CN207521906U - Busbar welding equipment - Google Patents

Busbar welding equipment Download PDF

Info

Publication number
CN207521906U
CN207521906U CN201721291863.4U CN201721291863U CN207521906U CN 207521906 U CN207521906 U CN 207521906U CN 201721291863 U CN201721291863 U CN 201721291863U CN 207521906 U CN207521906 U CN 207521906U
Authority
CN
China
Prior art keywords
busbar
battery strings
loading end
strings group
welding equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201721291863.4U
Other languages
Chinese (zh)
Inventor
李文
马霁
蒋蒙
喻双喜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuxi Autowell Technology Co Ltd
Original Assignee
Wuxi Autowell Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuxi Autowell Technology Co Ltd filed Critical Wuxi Autowell Technology Co Ltd
Priority to CN201721291863.4U priority Critical patent/CN207521906U/en
Application granted granted Critical
Publication of CN207521906U publication Critical patent/CN207521906U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Resistance Welding (AREA)

Abstract

The utility model provides a kind of busbar welding equipment, including welder and bogey, welder is one to three set, three positions are corresponded to respectively, first position is the first battery strings group head position, the second position is the second battery strings group tail position, and the third place is the position that the first battery strings group tail portion and the second battery strings group head connect;Bogey includes the first loading end, the second loading end and third loading end, first loading end corresponds to first position, second loading end corresponds to the second position, and third loading end corresponds to the third place, and carrying busbar is used on the first loading end, the second loading end and third loading end;Welder is used to weld the welding on busbar and battery strings group.In the utility model, by welder and bogey collective effect, the three parts busbar welding to two battery strings groups is realized on one device, automatization level greatly improves.

