CN207457487U - A kind of system of electronization investigation and analysis electric energy meter exception - Google Patents

A kind of system of electronization investigation and analysis electric energy meter exception Download PDF

Info

Publication number
CN207457487U
CN207457487U CN201721031059.2U CN201721031059U CN207457487U CN 207457487 U CN207457487 U CN 207457487U CN 201721031059 U CN201721031059 U CN 201721031059U CN 207457487 U CN207457487 U CN 207457487U
Authority
CN
China
Prior art keywords
electric energy
energy meter
investigation
electricity
terminal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721031059.2U
Other languages
Chinese (zh)
Inventor
袁继忠
谢琦
王巡
杨奕建
王仰
潘旭藩
陈伟生
陈坚雄
卢林煜
林丽霞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jieyang Power Supply Bureau of Guangdong Power Grid Co Ltd
Original Assignee
Jieyang Power Supply Bureau of Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jieyang Power Supply Bureau of Guangdong Power Grid Co Ltd filed Critical Jieyang Power Supply Bureau of Guangdong Power Grid Co Ltd
Priority to CN201721031059.2U priority Critical patent/CN207457487U/en
Application granted granted Critical
Publication of CN207457487U publication Critical patent/CN207457487U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The system that the utility model discloses a kind of electronization investigation and analysis electric energy meter exception moves back benefit device including electric energy meter, terminal, metering automation system, electric energy meter investigation and analytical equipment and electricity extremely, wherein:Electric energy meter is connected by terminal with metering automation system;And investigation and analytical equipment connect metering automation system to electric energy meter extremely and electricity moves back benefit device;And electricity moves back benefit device and is also connected with metering automation system.The utility model moves back the connection network system realization electronization investigation for mending device by electric energy meter investigation and analytical equipment extremely with electric energy meter, terminal, metering automation system and electricity and analysis electric energy meter is abnormal, it improves work efficiency, effectively prevents the situation of electric energy meter anomaly analysis mistakes and omissions.

