CN207525883U - Connecting structure of beam column of prefabricated concrete structure - Google Patents

Connecting structure of beam column of prefabricated concrete structure Download PDF

Info

Publication number
CN207525883U
CN207525883U CN201721449034.4U CN201721449034U CN207525883U CN 207525883 U CN207525883 U CN 207525883U CN 201721449034 U CN201721449034 U CN 201721449034U CN 207525883 U CN207525883 U CN 207525883U
Authority
CN
China
Prior art keywords
precast beam
prefabricated
shear key
prefabricated post
connection structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721449034.4U
Other languages
Chinese (zh)
Inventor
丁克伟
陈雷雨
崔建华
马巍
陈东
刘旋
刘运林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Jianzhu University
Original Assignee
Anhui Jianzhu University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Jianzhu University filed Critical Anhui Jianzhu University
Priority to CN201721449034.4U priority Critical patent/CN207525883U/en
Application granted granted Critical
Publication of CN207525883U publication Critical patent/CN207525883U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses a connecting structure of a beam column with an assembled concrete structure, which comprises a prefabricated column and a prefabricated beam; the novel horizontal bed is characterized by also comprising a sawtooth type shear key, wherein the sawtooth type shear key is in a horizontal king-shaped shape; the connecting end of the precast beam is a variable cross-section end, the variable cross-section end is connected with the bracket of the precast column through a pre-buried sawtooth type shear key, the upper half part of the shear key is embedded into the precast beam, and the lower half part of the shear key is embedded into the bracket of the precast column. The utility model discloses structural design is simple, the assembly of being convenient for, and firm in connection easily promotes.

