CN207368560U - A kind of high ring main unit of installation effectiveness - Google Patents
A kind of high ring main unit of installation effectiveness Download PDFInfo
- Publication number
- CN207368560U CN207368560U CN201721317302.7U CN201721317302U CN207368560U CN 207368560 U CN207368560 U CN 207368560U CN 201721317302 U CN201721317302 U CN 201721317302U CN 207368560 U CN207368560 U CN 207368560U
- Authority
- CN
- China
- Prior art keywords
- operation panel
- breaking
- hole
- cover board
- eaves portion
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000009434 installation Methods 0.000 title claims abstract description 13
- 230000007246 mechanism Effects 0.000 claims description 21
- 238000012544 monitoring process Methods 0.000 claims description 14
- 230000000694 effects Effects 0.000 description 4
- 230000005611 electricity Effects 0.000 description 4
- 238000002955 isolation Methods 0.000 description 4
- 238000004519 manufacturing process Methods 0.000 description 3
- 238000005452 bending Methods 0.000 description 2
- 230000005540 biological transmission Effects 0.000 description 2
- 238000004146 energy storage Methods 0.000 description 2
- 238000004880 explosion Methods 0.000 description 2
- 230000009545 invasion Effects 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 230000000007 visual effect Effects 0.000 description 2
- 230000004888 barrier function Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000006243 chemical reaction Methods 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000009413 insulation Methods 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 238000005192 partition Methods 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
- 230000035515 penetration Effects 0.000 description 1
- 238000010248 power generation Methods 0.000 description 1
- 230000001131 transforming effect Effects 0.000 description 1
- 239000012780 transparent material Substances 0.000 description 1
Landscapes
- Patch Boards (AREA)
Abstract
The utility model provides a kind of installation effectiveness high ring main unit, ring main unit further includes operation panel, stored energy operation hole, breaking-closing operating hole, locating slot, the first cover board and the second cover board are provided with operation panel, stored energy operation bar is opposite with stored energy operation hole, and breaking-closing operating bar is opposite with breaking-closing operating hole;The top edge of operation panel is bent to form the first eaves portion, the lower edge of operation panel is bent to form the second eaves portion, and the first eaves portion is buckled in above upper beam, and the second eaves portion is buckled in below bottom end rail, first eaves portion is provided with cramp on the corresponding position of via, and cramp is through via and extends downward.And when operation panel is aligned and installed, convenient using the setting of eaves portion, cramp and via, contraposition, fastening positioning is convenient, and lower end is also to be fixed using eaves portion so that the installation of whole operation panel is more convenient.
Description
Technical field
It the utility model is related to high voltage electric equipment field, more particularly to the ring main unit that a kind of installation effectiveness is high.
Background technology
High voltage power distributing cabinet refers to be used for play break-make, control in electric system power generation, transmission of electricity, distribution, electric energy conversion and consumption
Or protection etc. effect, voltage class 3.6kV~550kV electric equipment products, mainly including high-voltage circuitbreaker, high voltage isolator
With earthing switch, high voltage load switch, high pressure automatic reclosing and sectionaliser, high-voltage actuating mechanism, high voltage explosion-proof power distribution device and
Several major classes such as high-tension switch cabinet.High voltage switch manufacturing industry is the manufacturing important component of power transmission and transforming equipment, in whole electric power
Occupy very important status in industry.
And ring main unit is a ring important in high voltage electric equipment, it is in metal or non-metallic insulation cabinet or makes
The electrical equipment of assembled compartment ring network power supplying units, its core use on-load switch and fuse, have it is simple in structure,
It is small, price is low, can improve the advantages that power supply parameter and performance and power supply safety.It is small that it is widely used in Urban House
In the power distribution station and box-type substation of the load centers such as area, skyscraper, large public building, factory and enterprise.
Existing ring main unit is typically provided with operation panel, and operating mechanism and height are broken by the handle hole of operation panel
Road device is operated, but existing operation panel still suffers from the problem of operation degree of protection is low, and such as handle hole can not be carried out
Closing locking, or latch-up structure excessively complex effects actually use, simultaneously as multiple location holes of operation panel and multiple
Handle hole needs to align alignment, and existing mounting means is aligned using screwing through hole, its inconvenient installation will influence production effect
Rate.