Description

A kind of system of electronization investigation and analysis electric energy meter exception
Technical field
The utility model is related to electric network faults to investigate field, and more particularly to a kind of electronization investigation and analysis electric energy meter are abnormal System.
Background technology
If power grid critical point, power plant and specially become user electric energy meter be abnormal, it would be possible to power plant, with electric unit, Power supply bureau brings economic loss and dispute.Office of prefectures and cities plant stand, large user's electric energy meter substantial amounts at present, from different The electric energy meter of producer also has different performance abnormal conditions.At present, for how running from the substantial amounts of electric energy meter of metering automation Data are filtered out there may be operation exception electric energy meter, and accurately data analysis is carried out to there may be abnormal electric energy meters, To judge whether the electric energy meter is that metering is abnormal, if need to carry out electricity and move back benefit and how to carry out electricity to move back that benefit etc. is a series of to ask Topic, main still using manually investigating one by one, manually investigation can not ensure the accuracy investigated extremely, and due to the number of electric energy meter Measure huge, work efficiency can not ensure.
Utility model content
The main purpose of the utility model is the system for proposing a kind of electronization investigation and analysis electric energy meter exception, it is intended to gram Take the above problem.
To achieve the above object, the utility model proposes include electric energy meter, terminal, metering automation system, electric energy meter Abnormal investigation and analytical equipment, electricity, which move back, mends device and its connection network, wherein:Electric energy meter passes through terminal and metering automation system System connection;And investigation and analytical equipment connect metering automation system to electric energy meter extremely and electricity moves back benefit device;And electricity moves back benefit Device is also connected with metering automation system;Metering automation system obtains the operation data of electric energy meter by terminal, sends to Electric energy meter investigation and analytical equipment extremely, electric energy meter investigation and analytical equipment extremely to the operation data of electric energy meter that receive into The abnormal investigation of row and analysis, and send final investigation analysis result to electricity and move back benefit device, electricity, which moves back, mends device according to final Investigation Analysis result calculation moves back benefit electricity and sends metering automation system to accordingly.
Preferably, the terminal include plant stand terminal and negative control terminal, the electric energy meter include plant stand terminal electric energy meter and Negative control terminal electric energy meter.
Preferably, the factory end end number is several numbers, and the plant stand terminal electric energy meter number is several numbers.
Preferably, the plant stand terminal connects into principal and subordinate's LAN, metering automation system with several plant stand terminal electric energy meters System connects into principal and subordinate's LAN with several plant stand terminals, connects the connection of the plant stand terminal electric energy meter and metering automation system Network is power private network.
Preferably, the negative control terminal number is several numbers, and the negative control terminal electric energy meter number is several numbers.
Preferably, the negative control terminal connects into principal and subordinate's LAN, metering automation system with several negative control terminal electric energy meters System connects into principal and subordinate's LAN with several negative control terminals, connects the connection of the negative control terminal electric energy meter and metering automation system Network is wirelessly or non-wirelessly public network.
Preferably, electric energy meter investigation and analytical equipment and electricity extremely moves back benefit device and is integrated in one.
Preferably, several plant stand terminal electric energy meters and several negative control terminal electric energy meters are respectively provided with different performance and investigate extremely Data, the electric energy meter investigation and analytical equipment extremely are equipped with all plant stand terminal electric energy meters and all whole terminal electric energy of negative control The different performance of table is investigated extremely and the field operation application software of analysis.
Preferably, the connection network for connecting the electric energy meter investigation and analytical equipment and metering automation system extremely is 4G Network or WIFI.
The utility model is by establishing electric energy meter, terminal, metering automation system, electric energy meter investigation and analytical equipment extremely And electricity moves back the electronic investigation of the connection communication real-time performance between benefit device and analysis electric energy meter is abnormal, instead of previous people For mode investigate one by one, further through electric energy meter investigation and analytical equipment extremely complete the accurate investigation of abnormal electric energy meter electronization and Analysis further, is moved back by electricity and mends device completion electricity with moving back benefit proper calculation, drastically increased work efficiency, have Anomaly analysis and electricity move back the situation misrepresented deliberately and failed to report mended and calculated caused by effect ground grind or sharpen has been exempted from artificially.
Description of the drawings
It in order to illustrate the embodiment of the utility model or the technical proposal in the existing technology more clearly, below will be to embodiment Or attached drawing needed to be used in the description of the prior art is briefly described, it should be apparent that, the accompanying drawings in the following description is only It is some embodiments of the utility model, for those of ordinary skill in the art, in the premise not made the creative labor Under, other attached drawings can also be obtained according to the structure shown in these attached drawings.
Fig. 1 is the structure diagram of an embodiment of the utility model;
The embodiments will be further described with reference to the accompanying drawings for the realization, functional characteristics and advantage of the utility model aim.
Specific embodiment
The following is a combination of the drawings in the embodiments of the present utility model, and the technical scheme in the embodiment of the utility model is carried out It clearly and completely describes, it is clear that described embodiment is only the part of the embodiment rather than whole of the utility model Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not making creative work premise Lower all other embodiments obtained, shall fall within the protection scope of the present invention.
If it is to be appreciated that related in the utility model embodiment directionality instruction (such as upper and lower, left and right, it is preceding, Afterwards ...), then directionality instruction be only used for explain it is opposite between each component under a certain particular pose (as shown in drawings) Position relationship, motion conditions etc., if the particular pose changes, directionality instruction also correspondingly changes correspondingly.
It if, should " first ", " the in addition, relate to the description of " first ", " second " etc. in the utility model embodiment Two " etc. description is only used for description purpose, and it is not intended that instruction or implying its relative importance or implicit indicating meaning The quantity of the technical characteristic shown." first " is defined as a result, the feature of " second " can express or implicitly include at least one A this feature.In addition, the technical solution between each embodiment can be combined with each other, but must be with ordinary skill Personnel can be implemented as basis, and this technical side is will be understood that when the combination appearance of technical solution is conflicting or can not realize The combination of case is not present, also not within the protection domain of the requires of the utility model.
