CN207437988U - The Quick Connect Kit of oxygen lance before metallurgical furnace - Google Patents

The Quick Connect Kit of oxygen lance before metallurgical furnace Download PDF

Info

Publication number
CN207437988U
CN207437988U CN201721242907.4U CN201721242907U CN207437988U CN 207437988 U CN207437988 U CN 207437988U CN 201721242907 U CN201721242907 U CN 201721242907U CN 207437988 U CN207437988 U CN 207437988U
Authority
CN
China
Prior art keywords
oxygen lance
coupling
screw thread
blowpipe
pipe fitting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721242907.4U
Other languages
Chinese (zh)
Inventor
季书民
薛忠林
李胜强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinjiang Bayi Iron and Steel Co Ltd
Original Assignee
Baosteel Group Xinjiang Bayi Iron and Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Baosteel Group Xinjiang Bayi Iron and Steel Co Ltd filed Critical Baosteel Group Xinjiang Bayi Iron and Steel Co Ltd
Priority to CN201721242907.4U priority Critical patent/CN207437988U/en
Application granted granted Critical
Publication of CN207437988U publication Critical patent/CN207437988U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Carbon Steel Or Casting Steel Manufacturing (AREA)

Abstract

The utility model discloses a kind of Quick Connect Kits of oxygen lance before metallurgical furnace, the hose of source of the gas connection is connected with the casing coupling head of the pipe fitting of casing coupling thread connection, the other end of casing coupling thread connection pipe fitting is connected through a screw thread both ends and has female coupling tunnel, the first pre-load nut is installed on casing coupling thread connection pipe fitting, cooperation is installed with the first inner tube successively in coupling tunnel, first rubber sleeve, second inner tube and the second rubber sleeve, the other end of coupling tunnel is connected through a screw thread blowpipe connector, the second pre-load nut is connected through a screw thread on blowpipe connector, intubation jackscrew is installed in the tube wall screw hole of blowpipe connector on the outside of the second pre-load nut, the steel oxygen lance and first being inserted into coupling tunnel, second inner tube clearance fit, with first, the sealing cooperation of second rubber sleeve, steel oxygen lance is positioned by being intubated jackscrew.The utility model is rational in infrastructure, solves the safely and fast articulation issues of source of the gas and steel oxygen lance, being capable of quick-replaceable steel oxygen lance.

