U CN 207605781 U CN207605781 U CN 207605781U
- Authority
- CN
- China
- Prior art keywords
- strut
- bearing seat
- shaft
- support plate
- cylinder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Crushing And Grinding (AREA)
Abstract
The utility model is related to a kind of crushing plant more particularly to a kind of metallurgical Large Fe ore crushing equipments.The technical problem to be solved by the present invention is to provide a kind of metallurgical Large Fe ore crushing equipments.In order to solve the above-mentioned technical problem, the utility model provides such a metallurgy Large Fe ore crushing equipment, includes bottom plate, cylinder, placement plate, holder, support plate, the first strut, motor, first rotating shaft, first bearing seat etc.;The left and right sides is arranged with cylinder on bottom plate, and left and right sides cylinder head is equipped with placement plate, and bottom plate upper left side is equipped with holder, holder is located at the cylinder left in left side, holder right upper portion is equipped with support plate, and support plate top right side is equipped with the first strut, and the first strut left end is equipped with motor.The utility model has achieved the effect that crushing efficiency height and can have been distributed in time to dust that people start cylinder elongation, and cylinder elongation drives placement plate to move up, and people close cylinder after placement plate is moved upwards up to suitable position.
Description
Technical field
The utility model is related to a kind of crushing plant more particularly to a kind of metallurgical Large Fe ore crushing equipments.
Background technology
Metallurgy is exactly that metal or metallic compound are extracted from mineral, and metal is made with certain with various processing methods
The process and technique of the metal material of performance.Metallurgy has long developing history, when from the Stone Age to subsequent bronze ware
Generation, then the extensive development to modern age smelting iron and steel.The history of human development has merged metallurgical developing history.Metallurgical technology
Include mainly pyrometallurgy, hydrometallurgy and electrometallurgy.As physical chemistry is applied successfully in metallurgy, metallurgy is walked from technique
To science, the then quality Personnel in Metallurgical Engineering in You Liao universities.
Iron ore is the important raw and processed materials of steel production enterprise, natural crystal(Iron ore)By being crushed, grinding, magnetic separation,
The programs such as flotation, gravity treatment gradually select iron.Iron ore is the mineral combination for capableing of economic utilization containing iron simple substance or iron compound
Body.
Iron ore is the important raw and processed materials of steel production enterprise, and people can carry out step by step raw iron ores before metallurgy
It is broken, it is usual iron ore be crushed when, it will usually have a large amount of dust appearance, if dust cannot distribute in time,
After being sucked by people body can be damaged, existing crushing plant there are crushing efficiency it is low and cannot in time to dust carry out
The shortcomings that distributing, therefore there is an urgent need for a kind of crushing efficiency height of research and development and dust can be distributed in time metallurgical with large-scale iron ore
Crushing plant.
Utility model content
(1)Technical problems to be solved
The utility model in order to overcome it is usual iron ore is crushed when, it will usually there is a large amount of dust to occur,
If dust cannot distribute in time, body can be damaged after being sucked by people, there are crushing efficiencies for existing crushing plant
Low and the shortcomings that cannot be distributed in time to dust, the technical problem to be solved by the present invention is to provide a kind of metallurgical with big
Sections ore crushing equipment.