Description

Busbar welding equipment
Technical field
The utility model is related to automatic battery production line in general, is set in particular to a kind of welding of busbar It is standby.
Background technology
At present, the demand of battery is increasing, and in cell production process, multiple battery strings is needed to be connected It connects, i.e., is welded together between the adjacent battery strings of each two by busbar.But it existing is welded to connect by busbar The technical process of battery strings needs individually to carry out, and carry out manual operation, seriously affects the percent of automatization of battery production, Er Qie great The big efficiency for reducing battery production.In addition, the technical process using human weld or manually carried, not only greatly reduces Production efficiency, and safety problem and working strength problem are also resulted in, and with the raising of cost of labor, objectively lift again The holistic cost of battery production is risen.
Therefore, the automatization level of battery strings welding how is improved, so as to improve battery production efficiency, reduce cost of labor And safety problem is avoided the occurrence of, is industry urgent problem.
Utility model content
One main purpose of the utility model is to overcome at least one defect of the above-mentioned prior art, provide it is a kind of from The horizontal very high busbar welding equipment of dynamicization.
To realize above-mentioned purpose of utility model, the utility model adopts the following technical solution:
A kind of busbar welding equipment welds the first battery strings group and the second battery strings group that connect, and described One battery strings group and the second battery strings group include more than two parallel cells strings, the busbar welding equipment packet It includes:
Welder, the welder are one to three set, correspond to three positions respectively, and first position is the described first electricity Pond string group head position, the second position are the second battery strings group tail position, and the third place is the first battery strings group The position that tail portion and the second battery strings group head connect;
Bogey, the bogey include the first loading end, the second loading end and third loading end, and described first Loading end corresponds to the first position, and second loading end corresponds to the second position, described in the third loading end corresponds to The third place is used to carrying busbar on first loading end, the second loading end and third loading end;
The welder is used to weld the welding on the busbar and the battery strings group.
An embodiment according to the present utility model, the welder are a set of, and corresponding three positions are movably Setting.
An embodiment according to the present utility model, the welder are three sets, correspond to three positions respectively and consolidate Determine or actively set.
An embodiment according to the present utility model, the bogey include the first load carrier, the second load carrier With third load carrier, first loading end is set on first load carrier, institute is set on second load carrier The second loading end is stated, the third loading end is set on the third load carrier.
An embodiment according to the present utility model, first load carrier include lifting structure so that described first Loading end lifts and/or second load carrier includes lifting structure so that second loading end lifts.
An embodiment according to the present utility model, first load carrier include left and right fine tuning structure so that described First loading end carries out left and right fine tuning and/or second load carrier includes left and right fine tuning structure so that described second holds Section carries out left and right fine tuning.
An embodiment according to the present utility model is provided with structure for conveying, the conveying on the third load carrier Structure is the third loading end.
An embodiment according to the present utility model is directly or indirectly provided with heat insulating strip on the third loading end, institute Heat insulating strip pad is stated to be located at below the busbar.
An embodiment according to the present utility model, the heat insulating strip are connected with drawing structure, and the drawing structure is used for Heat insulating strip extraction is laid on the loading plate and retracts the heat insulating strip from the loading plate.
An embodiment according to the present utility model, the busbar welding equipment further included busbar fetching and sending devices and Mechanism is raised, the busbar fetching and sending devices are used to busbar crawl being transferred to the third loading end, described to raise machine Structure is used to raise the part that two battery strings groups connect.
As shown from the above technical solution, it is the advantages of the busbar welding equipment of the utility model with good effect:
In the utility model, by welder and bogey collective effect, realized on one device to two batteries The three parts busbar welding of string group, whole prosthetic intervention, and pipeline rhythm is incorporated, automatization level greatly improves, So as to greatly improve the whole work efficiency of battery production.
Description of the drawings
Consider the detailed description of the following preferred embodiment to the utility model in conjunction with the accompanying drawings, the utility model it is each Kind target, feature and advantage will become apparent.Attached drawing is only the exemplary diagram of the utility model, is not necessarily It is drawn to scale.In the accompanying drawings, same reference numeral always shows same or similar component.Wherein:
Fig. 1 is the utility model busbar welding equipment structure diagram shown in the first exemplary embodiment.
Fig. 2 is the utility model busbar welding equipment structure diagram shown in the second exemplary embodiment.
Fig. 3 is the utility model busbar welding equipment structure diagram shown in third exemplary embodiment.
Fig. 4 is the operating process schematic diagram of the utility model busbar welding equipment shown in an exemplary embodiment.
Wherein, the reference numerals are as follows:
1st, 2,3, busbar welding equipment;10th, 20,30, stent;11st, 21,31, welder;111st, 211 it is, 311, flexible Structure;112nd, 212,312, soldering tip;213rd, transverse moving structure;12nd, 22,32, bogey;1201st, the 2201,3201, first carrying Face;1202nd, the 2202,3202, second loading end;1203rd, 2203,3203, third loading end;121st, the 221,321, first carrying machine Structure;122nd, the 222,322, second load carrier;123rd, 223,323, third load carrier;13rd, 23,33, busbar fetches and delivers dress It puts;131st, 231,331, moving structure;132nd, 232,332, structure is picked and placeed;133rd, 233,333, crawl structure;14th, 24,34, electricity Pond string group;141st, the 241,341, first battery strings group head welding;142nd, the 242,342, second battery strings group tail portion welding;143、 243rd, the 343, first battery strings group tail portion welding;144th, the 244,344, second battery strings group head welding;15th, 25,35, confluence Item;36th, heat insulating strip;361st, drawing structure;18th, mechanism is raised.
Specific embodiment
Example embodiment is described more fully with reference to the drawings.However, example embodiment can be with a variety of shapes Formula is implemented, and is not understood as limited to embodiment set forth herein;On the contrary, these embodiments are provided so that this practicality is new The design of example embodiment fully and completely, and comprehensively will be communicated to those skilled in the art by type.It is identical in figure Reference numeral represents same or similar structure, thus will omit their detailed description.
It is described below the difference to the utility model is exemplary, is carried out with reference to attached drawing, the attached drawing forms this practicality A novel part, and the exemplary knot of difference of many aspects of achievable the utility model is wherein shown by way of example Structure, system and step.It should be understood that other specified schemes of component, structure, exemplary means, system and step can be used, and And structural and functional modification can be carried out in the case of without departing from the scope of the utility model.It although moreover, can in this specification The different example features of the utility model are described using term " top ", " bottom ", " forepart ", " rear portion ", " side " etc. And element, but these terms are in this article merely for convenient, for example, with reference to the accompanying drawings described in exemplary direction.This explanation Any content in book is not necessarily to be construed that the specific three dimensional direction of Structure of need is just fallen into the scope of the utility model.
First embodiment
Fig. 1 is the utility model busbar welding equipment structure diagram shown in the first exemplary embodiment.
As shown in Figure 1, the busbar welding equipment 1 of the embodiment includes welder 11, bogey 12 and busbar Fetching and sending devices 13.Wherein, welder 11 is used to busbar 15 being welded to battery strings group 14, and bogey 12 is used to carry Battery strings group 14 and busbar 15, busbar fetching and sending devices 13 are used to fetch and deliver busbar 15.
In the embodiment, welder 11 is three sets, is respectively installed over the mount 10.Often set welder 11 can wrap Stretching structure 111 and soldering tip 112 are included, wherein, stretching structure 111 can be movable or be fixedly mounted on stent 10, another End installation soldering tip 112 so that soldering tip 112 can move up and down, and soldering tip 112 is for implementing welding action, by battery strings group 14 Weld together with busbar 15.In addition, in other specific embodiments, welder can also have and can all around move Dynamic structure, to adjust position, alignment needs the position welded.
In the embodiment, bogey 12 includes the first load carrier 121, the second load carrier 122 and third carrying machine Structure 123.In the embodiment, the first load carrier 121 and the second load carrier 122 are located at the two of third load carrier 123 respectively Side, and the top of the first load carrier 121, the second load carrier 122 and third load carrier 123 is respectively the first carrying Face 1201, the second loading end 1202 and third loading end 1203.In the embodiment, the first load carrier 121 and the second carrying machine Structure 122 includes lifting structure and left and right fine tuning structure, with respectively to the first loading end 1201 and the second loading end 1202 into Row lifting and left and right fine tuning.
In the embodiment, third load carrier 123 includes structure for conveying (not shown), which can be Conveyer belt, idler wheel etc. can also set loading plate, such as glass plate on the structure for conveying, to facilitate conveying placing battery strings Group 14.In the embodiment, battery strings group 14 is two sets, is mutually concatenated, i.e., end to end, the first battery strings group tail portion welding 143 It is welded with the second battery strings group head welding 144 by busbar 15, still alternatively, adds insulating tape.In addition, the first electricity Pond Chuan Zu heads welding 141 welds connection circuit by busbar 15, and the second battery strings group tail portion welding 142 passes through busbar 15 Weld connection circuit.Busbar 15 on corresponding first load carrier 121 of welding of first battery strings group head welding 141, the Busbar 15 on corresponding second load carrier 122 of welding of two battery strings group tail portion weldings 142.On third load carrier 123 Busbar 15 corresponding first battery strings group tail portion welding 143 and the second battery strings group head welding 144 simultaneously, and simultaneously with two Person welds.
In the embodiment, selectively using busbar fetching and sending devices 13, busbar 15 is captured into transfer automatically to realize To the third loading end 1203 of third load carrier 123.In the embodiment, busbar fetching and sending devices 13 include moving structure 131st, structure 132, crawl structure 133 are picked and placeed.Wherein, moving structure 131 picks and places structure 132 and crawl structure 133 for mobile, With corresponding crawl and the position of relieving busbar 15.Picking and placeing structure 132 can move up and down, so that the crawl contact confluence of structure 133 Busbar 15 is placed on third loading end 1203 by item 15.Crawl structure 133 can be sucker or manipulator, to facilitate certainly Dynamic crawl and relieving busbar 15.
In the embodiment, still alternatively using mechanism 18 is raised, it is close for raising battery strings group 14 to raise mechanism 18 Busbar 15, is placed by the part of the first battery strings group tail portion welding 143 and the second battery strings group head welding 144 with facilitating Below.It is a set of to raise the setting that mechanism 18 can be as shown in Figure 1, two sets can also be set simultaneously, determined as the case may be. Raising the function of mechanism 18 can be substituted with busbar fetching and sending devices 13, and structure is also identical with busbar fetching and sending devices 13, herein It repeats no more.
