CN207537247U CN201721302074.6U CN201721302074U CN207537247U CN 207537247 U CN207537247 U CN 207537247U CN 201721302074 U CN201721302074 U CN 201721302074U CN 207537247 U CN207537247 U CN 207537247U
Authority
CN
China
Prior art keywords
plane
system automatically
water supply
water
reutilization system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721302074.6U
Other languages
Chinese (zh)
Inventor
杨文清
付二军
李自雄
白阳
苏宇
郭志伟
赵淑慧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southern Beam Mining Industry Co Ltd
Original Assignee
Southern Beam Mining Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southern Beam Mining Industry Co Ltd filed Critical Southern Beam Mining Industry Co Ltd
Priority to CN201721302074.6U priority Critical patent/CN207537247U/en
Application granted granted Critical
Publication of CN207537247U publication Critical patent/CN207537247U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

The utility model discloses a kind of mine waters to precipitate reutilization system automatically, including being arranged on the sump of lower exploitation plane and being arranged on the cesspool of upper exploitation plane, the port of export of sump is connected to the arrival end of cesspool by discharge pipe line, sedimentation basin and clear water reserviors are additionally provided in upper exploitation plane, and cesspool is connected with sedimentation basin by filtering wall, sedimentation basin is connected with clear water reserviors by filtering wall, and the port of export of clear water reserviors is connected to the getting working face in lower exploitation plane by water supply pipe.The utility model is precipitated using underground sedimentation basin, is fed directly to the Water Districts domain such as next horizontal production, dust-proof by precipitation filtering, is realized mine water and rationally utilize.

Description

A kind of mine water precipitates reutilization system automatically
Technical field
The utility model is related to mine waters to recycle field, and in particular to a kind of mine water precipitates reutilization system automatically.
Background technology
Existing mine water is delivered to underground again from underground discharge ground after Sewage Disposal is handled, need it is artificial more, Time is long, heavy workload, and material consumption is serious.
Utility model content
The purpose of this utility model is to provide a kind of mine waters to precipitate reutilization system automatically, to solve the prior art Problem, the utility model are precipitated using underground sedimentation basin, and next horizontal production, dust-proof is fed directly to by precipitation filtering Water Districts domain is waited, mine water is realized and rationally utilizes.
In order to achieve the above objectives, the utility model adopts the following technical solution:
A kind of mine water precipitates reutilization system automatically, is opened including being arranged on the sump of lower exploitation plane and being arranged on The cesspool of plane is adopted, the port of export of sump is connected to the arrival end of cesspool by discharge pipe line, is also set in upper exploitation plane Sedimentation basin and clear water reserviors are equipped with, and cesspool is connected with sedimentation basin by filtering wall, sedimentation basin connects with clear water reserviors by filtering wall Logical, the port of export of clear water reserviors is connected to the getting working face in lower exploitation plane by water supply pipe.
Further, the vertical range between upper exploitation plane and lower exploitation plane is 40 meters.
Further, a diameter of 219mm of the discharge pipe line.
Further, a diameter of 219mm of the water supply pipe.
Further, the port of export of water supply pipe is connected to several getting working faces, and every by several water supply branch pipes Pressure gauge is both provided on water supply branch pipe.
Further, the port of export of water supply pipe is respectively connected to the first getting working face and by two water supply branch pipes Two getting working faces.
Compared with prior art, the utility model has technique effect beneficial below:
Water in sump in lower exploitation plane is delivered to by discharge pipe line positioned at upper exploitation by the utility model The cesspool of plane, water in cesspool flow to sedimentation basin by filtering wall and are precipitated, and the water in sedimentation basin is by filtering wall It flow to clear water reserviors, the water in clear water reserviors is delivered to getting working face by water supply pipe, for getting working face spray dust prevention, watering And industrial water, it firstly reduces mine water and is delivered to ground by Sewage Disposal processing routine, secondly sunk using underground Shallow lake pond is precipitated, and is fed directly to the Water Districts domain such as next horizontal production, dust-proof by precipitation filtering, is realized mine hydration Reason utilizes.
Further, the vertical range between upper exploitation plane and lower exploitation plane is 40 meters, can make to exploit under arrival The hydraulic pressure of plane reaches 0.4Mpa, meets getting working face water requirement.
Description of the drawings
Fig. 1 is the structure diagram of the utility model.
Wherein:1st, sump;2nd, lower exploitation plane;3rd, upper exploitation plane;4th, discharge pipe line;5th, water supply pipe;6th, cesspool; 7th, sedimentation basin;8th, wall is filtered;9th, clear water reserviors;10th, the first getting working face;11st, the second getting working face, exploitation is flat in D expressions Vertical range between face and lower exploitation plane, and D=40m.
Specific embodiment
The utility model is described in further detail below in conjunction with the accompanying drawings:
Referring to Fig. 1, a kind of mine water precipitates reutilization system automatically, and plane 3 and lower exploitation plane 2 are exploited including upper, on The vertical range D between plane 3 and lower exploitation plane 2 is exploited as 40 meters, further include be arranged on the sump 1 of lower exploitation plane 2 with And the cesspool 6 of exploitation plane 3 is arranged on, the port of export of sump 1 is connected to the arrival end of cesspool 6 by discharge pipe line 4, Sedimentation basin 7 and clear water reserviors 9 are additionally provided with, and cesspool 6 is connected with sedimentation basin 7 by filtering wall 8 in upper exploitation plane 3, precipitated Pond 7 is connected with clear water reserviors 9 by filtering wall 8, and the port of export of clear water reserviors 9 is connected with water supply pipe 5, the port of export of water supply pipe 5 The first getting working face 10 and the second getting working face 11 are respectively connected to, and on every water supply branch pipe by two water supply branch pipes It is both provided with pressure gauge, the diameter of discharge pipe line 4 and water supply pipe 5 is 219mm.
The operating process of the utility model is described in detail below:
Seam mining, 40 meters of vertical range between upper exploitation plane 3 and lower exploitation plane 2, lower exploitation plane 2 are divided in underground On sump 1 for main water drain storehouse, the cesspool 6 of upper exploitation plane 3 is designed in 1 vertical direction of sump, utilizes vertical perforating Technology, from the cesspool 6 of straight-through 1 time φ, 219 discharge pipe lines, the 4 supreme exploitation plane 3 of the sump 1 of lower exploitation plane 2, cesspool 6 In water flow to sedimentation basin 7 by filtering wall 8 and precipitated, the water in sedimentation basin 7 flow to clear water reserviors 9 by filtering wall 8, then by 9 perforating of clear water reserviors to lower exploitation plane 2 leads directly to 219 water supply pipe 5 of φ, using height difference principle, is generated by water level height difference Pressure, hydraulic pressure reaches 0.4Mpa when reaching lower exploitation plane 2, meets production needs, for lower exploitation 2 each getting working face of plane Spray dust prevention, watering, working surface production water.

