CN207552822U - Shield carriage track supporting rack in tunnel - Google Patents

Shield carriage track supporting rack in tunnel Download PDF

Info

Publication number
CN207552822U
CN207552822U CN201721676637.8U CN201721676637U CN207552822U CN 207552822 U CN207552822 U CN 207552822U CN 201721676637 U CN201721676637 U CN 201721676637U CN 207552822 U CN207552822 U CN 207552822U
Authority
CN
China
Prior art keywords
welded
plate
tunnel
supporting rack
curved plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721676637.8U
Other languages
Chinese (zh)
Inventor
丁保华
闵海洋
吴雷
刘建华
翟永亮
秦晓鹏
李建建
李亚峰
王岚
谢卿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou Yijian Group Co Ltd
Original Assignee
Zhengzhou No1 Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou No1 Construction Engineering Co Ltd filed Critical Zhengzhou No1 Construction Engineering Co Ltd
Priority to CN201721676637.8U priority Critical patent/CN207552822U/en
Application granted granted Critical
Publication of CN207552822U publication Critical patent/CN207552822U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses the shield carriage track supporting racks in a kind of tunnel, and level board is welded between erect plate and the upper end edge of curved plate, and the center in region surrounded in level board, curved plate and erect plate is welded with center brace panel;Inside positioning angle bar and outside positioning angle bar are respectively welded on the center line of the upper end of level board;Seamless steel pipe workpiece is welded on the downside of curved plate, in the fixation caulking groove which is set in tunnel inner concrete tube wall.The structure of the Novel trailer supporting rack of the use of the utility model than before is compared, and has apparent advantage, and cost-effective and activity time increases construction efficiency, is reduced construction material loss, is worth promoting the use of in constructing tunnel industry.