In the embodiment, section of bus item 15 is placed individually by the first loading end by manually or mechanically mode of operation 1201 and second on loading end 1202, and section of bus item 15 is placed near bogey 12.Then by two battery strings groups 14 are placed on third load carrier 123, and be adjusted in place.When being welded, held by the first load carrier 121 and second The adjustment of the lifting structure and left and right fine tuning structure of mounted mechanism 122 so that 15 position of busbar is in place.Meanwhile by raising machine Structure 18 raises the tail portion of the first battery strings group 14, then busbar 15 is placed into third loading end by busbar fetching and sending devices 13 On 1203, and below 14 tail portion of the first battery strings group, then the second battery strings group 14 is being raised by raising mechanism 18 Head, and pass through busbar fetching and sending devices 13 and busbar 15 is moved into the first battery strings group tail portion welding 143 and the second battery strings Below group 144 centered position of head welding.After location determination is suitable, by welder 11 to all busbars and welding into Row welding.In addition, for busbar 15 pick and place or on-line automaticization operate, by continuous productive process conveying in place, tool Body determines according to actual needs.
Second embodiment
Fig. 2 is the utility model busbar welding equipment structure diagram shown in the second exemplary embodiment.
As shown in Fig. 2, the busbar welding equipment 2 of the embodiment includes welder 21, bogey 22 and busbar Fetching and sending devices 23.The structure of welder 21, bogey 22 and busbar fetching and sending devices 23 and the basic phase of first embodiment Together, concrete structure referring to first embodiment statement and understand incorporated by reference to attached drawing 2, not reinflated explanation herein.
Compared with first embodiment, in the embodiment, welder 21 is one, and traversing knot has been added in welder 21 Structure 213, stretching structure 211 are mounted on by transverse moving structure 213 on stent 20, and transverse moving structure 213 is according to welding demand, Ke Yiyi Secondary to be moved to three different welding positions, butt joint 25 and battery strings group 24 are welded respectively.
In addition, compared with first embodiment, battery strings group 24 is raised using busbar fetching and sending devices 23 in the embodiment Corresponding position, busbar 25 is suitably positioned.Specifically, it first passes through the movement of moving structure 231 and picks and places knot Structure 232 and crawl structure 233 arrive the top of corresponding first battery strings group tail portion welding 243, then pick and place structure 232 and push crawl Structure 233 is fallen, and crawl structure 233 catches the tail portion of the first battery strings group 24, and then moving structure 231 is to the first battery strings 24 heads of group movement so that 24 tail portion of the first battery strings group is overturn, and reserves gap.Again by busbar fetching and sending devices 23 as above Busbar 25 is put into above-mentioned gap by the action, opens the second battery strings using busbar fetching and sending devices 23 again The head of group 24, and be continuing with busbar fetching and sending devices 23 and busbar 25 is moved into middle position, finally taken using busbar Send device 23 that battery strings group 24 is opened partial reset.
3rd embodiment
Fig. 3 is the utility model busbar welding equipment structure diagram shown in third exemplary embodiment.
As shown in figure 3, the busbar welding equipment 3 of the embodiment includes welder 31, bogey 32 and busbar Fetching and sending devices 33.Welder 31, the structure of bogey 32 and busbar fetching and sending devices 33 and first embodiment and second are in fact Apply that example is essentially identical, concrete structure referring to first embodiment and second embodiment statement and understand incorporated by reference to attached drawing 3, herein not Reinflated explanation.
Compared with first embodiment and second embodiment, in the embodiment, added on third loading end 3203 heat-insulated Item 36, busbar 35 are arranged on heat insulating strip 36, so as to reduce welder 31 in the welding process to third loading end 3203 Influence.In addition, to reduce cost and being conveniently operated, heat insulating strip 36 is reusable.Heat insulating strip 36 connects a drawing structure 361, heat insulating strip 36 is laid with before busbar 35 is placed on third loading end 3203, realizes automatic laying, when needing to fetch, Heat insulating strip 36 is retracted by the drawing structure 361.
In addition, compared with first embodiment and second embodiment, third loading end 3203 is by loading plate in the embodiment Upper surface is formed, which is placed on structure for conveying.Using the loading plate, facilitate and put two battery strings groups 34 in advance Good, which can be glass plate or steel plate etc..Finally, it is non-using loading plate when, automatic crawl structure can be used will be every The hot transfer of item 36 is placed on conveying third load carrier 323.The form of the automatic crawl structure can refer to busbar and fetch and deliver dress 33 are put, which can be fixed structure or a structure for conveying, so as to facilitate third loading end 3203 carry out position adjustment.
Finally, the busbar welding equipment of the utility model, to the first battery strings group for connecting and the second battery strings group into Row welding, the first battery strings group and the second battery strings group include more than two parallel cells strings, and welding includes the first weldering Area, the second welding zone and third welding zone;Wherein, in the first welding zone, busbar is welded to the head welding of the first battery strings group, In second welding zone, to the tail portion welding welding busbar of the second battery strings group, in third welding zone, by the first battery strings group tail portion Welding and the second battery strings group head welding be welded on same busbar.
It is wherein selectable, in third welding zone, insulating tape is set on busbar.
Fig. 4 is the operating process schematic diagram of the utility model busbar welding equipment shown in an exemplary embodiment. As shown in figure 4, in the embodiment, the welding process of third welding zone is as follows:
1st, the first battery strings group and the second battery strings group are placed to welding position;
2nd, the first battery strings group tail portion is raised;
3rd, busbar is placed to the first battery strings group lower part;
4th, the second battery strings group head is raised;
5th, busbar is adjusted to the first battery strings group tail portion and the lower section of the second battery strings group head connecting position;
6th, busbar and the first battery strings group tail portion welding and busbar and the second battery strings group head welding are carried out Welding.
In addition, other different flows also can be used to carry out in other embodiments, below just different flows expansion explanation.
Wherein, second procedure includes the following steps:
1st, the first battery strings group and the second battery strings group are placed to welding position;
2nd, the second battery strings group head is raised;
3rd, busbar is placed to the second battery strings group lower part;
4th, the first battery strings group tail portion is raised;
5th, busbar is adjusted to the first battery strings group tail portion and the lower section of the second battery strings group head connecting position;
6th, busbar and the first battery strings group tail portion welding and busbar and the second battery strings group head welding are carried out Welding.
Third flow includes the following steps:
1st, the first battery strings group and the second battery strings group are placed to welding position;
2nd, the position of the first battery strings group and the second battery strings group is adjusted;
3rd, the first battery strings group tail portion is raised;
4th, busbar is placed to the first battery strings group lower part;
5th, the second battery strings group head is raised;
6th, busbar is adjusted to the first battery strings group tail portion and the lower section of the second battery strings group head connecting position;
7th, busbar and the first battery strings group tail portion welding and busbar and the second battery strings group head welding are carried out Welding.
4th flow includes the following steps:
1st, the first battery strings group and the second battery strings group are placed to welding position;
2nd, the position of the first battery strings group and the second battery strings group is adjusted;
3rd, the second battery strings group head is raised;
4th, busbar is placed to the second battery strings group lower part;
5th, the first battery strings group tail portion is raised;
6th, busbar is adjusted to the first battery strings group tail portion and the lower section of the second battery strings group head connecting position;
7th, busbar and the first battery strings group tail portion welding and busbar and the second battery strings group head welding are carried out Welding.
5th flow includes the following steps:
1st, the first battery strings group and the second battery strings group are placed to welding position;
2nd, the first battery strings group tail portion is raised;
3rd, heat insulating strip is placed to the first battery strings group lower part;
4th, it places on busbar to heat insulating strip;
5th, the second battery strings group head is raised;
6th, busbar is adjusted to the first battery strings group tail portion and the lower section of the second battery strings group head connecting position;
7th, busbar and the first battery strings group tail portion welding and busbar and the second battery strings group head welding are carried out Welding.
6th flow includes the following steps:
1st, the first battery strings group and the second battery strings group are placed to welding position;
2nd, the second battery strings group head is raised;
3rd, heat insulating strip is placed to the second battery strings group lower part;
4th, it places on busbar to heat insulating strip;
5th, the first battery strings group tail portion is raised;
6th, busbar is adjusted to the first battery strings group tail portion and the lower section of the second battery strings group head connecting position;
7th, busbar and the first battery strings group tail portion welding and busbar and the second battery strings group head welding are carried out Welding.
7th flow includes the following steps:
1st, the first battery strings group and the second battery strings group are placed to welding position;
2nd, the position of the first battery strings group and the second battery strings group is adjusted;
3rd, the first battery strings group tail portion is raised;
4th, heat insulating strip is placed to the first battery strings group lower part;
5th, it places on busbar to heat insulating strip;
6th, the second battery strings group head is raised;
7th, busbar is adjusted to the first battery strings group tail portion and the lower section of the second battery strings group head connecting position;
8th, busbar and the first battery strings group tail portion welding and busbar and the second battery strings group head welding are carried out Welding.
8th flow includes the following steps:
1st, the first battery strings group and the second battery strings group are placed to welding position;
2nd, the position of the first battery strings group and the second battery strings group is adjusted;
3rd, the second battery strings group head is raised;
4th, heat insulating strip is placed to the second battery strings group lower part;
5th, it places on busbar to heat insulating strip;
6th, the first battery strings group tail portion is raised;
7th, busbar is adjusted to the first battery strings group tail portion and the lower section of the second battery strings group head connecting position;
8th, busbar and the first battery strings group tail portion welding and busbar and the second battery strings group head welding are carried out Welding.
In addition, it is necessary to explanation, more than each specific embodiment different structure between be that can carry out the group that intersects It closes, because length is limited, no longer expansion illustrates one by one herein, but all combined crosswise schemes ought to be included in this practicality In novel protection domain.
The utility model person of an ordinary skill in the technical field should be appreciated that institute in above-mentioned specific embodiment part What the concrete structure and technical process shown was merely exemplary, and not restrictive.Moreover, the affiliated technology neck of the utility model The those of ordinary skill in domain can be combined with structure the various technical characteristics shown in the above according to various possible modes The technical solution of Cheng Xin carries out other changes, and belongs within the scope of the utility model.