As shown in Figure 1, the utility model proposes a kind of electronization investigation and the system of analysis electric energy meter exception, including electric energy Table, terminal, metering automation system, electric energy meter investigation and analytical equipment, electricity extremely, which move back, mends device and its connection network, In:Electric energy meter is connected by terminal with metering automation system;And electric energy meter investigation extremely and analytical equipment connection metering are automatically Change system and electricity move back benefit device;And electricity moves back benefit device and is also connected with metering automation system;Terminal obtains the fortune of electric energy meter Row data send metering automation screening system to and go out to have abnormal electric energy meter, and there will be exceptions for metering automation system Electric energy meter data send electric energy meter investigation and analytical equipment extremely to, and electric energy meter investigation and analytical equipment extremely is to the electricity that receives The operation data of energy table carry out abnormal investigation and analysis, and send final investigation analysis result to electricity and move back benefit device, electricity It moves back to mend device and move back benefit electricity accordingly according to final investigation Analysis result calculation and sends metering automation system to.
In the present embodiment, the utility model connects electric energy meter, terminal, metering automation system respectively by connecting network System, electric energy meter investigation and analytical equipment and electricity extremely move back benefit device, and the electric energy meter is for measuring electrical equipment consumption electricity The instrument of energy is abnormal if being especially mounted to province's gateway mouth, power plant and the special electric energy meter for becoming user, it would be possible to power generation Factory brings economic loss and dispute with electric unit, power supply bureau;The metering automation system utilizes metering automation system Telemetry carry out substantial amounts of data examination, specially become by importing each substation of metering automation system or certain power supply area The data such as the electric energy meter electricity of one week of user, voltage and current realize electric energy meter operating condition batch quantity analysis, and filtering out may deposit In abnormal electric energy meter;The electric energy meter investigation and analytical equipment extremely realize the operation number to single one rapid lapse of time of electric energy meter According to anomaly analysis, by the abnormal electric energy meter inventory to filtering out, import electric energy meter one by one nearly 1 month or the longer time it is distant Measured data realizes the precise abnormal analysis to electric energy meter, judges with the presence or absence of metering operation exception, if need to carry out electricity and move back It mends;The electricity moves back to mend device and realize and move back to being judged as to carry out that electricity moves back the electric energy meter of benefit and to mend electricity and calculate automatically, and Institute's result of calculation is sent to metering automation system, it is referred to herein to move back that mend electricity and calculate automatically be to move back benefit meter by curing electricity It calculates formula and carrys out the accurate calculating that favorite moves back benefit into electricity, the electricity calculating for efficiently avoiding artificial mode causes electricity to move back to remedy defects Difference.
The utility model is by establishing electric energy meter, terminal, metering automation system, electric energy meter investigation and analytical equipment extremely And electricity moves back the electronic investigation of the connection communication real-time performance between benefit device and analysis electric energy meter is abnormal, instead of previous people For mode investigate one by one, further through electric energy meter investigation and analytical equipment extremely complete the accurate investigation of abnormal electric energy meter electronization and Analysis further, is moved back by electricity and mends device completion electricity with moving back benefit proper calculation, drastically increased work efficiency, have Anomaly analysis and electricity move back the situation misrepresented deliberately and failed to report mended and calculated caused by effect ground grind or sharpen has been exempted from artificially.
Further, the terminal includes plant stand terminal and negative control terminal, and the electric energy meter includes plant stand terminal electric energy meter With negative control terminal electric energy meter.
In the present embodiment, terminal described in the utility model was included for plant stand terminal and negative control terminal, the plant stand end It holds to apply the terminal in power plant and substation, can realize the acquisition storage of electric energy meter information and electric energy meter operating condition prison It surveys, and the information of acquisition is managed and transmitted, abbreviation plant stand terminal;The negative control terminal specially becomes user scene to be installed on For Site Service with management terminal device, realize to specially become user remote meter reading, electrical energy measurement, equipment working condition, client The functions such as power load and electric energy monitor, electric energy meter also accordingly includes plant stand terminal electric energy meter as a result, and negative control terminal is electric It can table.
Further, the factory end end number is several numbers, and the plant stand terminal electric energy meter number is several numbers.
Further, the plant stand terminal connects into principal and subordinate's LAN, metering automation with several plant stand terminal electric energy meters System connects into principal and subordinate's LAN with several plant stand terminals, connects the company of the plant stand terminal electric energy meter and metering automation system It is that connect the plant stand terminal electric energy meter and the connection network of metering automation system be power private network to power private network to connect network.
Further, the negative control terminal number is several numbers, and the negative control terminal electric energy meter number is several numbers.
Further, the negative control terminal connects into principal and subordinate's LAN, metering automation with several negative control terminal electric energy meters System connects into principal and subordinate's LAN with several negative control terminals, connects the company of the negative control terminal electric energy meter and metering automation system Network is connect as wirelessly or non-wirelessly public network.
In the present embodiment, plant stand terminal electric energy meter substantial amounts described in the utility model, with metering automation system Power private network is connected to, data are transmitted by power private network.The negative control terminal electric energy meter substantial amounts, with metering automation system System is connected by wired or wireless local public network.
Further, electric energy meter investigation and analytical equipment and electricity extremely moves back benefit device and is integrated in one.
In the present embodiment, it should be appreciated that ground is that electric energy meter investigation and analytical equipment and electricity extremely move back and mend device and can be It is independently arranged or the two is integrated in one.
Further, several plant stand terminal electric energy meters and several negative control terminal electric energy meters are respectively provided with different performance and arrange extremely Data are looked into, the electric energy meter investigation and analytical equipment extremely are equipped with all plant stand terminal electric energy meters and the whole terminal electricity of all negative controls It can the different performance exception investigation of table and the field operation application software of analysis.
Further, connecting electric energy meter investigation and analytical equipment and the connection network of metering automation system extremely is 4G networks or WIFI.
In the present embodiment, electric energy meter in the utility model investigation and analytical equipment extremely with metering automation system again It is connected by 4G or Wireless LAN, Wireless LAN has and is not limited to WIFI.Again because of several plant stand terminals in fortune Electric energy meter and several negative control terminal electric energy meters have different performance abnormal conditions, for this purpose, electric energy meter is abnormal from different producers Investigation and analytical equipment are equipped with all plant stand terminal electric energy meters and the different performance of all whole terminal electric energy meters of negative control is arranged extremely The field operation application software looked into and analyzed live can carry out accurately investigating and analyzing work by field operation application software Make.
The above is only the preferred embodiment of the present invention, and it does not limit the scope of the patent of the present invention, It is every under the inventive concept of the utility model, equivalent structure made based on the specification and figures of the utility model becomes It changes or directly/is used in other related technical areas indirectly and is included in the scope of patent protection of the utility model.

