CN207420026U - Part bracing means is poured after a kind of superimposed sheet - Google Patents
Part bracing means is poured after a kind of superimposed sheet Download PDFInfo
- Publication number
- CN207420026U CN207420026U CN201721424211.3U CN201721424211U CN207420026U CN 207420026 U CN207420026 U CN 207420026U CN 201721424211 U CN201721424211 U CN 201721424211U CN 207420026 U CN207420026 U CN 207420026U
- Authority
- CN
- China
- Prior art keywords
- superimposed sheet
- split bolt
- plank sheathing
- utility
- back cord
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The utility model pours part bracing means after disclosing a kind of superimposed sheet, including horizontal back cord, plank sheathing, split bolt, transverse steel and superimposed sheet, the superimposed sheet includes superimposed sheet, superimposed sheet and superimposed sheet, tight distribution, the superimposed sheet lower end for being distributed in centre position are equipped with plank sheathing in the horizontal direction for superimposed sheet, superimposed sheet and superimposed sheet;The superimposed sheet upper end is equipped with transverse steel;Run through on the superimposed sheet and be equipped with split bolt, the upper end of split bolt is through two transverse steels, while split bolt and transverse steel are by being welded and fixed;The plank sheathing lower end is equipped with horizontal back cord, and horizontal back cord is fixed on the lower end of plank sheathing by split bolt.The advantages that each component that the utility model uses carries out assembling construction using scene common used material, scene, has stabilized structure, and securely and reliably, good integrity is convenient to assemble and disassemble, and construction is convenient, and turnover utilization rate is high, the shortening formwork time.
Description
Technical field
The utility model, which relates to, builds work field, specifically pours part bracing means after a kind of superimposed sheet.
Background technology
According to architectural industrialization policy, State Council is just wideling popularize development assembled architecture.Since assembled architecture is special
Structure type, there are certain differences with traditional architecture in the construction process.For pouring strip after between two pieces of superimposed sheets
Formwork reinforcement measure is reinforced by the way of steel-tube die support mostly, and such reinforcing mode construction is inconvenient, while is poured with after
There may be the situations for interfering influence for the independent support of strip both sides.Recently as the gradual development of assembled architecture,
Formwork reinforcement system in work progress is particularly important, also obtains unit in charge of construction and more and more payes attention to.
Utility model content
The purpose of this utility model is to provide part bracing means is poured after a kind of superimposed sheet, so as to improve construction
Efficiency.
The purpose of this utility model can be achieved through the following technical solutions:
Part bracing means is poured after a kind of superimposed sheet, including horizontal back cord, plank sheathing, split bolt, transverse steel and is folded
Plywood, the superimposed sheet include superimposed sheet, superimposed sheet and superimposed sheet, and superimposed sheet, superimposed sheet and superimposed sheet tighten in the horizontal direction
Close distribution, the superimposed sheet lower end for being distributed in centre position are equipped with plank sheathing.
The superimposed sheet upper end is equipped with transverse steel.
Run through on the superimposed sheet and be equipped with split bolt, the upper end of split bolt is through two transverse steels, simultaneously
Split bolt and transverse steel are by being welded and fixed.
The plank sheathing lower end is equipped with horizontal back cord, and horizontal back cord is fixed on the lower end of plank sheathing by split bolt.
The width that the width of the plank sheathing is equal to superimposed sheet adds 10cm.
The width that the length of the transverse steel is equal to superimposed sheet adds 20cm.
The beneficial effects of the utility model:
Each component that the utility model uses carries out assembling construction using live common used material, scene, has stabilized structure,
Securely and reliably, the advantages that good integrity, convenient to assemble and disassemble, construction is convenient, and turnover utilization rate is high, the shortening formwork time.
Description of the drawings
The utility model will be further described below with reference to the accompanying drawings.
Fig. 1 is the utility model bracing means structure diagram;
Fig. 2 is the E-E of Fig. 1 to sectional view.