Description

The Quick Connect Kit of oxygen lance before metallurgical furnace
Technical field
The utility model belongs to oxygen blast before the auxiliary device of oxygen lance before ironmaking metallurgical furnace, particularly a kind of metallurgical furnace The Quick Connect Kit of pipe.
Background technology
Blast furnace and Ou Yelu are when burning iron mouth or other slag irons, it is necessary to introduce oxygen into oxygen blown steel pipe front end, then Steel pipe, burn through iron mouth or slag iron are lighted, since oxygen is dangerous combustion-supporting energy medium, while position is needed replacing in operation It puts, moves back and forth, this just needs source of the gas reliably to carry out flexible connected with steel oxygen lance, and easily by source of the gas to behaviour At work, due to burning of the steel oxygen lance when burning operation quickly, burn after use, size is shortened quickly, it is necessary to more The oxygen blown steel tubulation renewed, replacement finish carry out continued access burning operation that must be quickly, therefore for convenience efficiently by source of the gas Factory leads to operation area, it is necessary to solve the safely and fast articulation issues of source of the gas and steel oxygen lance, while must also quick-replaceable steel Oxygen lance processed, this burns the technical barrier that oxygen operates before becoming metallurgical furnace.
Utility model content
The purpose of this utility model is to provide a kind of Quick Connect Kit of oxygen lance before metallurgical furnace, structure is closed Reason, can solve the safely and fast articulation issues of source of the gas and steel oxygen lance, being capable of quick-replaceable steel oxygen lance.
What the purpose of this utility model was realized in:The Quick Connect Kit of oxygen lance, source of the gas before a kind of metallurgical furnace The hose of connection is connected with the casing coupling head of the pipe fitting of casing coupling thread connection, and the other end of casing coupling thread connection pipe fitting passes through screw thread It is connected to both ends and has female coupling tunnel, the first pre-load nut is installed on casing coupling thread connection pipe fitting, in coupling tunnel Inside cooperation is installed with the first inner tube, the first rubber sleeve, the second inner tube and the second rubber sleeve successively, and the other end of coupling tunnel passes through spiral shell Line is connected to blowpipe connector, and the second pre-load nut is connected through a screw thread on blowpipe connector, on the outside of the second pre-load nut Intubation jackscrew in the tube wall screw hole of blowpipe connector is installed, is inserted between the steel oxygen lance in coupling tunnel and first, second inner tube Gap coordinates, and seals and coordinates with first, second rubber sleeve, is positioned steel oxygen lance by being intubated jackscrew.
The utility model is rational in infrastructure, solves the safely and fast articulation issues of source of the gas and steel oxygen lance, realizes fast Speed replaces steel oxygen lance.
Description of the drawings
The utility model is further described below in conjunction with attached drawing, Fig. 1 illustrates for the utility model front view structure Figure.
Specific embodiment
The Quick Connect Kit of oxygen lance before a kind of metallurgical furnace, as shown in Figure 1, the hose 1 of source of the gas connection and casing coupling spiral shell The casing coupling first 2 of the pipe fitting of line connection is connected, and the other end of casing coupling thread connection pipe fitting 3 is connected through a screw thread both ends with interior The coupling tunnel 5 of screw thread is installed with the first pre-load nut 4 on casing coupling thread connection pipe fitting 3, and cooperation is pacified successively in coupling tunnel 5 The first inner tube 6, the first rubber sleeve 7, the second inner tube 8 and the second rubber sleeve 9, the other end of coupling tunnel 5 is filled with to be connected through a screw thread Blowpipe connector 10, the second pre-load nut 13 is connected through a screw thread on blowpipe connector 10, outside the second pre-load nut 13 Intubation jackscrew 11 in the tube wall screw hole of side-blown pipe fitting 10 is installed, is inserted into steel oxygen lance 12 and first in coupling tunnel 5, the Two inner tubes 6,8 clearance fits are sealed with first, second rubber sleeve 7,9 and coordinated, determined steel oxygen lance 12 by being intubated jackscrew 11 Position.One end of coupling tunnel 5 sets internal thread, and the other end sets undergauge screw hole.Connect in casing coupling thread connection pipe fitting casing coupling first 2 Hose fixture 14 is installed on the hose 1 connect.

Claims (3)

1. the Quick Connect Kit of oxygen lance before a kind of metallurgical furnace, it is characterized in that:The hose (1) of source of the gas connection and casing coupling screw thread The casing coupling head (2) of the pipe fitting of connection is connected, and the other end of casing coupling thread connection pipe fitting (3), which is connected through a screw thread both ends, to be had The coupling tunnel (5) of internal thread, is installed with the first pre-load nut (4) on casing coupling thread connection pipe fitting (3), in coupling tunnel (5) Cooperation is installed with the first inner tube (6), the first rubber sleeve (7), the second inner tube (8) and the second rubber sleeve (9), coupling tunnel (5) successively The other end be connected through a screw thread blowpipe connector (10), be connected through a screw thread the second pre-load nut on blowpipe connector (10) (13), positioned at intubation jackscrew (11) is installed on the outside of the second pre-load nut (13) in the tube wall screw hole of blowpipe connector (10), it is inserted into Steel oxygen lance (12) in coupling tunnel (5) and first, second inner tube (6,8) clearance fit, with first, second rubber sleeve (7, 9) sealing cooperation is positioned steel oxygen lance (12) by being intubated jackscrew (11).
2. the Quick Connect Kit of oxygen lance before metallurgical furnace according to claim 1, it is characterized in that:Coupling tunnel (5) One end sets internal thread, and the other end sets undergauge screw hole.
3. the Quick Connect Kit of oxygen lance before metallurgical furnace according to claim 1, it is characterized in that:Join in casing coupling screw thread Hose fixture (14) is installed on the hose (1) of jointed tubular workpieces casing coupling head (2) connection.
CN201721242907.4U 2017-09-26 2017-09-26 The Quick Connect Kit of oxygen lance before metallurgical furnace Expired - Fee Related CN207437988U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721242907.4U CN207437988U (en) 2017-09-26 2017-09-26 The Quick Connect Kit of oxygen lance before metallurgical furnace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721242907.4U CN207437988U (en) 2017-09-26 2017-09-26 The Quick Connect Kit of oxygen lance before metallurgical furnace