Claims (9)

1. the system of a kind of electronization investigation and analysis electric energy meter exception, which is characterized in that including electric energy meter, terminal, metering certainly Dynamicization system, electric energy meter investigation and analytical equipment, electricity extremely, which move back, mends device and its connection network, wherein:
Electric energy meter is connected by terminal with metering automation system;And
Electric energy meter investigation extremely and analytical equipment connection metering automation system and electricity move back benefit device;And
Electricity moves back benefit device and is also connected with metering automation system;
Terminal obtains the operation data of electric energy meter, sends metering automation screening system to and goes out to have abnormal electric energy meter, metering There will be abnormal electric energy meter data to send electric energy meter investigation and analytical equipment extremely to for automated system, and electric energy meter is investigated extremely And the operation data of electric energy meter of the analytical equipment to receiving carry out abnormal investigation and analysis, and will finally investigate analysis result biography It gives electricity and moves back benefit device, electricity, which moves back to mend device and move back benefit electricity accordingly according to final investigation Analysis result calculation, sends metering to Automated system.
2. the system of electronization investigation as described in claim 1 and analysis electric energy meter exception, which is characterized in that the terminal bag Plant stand terminal and negative control terminal are included, the electric energy meter includes plant stand terminal electric energy meter and negative control terminal electric energy meter.
3. the system of electronization investigation as claimed in claim 2 and analysis electric energy meter exception, which is characterized in that the plant stand is whole End number is several numbers, and the plant stand terminal electric energy meter number is several numbers.
4. the system of electronization investigation as claimed in claim 3 and analysis electric energy meter exception, which is characterized in that the plant stand is whole End connects into principal and subordinate's LAN with several plant stand terminal electric energy meters, and metering automation system connects into principal and subordinate with several plant stand terminals LAN, the connection network for connecting the plant stand terminal electric energy meter and metering automation system is power private network.
5. the system of electronization investigation as claimed in claim 2 and analysis electric energy meter exception, which is characterized in that the negative control is eventually End number is several numbers, and the negative control terminal electric energy meter number is several numbers.
6. the system of electronization investigation as claimed in claim 5 and analysis electric energy meter exception, which is characterized in that the negative control is eventually End connects into principal and subordinate's LAN with several negative control terminal electric energy meters, and metering automation system connects into principal and subordinate with several negative control terminals LAN, the connection network for connecting the negative control terminal electric energy meter and metering automation system is wirelessly or non-wirelessly public network.
7. the system of electronization investigation as described in claim 1 and analysis electric energy meter exception, which is characterized in that the electric energy meter Abnormal investigation and analytical equipment and electricity move back benefit device and are integrated in one.
8. such as claim 1-7 any one of them electronization investigation and the system of analysis electric energy meter exception, which is characterized in that if It is different that dry plant stand terminal electric energy meter and several negative control terminal electric energy meters are respectively provided with different performance investigation data, the electric energy meter extremely Often investigation and analytical equipment are equipped with the different performance suitable for all plant stand terminal electric energy meters and all negative control terminal electric energy meters The abnormal field operation application software investigated and analyze.
9. the system of electronization investigation as claimed in claim 8 and analysis electric energy meter exception, which is characterized in that connect the electricity The connection network of energy table investigation and analytical equipment and metering automation system extremely is 4G networks or WIFI.
CN201721031059.2U 2017-08-16 2017-08-16 A kind of system of electronization investigation and analysis electric energy meter exception Expired - Fee Related CN207457487U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721031059.2U CN207457487U (en) 2017-08-16 2017-08-16 A kind of system of electronization investigation and analysis electric energy meter exception

