CN207524971U - Oil tanker replaces the interim oil-collecting device of storage tank - Google Patents

Oil tanker replaces the interim oil-collecting device of storage tank Download PDF

Info

Publication number
CN207524971U
CN207524971U CN201721162096.7U CN201721162096U CN207524971U CN 207524971 U CN207524971 U CN 207524971U CN 201721162096 U CN201721162096 U CN 201721162096U CN 207524971 U CN207524971 U CN 207524971U
Authority
CN
China
Prior art keywords
storage tank
oil
interim
branch line
tanker
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721162096.7U
Other languages
Chinese (zh)
Inventor
温哲华
赵德喜
兰峰
李嘉
徐壮飞
蒋维军
苏毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Offshore Oil Corp CNOOC
CNOOC China Ltd Tianjin Branch
Original Assignee
China National Offshore Oil Corp CNOOC
CNOOC China Ltd Tianjin Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Offshore Oil Corp CNOOC, CNOOC China Ltd Tianjin Branch filed Critical China National Offshore Oil Corp CNOOC
Priority to CN201721162096.7U priority Critical patent/CN207524971U/en
Application granted granted Critical
Publication of CN207524971U publication Critical patent/CN207524971U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Pipeline Systems (AREA)

Abstract

A kind of oil tanker replaces the interim oil-collecting device of storage tank, including:The carried of crude oil bus that is connected with carried of crude oil pipeline, the interim oil storage tank transport branch line one end being respectively connected with carried of crude oil bus and export tanker transport branch line one end transport the interim oil storage tank that the branch line other end is connected with interim oil storage tank, wherein, the other end of export tanker transport branch line is connected with the input end of interim oil storage tank;The port of export of interim oil storage tank is connected with export tanker transport branch line, the other end of export tanker transport branch line is connect successively with flotation hose, export tanker, make to form an interim oil transportation circuit between interim oil storage tank and export tanker after interim oil storage tank stores up full oil, it can be realized as the switching of crude oil and interim oil storage tank by operation control valve, it will be in Crude Oil Transportation to export tanker.The utility model not only solves transport line or the problem of when storage tank needs repairing needs to stop production;Moreover, substantially increase crude oil online production efficiency.

Description

Oil tanker replaces the interim oil-collecting device of storage tank
Technical field
The utility model is related to the interim oil-collecting devices that oil-collecting device more particularly to a kind of oil tanker replace storage tank.Belong to stone Oily chemical field.
Background technology
At present, crude storage equipment is typically used as by storage tank during storage and transportation crude oil is produced in oil field, but It is that if transport line or storage tank need repairing, will result in halt production, greatly affected production capacity.
Utility model content
The main purpose of the utility model is that overcoming disadvantages mentioned above of the existing technology, and a kind of oil tanker is provided and is replaced The interim oil-collecting device of storage tank, it is simple in structure, it is easy to operate, storage tank can not only can be replaced to carry out connecing oil temporarily online, solved The problem of transport line of having determined or storage tank need to stop production when needing repairing;Moreover, not influencing the online production of crude oil, greatly improve Crude oil online production efficiency.
The purpose of this utility model is realized by following technical scheme:
A kind of oil tanker replaces the interim oil-collecting device of storage tank, it is characterised in that:Including:The original being connected with carried of crude oil pipeline Oil transport bus, the interim oil storage tank transport branch line one end being respectively connected with carried of crude oil bus and export tanker transport branch line one End, the interim oil storage tank being connected with the interim oil storage tank transport branch line other end, wherein, the other end of export tanker transport branch line leads to Interim oil storage tank external transport pipeline is crossed with the input end of interim oil storage tank to be connected;The port of export of interim oil storage tank is transported with export tanker Branch line is connected, export tanker transport branch line the other end connect successively with flotation hose, export tanker, make interim oil storage tank with outside An interim oil transportation circuit is formed between oil transportation wheel;And carried of crude oil bus and interim oil storage tank transport branch line between, interim oil storage Control valve is installed respectively between tank external transport pipeline and interim oil storage tank, between flotation hose and export tanker.
The control valve is ball valve.
The beneficial effects of the utility model:The utility model is due to the adoption of the above technical scheme, simple in structure, operation side Just, storage tank can not only can be replaced to carry out connecing oil temporarily online, solves transport line or when storage tank needs repairing needs to stop production The problem of;Moreover, not influencing the online production of crude oil, crude oil online production efficiency is substantially increased.
Description of the drawings
FIG. 1 is a schematic structural view of the utility model.
Major Symbol explanation in figure:
1. carried of crude oil bus, 2. first control valves, 21. second control valves, 22. third control valves, 3. interim oil storage tanks Transport branch line, 4. interim oil storage tanks, 5. export tankers, 6. export tankers transport branch line, defeated harbour outside 7., 8. flotation hoses, 9. Interim oil storage tank external transport pipeline.
Specific embodiment
As shown in Figure 1, the utility model includes:The carried of crude oil bus 1 that is connected with carried of crude oil pipeline, by three reduction of fractions to a common denominators Interim oil storage tank transport 3 one end of branch line and export tanker transport branch line 6 one end for not being connected with carried of crude oil bus 1, with it is interim The interim oil storage tank 4 that is connected of oil storage tank transport 3 other end of branch line, wherein, the other end of export tanker transport branch line 6 passes through interim Oil storage tank external transport pipeline 9 is connected with the input end of interim oil storage tank 4;The port of export of interim oil storage tank 4 and export tanker transport branch Line 6 is connected, and the other end of export tanker transport branch line 6 is connect successively with flotation hose 8, export tanker 5, makes interim oil storage tank 4 An interim oil transportation circuit is formed between export tanker 5;And between carried of crude oil bus 1 and interim oil storage tank transport branch line 3, face When oil storage tank external transport pipeline 3 and interim oil storage tank 4 between, between flotation hose 8 and export tanker 5 control valve (this is installed respectively The control valve of embodiment is:First control valve 2 is installed between carried of crude oil bus 1 and interim oil storage tank transport branch line 3;Temporarily Second control valve 21 is installed between oil storage tank external transport pipeline 9 and interim oil storage tank 4;Pacify between flotation hose 8 and export tanker 5 Equipped with third control valve 22, after interim oil storage tank stores up full oil, crude oil and interim storage can be realized as by operation control valve The switching of oil tank, will be in Crude Oil Transportation to export tanker 5.
Above-mentioned control valve is ball valve.
Above-mentioned export tanker 5 is rested on outer defeated harbour 7.After interim oil storage tank 4 stores up full oil, can very easily by In Crude Oil Transportation to export tanker 5.
It when former storage tank storing and transporting system repairs or fortuitous event occurs, does not need to stop production, only need to pass through operation and control Valve can realize the switching of two systems, and former storage tank storing and transporting system is converted to the interim oil system that connects carries out online production.And Being stopped at outer defeated harbour 7 has two export tankers 5, can realize that two oil tankers connect oil in turn.
The above descriptions are merely preferred embodiments of the present invention, and not the utility model is made in any form Limitation, it is every according to the technical essence of the utility model to above example made it is any it is simple modification, equivalent variations with Modification, in the range of still falling within technical solutions of the utility model.

