CN207533049U - Boiler flue gas desulfurization cleaning equipment - Google Patents

Boiler flue gas desulfurization cleaning equipment Download PDF

Info

Publication number
CN207533049U
CN207533049U CN201721441268.4U CN201721441268U CN207533049U CN 207533049 U CN207533049 U CN 207533049U CN 201721441268 U CN201721441268 U CN 201721441268U CN 207533049 U CN207533049 U CN 207533049U
Authority
CN
China
Prior art keywords
tubing
length
flue gas
desulfurizing tower
slurries
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721441268.4U
Other languages
Chinese (zh)
Inventor
王骞
刘军伟
李宝琦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG TAIBEI ENVIRONMENTAL PROTECTION EQUIPMENT CO Ltd
Original Assignee
SHANDONG TAIBEI ENVIRONMENTAL PROTECTION EQUIPMENT CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG TAIBEI ENVIRONMENTAL PROTECTION EQUIPMENT CO Ltd filed Critical SHANDONG TAIBEI ENVIRONMENTAL PROTECTION EQUIPMENT CO Ltd
Priority to CN201721441268.4U priority Critical patent/CN207533049U/en
Application granted granted Critical
Publication of CN207533049U publication Critical patent/CN207533049U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Treating Waste Gases (AREA)

Abstract

The utility model discloses a kind of boiler flue gas desulfurization cleaning equipments, belong to boiler smoke process field.The boiler flue gas desulfurization cleaning equipment includes desulfurizing tower, desulfurization pump and solution circulatory pool, the middle and lower part of desulfurization tower side wall is provided with gas inlet, top is provided with exhanst gas outlet, tower internal upper part is provided with spray equipment, spray equipment is connect by desulfurization pump with solution circulatory pool, admission line is provided at gas inlet, bottom is provided with slurries discharger in desulfurizing tower, slurries discharger includes the first length of tubing and the second length of tubing, Open Side Down and submerges below slurries liquid level for first length of tubing, bottom is provided with slurry pool in desulfurizing tower, the side wall of slurry pool is desulfurization tower wall, the bottom of slurry pool tilts down setting, the end at the bottom of slurry pool tilts to the lower section of the first length of tubing, height sensor is provided in the internal side wall of slurry pool.The utility model can not only realize function of holding one's breath, but also can discharge slurries in tower in time, prevent hydrops.

