CN207354268U CN201721515094.1U CN201721515094U CN207354268U CN 207354268 U CN207354268 U CN 207354268U CN 201721515094 U CN201721515094 U CN 201721515094U CN 207354268 U CN207354268 U CN 207354268U
Authority
CN
China
Prior art keywords
communication
power carrier
carrier communication
power
realization
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721515094.1U
Other languages
Chinese (zh)
Inventor
徐永兵
刘可新
李雅萍
王晶
聂晶
徐娜
郭奕萱
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Survey and Design Institute of Water Conservancy Co Ltd
Original Assignee
Shandong Survey and Design Institute of Water Conservancy Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Survey and Design Institute of Water Conservancy Co Ltd filed Critical Shandong Survey and Design Institute of Water Conservancy Co Ltd
Priority to CN201721515094.1U priority Critical patent/CN207354268U/en
Application granted granted Critical
Publication of CN207354268U publication Critical patent/CN207354268U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Cable Transmission Systems, Equalization Of Radio And Reduction Of Echo (AREA)

Abstract

The utility model belongs to technical field of information communication, discloses a kind of Real Time Hydrologic Information harvester based on power carrier communication, is provided with:Detect the sensor of data message;It is electrically connected with sensor, is used for realization the power carrier communication modem of gathered data modulation /demodulation;It is electrically connected with power carrier communication modem, is used for realization the communication host computer of data communication;It is electrically connected with power carrier communication modem, is used for realization the power supply of supply of electric power;It is electrically connected with power carrier communication modem, is used for realization check and the calibrating installation of information inspection.Power supply and communication are shared into a cable, i.e., carry out signal communication with power carrier on service cable, cable installation is simple and can effectively reducing the construction costs.During normal work, communicated using the compound port of powered communication, when needing check with calibration, enable spare communication terminal and carry out provisional communication connection.