The content of the invention
The purpose of this utility model provides a kind of operation panel installation effectiveness high ring main unit.
In order to realize the purpose of this utility model, the utility model provides a kind of installation effectiveness high ring main unit, including case
Body, is provided with base, support frame, high-voltage circuitbreaker, operating mechanism, monitoring unit and linear quadratic control room in babinet, operation
Mechanism is used to control high-voltage circuitbreaker separating brake or combined floodgate, and monitoring unit is used for the work shape for monitoring high-voltage circuitbreaker and operating mechanism
State, monitoring unit are arranged in linear quadratic control room, and support frame is connected between base and linear quadratic control room, high-voltage circuitbreaker and
Operating mechanism is fixed on the support frame;
Operating mechanism includes stored energy operation bar and breaking-closing operating bar;
Ring main unit further includes operation panel, be provided with operation panel stored energy operation hole, breaking-closing operating hole, locating slot,
First cover board and the second cover board, stored energy operation bar is opposite with stored energy operation hole, and breaking-closing operating bar is opposite with breaking-closing operating hole;
The first end of first cover board is hinged on operation panel, second end and the operation panel snap fit of the first cover board,
For first cover plate lid outside stored energy operation hole, the first cover board is additionally provided with the limit protrusion towards outer lug, is provided with limit protrusion
Limiting slot, limiting slot only have an opening towards locating slot, and spacing lug is through locating slot and in limiting slot;
The first end of second cover board is hinged on the top in breaking-closing operating hole, and the second end of the second cover board is in breaking-closing operating
The lower section snap fit in hole, the second cover plate lid is outside breaking-closing operating hole;
Support frame includes the upper beam close to linear quadratic control room and the bottom end rail close to base, and upper beam had been provided with
Hole;
The top edge of operation panel is bent to form the first eaves portion, and the lower edge of operation panel is bent to form the second eaves portion, the
One eaves portion is buckled in above upper beam, and the second eaves portion is buckled in below bottom end rail, and the first eaves portion is provided with the corresponding position of via
Cramp, cramp is through via and extends downward.
Further scheme is that support frame includes two curb girders being connected between upper beam and bottom end rail;Operation
Panel is respectively arranged with multiple mounting holes on the corresponding position of two curb girders, and mounting screw is installed to curb girder through mounting hole
On.
The beneficial effects of the utility model are, due to needing to prevent the main of illegal operation from including stored energy operation bar and division
Brake-operating rod(lever), therefore mainly it is protected, two operation levers can be respectively aligned to using handle hole, while also so that the first cover board
Cover alignment positioning, and the positioning is semienclosed, therefore can prevent the invasion and interference in the external world, effectively improves operation
The degree of protection of panel, while when aligning installation, using the setting of eaves portion, cramp and via, contraposition is convenient, fastens positioning side
Just, lower end is also to be fixed using eaves portion so that the installation of whole operation panel is more convenient.
Brief description of the drawings
Fig. 1 is the structure chart of the utility model ring main unit embodiment.
Fig. 2 is the structure chart of common case linear quadratic control room in the utility model ring main unit embodiment.
Fig. 3 is the structure chart of operation panel in the utility model ring main unit embodiment.
Fig. 4 is the structure chart that operation panel coordinates with support frame in the utility model ring main unit embodiment.
Fig. 5 is the structure chart of common bottom seat in the utility model ring main unit embodiment.
Fig. 6 is that bottom seat is total in the utility model ring main unit embodiment from the perspective view under side plate inwardly visual angle.
Fig. 7 is the structure chart of operating mechanism in the utility model ring main unit embodiment.
Fig. 8 is structure chart of the operating mechanism under another visual angle in the utility model ring main unit embodiment.
The utility model is described in further detail with reference to the accompanying drawings and embodiments.