(2)Technical solution
In order to solve the above-mentioned technical problem, the utility model provides such a metallurgy and is set with Large Fe ore reduction
It is standby, include bottom plate, cylinder, placement plate, holder, support plate, the first strut, motor, first rotating shaft, first bearing seat, reel,
Sliding rail, sliding block, crusher, the second strut, the first fixed pulley, the first drawstring, third strut, the second fixed pulley and the second drawstring,
The left and right sides is arranged with cylinder on bottom plate, and left and right sides cylinder head is equipped with placement plate, and bottom plate upper left side is equipped with holder, holder
Cylinder left positioned at left side, holder right upper portion are equipped with support plate, and support plate top right side is equipped with the first strut, the first strut left end
Equipped with motor, the output shaft of motor is equipped with first rotating shaft, and support plate centre is inserted to be equipped with first bearing seat, first bearing seat
Below motor, first rotating shaft lower end passes through first bearing seat, first rotating shaft lower end to be equipped with reel, the bottom of the support plate left and right sides
It is arranged with sliding rail, reel is located between two side's sliding rails of left and right, and sliding block is arranged on two side's sliding rails of left and right, and two sides of left and right are slided
It is equipped with crusher between block, is equipped with the second strut on the right side of the bottom of the support plate, the second strut is located at right sliding rail left, the second strut position
In reel right, the second strut lower end is equipped with the first fixed pulley, and crusher top right side is equipped with the first drawstring, the first drawstring end
End connect around the first fixed pulley with reel lower part, and third strut is equipped on the left of the bottom of the support plate, and third strut is located at left cunning
Rail right, third strut are located at reel left, and third strut lower end is equipped with the second fixed pulley, and crusher top left side is equipped with the
Two drawstrings, the second drawstring end connect around the first fixed pulley with reel top.
Preferably, further include having first bevel gear, fixed block, second bearing seat, the second shaft, second bevel gear, first
Belt pulley, the second belt pulley, flat belt, 3rd bearing seat, third shaft, turntable and blade, first rotating shaft middle part are equipped with first
Bevel gear, support plate top left side are equipped with fixed block, and fixed block is equipped with second bearing seat, second turn is equipped in second bearing seat
Axis, the second shaft right end are equipped with second bevel gear, and second bevel gear and first bevel gear engagement, the second shaft left end are equipped with first
Belt pulley, holder lower part are equipped with 3rd bearing seat, and third shaft is equipped on 3rd bearing seat, and third shaft left end is equipped with second
Flat belt is wound on belt pulley, the second belt pulley and the first belt pulley, third shaft right end is equipped with turntable, and turntable upper and lower ends are set
There is blade.
Preferably, further include having rubber pad, placement plate top center is provided with groove, and rubber pad is equipped in groove.
Operation principle:When people need to be crushed iron ore, preprepared iron ore is placed on by people
In placement plate, when people need adjust placement plate move up when, people start cylinder elongation, cylinder elongation drive placement plate to
Upper movement, people close cylinder after placement plate is moved upwards up to suitable position, when people need adjusting placement plate to move down,
People start cylinder and shorten, and cylinder, which shortens, drives placement plate to move down, and people are closed after placement plate is moved down into suitable position
It holds one's breath cylinder, so that people can freely adjust the height of placement plate, subsequent people start the rotation of motor positive direction, electricity
The rotation of machine positive direction drives the rotation of first rotating shaft positive direction, the rotation of first rotating shaft positive direction to drive the rotation of reel positive direction, around
The first drawstring and the second drawstring are received in the rotation of line wheel positive direction, and then crusher is driven to move up, and crusher is moved upwards up to conjunction
Right position postpones, and people start the rotation of motor negative direction, and the rotation of motor negative direction drives the rotation of first rotating shaft negative direction, first rotating shaft
Negative direction rotation drives reel to put the first drawstring and the second drawstring so that crusher is due to the downward freely falling body fortune of its own gravity
Dynamic, crusher, which moves down, hits the iron ore in placement plate, later people always repeated priming motor positive direction and
Negative direction rotates so that crusher, which can be moved up and down persistently, hits the iron ore in placement plate, when iron ore is broken
When broken crusher machine is to appropriate level, people close motor, then the iron ore being crushed in placement plate is taken out.