Claims (2)

1. a kind of oil tanker replaces the interim oil-collecting device of storage tank, it is characterised in that:Including:The crude oil being connected with carried of crude oil pipeline Transport bus, the interim oil storage tank transport branch line one end being respectively connected with carried of crude oil bus and export tanker transport branch line one End, the interim oil storage tank being connected with the interim oil storage tank transport branch line other end, wherein, the other end of export tanker transport branch line leads to Interim oil storage tank external transport pipeline is crossed with the input end of interim oil storage tank to be connected;The port of export of interim oil storage tank is transported with export tanker Branch line is connected, export tanker transport branch line the other end connect successively with flotation hose, export tanker, make interim oil storage tank with outside An interim oil transportation circuit is formed between oil transportation wheel;And carried of crude oil bus and interim oil storage tank transport branch line between, interim oil storage Control valve is installed respectively between tank external transport pipeline and interim oil storage tank, between flotation hose and export tanker.
2. oil tanker according to claim 1 replaces the interim oil-collecting device of storage tank, it is characterised in that:The control valve is ball Valve.
CN201721162096.7U 2017-09-12 2017-09-12 Oil tanker replaces the interim oil-collecting device of storage tank Expired - Fee Related CN207524971U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721162096.7U CN207524971U (en) 2017-09-12 2017-09-12 Oil tanker replaces the interim oil-collecting device of storage tank

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721162096.7U CN207524971U (en) 2017-09-12 2017-09-12 Oil tanker replaces the interim oil-collecting device of storage tank

Publications (1)

Publication Number Publication Date
CN207524971U true CN207524971U (en) 2018-06-22

Family

ID=62575915

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721162096.7U Expired - Fee Related CN207524971U (en) 2017-09-12 2017-09-12 Oil tanker replaces the interim oil-collecting device of storage tank

Country Status (1)

Country Link
CN (1) CN207524971U (en)

Similar Documents

Publication Publication Date Title
CN207524971U (en) Oil tanker replaces the interim oil-collecting device of storage tank
CN204185232U (en) Oiling oil discharge integrated apparatus
CN203346063U (en) Oil product storage and transport pipeline system with automatic pressure relief device
CN203082451U (en) Double-tube sealed nitrogen replacement leakage stopper with oil, gas and pressure
US10823334B2 (en) Hydraulic pressurization device for liquefied natural gas and liquefied-compressed natural gas
CN204870985U (en) A integrated valve block that is used for container empty van to pile high quick -witted hydraulic braking system
CN102705702B (en) Auxiliary unit used for hydraulic horizontal-pushing pressurizer and hydraulic horizontal-pushing pressurizer
CN205187003U (en) Nitrogen sealing system
CN207945491U (en) A kind of atmospheric storage tank feed liquor pipeline system
CN103925471B (en) A kind of hydrogen gas feed system
CN202176581U (en) On-line dispersing hydraulic station oil tank centralized oil supplementing system
CN103307312B (en) Floating valve, water wash system and engineering machinery
CN106629567A (en) Oil-distributing system in railway loading area for coastal finished product oil depots
CN204005245U (en) The many material-transporting systems of a kind of harbour A-grade in the first class's class
CN107476374A (en) A kind of municipal water supply equipment
CN208457576U (en) The dual-purpose pipeline of loading-unloading vehicle for LNG station field
CN204284918U (en) A kind of railway transport low temperature tank car mounting-and-dismounting device
CN208634799U (en) A kind of crude oil storage and transportation pipeline system
CN204213617U (en) Skid-mounted LNG two pump two-shipper filling apparatus
CN203060919U (en) On-line filtering device of coal conveying pipeline
CN202352453U (en) On-site oil storage tank of transformer
JP5660929B2 (en) Tanker cargo handling equipment
CN217843525U (en) Complete set petrochemical device interlocking protection device
CN104676159A (en) Eccentric reducing pipe joint
CN204213613U (en) Skid-mounted LNG two pump four machine filling apparatus

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180622

Termination date: 20190912