CN207363681U CN201721485022.7U CN201721485022U CN207363681U CN 207363681 U CN207363681 U CN 207363681U CN 201721485022 U CN201721485022 U CN 201721485022U CN 207363681 U CN207363681 U CN 207363681U
Authority
CN
China
Prior art keywords
steel
subsegment
drag
steel grating
connection structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721485022.7U
Other languages
Chinese (zh)
Inventor
冉金林
李廷春
周游
李春廷
管清升
殷齐浩
王洪闪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University of Science and Technology
Original Assignee
Shandong University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University of Science and Technology filed Critical Shandong University of Science and Technology
Priority to CN201721485022.7U priority Critical patent/CN207363681U/en
Application granted granted Critical
Publication of CN207363681U publication Critical patent/CN207363681U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

The utility model discloses a kind of drag-line steel grating bow member, it is the steel grating bow member for being close to excavation face surrounded by arc steel grating subsegment and vertical steel grating subsegment by some guy of twisted steel cable rings and subsegment connection structure;The guy of twisted steel cable ring is upper, middle and lower three parts one steel strand wires of other tensioning in arc steel grating subsegment, and connects cyclization by drag-line connection structure;The drag-line connection structure is that two angle steel are welded in non junction side on steel strand wires Three-head connector, and angle steel is equipped with a circular hole, a bolt is inserted with circular hole;The subsegment connection structure is formed by two pieces of square flange docking, and square flange is equipped with five circular holes, and four main reinforcements and a longitudinally connected muscle are inserted with circular hole.The utility model drag-line steel grating bow member steel consumption is small, overall uniform force, the advantages that installation is convenient, suitable for the preliminary bracing of mine working etc..