Because further including having first bevel gear, fixed block, second bearing seat, the second shaft, second bevel gear, the first belt
Wheel, the second belt pulley, flat belt, 3rd bearing seat, third shaft, turntable and blade, first rotating shaft middle part are equipped with the first cone tooth
Wheel, support plate top left side are equipped with fixed block, and fixed block is equipped with second bearing seat, the second shaft is equipped in second bearing seat,
Second shaft right end is equipped with second bevel gear, and second bevel gear and first bevel gear engagement, the second shaft left end are equipped with the first skin
Belt wheel, holder lower part are equipped with 3rd bearing seat, and third shaft is equipped on 3rd bearing seat, and third shaft left end is equipped with the second skin
Flat belt is wound on belt wheel, the second belt pulley and the first belt pulley, third shaft right end is equipped with turntable, and turntable upper and lower ends are equipped with
Blade will produce a large amount of dusts so when people are crushed iron ore, and people start motor rotation, and motor rotates band
Dynamic first rotating shaft rotation, first rotating shaft rotation drive first bevel gear and second bevel gear rotation, second bevel gear rotation to drive
Second shaft and the first pulley rotation, the first pulley rotation drive flat belt and the second pulley rotation, the second belt pulley
Rotation drives the rotation of third shaft, the rotation of third shaft to drive turntable and blade rotation, blade rotation that can dispel dust, from
And people is made not suck a large amount of dust in broken iron ore, motor is closed after people have been crushed, blade stops therewith
Rotation stop is dynamic.
Because further including having rubber pad, placement plate top center is provided with groove, rubber pad is equipped in groove, so working as people
When needing to be crushed iron ore, iron ore can be placed on rubber pad by people, so that crusher will not be to putting
Plate is set to damage.
The control mode of the utility model is automatically controlled by controller, and the control circuit of controller passes through this field
Technical staff's simple programming can be realized, belong to the common knowledge of this field, and the utility model is mainly used to protect machine
Tool device, so the utility model is not explained control mode and is connected with circuit.
(3)Advantageous effect
The utility model has achieved the effect that crushing efficiency height and can have been distributed in time to dust that people start cylinder and stretch
Long, cylinder elongation drives placement plate to move up, and people close cylinder after placement plate is moved upwards up to suitable position, when people need
When adjusting placement plate and moving down, people start cylinder and shorten, and cylinder, which shortens, drives placement plate to move down, and placement plate is downward
People close cylinder after being moved to suitable position, so that people can freely adjust the height of placement plate.
Description of the drawings
Fig. 1 is the main structure diagram of the utility model.
Label in attached drawing be:1- bottom plates, 2- cylinders, 3- placement plates, 4- holders, 5- support plates, the first struts of 6-, 7- electricity
Machine, 8- first rotating shafts, 9- first bearing seats, 10- reels, 11- sliding rails, 12- sliding blocks, 13- crushers, the second struts of 14-,
The first fixed pulleys of 15-, the first drawstrings of 16-, 17- third struts, the second fixed pulleys of 18-, the second drawstrings of 19-, 20- first bore tooth
Wheel, 21- fixed blocks, 22- second bearing seats, the second shafts of 23-, 24- second bevel gears, the first belt pulleys of 25-, 26- third axis
Bearing, 27- third shafts, the second belt pulleys of 28-, 29- flat belts, 30- turntables, 31- blades, 32- grooves, 33- rubber pads.
Specific implementation mode
The utility model is further described with reference to the accompanying drawings and examples.