Claims (10)

1. a kind of busbar welding equipment, which is characterized in that welded to the first battery strings group and the second battery strings group that connect It connects, the first battery strings group and the second battery strings group include more than two parallel cells strings, the busbar weldering Equipment is connect to include:
Welder, the welder are one to three set, correspond to three positions respectively, and first position is first battery strings Group head position, the second position are the second battery strings group tail position, and the third place is the first battery strings group tail portion The position to connect with the second battery strings group head;
Bogey, the bogey include the first loading end, the second loading end and third loading end, first carrying Face corresponds to the first position, and second loading end corresponds to the second position, and the third loading end corresponds to the third Position is used to carrying busbar on first loading end, the second loading end and third loading end;
The welder is used to weld the welding on the busbar and the battery strings group.
2. busbar welding equipment as described in claim 1, which is characterized in that the welder is a set of, described in correspondence Three positions are movably set.
3. busbar welding equipment as described in claim 1, which is characterized in that the welder is three sets, is corresponded to respectively Three positions are set fixed or movablely.
4. busbar welding equipment as described in claim 1, which is characterized in that the bogey includes the first carrying machine Structure, the second load carrier and third load carrier set first loading end on first load carrier, and described second holds Second loading end on mounted mechanism is set, the third loading end is set on the third load carrier.
5. busbar welding equipment as claimed in claim 4, which is characterized in that first load carrier includes lifting knot Structure is so that first loading end lifting and/or second load carrier include lifting structure so that second carrying Face lifts.
6. busbar welding equipment as claimed in claim 5, which is characterized in that it is micro- that first load carrier includes left and right Structure is adjusted so that first loading end carries out left and right fine tuning and/or second load carrier includes left and right fine tuning structure So that second loading end carries out left and right fine tuning.
7. busbar welding equipment as claimed in claim 4, which is characterized in that be provided with conveying on the third load carrier Structure is the third loading end above the structure for conveying.
8. busbar welding equipment as claimed in claim 7, which is characterized in that directly or indirectly set on the third loading end Heat insulating strip is equipped with, the heat insulating strip pad is located at below the busbar.
9. busbar welding equipment as claimed in claim 8, which is characterized in that the busbar welding equipment has further included pumping Pull-up structure and loading plate, the heat insulating strip connect the drawing structure, and the drawing structure is used to extract out the heat insulating strip and spread It is located on the loading plate and retracts the heat insulating strip from the loading plate.
10. the busbar welding equipment as described in claim 1-9 is any, which is characterized in that the busbar welding equipment is also Include busbar fetching and sending devices and raise mechanism, the busbar fetching and sending devices are used to busbar crawl being transferred to described the It is described to raise mechanism for raising the part that two battery strings groups connect on three loading ends.
CN201721291863.4U 2017-09-30 2017-09-30 Busbar welding equipment Withdrawn - After Issue CN207521906U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721291863.4U CN207521906U (en) 2017-09-30 2017-09-30 Busbar welding equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721291863.4U CN207521906U (en) 2017-09-30 2017-09-30 Busbar welding equipment