Claims (6)

1. a kind of mine water precipitates reutilization system automatically, which is characterized in that the sump including being arranged on lower exploitation plane (2) (1) and the cesspool (6) for exploiting plane (3) is arranged on, the port of export of sump (1) is connected to dirt by discharge pipe line (4) The arrival end in pond (6), upper exploit are additionally provided with sedimentation basin (7) and clear water reserviors (9) in plane (3), and cesspool (6) and precipitation Pond (7) is connected by filtering wall (8), and sedimentation basin (7) is connected with clear water reserviors (9) by filtering wall (8), the outlet of clear water reserviors (9) End is connected to the getting working face on lower exploitation plane (2) by water supply pipe (5).
2. a kind of mine water according to claim 1 precipitates reutilization system automatically, which is characterized in that above exploits plane (3) vertical range between lower exploitation plane (2) is 40 meters.
3. a kind of mine water according to claim 1 precipitates reutilization system automatically, which is characterized in that the discharge pipe line (4) a diameter of 219mm.
4. a kind of mine water according to claim 1 precipitates reutilization system automatically, which is characterized in that the water supply pipe (5) a diameter of 219mm.
5. a kind of mine water according to claim 1 precipitates reutilization system automatically, which is characterized in that water supply pipe (5) The port of export be connected to several getting working faces by several water supply branch pipes, and pressure gauge is both provided on every water supply branch pipe.
6. a kind of mine water according to claim 5 precipitates reutilization system automatically, which is characterized in that water supply pipe (5) The port of export be respectively connected to the first getting working face (10) and the second getting working face (11) by two water supply branch pipes.
CN201721302074.6U 2017-10-10 2017-10-10 A kind of mine water precipitates reutilization system automatically Expired - Fee Related CN207537247U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721302074.6U CN207537247U (en) 2017-10-10 2017-10-10 A kind of mine water precipitates reutilization system automatically

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721302074.6U CN207537247U (en) 2017-10-10 2017-10-10 A kind of mine water precipitates reutilization system automatically

Publications (1)

Publication Number Publication Date
CN207537247U true CN207537247U (en) 2018-06-26

Family

ID=62610175

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721302074.6U Expired - Fee Related CN207537247U (en) 2017-10-10 2017-10-10 A kind of mine water precipitates reutilization system automatically

Country Status (1)

Country Link
CN (1) CN207537247U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107540110A (en) * 2017-10-10 2018-01-05 陕西南梁矿业有限公司 A kind of mine water precipitates reutilization system and method automatically

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107540110A (en) * 2017-10-10 2018-01-05 陕西南梁矿业有限公司 A kind of mine water precipitates reutilization system and method automatically

Similar Documents

Publication Publication Date Title
CN104174191A (en) Integrated grit chamber for treating rainwater and treatment method
CN207537247U (en) A kind of mine water precipitates reutilization system automatically
CN203890159U (en) Remote intelligently controlled mining wastewater purification device
CN203989972U (en) Integrated grit chamber for treating rainwater
CN103203124B (en) A kind of tailings dewatering technique and device
CN204079562U (en) Black water refining plant
CN107540110A (en) A kind of mine water precipitates reutilization system and method automatically
CN207347290U (en) Mine down-hole continuous drainage sludge drainage system
CN209612287U (en) A kind of cutting mud reclaiming system
CN104831673B (en) A kind of Preservation for Aggregate Production System waste water processes Tailings Dam and operation method
CN204224348U (en) Tandem type double-layer horizontal sedimentation tank
CN203429012U (en) Efficient energy-saving pollution-free dry processing system of bauxite washing tailing pulp
CN207627998U (en) The drainage sedimentation device of deep basal pit
CN203794718U (en) Fracturing flowback liquid treating device
CN202924843U (en) Waste sludge and waste water automatic separation, recovery and reutilization device
CN203253210U (en) Power plant wastewater recycling and reusing device
CN205461164U (en) Tailing natural sedimentation backwater device
CN205760140U (en) A kind of recycle device of papermaking slurry
CN203715418U (en) Quick mine water treatment device
CN204767632U (en) Dense case of pipe chute
CN104941263A (en) Inclined tube concentration box
CN203384027U (en) Anti-blocking ore pulp pump pond
CN203971477U (en) The detention tank that contains modified pipeline
CN207512825U (en) The interim water supply pump system of project is built in a kind of room
CN214170613U (en) Underground water supply and drainage system for mining

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180626

Termination date: 20211010