Embodiment 1
A kind of metallurgical Large Fe ore crushing equipment, as shown in Figure 1, including bottom plate 1, cylinder 2, placement plate 3, holder
4, support plate 5, the first strut 6, motor 7, first rotating shaft 8, first bearing seat 9, reel 10, sliding rail 11, sliding block 12, crusher
13, the second strut 14, the first fixed pulley 15, the first drawstring 16, third strut 17, the second fixed pulley 18 and the second drawstring 19, bottom
The left and right sides is arranged with cylinder 2 on plate 1, and cylinder 2 top in the left and right sides is equipped with placement plate 3, and 1 upper left side of bottom plate is equipped with holder 4,
Holder 4 is located at 2 left of cylinder in left side, and 4 right upper portion of holder is equipped with support plate 5, and 5 top right side of support plate is equipped with the first strut 6, the
One strut, 6 left end is equipped with motor 7, and the output shaft of motor 7 is equipped with first rotating shaft 8, and 5 centre of support plate is inserted to be equipped with first bearing
Seat 9, first bearing seat 9 are located at the lower section of motor 7, and 8 lower end of first rotating shaft passes through first bearing seat 9,8 lower end of first rotating shaft equipped with around
Line wheel 10,5 bottom of the support plate left and right sides are arranged with sliding rail 11, and reel 10 is located between two side's sliding rails 11 of left and right, left and right two
It is arranged with sliding block 12 on square sliding rail 11, crusher 13 is equipped between two side's sliding blocks 12 of left and right, 5 bottom right of support plate is equipped with second
Strut 14, the second strut 14 are located at 11 left of right sliding rail, and the second strut 14 is located at 10 right of reel, 14 lower end of the second strut
Equipped with the first fixed pulley 15,13 top right side of crusher is equipped with the first drawstring 16, and 16 end of the first drawstring bypasses the first fixed pulley
15 connect with 10 lower part of reel, and 5 bottom left of support plate is equipped with third strut 17, and it is right that third strut 17 is located at left sliding rail 11
Side, third strut 17 are located at 10 left of reel, and 17 lower end of third strut is equipped with the second fixed pulley 18,13 top left side of crusher
Equipped with the second drawstring 19,19 end of the second drawstring connect around the first fixed pulley 15 with 10 top of reel.
Embodiment 2
A kind of metallurgical Large Fe ore crushing equipment, as shown in Figure 1, including bottom plate 1, cylinder 2, placement plate 3, holder
4, support plate 5, the first strut 6, motor 7, first rotating shaft 8, first bearing seat 9, reel 10, sliding rail 11, sliding block 12, crusher
13, the second strut 14, the first fixed pulley 15, the first drawstring 16, third strut 17, the second fixed pulley 18 and the second drawstring 19, bottom
The left and right sides is arranged with cylinder 2 on plate 1, and cylinder 2 top in the left and right sides is equipped with placement plate 3, and 1 upper left side of bottom plate is equipped with holder 4,
Holder 4 is located at 2 left of cylinder in left side, and 4 right upper portion of holder is equipped with support plate 5, and 5 top right side of support plate is equipped with the first strut 6, the
One strut, 6 left end is equipped with motor 7, and the output shaft of motor 7 is equipped with first rotating shaft 8, and 5 centre of support plate is inserted to be equipped with first bearing
Seat 9, first bearing seat 9 are located at the lower section of motor 7, and 8 lower end of first rotating shaft passes through first bearing seat 9,8 lower end of first rotating shaft equipped with around
Line wheel 10,5 bottom of the support plate left and right sides are arranged with sliding rail 11, and reel 10 is located between two side's sliding rails 11 of left and right, left and right two
It is arranged with sliding block 12 on square sliding rail 11, crusher 13 is equipped between two side's sliding blocks 12 of left and right, 5 bottom right of support plate is equipped with second
Strut 14, the second strut 14 are located at 11 left of right sliding rail, and the second strut 14 is located at 10 right of reel, 14 lower end of the second strut
Equipped with the first fixed pulley 15,13 top right side of crusher is equipped with the first drawstring 16, and 16 end of the first drawstring bypasses the first fixed pulley
15 connect with 10 lower part of reel, and 5 bottom left of support plate is equipped with third strut 17, and it is right that third strut 17 is located at left sliding rail 11
Side, third strut 17 are located at 10 left of reel, and 17 lower end of third strut is equipped with the second fixed pulley 18,13 top left side of crusher
Equipped with the second drawstring 19,19 end of the second drawstring connect around the first fixed pulley 15 with 10 top of reel.