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721031059.2U CN207457487U (en) 2017-08-16 2017-08-16 A kind of system of electronization investigation and analysis electric energy meter exception

Publications (1)

Publication Number Publication Date
CN207457487U true CN207457487U (en) 2018-06-05

Family

ID=62249119

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721031059.2U Expired - Fee Related CN207457487U (en) 2017-08-16 2017-08-16 A kind of system of electronization investigation and analysis electric energy meter exception

Country Status (1)

Country Link
CN (1) CN207457487U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107367706A (en) * 2017-08-16 2017-11-21 广东电网有限责任公司揭阳供电局 The system of electronization investigation and analysis electric energy meter exception
CN111506618A (en) * 2019-12-11 2020-08-07 国网重庆市电力公司北碚供电分公司 Abnormal electricity utilization behavior analysis method combined with lightgbm-stacking algorithm

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107367706A (en) * 2017-08-16 2017-11-21 广东电网有限责任公司揭阳供电局 The system of electronization investigation and analysis electric energy meter exception
CN111506618A (en) * 2019-12-11 2020-08-07 国网重庆市电力公司北碚供电分公司 Abnormal electricity utilization behavior analysis method combined with lightgbm-stacking algorithm
CN111506618B (en) * 2019-12-11 2023-09-01 国网重庆市电力公司北碚供电分公司 Abnormal electricity consumption behavior analysis method combined with lightgbm-stacking algorithm

Similar Documents

Publication Publication Date Title
CN104267374B (en) Metering device on-line checking and status assessing system
Palacios-Garcia et al. Using smart meters data for energy management operations and power quality monitoring in a microgrid
CN110928866A (en) Line topology checking method and system based on power failure information big data analysis
US11215979B2 (en) System for determining electric parameters of an electric power grid
CN104267373A (en) Gateway meter assessment device
CN207457487U (en) A kind of system of electronization investigation and analysis electric energy meter exception
CN105301552A (en) Electric energy metering device online verification system
CN204069172U (en) Live detection integrated system
Kilter et al. Guidelines for Power quality monitoring-Results from CIGRE/CIRED JWG C4. 112
CN113469488B (en) Online diagnosis and analysis system for topological structure of power distribution network equipment
CN105281346A (en) Remote rural network power distribution line reactive monitoring system
CN107367706A (en) The system of electronization investigation and analysis electric energy meter exception
CN107959475A (en) A kind of photovoltaic module outdoor test system and method
López et al. Monitoring system for the local distributed generation infrastructures of the smart grid
CN203350429U (en) On-line real-time error monitoring system for alternating current sampling measurement apparatus
Milanovic et al. Guidelines for monitoring power quality in contemporary and future power networks–results from CIGRE/CIRED JWG C4. 112
CN109544044A (en) A kind of wide area electricity quality evaluation system based on the driving of failure wave-recording big data
GB2576605A (en) System for determining electric parameters of an electric power grid
Bernal Heredia et al. Case study: Field evaluation of a low-cost circuit-level electrical submetering system
CN103439616A (en) Transformation-loss precision-measurement device
Wong et al. The Application of Advanced Data Analytics to Smart Meter Data
Zavoda et al. Current and future practice for selection of Power Quality Monitoring locations—Position paper of CIGRE/CIRED JWG C4. 112
CN113392414B (en) Closed-loop checking method for household variable relationship of power station area based on station area identifier
KR20190036753A (en) Electric Line Phase Identification Apparatus Using Power Line Communication Module
Shankar et al. AMR and GSM based Energy smart meter reading for billing purpose

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180605

CF01 Termination of patent right due to non-payment of annual fee