Description

A kind of connection structure of prefabricated concrete structure beam column
Technical field
The utility model is related to a kind of connection structures of prefabricated concrete structure beam column.
Background technology
Building industrialization is one of important development trend of Contemporary Architecture technology.Prefabricated concrete structure and cast-in-place coagulation Soil structure is compared, and has many advantages, such as that factorial praluction, situ wet operation is few, speed of application is fast, energy saving.The dress of good design Safety and the anti-seismic performance of fabricated construction can be greatly improved with formula structure, is the development that China's future architecture industrialization is built Direction.
The present assembled levels in China are restricted by design of node, and due to domestic first stage of construction, labour is opposite Inexpensively, construction technology is largely by artificial, and the developed countries such as external particularly American-European and Japan, assembled technology more into Ripe, construction technology relies primarily on machinery.The building level in China mostly rests on cast-in-place, it is impossible to fully achieve equally cast-in-place.And Building site is cast-in-place by resource restrictions such as time, manpowers, and speed of application is slow.It if can be completely using splicing and overlapping technology, institute There is accessory by prefabrication, transport to building-site, by splicing and overlap, connected completely using dry type, wet type is avoided to connect, Outdoor work is replaced with office operation, construction efficiency can be greatly improved.The design of novel fabricated building node is building work The key problem and apt word added to clinch the point of industry.There are a series of researchs, scholar Lv Xilin etc. to show to add in steel to this domestic and foreign scholars Even can more effectively improve the performance of node than adding in vinal concrete after fiber concrete, improve reinforcing bar with The adhesion strength of concrete improves ductility.2013, scholar Sun Yanbo devised a kind of connector to connect precast concrete beam Column border node makes it improve anti-seismic performance, i.e., shifts to an earlier date the ductility connecting rod of pre-buried alloy in pre- buried column, and alloy link passes through itself Plastic deformation carry out earthquake energy, so as to avoid the destruction of other components.Wang Qingjie etc. proposes a kind of novel steel tube coagulation The anti-seismic performance of earth pillar and section steel beam assembling type node, and low all reciprocation cycle loading examinations have been carried out to the node of different parameters It tests.
But apparently, main problem and limitation are for just current research, especially domestic research:First, largely set Meter cannot completely disengage cast-in-place, using dry-and-wet combined formula, still remain the situation of site welding, it is impossible to accomplish efficient quick;The Two, design of node is too complicated, and accessory is cumbersome, changes and is not easy.
Invention content
The technical problem to be solved by the present invention is to provide a kind of connection structures of concrete structure beam column.
In order to solve the above-mentioned technical problem, the technical solution adopted in the utility model is prefabricated concrete structure beam column Connection structure, including prefabricated post and precast beam;Serration type shear key is further included, serration type shear key is king's font of accumbency Shape;The connecting pin of precast beam is variable cross-section end, and variable cross-section end is connected by pre-buried serration type shear key with the bracket of prefabricated post, And the first half embedment precast beam of shear key, the lower half embedment prefabricated column bracket of shear key.
Preferably, prefabricated post is connected with the outside on the junction both sides of precast beam by steel plate, using bolt from being located at Precast beam or the steel plate of prefabricated post side pass through precast beam or prefabricated post, also cross the gap of pre-buried serration type shear key Place, is pierced by from the steel plate for the opposite side for being located at precast beam or prefabricated post and is fixed with nut.
Preferably, prefabricated post and precast beam use concreting of the intensity for C80, indulge muscle and use Q345 with stirrup Steel, it is prefabricated in assembled plant, it transports to live directly assembled.
Preferably, the bracket upper surface of prefabricated post and the variable cross-section end upper surface of precast beam are according to the sawtooth The size of formula shear key has stayed pre-buried position.
Preferably, serration type shear key is prefabricated in the factory according to die size, direct splicing is embedded in pre- at the scene Between column bracket and precast beam processed.
Preferably, bolt uses 8.8 grade high-strength bolts.
Preferably, the junction vertical plane part of prefabricated post and precast beam adds rubber sheet gasket.
The beneficial effects of the utility model are:
Structure design is simple, convenient for assembling, is connected firmly, easy to spread.
Description of the drawings
The utility model is described in further detail with reference to the accompanying drawings and detailed description.
Fig. 1 is the front view of the utility model embodiment.
Fig. 2 is the sectional view along A-A of Fig. 1.
Fig. 3 is the serration type shear key structure diagram of the utility model embodiment.
It is marked in figure:1- prefabricated posts, 2- precast beams, 3- serration type shear keies, 4- steel plates, 5- bolts, 6- rubber sheet gaskets.
Specific embodiment
Fig. 1 is a kind of connection structure of prefabricated concrete structure beam column, is resisted by prefabricated post 1, precast beam 2, serration type Key 3, steel plate 4, bolt 5, rubber sheet gasket 6 is cut to form.
The connecting pin of precast beam 1 is a step-like variable cross-section end, and the variable cross-section end of precast beam passes through serration type shear key 4 It is attached thereto at the bracket of prefabricated post 2, forms connecting node.
For the bonding strength of enhancing connecting portion, two blocks of steel plates 5 have also been correspondingly arranged in the both sides of precast beam and prefabricated post, Steel plate is in each point of sub- bracket part of beam and column half.4 intensity is used to connect the steel plate of both sides for 8.8 grades of high-strength bolt Fixed, bolt passes through steel plate, above two bolts wear beam and mistake, below two sub- brackets of bolt prick post and mistake, also cross saw The gap up and down (Fig. 2) for lying down king's word shape of tooth-like shear key.
Bolt and steel plate play fixed function.Position to prevent sawtooth shear key or bolt is overlapped with reinforcement location, institute Quantify to fix with the position of component and accessory, to ensure that bolt will not get to the detailing requiments such as reinforcing bar.
To buffer integrated member stress in the horizontal direction, flexible rubber has been installed additional at the gap that prefabricated post is connect with precast beam Glue material, i.e. precast beam and the vertical plane of prefabricated post contact portion are partially placed into rubber sheet gasket 3, make building by level side To power effect when with certain cushioning effect.
In figure 3, serration type shear key 3 is king's word shape of an accumbency, and serration type shear key uses Mold Making. The profile arrangement of serration type shear key is that thickness is 20mm, length 200mm, is highly 100mm.
Serration type shear key is to be embedded between prefabricated column bracket and precast beam in advance.When pre-buried, by serration type shearing resistance The top half of key is submerged in the precast beam on top, and the lower half portion of serration type shear key is submerged in the prefabricated column bracket of lower part, Each half, realization splice and resist horizontal force up and down in this way.
It, be according to the size of serration type shear key when being prefabricated in the factory at the side section end of prefabricated column bracket and precast beam Pre-buried position is stayed in advance, when assembling can efficiently be constructed with quick-assembling.
The primary effect of serration type shear key is resistant to shear, and limit levels direction is subjected to displacement, while also is able to increase The snap-in force of connecting portion.
Prefabricated post and precast beam use concreting of the intensity for C80, indulge muscle with stirrup using Q345 steel, exist Assembled plant is prefabricated, transports to live directly assembled.Wherein C80 concrete make prefabricated components under use environment have compared with Good durability, safety other than with high intensity, are also provided with many new technical indicators.
The present embodiment use assembled technique, scene avoid it is cast-in-place, save the duration, articulated connection mode is with ensure that node Free Transform under the lower effect of shake effect, so as to improve integrally-built anti-seismic performance.
Above-described the utility model embodiment, does not form the restriction to scope of protection of the utility model.It is any Modifications, equivalent substitutions and improvements made within spirit of the present utility model and principle etc., should be included in the utility model Claims within.