Further include having first bevel gear 20, fixed block 21, second bearing seat 22, the second shaft 23, second bevel gear 24,
One belt pulley 25, the second belt pulley 28, flat belt 29,3rd bearing seat 26, third shaft 27, turntable 30 and blade 31, first
8 middle part of shaft is equipped with first bevel gear 20, and 5 top left side of support plate is equipped with fixed block 21, and fixed block 21 is equipped with second bearing seat
22, the second shaft 23 is installed, 23 right end of the second shaft is equipped with second bevel gear 24, second bevel gear 24 in second bearing seat 22
It being engaged with first bevel gear 20,23 left end of the second shaft is equipped with the first belt pulley 25, and 4 lower part of holder is equipped with 3rd bearing seat 26,
Third shaft 27 is installed, 27 left end of third shaft is equipped with the second belt pulley 28,28 He of the second belt pulley on 3rd bearing seat 26
Flat belt 29 is wound on first belt pulley 25,27 right end of third shaft is equipped with turntable 30, and 30 upper and lower ends of turntable are equipped with blade 31.
Embodiment 3
A kind of metallurgical Large Fe ore crushing equipment, as shown in Figure 1, including bottom plate 1, cylinder 2, placement plate 3, holder
4, support plate 5, the first strut 6, motor 7, first rotating shaft 8, first bearing seat 9, reel 10, sliding rail 11, sliding block 12, crusher
13, the second strut 14, the first fixed pulley 15, the first drawstring 16, third strut 17, the second fixed pulley 18 and the second drawstring 19, bottom
The left and right sides is arranged with cylinder 2 on plate 1, and cylinder 2 top in the left and right sides is equipped with placement plate 3, and 1 upper left side of bottom plate is equipped with holder 4,
Holder 4 is located at 2 left of cylinder in left side, and 4 right upper portion of holder is equipped with support plate 5, and 5 top right side of support plate is equipped with the first strut 6, the
One strut, 6 left end is equipped with motor 7, and the output shaft of motor 7 is equipped with first rotating shaft 8, and 5 centre of support plate is inserted to be equipped with first bearing
Seat 9, first bearing seat 9 are located at the lower section of motor 7, and 8 lower end of first rotating shaft passes through first bearing seat 9,8 lower end of first rotating shaft equipped with around
Line wheel 10,5 bottom of the support plate left and right sides are arranged with sliding rail 11, and reel 10 is located between two side's sliding rails 11 of left and right, left and right two
It is arranged with sliding block 12 on square sliding rail 11, crusher 13 is equipped between two side's sliding blocks 12 of left and right, 5 bottom right of support plate is equipped with second
Strut 14, the second strut 14 are located at 11 left of right sliding rail, and the second strut 14 is located at 10 right of reel, 14 lower end of the second strut
Equipped with the first fixed pulley 15,13 top right side of crusher is equipped with the first drawstring 16, and 16 end of the first drawstring bypasses the first fixed pulley
15 connect with 10 lower part of reel, and 5 bottom left of support plate is equipped with third strut 17, and it is right that third strut 17 is located at left sliding rail 11
Side, third strut 17 are located at 10 left of reel, and 17 lower end of third strut is equipped with the second fixed pulley 18,13 top left side of crusher
Equipped with the second drawstring 19,19 end of the second drawstring connect around the first fixed pulley 15 with 10 top of reel.
Further include having first bevel gear 20, fixed block 21, second bearing seat 22, the second shaft 23, second bevel gear 24,
One belt pulley 25, the second belt pulley 28, flat belt 29,3rd bearing seat 26, third shaft 27, turntable 30 and blade 31, first
8 middle part of shaft is equipped with first bevel gear 20, and 5 top left side of support plate is equipped with fixed block 21, and fixed block 21 is equipped with second bearing seat
22, the second shaft 23 is installed, 23 right end of the second shaft is equipped with second bevel gear 24, second bevel gear 24 in second bearing seat 22
It being engaged with first bevel gear 20,23 left end of the second shaft is equipped with the first belt pulley 25, and 4 lower part of holder is equipped with 3rd bearing seat 26,
Third shaft 27 is installed, 27 left end of third shaft is equipped with the second belt pulley 28,28 He of the second belt pulley on 3rd bearing seat 26
Flat belt 29 is wound on first belt pulley 25,27 right end of third shaft is equipped with turntable 30, and 30 upper and lower ends of turntable are equipped with blade 31.