Description

Boiler flue gas desulfurization cleaning equipment
Technical field
The utility model is related to boiler smoke process fields, particularly relate to a kind of boiler flue gas desulfurization cleaning equipment.
Background technology
Recently as industrial expansion, the influence to environment is increasingly shown especially, haze weather, global warming, air Pollution control is the problem of mankind's facing.And the generations such as coal-burning boiler, Industrial Stoves and waste incinerator contain dioxy Change the flue gas of sulphur, carbon dioxide, be its arch-criminal.Therefore, the purification of boiler smoke is extremely important.
Boiler flue gas desulfurization denitration cleaning equipment can carry out desulphurization denitration purification, desulphurization denitration cleaning equipment one to flue gas As include boiler flue gas desulfurization cleaning equipment, spray equipment, desulfurization pump, discharge line and solution circulatory pool.It is net in desulphurization denitration During change, magnesia or calcium oxide solution in solution circulatory pool are transported to by desulfurization pump, spray piping in spray equipment, It reacts with sulfur dioxide, the nitrogen oxides in flue gas in boiler flue gas desulfurization cleaning equipment, then, solution is with desulfurizing tower The bottom of boiler flue gas desulfurization cleaning equipment is reached, is flowed into solution circulatory pool by discharge line, it is raw in solution circulatory pool It is precipitated into magnesium sulfate, magnesium nitrate or calcium sulfate and calcium nitrate crystallization.In the process, since gas inlet is located at spray equipment Lower section, (can react into the flue gas in boiler flue gas desulfurization cleaning equipment with slurries with flue gas in spray equipment Solution afterwards) it is discharged by discharge line.
Slurries discharger is generally in a manner that base cone adds pipeline at present, and solution is after spray equipment is fallen in which Due to the factors such as flue gas resistance influence can there are slurry flow rate it is bad determining the problem of, and then lead to the straight of cone mouth and pipeline Diameter can not determine that caliber, which has selected big, can cause slurries to fill out discontented pipeline, and flue gas leaks, caliber selected small to cause slurries cannot and When discharge, it is cumulative.
Utility model content
The utility model provides a kind of boiler flue gas desulfurization cleaning equipment, can not only realize function of holding one's breath, but also can will be in tower Slurries are discharged in time, prevent hydrops.
In order to solve the above technical problems, the utility model offer technical solution is as follows:
A kind of boiler flue gas desulfurization cleaning equipment, including desulfurizing tower, desulfurization pump and solution circulatory pool, the desulfurization tower side wall Middle and lower part be provided with gas inlet, exhanst gas outlet is provided at the top of the desulfurizing tower, the desulfurizing tower internal upper part is provided with Spray equipment, the spray equipment are pumped by the desulfurization and are connect with the solution circulatory pool, and the spray equipment is included from upper And several spraying layers of lower setting, admission line is provided at the gas inlet, and bottom is provided with slurry in the desulfurizing tower Liquid discharger, wherein:
The admission line is set to the desulfurization tower side wall and stretches into the desulfurizing tower to incline to desulfurizing tower lower section Tiltedly, the admission line and the angle of horizontal direction are 0 °~20 °;
The slurries discharger includes the first vertically arranged length of tubing and the transverse direction being connect with first length of tubing Setting the second length of tubing, first length of tubing Open Side Down and submerge slurries liquid level hereinafter, first length of tubing with The junction of second length of tubing is provided with elbow structure;
Bottom is provided with slurry pool in the desulfurizing tower, and the side wall of the slurry pool is desulfurization tower wall, the slurry pool Bottom tilts down setting, and the end at the bottom of the slurry pool tilts to the lower section of first length of tubing, the bottom of the slurry pool The difference in height of end and the first segment pipe end be 1cm~5cm;
Height sensor is provided in the internal side wall of the slurry pool, the height sensor is connected with warning device, The control system of the height sensor and warning device with boiler flue gas desulfurization cleaning equipment is connected.
Further, the exit of second length of tubing is provided with to assist first length of tubing and double section tube The water pump that slurries are discharged in road, the suction inlet of the water pump stretch to the middle part of second length of tubing.
Further, it is described detachably to connect to be detachably connected between first length of tubing and second length of tubing It is connected in flanged joint.
Further, the blowning installation for slurries sediment to be assisted to discharge is provided on the bottom of the slurry pool, it is described Air pump is provided with below the bottom of slurry pool, the air pump connects the blowning installation by pipeline, and the blowning installation is circle Annular blowning installation, the surrounding of the circular ring shape blowning installation are provided with several towards different going out gas branch pipe.
Further, the admission line stretches to the middle part of the desulfurizing tower inner cavity, and the admission line stretches to institute The upper end for stating desulfurizing tower inside points is provided with several open slots.
Further, if being provided with dry flue gas water conservancy diversion gear close to the side of the desulfurizing tower central axes at the open slot Plate, the flue gas flow apron are vertical with the side wall of the admission line.
The utility model has the advantages that:
The boiler flue gas desulfurization cleaning equipment of the utility model, admission line are arranged on the middle and lower part of desulfurizing tower, and stretch into To desulfurizing tower inclined downward in desulfurizing tower, the angle of admission line and horizontal direction is 0 °~20 °, and slurries can be avoided (to spray Slurries after reacting in shower device with flue gas) it is flowed out during slurry pool is flowed by admission line;Slurries are discharged Open Side Down and submerges slurries liquid level hereinafter, when the liquid level in slurry pool is higher than double section tube for first length of tubing of device Slurries could discharge during the upper end in road, avoid flue gas and leak, and have effect of holding one's breath;In desulfurizing tower the bottom of the slurry pool of bottom to Under be obliquely installed, the end at the bottom of slurry pool tilts to the lower section of the first length of tubing, end and the first segment pipe at the bottom of slurry pool The difference in height of road end is 1cm~5cm, which can make the utility model in an inverted cone without being done as the prior art Current-collecting device can facilitate the discharge of slurries, and if slurries have precipitation, be also convenient for together discharging the precipitation in slurries; Height sensor is provided in the internal side wall of slurry pool, height sensor is connected with warning device, height sensor and alarm Control system of the device with boiler flue gas desulfurization cleaning equipment is connected, and the flow velocity of slurries can be surveyed according to by height sensor The height of slurries determine, so that it is determined that the caliber of the first length of tubing and the second length of tubing of slurries discharger used Size in order to ensure the discharge of slurries in slurry pool, can amplify caliber, and caliber is much all not to interfere with effect of holding one's breath Fruit.
Description of the drawings
Fig. 1 is the structure diagram of the boiler flue gas desulfurization cleaning equipment of the utility model;