Specific embodiment
The following is a combination of the drawings in the embodiments of the present utility model, and the technical scheme in the embodiment of the utility model is carried out
It clearly and completely describes, it is clear that the described embodiments are only a part of the embodiments of the utility model rather than whole
Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are without creative efforts
The all other embodiment obtained, shall fall within the protection scope of the present invention.
In the description of the utility model, it is to be understood that term " perforate ", " on ", " under ", " thickness ", " top ",
" in ", " length ", " interior ", indicating positions or the position relationship such as " surrounding ", be for only for ease of description the utility model and simplification
Description rather than instruction imply that signified component or element must have specific orientation, with specific azimuth configuration and behaviour
Make, therefore it is not intended that limitation to the utility model.
Part bracing means is poured after a kind of superimposed sheet, including horizontal back cord 1, plank sheathing 2, split bolt 3, transverse steel 4
With superimposed sheet 5, as shown in Figs. 1-2, superimposed sheet 5 includes superimposed sheet 5A, superimposed sheet 5B and superimposed sheet 5C, superimposed sheet 5A, superimposed sheet
Tight distribution, the superimposed sheet 5B lower ends for being distributed in centre position are equipped with plank sheathing 2, wooden model to 5B and superimposed sheet 5C in the horizontal direction
The width that the width of plate 2 is equal to superimposed sheet 5 adds 10cm.Superimposed sheet 5B upper ends are equipped with transverse steel 4, the length of transverse steel 4
Width equal to superimposed sheet 5 adds 20cm.For superimposed sheet 5B through there is split bolt 3, the upper end of split bolt 3 passes through two transverse directions
Between reinforcing bar 4, while split bolt 3 and transverse steel 4 are by being welded and fixed.2 lower end of plank sheathing is equipped with horizontal back cord 1, laterally
Back cord 1 is fixed on the lower end of plank sheathing 2 by split bolt 3.
This implementation example is to be illustrated using superimposed sheet 5A, superimposed sheet 5B and superimposed sheet 5C as one group, is in actual use
Multigroup superimposed sheet common horizontal is laid with.
The utility model supports superimposed sheet 5 by plank sheathing 2, and split bolt 3 tenses horizontal back cord 1 and reinforces superimposed sheet 5, when
When the laying of superimposed sheet 5 finishes, in 5 upper end joints cement of superimposed sheet, part 6 is poured after forming superimposed sheet.
In the description of this specification, the description of reference term " one embodiment ", " example ", " specific example " etc. means
At least one of the utility model is contained in reference to the embodiment or example particular features, structures, materials, or characteristics described
In embodiment or example.In the present specification, schematic expression of the above terms be not necessarily referring to identical embodiment or
Example.Moreover, particular features, structures, materials, or characteristics described can be in any one or more embodiments or example
In combine in an appropriate manner.
The advantages of basic principle, main feature and the utility model of the utility model has been shown and described above.One's own profession
The technical staff of industry is it should be appreciated that the present utility model is not limited to the above embodiments, described in above embodiments and description
Simply illustrate the principle of the utility model, on the premise of not departing from the spirit and scope of the utility model, the utility model is also
Various changes and modifications are had, these various changes and improvements fall within the scope of the claimed invention.
Claims (3)
1. part bracing means is poured after a kind of superimposed sheet, including horizontal back cord (1), plank sheathing (2), split bolt (3), horizontal steel
Muscle (4) and superimposed sheet (5), which is characterized in that the superimposed sheet (5) includes superimposed sheet (5A), superimposed sheet (5B) and superimposed sheet
(5C), superimposed sheet (5A), superimposed sheet (5B) and superimposed sheet (5C) tight distribution in the horizontal direction are distributed in the folded of centre position
Plywood (5B) lower end is equipped with plank sheathing (2);
Superimposed sheet (5B) upper end is equipped with transverse steel (4);
Run through on the superimposed sheet (5B) and be equipped with split bolt (3), the upper end of split bolt (3) passes through two transverse steels (4)
Between, while split bolt (3) and transverse steel (4) are by being welded and fixed;
Plank sheathing (2) lower end is equipped with horizontal back cord (1), and horizontal back cord (1) is fixed on plank sheathing by split bolt (3)
(2) lower end.