Publications (1)

Publication Number Publication Date
CN207521906U true CN207521906U (en) 2018-06-22

Family

ID=62569691

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721291863.4U Withdrawn - After Issue CN207521906U (en) 2017-09-30 2017-09-30 Busbar welding equipment

Country Status (1)

Country Link
CN (1) CN207521906U (en)

Similar Documents

Publication Publication Date Title
CN106853566B (en) A kind of welding set easy to use
CN207459099U (en) A kind of Full-automatic battery cell package machine
CN109108444A (en) A kind of button cell butt-welding machine can be realized pole piece automatic charging
CN102340032A (en) Automatic baking equipment of lithium battery
CN107552989A (en) Busbar welding equipment
CN205927578U (en) Busbar welding machine
CN207723717U (en) A kind of string welding machine
CN109539746A (en) A kind of lithium battery contact heating vacuum tunnel baking line
CN102969536A (en) Baking cooling equipment
CN207521906U (en) Busbar welding equipment
CN209484994U (en) A kind of charging and discharging mechanism of lithium battery contact heating vacuum tunnel baking line
CN202571579U (en) Energy storage type resistance welding special machine for freeze dryer shelf
CN105364613B (en) A kind of input and output auxiliary body for the CNC equipment for processing automobile workpiece
CN206047418U (en) For the welder of photovoltaic module
CN107552909A (en) Busbar welding method
CN211889418U (en) Semi-automatic ultrasonic welding equipment
CN205984631U (en) Box transformer production line
CN202905902U (en) Baking cooling equipment
CN209484993U (en) A kind of lithium battery contact heating vacuum tunnel baking line
CN207668760U (en) A kind of busbar welder
CN207618049U (en) A kind of backing plate automatic packing device
CN207558946U (en) Formation device
CN207529961U (en) Cell piece string welding machine
CN207205546U (en) A kind of stitch welding machine driving track structure
CN102849459A (en) Automatic feeder for electrode plates

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20180622

Effective date of abandoning: 20230120

AV01 Patent right actively abandoned

Granted publication date: 20180622

Effective date of abandoning: 20230120

AV01 Patent right actively abandoned
AV01 Patent right actively abandoned