Claims (7)

1. a kind of connection structure of prefabricated concrete structure beam column, including prefabricated post and precast beam;It is characterized in that, it further includes Serration type shear key, serration type shear key are king's word shape of accumbency;The connecting pin of the precast beam be variable cross-section end, the change Section end is connected by pre-buried serration type shear key with the bracket of prefabricated post, and the first half embedment precast beam of shear key, is resisted Cut the lower half embedment prefabricated column bracket of key.
2. connection structure according to claim 1, it is characterised in that:The junction both sides of the prefabricated post and precast beam Outside is connected by steel plate, passes through precast beam or prefabricated post from the steel plate for being located at precast beam or prefabricated post side using bolt, together When across the gap of pre-buried serration type shear key, be pierced by from the steel plate for the opposite side for being located at precast beam or prefabricated post and use spiral shell Cap is fixed.
3. connection structure according to claim 1, it is characterised in that:The prefabricated post and precast beam use intensity as C80 Concreting, indulge muscle and stirrup using Q345 steel, it is prefabricated in assembled plant, transport to live directly assembled.
4. connection structure according to claim 1, it is characterised in that:The bracket upper surface of the prefabricated post and precast beam Pre-buried position is stayed according to the size of the serration type shear key in variable cross-section end lower surface.
5. connection structure according to claim 1, it is characterised in that:The serration type shear key is according to die size in work Factory is prefabricated, and direct splicing is embedded between prefabricated column bracket and precast beam at the scene.
6. connection structure according to claim 2, it is characterised in that:The bolt uses 8.8 grade high-strength bolts.
7. connection structure according to claim 1, it is characterised in that:The junction vertical plane of the prefabricated post and precast beam Part plus rubber sheet gasket.
CN201721449034.4U 2017-11-02 2017-11-02 Connecting structure of beam column of prefabricated concrete structure Expired - Fee Related CN207525883U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721449034.4U CN207525883U (en) 2017-11-02 2017-11-02 Connecting structure of beam column of prefabricated concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721449034.4U CN207525883U (en) 2017-11-02 2017-11-02 Connecting structure of beam column of prefabricated concrete structure

Publications (1)

Publication Number Publication Date
CN207525883U true CN207525883U (en) 2018-06-22

Family

ID=62572122

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721449034.4U Expired - Fee Related CN207525883U (en) 2017-11-02 2017-11-02 Connecting structure of beam column of prefabricated concrete structure

Country Status (1)