Embodiment
With reference to Fig. 1, Fig. 1 is the structure chart of ring main unit, in order to show the babinet for clearly eliminating outside, the open circuit of multiple high pressures
Device, multiple monitoring units etc., but do not influence the utility model and stated for the structure of each invention for apparatus point.Ring main unit includes case
Body, it is secondary to be provided with common bottom seat 3, multiple high-voltage circuitbreakers, multiple operating mechanisms 4, multiple monitoring units, common case in babinet
Control room 1 and operation panel 2, operating mechanism are used to control high-voltage circuitbreaker separating brake or combined floodgate, and monitoring unit is used to monitor high pressure
The working status of breaker and operating mechanism,
Ring main unit is provided with common case linear quadratic control room 1 in the top of operating mechanism 4, and case linear quadratic control room 1 is included along electricity altogether
Cable room arranged direction through the babinet 11 that sets and multiple with the hinged linear quadratic control panel 12 of babinet, babinet 11 by bottom plate, after
Plate, top plate and two lateral columns 112 are formed, therefore babinet 11 forms the cavity 111 in a penetrating length direction, three linear quadratic control faces
Plate 12 is covered in the front of cavity 111, and multiple monitoring units are arranged in babinet 11.It is provided with linear quadratic control panel 12
Distribution line Fault Control terminal 123, combined floodgate indicator light 121, separating brake indicator light 122 and energy storage indicator light 124.
With reference to Fig. 3 and Fig. 4 and combine, ring main unit further includes operation panel 22, and stored energy operation is provided with operation panel 2
Hole 22, breaking-closing operating hole 271, locating slot 23, the first cover board 21 and the second cover board 26, stored energy operation bar 41 and stored energy operation
Hole 22 is opposite, and breaking-closing operating bar 42 is opposite with breaking-closing operating hole 271.
First cover board 21 is made by transparent material, and the first end of the first cover board 21 is hinged on operation panel 2, and first
The second end of cover board 21 and 2 snap fit of operation panel, the first cover board 21 rotate in the horizontal direction, and the first cover board 21 is covered in energy storage
Outside handle hole 22, the first cover board 21 is additionally provided with the limit protrusion 211 towards outer lug, and limiting slot is provided with limit protrusion 211
212, limiting slot 212 only has an opening 212 towards locating slot 23, and spacing lug 43 is through locating slot 23 and for positioned at spacing
In groove 212, the second end of the first cover board 21 is provided with straight slot, and operation panel 2 is provided with closing piece 24 on the corresponding position of straight slot,
Closing piece 24 passes through straight slot, and closing piece 24 is provided with lockhole on the outside of straight slot.
The first end of second cover board 26 is hinged on the top in breaking-closing operating hole 271, and the second cover board 26 is along operation panel
Vertical plane rotates, and in the lower section snap fit in breaking-closing operating hole 271, the second cover board 26 covers for the second end of the second cover board 26
Outside breaking-closing operating hole 271, the second end of the second cover board 26 is provided with the first locking plate 261, and operation panel 2 is in the first locking plate 261
Opposite position is provided with the second locking plate 272, and the first locking plate 261 and 272 ground of the second locking plate are provided with lockhole, the first locking plate
261 are extended with banking stop 262 on side towards the bending of 272 ground of the second locking plate in a rotational direction, and banking stop 262 and second is locked
Piece 272 abuts.
With reference to Fig. 4, ring main unit further includes support frame, the structure of support frame is represented by dashed line in Fig. 4, support frame connects
It is connected between common bottom seat 3 and altogether case linear quadratic control room 1, high-voltage circuitbreaker and operating mechanism are fixed on the support frame, support
Frame includes the upper beam 281 close to linear quadratic control room and the bottom end rail 284 close to base, and upper beam 281 is being provided with two
Via 282;Support frame includes two curb girders 283 being connected between upper beam 281 and bottom end rail 284.
The top edge of operation panel is bent to form the first eaves portion 291, and the lower edge of operation panel is bent to form the second eaves portion
292, the first eaves portion 291 is buckled in the top of upper beam 281, and the second eaves portion 292 is buckled in the lower section of bottom end rail 284, and the first eaves portion 291 exists
Cramp 293 is provided with 282 corresponding position of via, cramp 293 is through via 282 and extends downward, and cramp 293 is in two-part
Bending arrangement.