Description

A kind of drag-line steel grating bow member
Technical field
A kind of drag-line steel grating bow member and its construction method are the utility model is related to, belongs to coal, military project, metallurgy, friendship The underground engineering support fields such as logical, water conservancy.
Background technology
The problems such as in order to solve land deterioration, population explosion, shortage of resources, underground engineering construction enters rapid development Stage.During underground engineering construction, in order to relax Surrounding Rock Movement, suppress roof delamination, prevent stone from dropping, prevent side wall Wall caving etc. to underground engineering, it is necessary to carry out supporting, one of which method for protecting support is bow member supporting.Arch support supporting contractibility The good, large carrying capacity of energy, can effectively suppress the deformation of country rock, be widely used in the ground such as coal, military project, metallurgy, traffic, water conservancy In lower engineering.
The arch support for mostly descending engineer application at present is steel arch-shelf.Steel arch-shelf overall stiffness is big, can provide compared with Big early stage supporting intensity, belongs to permanent support.But in the combined supporting combined with anchor pole, bar-mat reinforcement, gunite concrete, The combination situation of steel arch-shelf is relatively low, and in the junior underground engineering of Surrounding Rock Strength, be easy to cause the waste of steel.In order to Overcome this shortcoming, attempt to use grillage in some underground engineerings.Grillage common at present has:
Such as:Chinese utility model patent ZL201120448709.X discloses bored tunnel grillage, the invention bag Include at least four main reinforcements, more stirrups and reinforcing rib, main reinforcement, stirrup and reinforcing rib are welded to be formed the first pedestal bow member, in Between bow member and the second pedestal bow member be once spliced into the arc coordinated with tunnel.The grillage has certain supporting intensity, But overall unbalance stress, local deformation are serious in the underground engineering of country rock weak broken.
Chinese invention patent ZL201410251336.5 discloses the steel grating bow member and its construction method of size adjustable, should Invention includes some Arc grid subsegments, subsegment connection structure and collapsible connection structure, and Arc grid subsegment is passed through subsegment Connection structure and collapsible connection structure, which form a circle, is close to the steel grating bow member for excavating end face.The grillage size adjustable, Each face of bow member can be made to be touched with the excavated section backbreak, but the total bearing capacity of grillage is still up for improving.
In conclusion the steel grating bow member of bored tunnel grillage and size adjustable, although strong with certain supporting Degree, but because of overall discontinuity, locally occur large deformation cause steel grating bow member to destroy, drag-line steel grating bow member It can solve the problems, such as that common lattice steel grid bow member entirety unbalance stress and local deformation are serious, reach the mesh for improving total bearing capacity 's.
The content of the invention
Deficiency the purpose of the utility model is to overcome existing grillage provides that a kind of steel consumption is small, cost price It is low, supporting intensity is high, lightweight construction, speed of application are fast, the drag-line steel grating bow member of overall uniform force.Pass through the steel lattice Grid bow member solves the problems, such as the preliminary bracing of subway tunnel, mine working etc..
A kind of construction of drag-line steel grating bow member of the utility model is:It is by arc steel grating subsegment, vertical steel lattice Grid subsegment, guy of twisted steel cable ring and subsegment connection structure composition, it is characterised in that the arc steel grating subsegment and vertical steel Grid subsegment is connected by two internal main reinforcements and two exterior main reinforcement compositions, four main reinforcements by stirrup, and inside and outside main reinforcement is led to Cross reinforcing rib connection;Arc steel grating subsegment and vertical steel grating subsegment pass through some guy of twisted steel cable rings and subsegment connection structure What is surrounded is close to the steel grating bow member of excavation face;The guy of twisted steel cable ring is the upper, middle and lower three in arc steel grating subsegment One steel strand wires of tensioning respectively, and cyclization is connected by drag-line connection structure;The drag-line connection structure is in steel strand wires three Two angle steel are welded on head connector non junction side, angle steel is equipped with a circular hole, a bolt is inserted with circular hole;Described Subsegment connection structure is formed by two pieces of square flange docking, and square flange is equipped with five circular holes, and four are inserted with circular hole Main reinforcement and a longitudinally connected muscle.
It is before steel strand wires both ends fixation is carried out, it is necessary to logical to prevent steel strand wires from producing cable sag effect under Gravitative Loads Cross tensioner and symmetrical tensioning is carried out at the same time to the both ends of steel strand wires.
To strengthen the concatenation ability of subsegment connection structure, two eight word muscle, the intersection point of eight word muscle are welded at four main reinforcements The position slightly center hole away from square flange, in order to penetrate longitudinally connected muscle from center hole.
