CN207583394U - A kind of band mould negative pressure mud jacking system for tunnel double-lining - Google Patents

A kind of band mould negative pressure mud jacking system for tunnel double-lining Download PDF

Info

Publication number
CN207583394U
CN207583394U CN201721669035.XU CN201721669035U CN207583394U CN 207583394 U CN207583394 U CN 207583394U CN 201721669035 U CN201721669035 U CN 201721669035U CN 207583394 U CN207583394 U CN 207583394U
Authority
CN
China
Prior art keywords
mud jacking
high pressure
lining
hose
steel wire
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721669035.XU
Other languages
Chinese (zh)
Inventor
李新强
王英俊
薛彦军
刘奇
赵炜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 5 Co Ltd
Original Assignee
Sinohydro Bureau 5 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 5 Co Ltd filed Critical Sinohydro Bureau 5 Co Ltd
Priority to CN201721669035.XU priority Critical patent/CN207583394U/en
Application granted granted Critical
Publication of CN207583394U publication Critical patent/CN207583394U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model provides a kind of band mould negative pressure mud jacking system for tunnel double-lining, and structure is:Hole is uniformly distributed on high pressure steel wire mud jacking hose;High pressure steel wire mud jacking hose is arranged along splash guard, and is placed between splash guard and two lined steel muscle, and is fixed on two lined steel muscle with U-shaped reinforcing bar clamp ring at spacing intervals;High pressure steel wire mud jacking hose one end seals and is fixed in two lined steel muscle, and the other end is fixed on the template mud jacking hole of two lining trolley formwork ends;Template mud jacking hole connects high pressure steel fiber tube, and high pressure steel fiber tube is connected to mudjack, and mudjack is connected to blender;PPR exhaust pipes one end is placed in by template gas vent in two lining cavities, and one end is connected with three-way connection, and the another both ends of three-way connection connect discharge pipe and vacuum pump respectively.The utility model improves the plumpness and compactness of two lining mud jacking, avoids vault and comes to nothing the generation of problem, while shortened for two lining mud jacking activity durations.