Description

A kind of Real Time Hydrologic Information harvester based on power carrier communication
Technical field
The utility model belongs to technical field of information communication, more particularly to a kind of Real Time Hydrologic based on power carrier communication Information collecting device.
Background technology
At present, in hydraulic engineering, emphasis hydraulic structure periphery generally require installation rainfall gauge, water-level gauge, flowmeter, The sensors such as atmidometer.To make these normal operation of sensor, it usually needs the corresponding power supply of laying and communication cable, due to wanting Consider the factor such as anti-tampering of the communications cable, power supply is frequently necessary to be in charge of with the communications cable(Cable protection pipe)Laying, causes to pacify Dress is complicated, cable is practical more, and construction cost is high.The sensors such as rainfall gauge, water-level gauge, flowmeter need regular scene to be checked Debugging circuit is calibrated, it is necessary to remove original communication line and overlap temporarily with calibration, dismounting and connection repeatedly, so Not only add workload but also unnecessary abrasion can be carried out to the wire connection terminal and cable tie of work, and in turn result in sensor operation The reduction of performance.
In conclusion problem existing in the prior art is:Power supply is frequently necessary to be in charge of with the communications cable(Cable protection pipe) Laying, causes installation complexity, cable practical more, construction cost is high.The sensors such as rainfall gauge, water-level gauge, flowmeter need regular Scene check with calibration, it is necessary to which removing original communication line overlaps calibration debugging circuit, tearing open repeatedly temporarily Unload and connect, so not only added workload but also unnecessary abrasion can be carried out to the wire connection terminal and cable tie of work, and then Cause the reduction of sensor runnability.
The content of the invention
In view of the problems of the existing technology, the utility model provides a kind of Real Time Hydrologic based on power carrier communication Information collecting device.
The utility model is realized in this way Real Time Hydrologic Information harvester setting that should be based on power carrier communication Have:
Detect the sensor of data message;
It is electrically connected with sensor, is used for realization the power carrier communication modem of gathered data modulation /demodulation;
It is electrically connected with power carrier communication modem, is used for realization the communication host computer of data communication;
It is electrically connected with power carrier communication modem, is used for realization the power supply of supply of electric power;
It is electrically connected with power carrier communication modem, is used for realization check and the calibrating installation of information inspection.
Further, the power carrier communication modem is equipped with some pins and connects the wire connection terminal of power supply.
Further, the power carrier communication modem is realized by eight screws and is mechanically fixed and installs.
The advantages of the utility model and good effect are:
1st, power supply and communication are shared into a cable, i.e., carries out signal communication, cable with power carrier on service cable Installation is simple and can effectively reduce pipeline construction cost more than 35%.
When the 2nd, working normally, communicated using the compound port of powered communication, when needing check with calibration, Enable spare communication terminal and carry out provisional communication connection, the compound port of powered communication only has equipment function of supplying power at this time, treats Check and be connected with removing provisional communication after the completion of calibration, the compound port of powered communication restores electricity and the work(that communicates again at this time Energy.Workload was so not only reduced but also the abrasion of the wire connection terminal and cable of work can be reduced, Mean can be extended Time(MTBF)3000 it is small when more than.
Brief description of the drawings
Fig. 1 is a kind of Real Time Hydrologic Information harvester based on power carrier communication that the utility model embodiment provides Structure diagram;
Fig. 2 is that the Real Time Hydrologic Information harvester based on power carrier communication that the utility model embodiment provides is normal Operating diagram;
Fig. 3 is that the Real Time Hydrologic Information harvester based on power carrier communication that the utility model embodiment provides is checked Schematic diagram during calibration;
In figure:1st, power carrier communication modem;2nd, sensor;3rd, communicate host computer;4th, power supply;5th, check With calibrating installation.
Embodiment
For that can further appreciate that the invention, features and effects of the utility model, the following examples are hereby given, and coordinates Attached drawing describes in detail as follows.
The structure of the utility model is explained in detail below in conjunction with the accompanying drawings.
The Real Time Hydrologic Information harvester based on power carrier communication is provided with:
Detect the sensor 2 of data message;
It is electrically connected with sensor 2, is used for realization the power carrier communication modem 1 of gathered data modulation /demodulation;
It is electrically connected with power carrier communication modem 1, is used for realization the communication host computer 3 of data communication;
It is electrically connected with power carrier communication modem 1, is used for realization the power supply 4 of supply of electric power;
It is electrically connected with power carrier communication modem 1, is used for realization check and the calibrating installation 5 of information inspection.
As the preferred embodiment of the utility model, the power carrier communication modem 1 be equipped with some pins and Connect the wire connection terminal of power supply.
As the preferred embodiment of the utility model, the power carrier communication modem 1 passes through eight screw realities Now it is mechanically fixed and installs.
The operation principle of the utility model:
A kind of specific communication mode of information transmitting medium data transfer is used as by the use of 220V low-voltage distribution wires.Should be based on electricity The power carrier modem that the Real Time Hydrologic Information harvester of power carrier communication is selected can realize RS485 interfaces and electricity The switching of power carrier wave(This programme selects PLM39 power carrier communications modem 1), 2 delivery outlet of sensor also uses RS485 Interface modes.
The effect of power carrier interface is the connection established between carrier circuit and external communication medium, under normal circumstances, What carrier media was connected together with power supply 4.When sensor 2 works normally, power supply 4 only need to be connected, carrier wave is just It can be communicated by power cord, the 3-4 feet of PortA link together in the internal 1-2 feet with PortA at this time, to outside For, 3-4 feet do not connect vacantly.
The water level, the high-frequency signal of the information such as flow that are loaded with are loaded on electric current by the utility model, then utilize 220V etc. The power line transmission of level, the modem for receiving information is separated high-frequency signal from electric current again, and is transmitted to information Gather host computer.
When sensor 2 check with calibration, carrier wave is separate with power supply, at this time the 1-2 connection works of PortA Make power supply, the 3-4 feet of PortA are connected with exterior provisional communication medium, they are mutually independent, and inside is short-circuit even without progress Connect.
Wait to check and be connected with removing provisional communication after the completion of calibration, the compound port of powered communication restores electricity again at this time With communication function.The 3-4 feet of PortA recover to link together again in the internal 1-2 feet with PortA.
The above is only the preferred embodiment to the utility model, and not the utility model is made in any form Limitation, it is every according to the technical essence of the utility model to any simple modification made for any of the above embodiments, equivalent variations with Modification, belongs in the range of technical solutions of the utility model.