A kind of construction method of drag-line steel grating bow member of the utility model is:The top of arc steel grating subsegment, in A steel strand wires are laid in portion and lower part respectively, and steel strand wires both ends are carried out at the same time with symmetrical tensioning by tensioner, it is to be tensioned extremely It is fixed in after design load in drag-line connection structure;Stirrup is placed in the gap in drag-line connection structure between two angle steel, is treated Apply certain pretightning force after adjusting to suitable position by bolt;By the above method in arc steel grating subsegment key node After locating three guy of twisted steel cable rings of tensioning, it is close to excavation face and sets up arc steel grating subsegment and vertical steel grating subsegment, will be each Four main reinforcements of subsegment end are rolled over and correspond in insertion square flange surrounding circular hole, and apply certain pretension by bolt Power, forms overall drag-line steel grating bow member;More Pin drag-lines steel grating bow members at square flange center hole by setting up Longitudinally connected muscle is connected with each other, and longitudinally connected muscle is welded at eight word muscle nodes.
A kind of drag-line steel grating bow member of the utility model has the following advantages that:
(1) guy of twisted steel cable ring set, can be effective using the high characteristic of steel strand wires tensile strength on arc-shaped steel grillage So that the overall uniform force of steel grating bow member, can effectively prevent under pressure from surrounding rock effect steel grating bow member locally occur it is excessive Deformation;
(2) the symmetrical simultaneous tension in steel strand wires both ends, is disposably stretched to design load, saves the construction time;
(3) steel strand tension process can apply prestressing force to arc steel grating subsegment, can effectively improve steel grating bow member Bending resistance and rigidity, increase steel grating bow member durability;
(4) arc steel grating subsegment and vertical steel grating subsegment can be spliced by subsegment connection structure, can make steel lattice It is close to excavation face in each face of grid bow member;
(5) circular hole is equipped among square flange, longitudinally connected muscle can be penetrated by circular hole, realize more Pin drag-lines The quick connection of steel grating bow member.
Brief description of the drawings
Fig. 1 is a kind of structure diagram of drag-line steel grating bow member of the utility model;
Fig. 2 is the structure diagram of arc steel grating subsegment in the utility model;
Fig. 3 is A-A profiles in the utility model;
Fig. 4 is the structure diagram of drag-line connection structure in the utility model;
Fig. 5 is the structure diagram of the utility model neutron section connection structure.
Marginal data:1- arc steel grating subsegments;The vertical steel grating subsegments of 2-;3- guy of twisted steel cable rings;4- subsegments connect Structure;5- main reinforcements;6- stirrups;7- reinforcing ribs;8- steel strand wires;9- drag-line connection structures;10- steel strand wires Three-head connectors;11- angles Steel;12- bolts;13- square flanges;Eight word muscle of 14-;The longitudinally connected muscle of 15-.
Embodiment
A kind of drag-line steel grating bow member as shown in Figure 1 is twisted by arc steel grating subsegment 1, vertical steel grating subsegment 2, steel Line drag-line ring 3 and subsegment connection structure 4 form, and the arc steel grating subsegment 1 and vertical steel grating subsegment 2 are by two Portion's main reinforcement 5 and two exterior main reinforcements 5 form, and four main reinforcements 5 are connected by stirrup 6, and inside and outside main reinforcement 5 is connected by reinforcing rib 7; Arc steel grating subsegment 1 and vertical steel grating subsegment 2 are surrounded tight by some guy of twisted steel cable rings 3 and subsegment connection structure 4 Paste the steel grating bow member of excavation face;The guy of twisted steel cable ring 3 is other of the upper, middle and lower three parts in arc steel grating subsegment 1 A steel strand wires 8 are drawn, and cyclization is connected by drag-line connection structure 9;The drag-line connection structure 9 is in three companies of steel strand wires Two angle steel 11 of welding, angle steel 11 on 10 non junction side of device is connect to be equipped with a circular hole, a bolt 12 is inserted with circular hole;Institute The subsegment connection structure 4 stated is docked by two pieces of square flanges 13 and formed, and square flange 13 is equipped with five circular holes, in circular hole It is inserted with four main reinforcements 5 and a longitudinally connected muscle 15.
A kind of construction method of drag-line steel grating bow member of the utility model is:The top of arc steel grating subsegment 1, A steel strand wires 8 are laid in middle part and lower part respectively, and symmetrical tensioning is carried out at the same time to 8 both ends of steel strand wires by tensioner, wait to open It is fixed in after being pulled to design load in drag-line connection structure 9;Stirrup 6 is placed in drag-line connection structure 9 between two angle steel 11 Gap, it is to be adjusted to applying certain pretightning force by bolt 12 after suitable position;By the above method in arc steel grating At 1 key node of subsegment after three guy of twisted steel cable rings 3 of tensioning, it is close to excavation face and sets up arc steel grating subsegment 1 and vertical steel Grid subsegment 2, by four main reinforcements 5 of each subsegment end are rolled over and corresponding insertion 13 surrounding circular hole of square flange in, and lead to Cross bolt 12 and apply certain pretightning force, form overall drag-line steel grating bow member;More Pin drag-lines steel grating bow member sides of passing through Longitudinally connected muscle 15 is set up at 13 center hole of shape ring flange to be connected with each other, and longitudinally connected muscle weldering 15 is connected on eight word muscle, 14 node Place.