Fig. 2 is provided with schematic diagram during open slot for admission line in boiler flue gas desulfurization cleaning equipment shown in FIG. 1;
Structure diagrams of the Fig. 3 for the blowning installation of the boiler flue gas desulfurization cleaning equipment of the utility model, wherein Fig. 3 (a) it is front view, Fig. 3 (b) is sectional view.
Specific embodiment
In order to make the technical problems, technical solutions and advantages to be solved by the utility model clearer, below in conjunction with attached drawing And specific embodiment is described in detail.
The utility model provides a kind of boiler flue gas desulfurization cleaning equipment, as shown in FIG. 1 to 3, including desulfurizing tower 1, takes off Sulphur pumps (not shown) and solution circulatory pool 2, the middle and lower part of 1 side wall of desulfurizing tower are provided with gas inlet 3, and the top of desulfurizing tower 1 is set Exhanst gas outlet 4 is equipped with, 1 internal upper part of desulfurizing tower is provided with spray equipment 5, and spray equipment 5 passes through desulfurization pump 1 and solution circulatory pool 2 Connection, spray equipment 5 include several spraying layers set from top to bottom, admission line 6, desulfurization are provided at gas inlet 3 Bottom is provided with slurries discharger 7 in tower 1, wherein:
Admission line 6 is set to 1 side wall of desulfurizing tower and stretches into desulfurizing tower 1 to 1 inclined downward of desulfurizing tower, admission line 6 Angle α with horizontal direction is 0 °~20 ° (preferably 5 °~15 °);
Slurries discharger 7 includes the first vertically arranged length of tubing 7-1 and is set with the first length of tubing 7-1 transverse directions connecting Open Side Down and submerges slurries liquid level hereinafter, the first length of tubing 7-1 and by the second the length of tubing 7-2, the first length of tubing 7-1 put The junction of double section tube road 7-2 is provided with elbow structure 7-3;
Bottom is provided with slurry pool 8 in desulfurizing tower 1, and the side wall of slurry pool 8 is desulfurization tower wall, and the bottom 9 of slurry pool dips down Tiltedly setting, the end at the bottom 9 of slurry pool tilt to the lower section of the first length of tubing 7-1, end and the first segment pipe at the bottom 9 of slurry pool The difference in height of road 7-1 ends is 1cm~5cm;
Height sensor 10 is provided in the internal side wall of slurry pool 8, height sensor 10 is connected with warning device, height The control system of sensor 10 and warning device with boiler flue gas desulfurization cleaning equipment is connected.
The boiler flue gas desulfurization cleaning equipment of the utility model, admission line are arranged on the middle and lower part of desulfurizing tower, and stretch into To desulfurizing tower inclined downward in desulfurizing tower, the angle of admission line and horizontal direction is 0 °~20 °, and slurries can be avoided (to spray Slurries after reacting in shower device with flue gas) it is flowed out during slurry pool is flowed by admission line;Slurries are discharged Open Side Down and submerges slurries liquid level hereinafter, when the liquid level in slurry pool is higher than double section tube for first length of tubing of device Slurries could discharge during the upper end in road, avoid flue gas and leak, and have effect of holding one's breath;In desulfurizing tower the bottom of the slurry pool of bottom to Under be obliquely installed, the end at the bottom of slurry pool tilts to the lower section of the first length of tubing, end and the first segment pipe at the bottom of slurry pool The difference in height of road end is 1cm~5cm, which can make the utility model in an inverted cone without being done as the prior art Current-collecting device can facilitate the discharge of slurries, and if slurries have precipitation, be also convenient for together discharging the precipitation in slurries; Height sensor is provided in the internal side wall of slurry pool, height sensor is connected with warning device, height sensor and alarm Control system of the device with boiler flue gas desulfurization cleaning equipment is connected, and the flow velocity of slurries can be surveyed according to by height sensor The height of slurries determine, so that it is determined that the caliber of the first length of tubing and the second length of tubing of slurries discharger used Size in order to ensure the discharge of slurries in slurry pool, can amplify caliber, and caliber is much all not to interfere with effect of holding one's breath Fruit.
Further, the exit of the second length of tubing 7-2 is provided with to assist the first length of tubing 7-1 and the second length of tubing The water pump that slurries are discharged in 7-2, the suction inlet of water pump stretch to the middle part of the second length of tubing 7-2.When height sensor detects slurry Liquid level in liquid pool is excessively high, i.e., when slurries cannot discharge in time, water pump can assist slurries to discharge;Or when each length of tubing occurs During blocking, water pump can assist dredging each length of tubing, clear up impurity therein.
Preferably, between the first length of tubing 7-1 and the second length of tubing 7-2 flange is detachably connected as to be detachably connected Connection.Flanged joint is that gasket is put into the centre of a pair of flange being fixed on two nozzles, makes it close with bolt tension A kind of dismountable connector combined, flanged joint have preferable intensity and compactness, and applicable size range is wide, tears open It unloads conveniently;, can be by demounting bolt after the damage of each length of tubing, the slurry discharge line that more renews.
In the utility model, the blowning installation for slurries sediment to be assisted to discharge, slurries are provided on the bottom 9 of slurry pool The lower section at the bottom 9 in pond is provided with air pump, and air pump connects the blowning installation by pipeline, and blowning installation is preferably provided at first segment pipe Around road 7-1, as shown in Fig. 3 (a) and Fig. 3 (b), blowning installation can be circular ring shape blowning installation 12, and circular ring shape, which is blown, to be filled Put 12 surrounding be provided with it is several towards different going out gas branch pipe 13.It can be blown towards different going out gas branch pipe to all directions Gas discharges the precipitation mixed serum in slurries together, prevents from being deposited in slurry pool getting deeper so that blocking pipeline Mouthful.
In order to uniformly disperse the flue gas entered in desulfurizing tower, admission line 6 stretches to the middle part of 1 inner cavity of desulfurizing tower, such as Shown in Fig. 2, the upper center that admission line 6 stretches to 1 inside points of desulfurizing tower is provided with several open slot 6-1.Admission line is not Using the structure type of inner cylinder, materials can be saved, it is cost-effective;Meanwhile admission line stretches to the upper of desulfurizing tower inside points End middle part setting open slot, the flue gas in admission line can be flowed out by open slot so that the flue gas in desulfurizing tower is more equal Rise evenly, improve desulfuration efficiency.
Further, if being led as shown in Fig. 2, being provided with dry flue gas close to the side of 1 central axes of desulfurizing tower at open slot 6-1 Flow baffle 11, and the length of flue gas flow apron 11 is sequentially increased along the airintake direction of admission line 6, flue gas flow apron 11 with The side wall of admission line 6 is vertical, and the end of flue gas flow apron 11 is the arc of bending, and bends towards the air inlet of admission line 6 Side.The design can be such that flue gas further more uniformly rises, and can ensure flue gas and the doctor solution in spray equipment Fully reaction improves desulfurization effect.
The above is the preferred embodiment of the utility model, it is noted that for the ordinary skill of the art For personnel, under the premise of principle described in the utility model is not departed from, several improvements and modifications can also be made, these improvement The scope of protection of the utility model is also should be regarded as with retouching.