Claims (3)

1. a kind of Real Time Hydrologic Information harvester based on power carrier communication, it is characterised in that described to be based on power carrier The Real Time Hydrologic Information harvester of communication is provided with:
Detect the sensor of data message;
It is electrically connected with sensor, is used for realization the power carrier communication modem of gathered data modulation /demodulation;
It is electrically connected with power carrier communication modem, is used for realization the communication host computer of data communication;
It is electrically connected with power carrier communication modem, is used for realization the power supply of supply of electric power;
It is electrically connected with power carrier communication modem, is used for realization check and the calibrating installation of information inspection.
2. the Real Time Hydrologic Information harvester based on power carrier communication as claimed in claim 1, it is characterised in that described Power carrier communication modem is equipped with some pins and connects the wire connection terminal of power supply.
3. the Real Time Hydrologic Information harvester based on power carrier communication as claimed in claim 1, it is characterised in that described Power carrier communication modem is realized by eight screws and is mechanically fixed and installs.
CN201721515094.1U 2017-11-14 2017-11-14 A kind of Real Time Hydrologic Information harvester based on power carrier communication Active CN207354268U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721515094.1U CN207354268U (en) 2017-11-14 2017-11-14 A kind of Real Time Hydrologic Information harvester based on power carrier communication

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721515094.1U CN207354268U (en) 2017-11-14 2017-11-14 A kind of Real Time Hydrologic Information harvester based on power carrier communication

Publications (1)

Publication Number Publication Date
CN207354268U true CN207354268U (en) 2018-05-11

Family

ID=62350307

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721515094.1U Active CN207354268U (en) 2017-11-14 2017-11-14 A kind of Real Time Hydrologic Information harvester based on power carrier communication

Country Status (1)

Country Link
CN (1) CN207354268U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108768461A (en) * 2018-06-11 2018-11-06 中国水利水电科学研究院 A kind of engineering communication transferring device and system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108768461A (en) * 2018-06-11 2018-11-06 中国水利水电科学研究院 A kind of engineering communication transferring device and system

Similar Documents

Publication Publication Date Title
CN204334632U (en) A kind of master-slave communication circuit and air conditioner
CN106059266B (en) A kind of power supply power entry module applied to cube star
CN108566324B (en) System and method based on isolated dual Ethernet and dual CAN communication
CN207354268U (en) A kind of Real Time Hydrologic Information harvester based on power carrier communication
CN104504876A (en) Split-type power utility information collector
CN205921521U (en) Power of being applied to cube star supplies distribution module
CN105445633A (en) High-voltage cable protective layer loop current multi-state monitoring device
CN207380034U (en) Soil moisture monitoring system
CN202940824U (en) Power over Ethernet (POE) device
CN103780279B (en) Indoor energy efficiency management terminal communication module
CN206807149U (en) A kind of Electrical Safety control system based on broadband power line carrier
CN207066526U (en) A kind of Internet of Things water meter device
CN102663881A (en) Vibration monitoring node with functions of wire communication and wireless networking
CN205720377U (en) Bus power supply type multifunctional electric meter
US20070034003A1 (en) Water-level control device having power frequency carrier
CN207529181U (en) A kind of RS485 telecommunication circuits
CN207039295U (en) The outlet power administrative unit of the entrance of electronic single-phase one/ten
CN201600593U (en) Bus carrier wave intelligent water controller
CN209417919U (en) A kind of MBUS-485 converter
CN201278304Y (en) Anti-interference electric transformer on-line monitoring local discharging
CN105739362A (en) Transformer station measurement and control protection device
CN203848003U (en) Water seepage detecting system of deionized water cooling device
CN106707946A (en) Data line for communication between S7-200PLC and ACE3600RTU
CN111351543A (en) Wet-type water meter M-BUS BUS photoelectric direct-reading sensor
CN206819349U (en) Serial server

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240602

Address after: 250013 No. 121 Lishan Road, Lixia District, Shandong, Ji'nan

Patentee after: Shandong water resources survey and Design Institute Co.,Ltd.

Country or region after: China

Address before: 250013 No. 121 Lishan Road, Shandong, Ji'nan

Patentee before: SHANDONG SURVEY AND DESIGN INSTITUTE OF WATER CONSERVANCY

Country or region before: China