Further include having rubber pad 33,3 top center of placement plate is provided with groove 32, and rubber pad 33 is equipped in groove 32.
Preferred embodiments of the present invention above described embodiment only expresses, the description thereof is more specific and detailed,
But it should not be understood as limiting the scope of the patent of the utility model.It should be pointed out that for the common of this field
For technical staff, without departing from the inventive concept of the premise, several deformations can also be made, improves and substitutes, these are all
Belong to the scope of protection of the utility model.Therefore, the protection domain of the utility model patent should be determined by the appended claims.
Claims (3)
1. a kind of metallurgical Large Fe ore crushing equipment, which is characterized in that include bottom plate(1), cylinder(2), placement plate
(3), holder(4), support plate(5), the first strut(6), motor(7), first rotating shaft(8), first bearing seat(9), reel(10)、
Sliding rail(11), sliding block(12), crusher(13), the second strut(14), the first fixed pulley(15), the first drawstring(16), third branch
Bar(17), the second fixed pulley(18)With the second drawstring(19), bottom plate(1)The upper left and right sides is arranged with cylinder(2), the left and right sides
Cylinder(2)Top is equipped with placement plate(3), bottom plate(1)Upper left side is equipped with holder(4), holder(4)Cylinder positioned at left side(2)It is left
Side, holder(4)Right upper portion is equipped with support plate(5), support plate(5)Top right side is equipped with the first strut(6), the first strut(6)Left end
Equipped with motor(7), motor(7)Output shaft be equipped with first rotating shaft(8), support plate(5)It is intermediate inserted equipped with first bearing seat
(9), first bearing seat(9)Positioned at motor(7)Lower section, first rotating shaft(8)Lower end passes through first bearing seat(9), first rotating shaft(8)
Lower end is equipped with reel(10), support plate(5)It is arranged with sliding rail at left and right sides of bottom(11), reel(10)Positioned at two sides of left and right
Sliding rail(11)Between, two side's sliding rails of left and right(11)On be arranged with sliding block(12), two side's sliding blocks of left and right(12)Between be equipped with it is broken
Machine(13), support plate(5)Bottom right is equipped with the second strut(14), the second strut(14)Positioned at right sliding rail(11)Left, second
Strut(14)Positioned at reel(10)Right, the second strut(14)Lower end is equipped with the first fixed pulley(15), crusher(13)Top
Right side is equipped with the first drawstring(16), the first drawstring(16)End bypasses the first fixed pulley(15)With reel(10)Lower part connects,
Support plate(5)Bottom left is equipped with third strut(17), third strut(17)Positioned at left sliding rail(11)Right, third strut(17)
Positioned at reel(10)Left, third strut(17)Lower end is equipped with the second fixed pulley(18), crusher(13)Top left side is equipped with
Second drawstring(19), the second drawstring(19)End bypasses the first fixed pulley(15)With reel(10)Top connects.
2. a kind of metallurgical Large Fe ore crushing equipment according to claim 1, which is characterized in that further include having first
Bevel gear(20), fixed block(21), second bearing seat(22), the second shaft(23), second bevel gear(24), the first belt pulley
(25), the second belt pulley(28), flat belt(29), 3rd bearing seat(26), third shaft(27), turntable(30)And blade
(31), first rotating shaft(8)Middle part is equipped with first bevel gear(20), support plate(5)Top left side is equipped with fixed block(21), fixed block
(21)It is equipped with second bearing seat(22), second bearing seat(22)On the second shaft is installed(23), the second shaft(23)Right end
Equipped with second bevel gear(24), second bevel gear(24)And first bevel gear(20)Engagement, the second shaft(23)Left end is equipped with the
One belt pulley(25), holder(4)Lower part is equipped with 3rd bearing seat(26), 3rd bearing seat(26)On third shaft is installed
(27), third shaft(27)Left end is equipped with the second belt pulley(28), the second belt pulley(28)With the first belt pulley(25)On be wound with
Flat belt(29), third shaft(27)Right end is equipped with turntable(30), turntable(30)Upper and lower ends are equipped with blade(31).