Description

A kind of band mould negative pressure mud jacking system for tunnel double-lining
Technical field
The utility model is related to tunnel double-lining Grouting Technology field, specially a kind of band mould negative pressure pressure for tunnel double-lining Slurry system.
Background technology
Metro construction has tended to the white-hot stage at present, high-quality, high standard tunnel construction technology to rapidly sending out Decisive role is played in the subway construction of exhibition, and two lining constructions in constructing tunnel are then the key links of constructing tunnel.Needle It constructs to current domestic tunnel double-lining, compactness, the plumpness of two lining mud jacking are but particularly important, and two traditional lining mud jacking Technique not only construct it is cumbersome influence two lining presentation qualities, but also two lining construction periods, the various resources of waste can be extended, it is prior It is to serve as a contrast mud-jacking technologies using traditional two, air cannot exclude in cavity, can make to contain a large amount of gas in the slurry of press-in in this way Bubble, causes two backing portion to form cavity or come to nothing, and leads to two lining structure leakiness, reduces by two lining bearing capacitys, promotes under vault It is heavy to cause major safety risks.
Utility model content
The technical problem to be solved by the utility model is to provide a kind of band mould negative pressure mud jacking system for tunnel double-lining, Solve two lining mud jacking leakiness in conventional method, it is not full caused by two lining structure bearing capacitys reduce, vault sinking problem.
In order to solve the above technical problems, the technical solution adopted in the utility model is:
A kind of negative pressure mud jacking system for tunnel double-lining, including high pressure steel wire mud jacking hose, the high pressure steel wire mud jacking Hole is uniformly distributed on hose;The high pressure steel wire mud jacking hose is arranged along splash guard, and is placed in splash guard and two lined steel muscle Between, and be fixed on two lined steel muscle with U-shaped reinforcing bar clamp ring at spacing intervals;High pressure steel wire mud jacking hose one end seals and consolidates It is scheduled in two lined steel muscle, the other end is fixed on the template mud jacking hole of two lining trolley formwork ends;
Template mud jacking hole connects high pressure steel fiber tube, and the high pressure steel fiber tube is connected to mudjack, and the mudjack reconnects To blender;
PPR exhaust pipes are provided with, described PPR exhaust pipes one end is placed in by template gas vent in two lining cavities, and one end connects Three-way connection is connected to, the another both ends of three-way connection connect discharge pipe and vacuum pump respectively.
Further, another high pressure steel wire mud jacking hose, referred to as the second high pressure steel wire mud jacking hose are additionally provided with;Second High pressure steel wire mud jacking hose is equally arranged along splash guard, and is placed between splash guard and two lined steel muscle, and sealed end is arranged in The mud jacking extreme direction of one high pressure steel wire mud jacking hose, mud jacking end are arranged in the sealed end of first high pressure steel wire mud jacking hose Direction.
Further, the PPR exhaust pipe lengths are 60cm, are provided with twice notch in one end, slot opening 6mm is deep 10mm。
Further, the hole diameter of the high pressure steel wire mud jacking hose is 6mm, and hole spacing is 5cm.
Further, the spacing between each U-shaped reinforcing bar clamp ring is 50cm.
Compared with prior art, the beneficial effects of the utility model are:1st, artificial, mechanical, material consumption is saved, and Construction technology is relatively simple;2nd, the plumpness and compactness of two lining mud jacking are improved;3rd, vault is avoided to come to nothing the generation of problem; 4th, shortened for two lining mud jacking activity durations;5th, the expense of later stage defect processing is reduced.
Description of the drawings
Fig. 1 is for the negative pressure mud jacking overall system architecture of tunnel double-lining and arrangement schematic diagram in the utility model.
Fig. 2 is that the utility model mesohigh steel wire madjack pipe fixes schematic diagram.
Fig. 3 is the enlarged diagram at position shown in A in Fig. 2.
Fig. 4 is the structure diagram after the processing of PPR exhaust pipes in the utility model.
In figure:In figure:1- high pressure steel wire mud jacking hoses;Bis- lined steel muscle of 2-;3-U steel bar snap rings;4- splash guards;5- mud jacking Pump;6- blenders;7- vacuum pumps;8- discharge pipes;9- ball valves;10- template gas vents;11- bis- serves as a contrast trolley formwork;12- template pressures Starch hole.Note:Second high pressure steel wire mud jacking hose belongs to high pressure steel wire mud jacking hose, is intended merely to the differentiation of description, therefore, still So represented with label 1.
Specific embodiment
The utility model is described in further detail with reference to the accompanying drawings and detailed description.
The utility model mud jacking system includes high pressure steel wire mud jacking hose 1, PPR exhaust pipes, mudjack 5, blender 6 and true Sky pump 7.Mudjack 5 should have multistage pressure control, and mud jacking pressure is detected by pressure gauge during mud jacking, is controlled. In addition, mud jacking equipment, should have the active control unit for mixing slurry water, so as to water that is simple, facilitating control additional.The spice Machine 6 should use high-speed mixing equipment, and the rotating speed of blade is at least 1000rpm, the ceiling for accumulation speed of blade be limited in 15m/sec with Interior, the mixing time is no more than 6min.High pressure steel wire mud jacking hose 1 is the mud jacking hose of Φ 32.PPR exhaust pipes are the row of Φ 32 Tracheae.