Claims (6)

1. a kind of boiler flue gas desulfurization cleaning equipment, including desulfurizing tower, desulfurization pump and solution circulatory pool, the desulfurization tower side wall Middle and lower part is provided with gas inlet, and exhanst gas outlet is provided at the top of the desulfurizing tower, and the desulfurizing tower internal upper part is provided with spray Shower device, the spray equipment are pumped by the desulfurization and connect with the solution circulatory pool, the spray equipment including from upper and Several spraying layers of lower setting, which is characterized in that be provided with admission line at the gas inlet, bottom in the desulfurizing tower Slurries discharger is provided with, wherein:
The admission line is set to the desulfurization tower side wall and stretches into the desulfurizing tower to the desulfurizing tower inclined downward, institute The angle for stating admission line and horizontal direction is 0 °~20 °;
The lateral setting that the slurries discharger includes the first vertically arranged length of tubing and connect with first length of tubing The second length of tubing, first length of tubing Open Side Down and submerge slurries liquid level hereinafter, first length of tubing with it is described The junction of second length of tubing is provided with elbow structure;
Bottom is provided with slurry pool in the desulfurizing tower, and the side wall of the slurry pool is desulfurization tower wall, the bottom of the slurry pool to Under be obliquely installed, the end at the bottom of the slurry pool tilts to the lower section of first length of tubing, the end at the bottom of the slurry pool The difference in height of end and the first segment pipe end is 1cm~5cm;
Height sensor is provided in the internal side wall of the slurry pool, the height sensor is connected with warning device, described The control system of height sensor and warning device with boiler flue gas desulfurization cleaning equipment is connected.
2. boiler flue gas desulfurization cleaning equipment according to claim 1, which is characterized in that the outlet of second length of tubing Place is provided with for assisting the water pump that slurries are discharged in first length of tubing and the second length of tubing, and the suction inlet of the water pump stretches into To the middle part of second length of tubing.
3. boiler flue gas desulfurization cleaning equipment according to claim 2, which is characterized in that first length of tubing with it is described It is described to be detachably connected as flanged joint to be detachably connected between second length of tubing.
4. according to any boiler flue gas desulfurization cleaning equipments of claim 1-3, which is characterized in that the bottom of the slurry pool On be provided with blowning installation for slurries sediment to be assisted to discharge, be provided with air pump below the bottom of the slurry pool, it is described Air pump connects the blowning installation by pipeline, and the blowning installation is circular ring shape blowning installation, the circular ring shape blowning installation Surrounding be provided with it is several towards different going out gas branch pipe.
5. boiler flue gas desulfurization cleaning equipment according to claim 4, which is characterized in that the admission line stretches to institute The middle part of desulfurizing tower inner cavity is stated, the upper end that the admission line stretches to the desulfurizing tower inside points is provided with several open slots.
6. boiler flue gas desulfurization cleaning equipment according to claim 5, which is characterized in that close to described at the open slot If the side of desulfurizing tower central axes is provided with dry flue gas flow apron, the side wall of the flue gas flow apron and the admission line Vertically.
CN201721441268.4U 2017-11-01 2017-11-01 Boiler flue gas desulfurization cleaning equipment Active CN207533049U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721441268.4U CN207533049U (en) 2017-11-01 2017-11-01 Boiler flue gas desulfurization cleaning equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721441268.4U CN207533049U (en) 2017-11-01 2017-11-01 Boiler flue gas desulfurization cleaning equipment