Description

Shield carriage track supporting rack in tunnel
Technical field
The utility model belongs to the Auxiliary support component of field of engineering technology, and in particular to the shield trailer in a kind of tunnel Crane Rail supporting rack.
Background technology
Shield machine is common equipment in constructing metro tunnel, and very important effect is played in metro construction. Shield machine is generally made of host and rear mating trailer, and host length is 10 meters or so, and trailer's length is generally at 70 meters or so.It is main Machine is moved ahead in the soil body under the thrust of hydraulic jack, and trailer is to be drawn to walk in molding section of jurisdiction expert by host. Trailer walking Forward mode:Trailer support frame is laid in section of jurisdiction, track is then laid with above, it is desirable that supporting rack and track energy Enough fixations, do not walk, are indeformable, not shaking, meeting the steady safety of trailer, and welding, bolt fixation etc. may be used Form reaches the fixed effect of requirement.In construction, need to transport on the materials to host side such as section of jurisdiction, and generate promoting Dregs transportation to tunnel outside, therefore one group of track is reserved in trailer, for transporting the operation of locomotive.
In earliest China's subway work, using support of the sleeper of shaped steel cutting as transport locomotive and trailer Frame.This sleeper is cut using the H profile steel of 200mm according to the shape of design, while as transport locomotive and trailer rail The supporting rack in road needs to process the mounting hole of errant fixing bolt on shaped steel, and track manually uses bolt after putting in place With pressing plate track fixation.The supporting rack of this structure, which has, to be stablized, is heavy(Single weight about 136kg), it is of high cost, become The characteristics of should not being repaired after property.
Utility model content
The utility model proposes the shield carriage track in a kind of tunnel to solve problems of the prior art Supporting rack.
In order to solve the above-mentioned technical problem, the utility model provides the shield carriage track support in a kind of tunnel Frame is welded with erect plate, in erect plate and arc on the upside of one with the matched curved plate of tunnel inner concrete tube wall radian Level board is welded between the upper end edge of shape steel plate, the centre bit in region surrounded in level board, curved plate and erect plate It puts, is welded with center brace panel;Inside positioning angle bar and outside are respectively welded on the center line of the upper end of the level board Positioning angle bar, and the interior angle face of two angle bar;Seamless steel pipe workpiece is welded on the downside of the curved plate, the nothing In the fixation caulking groove that is set in tunnel inner concrete tube wall of seam steel pipe workpiece Matching installation, and pass through that fixed caulking groove is pre-buried to be consolidated Fixed pole part carries out seamless steel pipe workpiece to insert Guan County's dress.
Simultaneously positioned at the center of the erect plate and the hypomere of curved plate, it is welded with lower support plate.
Securing plate is welded between the arc-shaped surface of the seamless steel pipe workpiece and curved plate.
The seamless steel pipe workpiece is oval pipe fitting.
The beneficial effects of the utility model:This transporter track pillow that is designed as of the utility model is an arc knot Structure, trailer support frame are 2 triangular structure parts, are placed in arc sleeper both sides, and track fixes the knot using bolt and pressing plate Configuration formula.Such sleeper and trailer support frame have compact structure, one can pick up and put, and need to be applied in combination, in reality It is easily influenced and is shifted by locomotive walking vibrations there are sleeper during the use of border, just need to be fixed on pipe every 5 endless tube pieces In chip architecture.
Locomotive sleeper and trailer support frame can also be completed separation, it is respectively independent.Trailer support frame is solid by hanging ring installation It is scheduled on segment bolt, it is completely separable with locomotive sleeper.Trailer walking track is fixed on by bolt and pressing plate on supporting rack.It is this The trailer support frame of design has that light-weight, expense is low, and installing and dismounting is needed with the elastic segment bolt of spanner.
The structure of the Novel trailer supporting rack of the use of the utility model than before is compared, and has apparent advantage, is saved Cost and activity time, increase construction efficiency, reduce construction material loss, are worth promoting the use of in constructing tunnel industry.
Description of the drawings:
Fig. 1 is the side structure schematic diagram of the utility model.
Fig. 2 is the overlooking the structure diagram of Fig. 1.
Fig. 3 is the usage state diagram of Fig. 1.
Figure label:1 is curved plate, and 2 be erect plate, and 3 be level board, and support plate centered on 4,5 be lower support plate, 6 be inside positioning angle bar, and 7 be outside positioning angle bar, and 8 be seamless steel pipe workpiece, and 9 be tunnel inner concrete tube wall, and 10 be solid Determine caulking groove.
Specific embodiment
Embodiment 1:Shield carriage track supporting rack in tunnel as shown in Figure 1-Figure 3, in one with tunnel The upside of the matched curved plate 1 of 9 radian of concrete tube wall is welded with erect plate 2, in the upper end of erect plate 2 and curved plate 1 Level board 3 is welded between side, the center in region surrounded in level board 3, curved plate 1 and erect plate 2 is welded with Center brace panel 4.Inside positioning angle bar 6 and outside orientation angle are respectively welded on the center line of the upper end of the level board 3 Iron 7, and the interior angle face of two angle bar, track are installed between inside positioning angle bar 6 and outside positioning angle bar 7.
Seamless steel pipe workpiece 8 is welded in the downside of the curved plate 1 again, the seamless steel pipe workpiece 8 matching peace In the fixation caulking groove 10 set loaded on tunnel inner concrete tube wall 9, and pass through the pre-buried fixed beam of fixed caulking groove 10 to seamless Steel pipe workpiece 8 carries out inserting Guan County's dress.This fixed form is very simple, without additional expansible plug or in tunnel Concrete tube wall 9 sets built-in connection.And this fixed form is also conducive to dismounting and safeguards, can significantly improve construction effect Rate.
Furthermore it is possible to it is oval pipe fitting by the seamless steel pipe workpiece 8.So as to have mobile constraint after mounting Property.During carrying rail and pressure of vehicle are big, which can pass to pressure portion tunnel inner concrete tube wall 9, Part passes to the pre-buried fixed beam in the fixation caulking groove 10 and fixed caulking groove 10 of tunnel inner concrete tube wall 9.
Embodiment 2:On the basis of embodiment 1, positioned at the center of the erect plate 2 and the hypomere of curved plate 1, It is welded with lower support plate 5.So as to which seamless steel pipe workpiece 8 to be designed to the bottom lower position in curved plate 1.To carry The weld strength of high seamless steel pipe workpiece 8, can also be in the arc-shaped surface of the seamless steel pipe workpiece 8 and curved plate 1 Between be welded with securing plate.
The material that structural member uses in Fig. 1 is 8mm steel plates and 50mm angle bar and a section 95mm seamless steel pipe cutting Part.
This structure of the utility model utilizes the circular arc characteristic of segment bolt hand hole, is cut into accordingly using seamless steel pipe Shape be stuck in bolt hand hole, supporting rack gable and seamless steel pipe cutting member firm welding, supporting rack entire in this way It is secured on bolt hand hole, can only lift and can take out toward tiltedly upper angle, other directions are immovable.This structural member is using In the process, frictional resistance when pressure and the Forward of trailer weight is born, supporting rack generation cannot be made the changes such as to topple, slide It is dynamic, it can steadily play a supporting role.Trailer walking track can be placed directly among the angle bar of 2, supporting rack top, utilized The position of the position-limiting action trapped orbit of angle bar keeps suitable rail square, meets the stationarity of trailer walking.Practical effect Such as Fig. 3:
This supporting rack designs single weight as 12.2kg, and common laborer's one hand easily can be picked up and be put.
Structure is compared and is had the advantage that than before:
1st, it is light-weight, it puts conveniently;
2nd, dismounting segment bolt is not needed to, process is reduced and the time is delayed;
3rd, track fixation is fixed using angle bar screens compares with pervious structure, reduces pressing plate and bolt, saves cost With reduce the track set time;
4th, it when supporting rack recycles, can easily take out, the time of structure type saving demounting bolt than before;
5th, during entire supporting rack use, difficult deformation damage, there is no wearing detail, consumables, save input With the cost used;
6th, supporting rack and transporter track pillow are mutually not attached to, and will not be generated and be influenced each other.