Specifically, mud jacking system in the utility model, structure are:Including high pressure steel wire mud jacking hose 1, the high pressure steel Hole is uniformly distributed on silk mud jacking hose 1;The high pressure steel wire mud jacking hose 1 is arranged, and be placed in splash guard 4 along splash guard 4 Between two lined steel muscle 2, and it is fixed on two lined steel muscle 2 with U-shaped reinforcing bar clamp ring 3 at spacing intervals;High pressure steel wire mud jacking is soft 1 one end of pipe seals and is fixed in two lined steel muscle 2, and the other end is fixed on the template mud jacking hole 12 of two lining trolley formworks, 11 end; Template mud jacking hole 12 connects high pressure steel fiber tube, and the high pressure steel fiber tube is connected to mudjack 5, and the mudjack 5, which is connected to, to be mixed Material machine 6;PPR exhaust pipes are provided with, described PPR exhaust pipes one end is placed in by template gas vent 10 in two lining cavities, and one end connects Three-way connection is connected to, the another both ends of three-way connection connect discharge pipe 8 and vacuum pump 7 respectively.
It delays work rate to promote working efficiency and reducing, is additionally provided with another high pressure steel wire mud jacking hose 1, referred to as second High pressure steel wire mud jacking hose 1;Second high pressure steel wire mud jacking hose 1 is equally arranged along splash guard 4, and is placed in the lining of splash guard 4 and two Between reinforcing bar 2, sealed end is arranged in the mud jacking extreme direction of first high pressure steel wire mud jacking hose 1, and mud jacking end is arranged in The sealing extreme direction of one high pressure steel wire mud jacking hose 1.
The mud jacking method of the utility model negative pressure mud jacking system, includes the following steps:
Step 1:PPR exhaust pipes are connected to three-way connection by ring flange at template exhaust pipe, another the two of three-way connection Head connects discharge pipe 8 and vacuum pump 7 respectively;The high pressure steel wire mud jacking hose 1 for being fixed on mud jacking hole ring flange is passed through into connection Ring flange is connect by connector with mudjack 5;Later, spare template mud jacking hole 12 and template gas vent 10 are closed;Step 2:It adopts Air in cavity is extracted between two lining concrete with vacuum pump 7, the constant pressure negative pressure that generation is certain is made in the cavity in;Step 3:Open mud jacking 5 mud jacking are pumped, after mud jacking is full, are kept for the voltage stabilizing phase of certain time;Step 4:It carries out pressure and mends slurry, until there is homogeneous slurry in outlet Outflow.
During realization, it can be carried out by mode particularized below:32 high pressure steel wire mud jacking hoses 1 of Φ are punched in advance and are added Work punches spacing 5cm, and hole diameter 6mm, hole is arranged in blossom type, is sealed after punching with adhesive tape.PPR is arranged Tracheae is processed in advance, and length interception 60cm, both ends are truncated, and twice notch, slot opening 6mm, deep 10mm are opened in one end.Each U Spacing between steel bar snap ring 3 is 50cm.The range of constant pressure negative pressure is -0.06Mpa to -0.08Mpa.In step 3, mud jacking The mud jacking pressure of pump 5 is less than 0.6Mpa.More optimizing, the mud jacking pressure limit of mudjack 5 is maintained at 0.5Mpa to 0.6Mpa, and Voltage stabling control is more than 3min.In step 4, the pressure that pressure mends slurry is 0.5Mpa, voltage stabling control 5min.
The utility model mud jacking System Working Principle is:When two lined steel muscle 2 are bound, it is being most disadvantageous in tunnel double-lining concrete The high pressure steel wire mud jacking hose 1 that the pre-buried twice of section part poured are made in advance, the high pressure steel wire mud jacking hose 1 are accomplished fluently in advance Hole uses rubber belt sealing;One 1 one end of high pressure steel wire mud jacking hose seals and is fixed in two lined steel muscle 2, and the other end is fixed on The end mud jacking hole of two lining trolley formworks 11, another then direction is pre-buried in contrast is fixed on trolley tail portion mud jacking hole, in platform At vehicle mud jacking hole mudjack 5 is connected to high pressure steel fiber tube.Using two lining trolleys, treat that two lining concrete initial sets can carry out mud jacking and apply Work before mud jacking, first with three-way connection connection PPR exhaust pipes pre-buried in advance, then passes through PPR exhaust pipes with vacuum pump 7 and draws two Lining cavity in air, the vacuum degree in cavity is made to reach 0.06~0.08MPa of negative pressure, then the other end with mudjack 5 with The pressure of 0.4~0.6MPa is empty by two lining of the M20 micro-expansibilities cement mortar being stirred press-in.When a wherein high pressure steel wire The blocking of mud jacking hose 1 can start another 1 operation of high pressure steel wire mud jacking hose when being unable to mud jacking, can accomplish that precautions averts perils in this way, Squeezing quality can also be improved by greatly improving mud jacking efficiency.Due to there was only a small amount of air in cavity, slurry is hardly formed this method Bubble causes cavity;Simultaneously as the positive/negative-pressure force difference in cavity between mudjack 5, is not only " to press " and be the increase in The function of " suction ", the push and draw force formed under this suction function greatly improve the full weight and compactness of slurry in cavity, from And it is uncompacted to efficiently solve the problems, such as that tradition two serves as a contrast mud jacking.