Publications (1)

Publication Number Publication Date
CN207533049U true CN207533049U (en) 2018-06-26

Family

ID=62611999

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721441268.4U Active CN207533049U (en) 2017-11-01 2017-11-01 Boiler flue gas desulfurization cleaning equipment

Country Status (1)

Country Link
CN (1) CN207533049U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114307501A (en) * 2022-01-04 2022-04-12 中煤科工集团重庆研究院有限公司 Antiseized patching machine dust collector

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114307501A (en) * 2022-01-04 2022-04-12 中煤科工集团重庆研究院有限公司 Antiseized patching machine dust collector

Similar Documents

Publication Publication Date Title
CN204816188U (en) Stainless steel water bath dust removal desulfurizing tower
CN207533049U (en) Boiler flue gas desulfurization cleaning equipment
JP2004521733A5 (en)
CN208583178U (en) A kind of anti-deposition disturbance device of wet desulfuration tower tower bottom
CN207076323U (en) A kind of Full connected wet desulphurization tower
CN204911100U (en) Water bath dedusting desulphurizer
CN219540005U (en) Calcium desulfurization tower cauldron thick liquid agitating unit
CN212369950U (en) Hydraulic stirring system for ammonia flue gas desulfurization
CN206262348U (en) A kind of wet desulphurization tower
CN206950968U (en) Boiler flue gas desulfurization cleaning equipment
CN208115491U (en) A kind of venturi effect tower
CN205925422U (en) Prevent to spray desulfurizing tower of layer and nozzle jam
CN208809779U (en) A kind of pitch waste gas purification apparatus with warning device
CN209271105U (en) A kind of power plant desulfurization dewatering system vacuum pump vacuum in condenser device
CN207413108U (en) A kind of wet desulphurization absorption tower
CN208802891U (en) A kind of energy dissipating gas operated device for fluid delivery system in sewage treatment
CN105126516A (en) Cylindrical vertical-type wet-type explosion-proof compression-resistant desulphurizing and dedusting device
CN208018403U (en) Energy saving gravity flow flue gas processing device
CN208534866U (en) Pneumatic water pump and big flow precipitation system
CN2289596Y (en) High-efficiency dust-rmeoval desulfurization device for boiler smoke
CN207324180U (en) Novel air stripping mud discharging device
CN207076332U (en) A kind of desulfurization column in series stock tank intercommunicating device
CN207507249U (en) A kind of odor purification tower and odor purification tower group
CN206566555U (en) A kind of new vertical sedimentation basin
CN100450588C (en) Square absorption tower for wet method desulfurization of flue gas

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: Boiler flue gas desulfurization and purification equipment

Effective date of registration: 20220708

Granted publication date: 20180626

Pledgee: Bank of Weifang Limited by Share Ltd. Weifang hope branch

Pledgor: SHANDONG TAIBEI ENVIRONMENTAL PROTECTION EQUIPMENT Co.,Ltd.

Registration number: Y2022370010110

PE01 Entry into force of the registration of the contract for pledge of patent right