Operation panel is respectively arranged with multiple mounting holes on 283 corresponding position of the first curb girder 283 and the second curb girder
294, mounting screw is installed on curb girder 283 through mounting hole 294
With reference to Fig. 5 and Fig. 6, common bottom seat 3 includes the first side plate 32, the second side plate 33 and transverse slat 31,32 He of the first side plate
Second side plate 33 is connected to the both ends of transverse slat 31, and transverse slat 31 makes respectively positioned at the middle part of the first side plate 32 and the second side plate 33
The first side plate 32, the second side plate 33 and transverse slat 31 is obtained to arrange in H-type.
Multiple cable vaults 34 are abreast provided with the front side of transverse slat 31, operation panel 2 is directed towards on front side of the present embodiment
Side, be spaced using one piece of partition plate 35 between adjacent cable room 34, transverse slat 31 is set respectively at the position of each cable vault 34
Pressure relief opening 311 is equipped with, pressure relief opening 311 is located at 38 side of material storage room and is provided with isolation board (not shown), in the rear side storing of transverse slat 31
Room 38, between 311 communication cable room 34 of pressure relief opening and material storage room 38, a high-voltage circuitbreaker and an operating mechanism are arranged on one
In a cable vault 34, cable vault's door-plate is covered with the front end of cable vault 34, specifically, the upper end of cable vault's door-plate be provided with to
Few two lockholes, the rigidity of the ratio of rigidity isolation board of cable vault's door-plate is big, and when explosion time is sent out by cable vault 34, blast pressure is to break through
Isolation board is simultaneously released from pressure relief opening, so that the safety on front side of effective guarantee.
The bottom of cable vault 34 is provided with outlet hole 36, and limiting plate 341, two limits are provided with the both sides of outlet hole 36
Sliding slot is formed between the plate 341 of position, ring main unit further includes clamping plate 37, and clamping plate 37 includes 371 He of folder portion positioned at the top of outlet hole 36
Positioned at the cunning portion 372 of 37 both sides of clamping plate, cunning portion 372 is bent from folder portion 371, extending direction and the limiting plate 341 in cunning portion 372
Extending direction is parallel, and cunning portion 372 and the madial wall of limiting plate 341 abut, and limiting plate 341 and cunning portion 372 penetratingly set limited
Position hole, banking pin pass through limit hole, by outlet hole 36 and the lap fit of folder portion 371, then realize the clamping to cable.
With reference to Fig. 7 and Fig. 8, operating mechanism includes frame, hard interlock assembly, stored energy operation bar 41, breaking-closing operating bar 42
With spacing lug 43, stored energy operation bar 41 and breaking-closing operating bar 42 are rotationally erected on frame, and spacing lug 43 is outwardly
Ground extends and horizontally arranges, spacing lug 43 is arranged between 454 division and combination brake-operating rod(lever) 454 of stored energy operation bar.
Hard interlock assembly includes cam 48, pushing block 47, jam plate 44 and elastic component 46, and cam 48 is arranged on breaking-closing operating
The middle part of bar 42, cam 48 are rotated with the rotation of breaking-closing operating bar 42, and cam 48 is provided with pin hole.
Jam plate 44 can be vertically slidably arranged on frame, and jam plate 44 is included towards outer end face and bottom plate 451, under
With being in horizontally disposed towards outer end face, bottom plate 451, sliding slot vertically is being provided with towards outer end face on vertically for end plate 451
452, screw 453 is fixed on frame through sliding slot 452, and the operation lever 454 to extend outwardly is arranged on towards on outer end face, operation
Bar 454 passes through the hole 25 of operation panel 2, and jam plate 44 sets at least two lock pillars 45 in bottom plate 451, and lock pillar 45 is used for and electricity
The lockhole of cable room door-plate coordinates, and elastic component 46 is connected between bottom plate 451 and frame, and specifically, lock pillar 45 passes through bottom plate
451 ground are set, and elastic component 46 is spring, and spring pocket is outer in lock pillar 45 and is abutted with bottom plate 451.