2. pour part bracing means after a kind of superimposed sheet according to claim 1, which is characterized in that the plank sheathing (2)
Width be equal to superimposed sheet (5B) width add 10cm.
3. pour part bracing means after a kind of superimposed sheet according to claim 1, which is characterized in that the transverse steel
(4) width that length is equal to superimposed sheet (5B) adds 20cm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721424211.3U CN207420026U (en) | 2017-10-31 | 2017-10-31 | Part bracing means is poured after a kind of superimposed sheet |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721424211.3U CN207420026U (en) | 2017-10-31 | 2017-10-31 | Part bracing means is poured after a kind of superimposed sheet |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207420026U true CN207420026U (en) | 2018-05-29 |
Family
ID=62310252
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721424211.3U Expired - Fee Related CN207420026U (en) | 2017-10-31 | 2017-10-31 | Part bracing means is poured after a kind of superimposed sheet |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207420026U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109914697A (en) * | 2019-04-18 | 2019-06-21 | 中民筑友房屋科技集团有限公司 | A kind of assembling frame structural construction prefabricated post |
CN111636677A (en) * | 2020-05-28 | 2020-09-08 | 江苏中南建筑产业集团有限责任公司 | Construction process of assembly type building laminated slab post-cast plate strip support-free system |
-
2017
- 2017-10-31 CN CN201721424211.3U patent/CN207420026U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109914697A (en) * | 2019-04-18 | 2019-06-21 | 中民筑友房屋科技集团有限公司 | A kind of assembling frame structural construction prefabricated post |
CN111636677A (en) * | 2020-05-28 | 2020-09-08 | 江苏中南建筑产业集团有限责任公司 | Construction process of assembly type building laminated slab post-cast plate strip support-free system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201665952U (en) | Self-supporting floor deck | |
CN206987148U (en) | Concrete prefabricated board and laminated floor slab | |
CN110067185A (en) | A kind of steel pipe-steel plate combination web steel reinforced concrete combined box beam | |
CN207420026U (en) | Part bracing means is poured after a kind of superimposed sheet | |
CN208533725U (en) | A kind of steel bar girder plate side and connection joints of steel structure structure | |
CN110512765A (en) | A kind of fabricated shear wall and construction method with steel plate peg combined type diagonal brace | |
CN105887660A (en) | Perforated plate connecting piece with boot-shaped slots, steel beam and methods | |
CN208056469U (en) | Coupling beam framework of steel reinforcement fixing device between a kind of assembled superimposed sheet | |
CN108625488A (en) | A kind of detachable reinforcing steel truss plate end support node structure and construction method | |
CN205259072U (en) | Hollow mound of railway formwork support system that binds | |
CN207919358U (en) | A kind of bottom web reinforcement binding positioning moulding bed | |
CN208533724U (en) | A kind of detachable reinforcing steel truss edges of boards support node structure | |
CN206681262U (en) | A kind of prefabricated Concrete-Filled Square Steel Tube coupling beam of multilayer | |
CN205840082U (en) | A kind of BRT Lightweight core mould close rib composite floor structure | |
CN206581456U (en) | Steel construction wall component with reinforced pipe | |
CN106088470B (en) | Assembly concrete complex case shape beam and its construction method | |
CN103741857A (en) | Floor system with U-shaped steel beams, steel bar trusses and floor bearing plates | |
CN212926625U (en) | Panel muscle structure of dysmorphism structure floor external corner department | |
CN209244058U (en) | Composite floor and its floor structure | |
CN208294071U (en) | A kind of concrete construction formwork | |
CN208586890U (en) | A kind of concrete circular arc type formwork structure | |
CN209308227U (en) | A kind of structure of security protection wall or floor | |
CN207863226U (en) | A kind of built-in fabricated shear wall supported | |
CN205777528U (en) | A kind of lift-on/lift-off type metal form | |
CN203022129U (en) | RSC combined node continuously cut on web and partially cut on flanges |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180529 Termination date: 20201031 |
|