Claims (4)

1. the shield carriage track supporting rack in a kind of tunnel, it is characterized in that:In one and tunnel inner concrete tube wall arc It spends on the upside of matched curved plate and is welded with erect plate, level is welded between erect plate and the upper end edge of curved plate Plate, the center in region surrounded in level board, curved plate and erect plate, is welded with center brace panel;In the water Inside positioning angle bar and outside positioning angle bar are respectively welded on the center line of the upper end of tablet, and the interior angle of two angle bar is just It is right;Seamless steel pipe workpiece is welded on the downside of the curved plate, the seamless steel pipe workpiece Matching installation is in tunnel In the fixation caulking groove of concrete tube wall setting, and pass through fixed caulking groove pre-buried fixed beam and seamless steel pipe workpiece is inserted Guan County fills.
2. the shield carriage track supporting rack in tunnel according to claim 1, it is characterized in that:Simultaneously positioned at institute The center of the hypomere of erect plate and curved plate is stated, is welded with lower support plate.
3. the shield carriage track supporting rack in tunnel according to claim 1, it is characterized in that:In the seamless steel Securing plate is welded between the arc-shaped surface and curved plate of pipe workpiece.
4. the shield carriage track supporting rack in tunnel according to claim 1, it is characterized in that:The seamless steel pipe Workpiece is oval pipe fitting.
CN201721676637.8U 2017-12-06 2017-12-06 Shield carriage track supporting rack in tunnel Expired - Fee Related CN207552822U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721676637.8U CN207552822U (en) 2017-12-06 2017-12-06 Shield carriage track supporting rack in tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721676637.8U CN207552822U (en) 2017-12-06 2017-12-06 Shield carriage track supporting rack in tunnel

Publications (1)

Publication Number Publication Date
CN207552822U true CN207552822U (en) 2018-06-29

Family

ID=62665955

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721676637.8U Expired - Fee Related CN207552822U (en) 2017-12-06 2017-12-06 Shield carriage track supporting rack in tunnel

Country Status (1)

Country Link
CN (1) CN207552822U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110195384A (en) * 2019-05-24 2019-09-03 中交一公局第三工程有限公司 A kind of combined type supporting leg for shield trolley track

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110195384A (en) * 2019-05-24 2019-09-03 中交一公局第三工程有限公司 A kind of combined type supporting leg for shield trolley track

Similar Documents

Publication Publication Date Title
CN201809959U (en) Full-door scaffold support system
CN207552822U (en) Shield carriage track supporting rack in tunnel
CN203891543U (en) Two-angle-steel iron tower
CN203374285U (en) High-resistance-increasing type combined steel supporting frame
CN110258294A (en) Steel truss arch bridge installs system and its construction method
CN206376561U (en) A kind of cladding glass transporting device
CN205916093U (en) Semitrailer bearing structure's fixing device
CN211142453U (en) Split type embroidery machine frame
CN214464175U (en) Assembled shield constructs empty counterforce device that pushes away of TBM complete machine
CN205135656U (en) Modular two lining platform trucks of multipurpose
CN206154097U (en) Foundation ring platform of polishing
CN207121766U (en) One kind receives rail crane
CN207390832U (en) A kind of gantry crane rail stent
CN206029104U (en) Large -scale steel structure welder shelves
CN215172808U (en) Movable concrete ground pump frame body device
CN219138295U (en) Multifunctional scaffold for indoor decoration
CN210970013U (en) Acrylic tunnel curved plate annealing tool
CN210066819U (en) Utility tunnel steel form bearing structure
CN217379228U (en) Cold-formed thin-wall light steel keel building structure body for liquefied petroleum gas storage room
CN203614916U (en) Movable pump pipe fixing support
CN211058819U (en) Frame of tunnel pipe gallery fortune frame machine
CN214366110U (en) Quick assembling socket steel frame structure
CN215999302U (en) Be used for colliery inclined shaft TBM construction inverted arch piece steel reinforcement cage processing platform device
CN210766208U (en) Shield constructs construction and uses arc dregs car sleeper
CN215106028U (en) Lapping device for steel purlin

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 450000 Shangxian Street, Longzihu Wisdom Island, Zhengdong New District, Zhengzhou City, Henan Province

Patentee after: Zhengzhou Yijian Group Co.,Ltd.

Address before: 450000, No. 91, Bauhinia Road, Zhengzhou City, Henan Province

Patentee before: ZHENGZHOU NO.1 CONSTRUCTION ENGINEERING GROUP Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180629

Termination date: 20211206