Claims (5)

1. a kind of band mould negative pressure mud jacking system for tunnel double-lining, which is characterized in that
Including high pressure steel wire mud jacking hose (1), hole is uniformly distributed on the high pressure steel wire mud jacking hose (1);The high pressure Steel wire mud jacking hose (1) is arranged along splash guard (4), and is placed between splash guard (4) and two lined steel muscle (2), and between certain Away from being fixed on two lined steel muscle (2) with U-shaped reinforcing bar clamp ring (3);High pressure steel wire mud jacking hose (1) one end seals and is fixed on two linings In reinforcing bar (2), the other end is fixed on the template mud jacking hole (12) of two lining trolley formwork (11) ends;
Template mud jacking hole (12) connects high pressure steel fiber tube, and the high pressure steel fiber tube is connected to mudjack (5), the mudjack (5) It is connected to blender (6);
PPR exhaust pipes are provided with, described PPR exhaust pipes one end is placed in by template gas vent (10) in two lining cavities, and one end connects Three-way connection is connected to, the another both ends of three-way connection connect discharge pipe (8) and vacuum pump (7) respectively.
2. a kind of band mould negative pressure mud jacking system for tunnel double-lining as described in claim 1, which is characterized in that be additionally provided with Another high pressure steel wire mud jacking hose (1), referred to as the second high pressure steel wire mud jacking hose (1);Second high pressure steel wire mud jacking hose (1) It equally arranges, and is placed between splash guard (4) and two lined steel muscle (2) along splash guard (4), sealed end is arranged in first high pressure The mud jacking extreme direction of steel wire mud jacking hose (1), mud jacking end are arranged in the sealed end side of first high pressure steel wire mud jacking hose (1) To.
A kind of 3. band mould negative pressure mud jacking system for tunnel double-lining as described in claim 1, which is characterized in that the PPR Exhaust pipe length is 60cm, and twice notch, slot opening 6mm, deep 10mm are provided in one end.
A kind of 4. band mould negative pressure mud jacking system for tunnel double-lining as described in claim 1, which is characterized in that the high pressure The hole diameter of steel wire mud jacking hose (1) is 6mm, and hole spacing is 5cm.
5. a kind of band mould negative pressure mud jacking system for tunnel double-lining as described in claim 1, which is characterized in that each U-shaped Spacing between reinforcing bar clamp ring (3) is 50cm.
CN201721669035.XU 2017-12-05 2017-12-05 A kind of band mould negative pressure mud jacking system for tunnel double-lining Expired - Fee Related CN207583394U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721669035.XU CN207583394U (en) 2017-12-05 2017-12-05 A kind of band mould negative pressure mud jacking system for tunnel double-lining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721669035.XU CN207583394U (en) 2017-12-05 2017-12-05 A kind of band mould negative pressure mud jacking system for tunnel double-lining

Publications (1)

Publication Number Publication Date
CN207583394U true CN207583394U (en) 2018-07-06

Family

ID=62735265

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721669035.XU Expired - Fee Related CN207583394U (en) 2017-12-05 2017-12-05 A kind of band mould negative pressure mud jacking system for tunnel double-lining

Country Status (1)

Country Link
CN (1) CN207583394U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107795324A (en) * 2017-12-05 2018-03-13 中国水利水电第五工程局有限公司 A kind of band mould negative pressure mud jacking system and mud jacking method for tunnel double-lining

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107795324A (en) * 2017-12-05 2018-03-13 中国水利水电第五工程局有限公司 A kind of band mould negative pressure mud jacking system and mud jacking method for tunnel double-lining

Similar Documents

Publication Publication Date Title
JP5529892B2 (en) Device for starting and reaching a shield machine in a sealed state
CN107795324A (en) A kind of band mould negative pressure mud jacking system and mud jacking method for tunnel double-lining
CN105603963A (en) Flat belt lateral swelling combined vacuum pre-pressing foundation processing device and method
CN202194686U (en) Well-point dewatering device at bottom of tunnel
CN207583394U (en) A kind of band mould negative pressure mud jacking system for tunnel double-lining
CN205475195U (en) Bloated joint vacuum preloading ground processing apparatus of bandlet side
CN204826429U (en) Cast member reinforcing bar grout connecting piece
CN201599041U (en) Synchronous slip casting device for shielding machine
CN203430466U (en) Drill hole sealing device for gas extraction of coal mine
CN204921021U (en) Flat hole gas drainage structure
CN210840668U (en) Novel fertilizer can for irrigation
CN106121683A (en) A kind of tunnel penstock lower concrete constructing device
CN210686009U (en) Shield tunnel two-lining concrete structure
CN111648823A (en) Collapse treatment method suitable for fault fracture zone tunnel
CN106827226A (en) Prefabricated components preparation method with connection reinforcing bar
CN202895534U (en) Elbow pipe de-molding machine
CN206230662U (en) Horizontal shaping piping lane punching block
CN206221798U (en) A kind of hydraulic engineering pipe laying actinobacillus device
CN204955087U (en) Cement pipe refining cloth machine
CN206111217U (en) Device is only starched to nylon cloth membrane bag
CN206205902U (en) A kind of tunnel-liner end template structure with guarded drainage function
CN109538823A (en) A kind of construction method of two-tube dislocation alternating jacking
CN214993136U (en) A prestressing force bellows exhaust hole device for continuous beam construction
CN201763365U (en) Hollow anchor rod pipe head for large-elevation grouting
CN205775867U (en) It is applied to the steel hoop support system of steel bottom of cylinder

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180706