Claims (1)

1. a kind of drag-line steel grating bow member, it be by arc steel grating subsegment, vertical steel grating subsegment, guy of twisted steel cable ring and Subsegment connection structure forms, it is characterised in that arc steel grating subsegment and vertical steel grating subsegment pass through some guy of twisted steel cable What ring and subsegment connection structure surrounded is close to the steel grating bow member of excavation face;The guy of twisted steel cable ring is in arc steel grating Upper, middle and lower three parts one steel strand wires of other tensioning of subsegment, and cyclization is connected by drag-line connection structure;The drag-line connection Structure is that two angle steel of welding, angle steel are equipped with a circular hole, a bolt are inserted with circular hole on steel strand wires Three-head connector; The subsegment connection structure is formed by two pieces of square flange docking, and square flange is equipped with five circular holes, is inserted in circular hole There are four main reinforcements and a longitudinally connected muscle.
CN201721485022.7U 2017-11-09 2017-11-09 A kind of drag-line steel grating bow member Active CN207363681U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721485022.7U CN207363681U (en) 2017-11-09 2017-11-09 A kind of drag-line steel grating bow member

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721485022.7U CN207363681U (en) 2017-11-09 2017-11-09 A kind of drag-line steel grating bow member

Publications (1)

Publication Number Publication Date
CN207363681U true CN207363681U (en) 2018-05-15

Family

ID=62345940

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721485022.7U Active CN207363681U (en) 2017-11-09 2017-11-09 A kind of drag-line steel grating bow member

Country Status (1)

Country Link
CN (1) CN207363681U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107605510A (en) * 2017-11-09 2018-01-19 山东科技大学 A kind of drag-line steel grating bow member and its construction method
CN114562296A (en) * 2022-04-06 2022-05-31 中铁第一勘察设计院集团有限公司 Grid steel frame structure with spiral stirrups and construction method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107605510A (en) * 2017-11-09 2018-01-19 山东科技大学 A kind of drag-line steel grating bow member and its construction method
CN107605510B (en) * 2017-11-09 2023-08-22 山东科技大学 Dragline type steel grid arch frame and construction method thereof
CN114562296A (en) * 2022-04-06 2022-05-31 中铁第一勘察设计院集团有限公司 Grid steel frame structure with spiral stirrups and construction method thereof

Similar Documents

Publication Publication Date Title
CN107288653B (en) Double-side-wall pilot tunnel three-step excavation supporting structure for weak surrounding rock large-section tunnel and construction method
WO2018006558A1 (en) Confined high-strength concrete support system applicable to underground tunnel
CN206769052U (en) A kind of New Types of Beam column Connections
CN107227808A (en) A kind of buckling-restrained steel plate shear force wall system of full assembled
CN102226398A (en) Soft rock four-line large-span tunnel compound double-side wall bracing cable conversion excavation construction method
CN107605510A (en) A kind of drag-line steel grating bow member and its construction method
CN207363681U (en) A kind of drag-line steel grating bow member
CN108203984A (en) A kind of Dangerous Rock Body bolting with wire mesh method
CN111663444A (en) Suspension bridge tunnel anchor and rock mass anchor combined type anchorage structure and construction method
CN109898521A (en) A kind of anchored pile supporting and construction method for foundation pit external corner
CN210599028U (en) Primary support supporting structure of super-large-span underground engineering in hard rock area
CN215444085U (en) High-strength flexible stainless steel part
CN109113749A (en) Four line large section railway tunnel construction method of weak surrounding rock
CN200985510Y (en) Anchored exterior-protected construction
CN212404803U (en) Tunnel inverted arch combined type cableway bridge abutment
CN105369814A (en) Prefabricated assembled type prestressed concrete support and erecting method thereof
KR100746593B1 (en) Method for Supporting Temporary Retaining Wall Using Support-line and Pre-loading Strut
CN202596187U (en) Concrete rod restoring and reinforcing hoop
CN110513122B (en) Prestressed truss support system and method for pipe curtain construction
CN212506313U (en) Combined foundation pit supporting structure
CN105155413B (en) Partial non-bonded tunnel type compound anchorage system and method
CN106499053A (en) A kind of assembled integral pre-stressed concrete frame structure connection member
CN210975547U (en) Suspension bridge bell jar formula anchorage structure
CN208885322U (en) Expansion type rock bolt permanent support structure with interim detachable Fuse Type anchor cable
CN206941607U (en) The foundation ditch concrete support pilework that live borehole pours

Legal Events

Date Code Title Description
GR01 Patent grant