Frame is provided through ground limiting slot, and pushing block 47 passes through limiting slot, and upper end 471 and bottom 472 are located at respectively
The both ends of limiting slot, pushing block 47 can be arranged on frame with radially sliding along breaking-closing operating bar 42, you can in the horizontal direction
Slip also can be slided vertically.The upper end 471 of pushing block 47 is provided with sliding slot, and sliding slot is vertically extension and upper end
The sliding slot of open lower end closing, pin 49 pass through pin hole and sliding slot, and the bottom 472 of pushing block 47 can be connected with bottom plate 451.
Therefore by the setting of hard interlock assembly, when breaking-closing operating bar is rotated and closed a floodgate, turn with moving cam
It is dynamic so that pushing block pushes lock pillar downward, then realizes that the physics of cable vault's door-plate locks firmly, and under gate-dividing state, pushing block with
Bottom plate separates, and the physics that cable vault's door-plate is also that by under the set pressure of elastic component locks firmly, and at this time
Operation lever can be operated lock pillar is up lifted and unlocked, under "on" position, the effect based on pushing block, operation lever is to grasp
Make what is used, therefore can realize the protection to cable vault's door-plate well, improve barrier propterty.
Simultaneously as need to prevent the main of illegal operation from including stored energy operation bar and breaking-closing operating bar, therefore it is main right
It is protected, and is by setting spacing lug first, is not only enabled operation panel accurate contraposition, also enables handle hole
Enough it is respectively aligned to two operation levers, while also so that the first cover board covers alignment positioning, and the positioning is semienclosed, therefore energy
Enough prevent the invasion and interference in the external world.In contrast, the protection priority level of breaking-closing operating bar is higher than stored energy operation bar, therefore right
The protection of stored energy operation bar is to use the rotating cover board of horizontal direction so that after opening will not be on automatic cover, convenient operation, and
For breaking-closing operating bar, since the second cover board is vertically rotated along operation panel, therefore after end of operation, in gravity
Under drop, then automatically reset, effectively improve the degree of protection of operation panel, while using pellucidly setting, can be more
Intuitively operated, and do not influence overall aesthetic degree.
And when operation panel is aligned and installed, it is convenient using the setting of eaves portion, cramp and via, contraposition, fasten positioning side
Just, lower end is also to be fixed using eaves portion so that the installation of whole operation panel is more convenient.
And the setting by common bottom seat, the transverse slat and the side plate at both ends put in mainly utilizing, are determining that switch is single
After the quantity of member, using the cable vault of baffle interval respective numbers, due to being to be used to install high-voltage circuitbreaker above cable vault
Closed gas tank, therefore easily heavier high-voltage circuitbreaker can be sling using lifting equipment, then be separately mounted to each electricity
The top of cable room, meanwhile, pressure relief opening and isolation board are additionally provided with, when explosion time occurs for cable vault, blast pressure can be from pressure relief opening
Discharge, prevents from producing from front side so as to protect user, and sets corresponding clamping-line structure in bottom, facilitates construction personnel
Arrange circuit.
Then, common case linear quadratic control room is installed, since control circuit, monitoring circuit are various, especially opened more
Under the application scenarios for closing unit, the indoor wiring of case linear quadratic control is especially complicated altogether, therefore this case uses the arrangement of penetration type, solves
Connectivity problem between single switch element in the prior art, all control circuits, monitoring circuit in ring main unit are being passed through
Arrangement in the cavity worn, not only facilitates installation and is also convenient for debugging.