Country Link
CN (1) CN207525883U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108980689A (en) * 2018-06-27 2018-12-11 合肥草木蕃景生态科技有限公司 A kind of Landscape Lamp with locking structure
CN109162350A (en) * 2018-10-25 2019-01-08 安徽建筑大学 Connection node of assembled concrete beam column
CN109296076A (en) * 2018-12-04 2019-02-01 安徽建筑大学 A kind of connecting node of concealed type assembling frame Structure Beam-column
CN109296075A (en) * 2018-12-04 2019-02-01 安徽建筑大学 A kind of connecting node of high deformability assembling frame Structure Beam-column
CN110173043A (en) * 2019-07-03 2019-08-27 安徽建筑大学 A kind of beam-column connection assembled using high-strength bolt
CN114687445A (en) * 2020-12-31 2022-07-01 上海浦东建筑设计研究院有限公司 Dry-type hinged joint suitable for assembled beam column is connected

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108980689A (en) * 2018-06-27 2018-12-11 合肥草木蕃景生态科技有限公司 A kind of Landscape Lamp with locking structure
CN109162350A (en) * 2018-10-25 2019-01-08 安徽建筑大学 Connection node of assembled concrete beam column
CN109296076A (en) * 2018-12-04 2019-02-01 安徽建筑大学 A kind of connecting node of concealed type assembling frame Structure Beam-column
CN109296075A (en) * 2018-12-04 2019-02-01 安徽建筑大学 A kind of connecting node of high deformability assembling frame Structure Beam-column
CN109296076B (en) * 2018-12-04 2024-04-30 安徽建筑大学 Hidden type connecting node of beam column with assembled frame structure
CN109296075B (en) * 2018-12-04 2024-04-30 安徽建筑大学 High deformability assembled frame structure beam-column connection node
CN110173043A (en) * 2019-07-03 2019-08-27 安徽建筑大学 A kind of beam-column connection assembled using high-strength bolt
CN114687445A (en) * 2020-12-31 2022-07-01 上海浦东建筑设计研究院有限公司 Dry-type hinged joint suitable for assembled beam column is connected

Similar Documents

Publication Publication Date Title
CN207525883U (en) Connecting structure of beam column of prefabricated concrete structure
CN207244839U (en) A kind of Self-resetting precast concrete concrete frame joint
CN106869315B (en) Concrete-filled steel tubular frame and its construction method with presstressed reinforcing steel
CN205776734U (en) A kind of assembly concrete connecting structure of beam column nodes
CN206554274U (en) Novel fabricated timber buildings cross steel plate connecting node
CN103669650B (en) Easily steel shaped pile frame-steel plate shear force wall is repaired after a kind of shake
CN105649202B (en) Prestressing force assembling frame node structure and its construction method
CN203174771U (en) Annular plate node of steel pipe concrete column and bonded prestress steel bar concrete beam
CN107313540A (en) The anti-buckling assembled combination beam of fire prevention and construction method
CN103924680B (en) Prestressing without bondn is connected precast concrete beam square steel tube concrete column combination node with regular reinforcement
CN106836492A (en) A kind of group frame-embedded faced wall Lateral Resistant System
CN103711329A (en) Method for reinforcing structure by means of method of externally attaching steel-reinforced concrete framework
CN108661174A (en) Discontinuous Section Column switching node and its method of construction
CN108468378B (en) Prefabricated node of concrete structure
CN106368348A (en) Overlapped combined shear wall with double-phase stress characteristic
CN108755948A (en) The assembled beam-column node structure and its construction method of tenon formula connection
CN106869326A (en) Frame system and construction method that hollow steel tube concrete integral node is constituted
CN110644806A (en) External prestress assembly type concrete frame-energy dissipation support reinforcing structure of existing structure
CN106978908B (en) Embedded prestress assembly type frame reinforcing structure with shearing mild steel damper
CN106948476B (en) The frame and its construction method that prestressing with bond combination beam is constituted
CN105804262B (en) Energy dissipation brace and the dual energy dissipation node of assembly concrete frame and assembly method
CN103924679B (en) Prestressed concrete beam and circular steel pipe concrete column combined joint connected with regular rebars
CN208981567U (en) A kind of assembly concrete shear wall connecting joint structure
CN208023717U (en) A kind of prefabrication and assembly construction steel reinforced concrete beam column fast joint structure
CN109680833A (en) The prefabricated reinforcing bar concrete panel component of self-bearing type, wall, structural system and production method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180622

Termination date: 20181102

CF01 Termination of patent right due to non-payment of annual fee