Publications (1)

Publication Number Publication Date
CN207437988U true CN207437988U (en) 2018-06-01

Family

ID=62295051

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721242907.4U Expired - Fee Related CN207437988U (en) 2017-09-26 2017-09-26 The Quick Connect Kit of oxygen lance before metallurgical furnace

Country Status (1)

Country Link
CN (1) CN207437988U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110332395A (en) * 2019-06-27 2019-10-15 唐山钢铁集团有限责任公司 A kind of oxygen lance safe connection equipment

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110332395A (en) * 2019-06-27 2019-10-15 唐山钢铁集团有限责任公司 A kind of oxygen lance safe connection equipment

Similar Documents

Publication Publication Date Title
CN207437988U (en) The Quick Connect Kit of oxygen lance before metallurgical furnace
CN101225914B (en) Automatic abutting joint for gas pipe
CN208545450U (en) A kind of iron mouth oxygen rifle
CN201187648Y (en) Fast joint of oxygen blowing pipe
CN208804368U (en) A kind of connecting device of oxygen lance
CN204603546U (en) Pipeline welding inside filled argon protection device
CN203413268U (en) Oxygen lance joint
CN201575254U (en) Tube quick joint
CN207906683U (en) A kind of telescopic H-type pipe fitting
CN208684997U (en) A kind of novel oxygen lance fast replacing device
CN202032216U (en) Anti-backfire oxygen-combustion quick joint for metallurgy
CN215668067U (en) Oxygen blowing lance
CN202066342U (en) Connecting joint of roller hearth furnace
CN210030759U (en) Portable oxygen burning connector for blast furnace
CN220099083U (en) Blast furnace iron notch oxygen gun with video monitoring
CN203348791U (en) Plastic-coated composite steel pipe connecting structure
CN203855597U (en) Iron notch burning oxygen gun device in front of blast furnace
CN104295829A (en) Connecting structure of plastic-coated composite steel pipe and connecting method thereof
CN220012678U (en) Blast furnace iron notch oxygen lance with temperature measuring device
CN218762730U (en) Improved oxygen interface device
CN214032560U (en) Be used for clear stifled equipment of blast furnace taphole mediation
CN219712308U (en) Air tightness detection plug
CN201739689U (en) Expansion type corrugated nipple union
CN206666578U (en) Steep-taper quick change oxygen rifle is used in one kind steel-making
CN216201440U (en) Quick connecting device of pipeline for oxygen burning

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20180716

Address after: 830022 No. 1 Bayi Road, Toutun River District, Urumqi, the Xinjiang Uygur Autonomous Region

Patentee after: XINJIANG BAYI IRON & STEEL Co.,Ltd.

Address before: 830022 No. 1 Xingang Road, Toutun River District, Urumqi, the Xinjiang Uygur Autonomous Region.

Patentee before: BAOSTEEL GROUP XINJIANG BAYI IRON & STEEL Co.,Ltd.

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180601

Termination date: 20210926

CF01 Termination of patent right due to non-payment of annual fee