Claims (2)
1. a kind of high ring main unit of installation effectiveness, including babinet, base, support frame, height are provided with the babinet and is broken
Road device, operating mechanism, monitoring unit and linear quadratic control room, the operating mechanism are used to control the high-voltage circuitbreaker separating brake or conjunction
Lock, the monitoring unit are used for the working status for monitoring the high-voltage circuitbreaker and the operating mechanism, and the monitoring unit is set
Put in the linear quadratic control room, the support frame is connected between the base and the linear quadratic control room, the high pressure
Breaker and the operating mechanism are fixed in the support frame;
It is characterized in that:
The operating mechanism includes stored energy operation bar and breaking-closing operating bar;
The ring main unit further includes operation panel, and stored energy operation hole, breaking-closing operating hole, positioning are provided with the operation panel
Groove, the first cover board and the second cover board, the stored energy operation bar is opposite with the stored energy operation hole, the breaking-closing operating bar and institute
It is opposite to state breaking-closing operating hole;
The first end of first cover board is hinged on the operation panel, second end and the operating surface of first cover board
Plate snap fit, for first cover plate lid outside the stored energy operation hole, first cover board is additionally provided with the limit towards outer lug
Position is raised, is provided with limiting slot in the limit protrusion, the limiting slot only has an opening towards the locating slot, spacing
Lug is through the locating slot and in the limiting slot;
The first end of second cover board is hinged on the top in the breaking-closing operating hole, and the second end of second cover board is in institute
The lower section snap fit in breaking-closing operating hole is stated, second cover plate lid is outside the breaking-closing operating hole;
The support frame includes the upper beam close to the linear quadratic control room and the bottom end rail close to the base, the upper horizontal stroke
Beam is being provided with via;
The top edge of the operation panel is bent to form the first eaves portion, and the lower edge of the operation panel is bent to form the second eaves
Portion, first eaves portion are buckled in above the upper beam, and second eaves portion is buckled in below the bottom end rail, first eaves portion
Cramp is provided with the corresponding position of the via, the cramp is through the via and extends downward.
2. ring main unit according to claim 1, it is characterised in that:
The support frame includes two curb girders being connected between the upper beam and the bottom end rail;
The operation panel is respectively arranged with multiple mounting holes on the corresponding position of two curb girders, and mounting screw passes through institute
Mounting hole is stated to be installed on the curb girder.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721317302.7U CN207368560U (en) | 2017-10-12 | 2017-10-12 | A kind of high ring main unit of installation effectiveness |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721317302.7U CN207368560U (en) | 2017-10-12 | 2017-10-12 | A kind of high ring main unit of installation effectiveness |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207368560U true CN207368560U (en) | 2018-05-15 |
Family
ID=62347496
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721317302.7U Expired - Fee Related CN207368560U (en) | 2017-10-12 | 2017-10-12 | A kind of high ring main unit of installation effectiveness |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207368560U (en) |
-
2017
- 2017-10-12 CN CN201721317302.7U patent/CN207368560U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207250983U (en) | It is a kind of to operate the high ring main unit of degree of protection | |
CN207367817U (en) | The ring main unit that a kind of cable vault's door-plate interlocks firmly | |
CN205159875U (en) | Low -voltage distribution box | |
CN207368560U (en) | A kind of high ring main unit of installation effectiveness | |
CN204464761U (en) | A kind of substation transformer leading-out terminal integration power distribution cabinet | |
KR100920405B1 (en) | High integrated power incoming panel | |
CN207368452U (en) | A kind of ring main unit with case linear quadratic control room altogether | |
CN201750635U (en) | Comprehensive access cabinet of traffic control equipment | |
CN207719641U (en) | A kind of ring main unit with bottom seat altogether | |
CN103603553A (en) | Key box for electric locomotive or bullet train | |
CN216144859U (en) | Outdoor high-voltage intelligent prepayment metering box with mutually independent functional compartments | |
CN205195071U (en) | Novel low pressure rural power grids switch board | |
CN210201245U (en) | Outdoor mobile AC emergency power distribution device | |
CN204190303U (en) | Photoelectric comprehensive distributing cabinet allocation units | |
CN213026998U (en) | Switch cabinet with insulation protection | |
CN203056410U (en) | Low-voltage high-capacity user metering device | |
CN203515024U (en) | Key locker for electric locomotive or power car | |
CN212159899U (en) | Multi-functional portable removes metering device | |
CN209675774U (en) | It is a kind of to take single-phase six ammeter boxes of control | |
CN208142612U (en) | A kind of distributed board outdoor being easily installed | |
CN220139035U (en) | Grid-connected box | |
CN212114405U (en) | Low-voltage draw-out type switch cabinet with locking function | |
CN218102089U (en) | Prevent destroying external safety switch cabinet | |
CN111157772B (en) | Multifunctional portable mobile metering device | |
CN219304215U (en) | Two-stage temporary electricity distribution box |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180515 |