3. a kind of metallurgical Large Fe ore crushing equipment according to claim 2, which is characterized in that further include having rubber
Pad(33), placement plate(3)Top center is provided with groove(32), groove(32)It is interior to be equipped with rubber pad(33).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721514199.5U CN207605781U (en) | 2017-11-14 | 2017-11-14 | A kind of metallurgical Large Fe ore crushing equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721514199.5U CN207605781U (en) | 2017-11-14 | 2017-11-14 | A kind of metallurgical Large Fe ore crushing equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207605781U true CN207605781U (en) | 2018-07-13 |
Family
ID=62795679
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721514199.5U Expired - Fee Related CN207605781U (en) | 2017-11-14 | 2017-11-14 | A kind of metallurgical Large Fe ore crushing equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207605781U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111672559A (en) * | 2020-05-20 | 2020-09-18 | 陈松妹 | Medical waste crushing and sterilizing device |
CN112604745A (en) * | 2020-11-19 | 2021-04-06 | 葛寒 | Sweet potato starch piece pulverizes collecting device |
-
2017
- 2017-11-14 CN CN201721514199.5U patent/CN207605781U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111672559A (en) * | 2020-05-20 | 2020-09-18 | 陈松妹 | Medical waste crushing and sterilizing device |
CN112604745A (en) * | 2020-11-19 | 2021-04-06 | 葛寒 | Sweet potato starch piece pulverizes collecting device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206887920U (en) | A kind of small-sized river course river surface floating refuse cleaning plant | |
CN207605781U (en) | A kind of metallurgical Large Fe ore crushing equipment | |
CN107115924A (en) | A kind of mining industry ore efficiency crushing device | |
CN205650327U (en) | High -efficient collection device of building site scrap iron | |
CN107115910A (en) | A kind of road construction ratchel efficiency crushing equipment | |
CN206304803U (en) | A kind of preliminary breaker of waste water clod for building | |
CN209427750U (en) | A kind of automatic charging device of shot-blasting machine | |
CN206810382U (en) | A kind of mining industry ore efficiency crushing device | |
CN206082731U (en) | Grinder is used in preparation of industry cement | |
CN106403620B (en) | A kind of industrial metallurgical cooling device | |
CN205731022U (en) | A kind of copper metallurgy copper ore high efficient mixed device | |
CN107199177A (en) | One kind, which is smelted, uses blast furnace slag high-efficient treatment device | |
CN107159378A (en) | A kind of cartridge type rainbow conk crushing and screening equipment | |
CN106391480A (en) | Separation device for fruit sorting | |
CN107398714A (en) | A kind of semi-automatic tire bearing installation equipment | |
CN206778940U (en) | One kind, which is smelted, uses blast furnace slag high-efficient treatment device | |
CN106552685A (en) | A kind of lithium battery processing technology graphite ore quick crashing equipment | |
CN205996720U (en) | A kind of can self-feeding centerless grinder | |
CN205550393U (en) | Roller dynamic formula ore crusher | |
CN204366749U (en) | The closed dedusting polishing machine of a kind of aluminium section bar | |
CN108339663A (en) | A kind of spiral self-discharging deironing device | |
CN210787466U (en) | Jaw crusher convenient to change movable jaw plate | |
CN206549741U (en) | A kind of Production of Ceramics ball mill | |
CN207254531U (en) | A kind of river sand iron powder separator | |
CN207724081U (en) | A kind of sand sponge ray machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |